By introducing a heavy-load transverse system of the slide-type cable saddle cable hoisting system into the cable hoisting system, the problem of inability to transport beams and arch rib sections in restricted sites such as mountain canyons, achieving stable and stable heavy weight The load is moved horizontally, reducing construction costs and environmental impact.
Patent Information
- Application Number
- CN202411702720.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-26
- Publication Date
- 2025-02-11
AI Technical Summary
When the existing cable lifting system is installed in restricted locations such as mountain canyons, the processed beams and arch rib sections cannot be transported to the central axis of the arch rib of the bridge design to be lifted, and the traditional load-lifting structure is not mature enough.
A heavy-duty transverse system of a slippery cable hoisting system is provided, including a stable structure, a slip structure and a power structure on the tower. The stable structure consists of tower top beams and wind cables. The slip structure includes a slide, a slip car, a PTFE plate and a limit pulley. The power structure uses jack-finished rebar tensioning equipment.
The heavy load transverse movement in restricted sites is achieved at a stable, stable and uniform speed, avoiding the high demand for the site in traditional methods, reducing construction costs and environmental impacts, and improving construction speed and safety.
Smart Images

Figure CN119411484A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of bridge construction, and relates to a sliding boat type heavy load transverse movement system in a cable hoisting system in a cable hoisting process. Background Art
[0002] The cable hoisting system is a common hoisting tool when building arch bridges and suspension bridges in mountainous canyons. However, when the cable hoisting system needs to be used in locations with limited space, such as mountainous canyons, the processed beams and arch rib segments cannot be transported to the arch rib centerline of the bridge design for lifting. The traditional load-bearing transverse structure is a slideway sliding structure, and the pulley saddle load-bearing transverse structure is still in the trial process, and the technology is not mature enough. Summary of the invention
[0003] In order to solve the technical problem that when the cable lifting system in the prior art is installed in a location with limited space such as a mountain canyon, the processed beams and arch rib segments cannot be transported to the arch rib centerline of the bridge design for lifting, the present invention provides a heavy-load lateral movement system for a sliding boat type saddle cable lifting system.
[0004] The present invention provides a sliding boat type heavy-load transverse movement system in a cable hoisting system, wherein the heavy-load transverse movement system comprises a stable structure arranged on a tower in the sliding boat type saddle cable hoisting system, a sliding structure connected to the stable structure, and a power structure for driving the sliding structure to slide relative to the stable structure; the stable structure comprises a tower top crossbeam and a wind cable, the sliding structure comprises a slideway, a sliding trolley, a polytetrafluoroethylene plate and a limit pulley; the power structure is configured as a jack-finished rolled threaded steel tensioning device;
[0005] The process of constructing the heavy-load traverse system is as follows:
[0006] Step 1: Preliminary preparation: Process each component of the heavy-load lateral movement system separately;
[0007] Step 2: Install the heavy-load lateral movement system;
[0008] S2.1, install a stable structure;
[0009] ① Divide the tower top cross beam into standard section, transition section, reinforcement section, cross brace section and column cap section; assemble the tower top cross beam as a whole and hoist it to the installation site;
[0010] ② Install the tower frame to the column cap section, and then install at least one distribution beam on the column cap section along the longitudinal direction of the bridge;
[0011] ③. Use full penetration welding to connect the top plate and standard section, the top plate and transition section, the top plate and reinforcement section, and the top plate and cross bracing section in the distribution beam to complete the installation of the tower top beam;
[0012] ④. Use the total station to level the tower top beam;
[0013] ⑤. Install the limit baffle and wind cable on the tower top beam in sequence to complete the installation of the stable structure;
[0014] S2.2, install the sliding structure;
[0015] ①. Install the slideway on the top beam of the tower;
[0016] ② Assemble the sliding trolley, polytetrafluoroethylene plate and limiting pulley to form a sliding assembly;
[0017] ③. Install a stainless steel slideway that matches the sliding slideway at the bottom of the sliding assembly, and apply paraffin oil on the stainless steel slideway for lubrication to complete the installation of the sliding structure;
[0018] S2.3, install the power structure;
[0019] Using a set of threaded holes reserved at the bottom of the sliding trolley, the fine-rolled threaded steel in the jack-fine-rolled threaded steel tensioning equipment is installed on the fine-rolled nuts through the connecting sleeves and then installed on both sides of the sliding trolley; then the two ends of the fine-rolled threaded steel are respectively passed through the connecting plates and jack reaction seats in the jack-fine-rolled threaded steel tensioning device and then installed on the hydraulic jacks; the installation of the power structure is completed.
[0020] Optionally, the stabilizing structure is provided with two groups respectively connected to the two towers;
[0021] The two groups of sliding structures are respectively arranged in one-to-one correspondence with the two groups of stable structures;
[0022] The power structure is provided with two groups which are respectively arranged in one-to-one correspondence with the two groups of sliding structures.
[0023] Optionally, a single group of the stabilizing structure includes a tower top beam, a limit baffle and a wind cable; the tower top beam is installed on the upper end surface of the tower in the pulley-type saddle cable lifting system; the limit baffle is arranged on the side of the tower top beam; one end of the wind cable is hinged to the single-piece tower through a wire rope jack, and the other end of the wind cable is connected to the ground anchor through a hook pulley.
[0024] Optionally, the limit baffle is provided with two pieces respectively arranged on two parallel side surfaces of the tower top beam, the two limit baffles are extended along the length direction of the tower top beam, and one end of the two limit baffles is connected to the upper end surface of the tower top beam, and the other ends of the two limit baffles are extended along the height direction away from the tower top beam.
[0025] Optionally, a reinforcement rib group is provided between the single limit baffle and the tower top cross beam, and the single reinforcement rib group includes a plurality of reinforcement ribs that are spaced apart from each other along the extension direction of the limit baffle.
[0026] Optionally, two wind cables respectively arranged in two groups of the stabilizing structures are arranged in an "eight" shape with respect to each other, and an angle between the two wind cables is set to 45°-60°.
[0027] Optionally, a single group of the sliding structure includes a device installed on the upper end surface of the tower top beam, and the single group of the sliding structure includes a slideway, a sliding trolley, a polytetrafluoroethylene plate and a limiting pulley;
[0028] The slideway is arranged on the upper end surface of the tower top crossbeam;
[0029] The sliding trolley is slidably installed on the slideway, and the sliding trolley is connected to the power structure.
[0030] Compared with the prior art, the present invention has the following beneficial effects:
[0031] The present invention provides a heavy-load lateral sliding system in a cable hoisting system, wherein: (1) a tower top crossbeam and a wind cable are used as a load-bearing lateral sliding stabilizing structure to effectively ensure the stability of the heavy-load lateral sliding system; a slideway and a sliding trolley are used as the sliding structure, and a polytetrafluoroethylene plate is installed at the bottom of the sliding trolley, a limit pulley is installed on the side, and a 301 stainless steel plate is laid on the slideway, and paraffin oil is applied between the slideway and the sliding rail of the sliding trolley and between the polytetrafluoroethylene plate and the stabilizing structure for lubrication to ensure the smooth, uniform and flexible sliding of the sliding structure; and a through-core jack and supporting high-pressure oil pump equipment, precision-rolled threaded steel, reaction support frame and other tensioning facilities are used as the lateral sliding traction power structure to effectively ensure that the sliding structure is uniform and smooth during lateral movement without being stuck. (2) The sliding boat type heavy load lateral movement system in the cable hoisting system provided by the present invention overcomes the conventional empty load lateral movement to the bridge design axis, which requires an open and flat site to ensure that beams, arches and other lifting objects are transported to the dedicated operating platform below the vertical lifting, thereby saving the costs of site excavation, filling, masonry and hardening of the site, and setting up other special platform facilities; secondly, it can increase the construction speed and reduce the use time of equipment and materials by assembling and storing large sections in advance, thereby saving costs. (3) The sliding boat type heavy load lateral movement system in the cable hoisting system provided by the present invention overcomes the safety risks in the fixed saddle hoisting when the site is limited and the heavy objects need to be swung at a large angle, and in the oblique pulling and oblique lifting. (4) The sliding boat type heavy load lateral movement system in the cable hoisting system provided by the present invention has green and environmental benefits in bridge engineering construction. In conventional hoisting, an open and flat site is required to ensure that beams, arches and other lifting objects are transported to the dedicated operating platform below the vertical lifting, reducing the environmental damage caused by large-scale excavation and construction of the mountain, and ensuring the integrity of the original terrain. (5) In the heavy-load transverse sliding system of the cable lifting system provided by the present invention, paraffin oil plays a huge role in the operation of the present invention. Paraffin oil is a homemade grease, and its formula quality ratio is: paraffin: engine oil = 1:1. The paraffin is first melted at high temperature, and then the engine oil is promptly added for fusion and stirring. Before the paraffin solidifies, it is promptly applied to the surface of the stainless steel slide. Since paraffin is a solid material, the paraffin oil applied to the slide can solidify on the slide in a short moment to form a layer of solid grease. When the solid grease is squeezed up and down, it will produce a certain resistance. Compared with other more diluted greases, the effect of this homemade paraffin grease is very obvious. (6) In the sliding boat type heavy load lateral movement system of a cable lifting system provided by the present invention, the side horizontal limit wheel plays a huge role in the operation of the present invention. Since the angles between the tower and the back cable, and between the tower and the mid-span load-bearing cable are different, the horizontal thrust exerted on the saddle during the lifting process greatly increases the frictional resistance of the saddle lateral movement. The side horizontal limit wheel reduces the frictional resistance by replacing the sliding friction with rolling friction, and plays a vital role in the present invention.
[0032] In addition to the above-described objects, features and advantages, the present invention has other objects, features and advantages. The present invention will be further described in detail with reference to the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] The drawings constituting a part of this application are used to provide a further understanding of the present invention. The exemplary embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation of the present invention. In the drawings:
[0034] Figure 1 It is a schematic diagram of the overall structure of a heavy-load transverse movement system in an embodiment of the present invention;
[0035] Figure 2 yes Figure 1 A schematic side view of the intermediate stable structure;
[0036] Figure 3 yes Figure 1 A partial schematic diagram of the connection between the intermediate stable structure and the sliding structure;
[0037] Figure 4 yes Figure 3 Schematic diagram of the AA section.
[0038] in:
[0039] 0. Tower, 1. Tower top beam, 2. Limit baffle, 3. Wind cable, 4. Sliding structure, 4.1. Sliding trolley, 4.2. Saddle, 4.3. Polytetrafluoroethylene plate, 4.4. Limit pulley, 4.5. Stainless steel plate slideway, 5. Power structure. DETAILED DESCRIPTION
[0040] In order to make the above-mentioned purposes, features and advantages of the present invention more clear and easy to understand, the specific implementation methods of the present invention are described in detail below in conjunction with the accompanying drawings. It should be noted that the drawings of the present invention are all simplified and use non-precise proportions, which are only used to conveniently and clearly assist in explaining the implementation of the present invention; the "number" mentioned in the present invention is not limited to the specific number in the examples in the accompanying drawings; the directions or positional relationships indicated by "front", "middle", "back", "left", "right", "up", "down", "top", "bottom", "middle", etc. mentioned in the present invention are based on the directions or positional relationships shown in the drawings of the present invention, and do not indicate or imply that the devices or components referred to must have a specific direction, nor can they be understood as limitations on the present invention.
[0041] Example:
[0042] See also Figures 1 to 4As shown, a sliding boat type heavy-load lateral movement system in a cable hoisting system provided by the present invention includes a stable structure arranged on a tower 0 in the sliding boat type saddle cable hoisting system, a sliding structure 4 connected to the stable structure, and a power structure 5 for driving the sliding structure 4 to slide relative to the stable structure.
[0043] Preferably, the stable structure is provided with two groups respectively connected to the two towers 0, the sliding structures 4 are respectively provided with two groups corresponding to the two stable structures, and the power structure 5 is provided with two groups respectively corresponding to the two sliding structures 4.
[0044] Furthermore, a single group of the stabilizing structure includes a tower top beam 1, a limit baffle 2 and a wind cable 3; the tower top beam 1 is installed on the upper end surface of the tower 0 in the pulley-type saddle cable lifting system; the limit baffle 2 is arranged on the side of the tower top beam 1; one end of the wind cable 3 is hinged to the single-piece tower 0 through a wire rope jack, and the other end of the wind cable 3 is connected to the ground anchor through a hook pulley.
[0045] Preferably, the limit baffle 2 is provided with two pieces respectively arranged on two parallel side surfaces of the tower top beam 1, the two limit baffles 2 are both extended along the length direction of the tower top beam 1, and one end of the two limit baffles 2 is connected to the upper end surface of the tower top beam 1, and the other ends of the two limit baffles 2 are both extended along the height direction in the direction away from the tower top beam 1.
[0046] Preferably, in order to increase the strength of the limit baffle 2 , a reinforcing rib group is provided between the single limit baffle and the tower top cross beam 1 , and a single group of reinforcing ribs is provided with a plurality of pieces spaced apart from each other along the extension direction of the limit baffle 2 .
[0047] Preferably, the two wind cables 3 respectively arranged in the two groups of the stable structures are arranged in an "eight" shape with respect to each other, and the ideal angle between the two wind cables 3 and the tower 0 should be set to 45°-60°.
[0048] Furthermore, a single group of the sliding structure 4 includes a stainless steel plate slideway 4.5, a sliding trolley 4.1, a polytetrafluoroethylene plate 4.3 and a limit pulley 4.4 installed on the upper end surface of the tower top cross beam 1; the sliding trolley 4.1 is connected to the power structure 5, so that the sliding trolley 4.1 and the slideway can be slidably connected, and a wear-resistant polytetrafluoroethylene plate 4.3 is also provided at the bottom of the sliding trolley 4.1. Limit pulleys are provided on both side surfaces of the sliding trolley 4.1, and the outer surfaces of the two limit pulleys are respectively contact-connected with the two limit baffles 2, so that the sliding trolley 4.1 generates horizontal thrust during the lifting process due to the different angles between the tower frame and the back cable and the mid-span load-bearing cable, and the increased frictional resistance is reduced. At the same time, the displacement of the sliding trolley 4.1 is also prevented.
[0049] Preferably, a paraffin oil layer is provided between the slideway and the polytetrafluoroethylene plate 4.3 to increase lubrication between the slideway and the polytetrafluoroethylene plate 4.3. Self-made paraffin oil is applied between the polytetrafluoroethylene plate 4.3 and the stainless steel slideway 4.5.
[0050] Preferably, in order to achieve the connection between the sliding trolley 4.1 and the pulley-type saddle cable hoisting system, a plurality of connecting pulleys and a saddle 4.2 are provided on the sliding trolley 4.1, and the pulley-type saddle cable hoisting system is connected to the sliding trolley 4.1 through the saddle 4.2.
[0051] Furthermore, a single group of the power structure 5 is configured as tensioning facilities such as a through-hole jack and supporting high-pressure oil pump equipment, precision-rolled threaded steel bars, and a reaction support frame.
[0052] Preferably, according to actual needs, a single power structure 5 may be provided with one or two or more elements spaced apart from each other.
[0053] As a further embodiment of the present invention, the present invention also provides a method for constructing the sliding boat type heavy load traverse system in the above-mentioned cable hoisting system, comprising the following steps:
[0054] Step 1: Preliminary preparation;
[0055] Before construction, the stability and load calculations of the tower top beam, the sliding trolley and the tower frame in the pulley-type saddle cable hoisting system were carried out;
[0056] Formulate detailed construction plans and proposals based on actual conditions, draw up plan drawings, compile safety measures, and clarify the construction process and technical requirements for load-carrying transverse movement;
[0057] Prepare materials for heavy-load traverse systems, and cut, process and manufacture according to the requirements of the plan drawings;
[0058] Complete the preliminary preparations.
[0059] Step 2: Install the heavy-load lateral movement system;
[0060] S2.1, install a stable structure;
[0061] ① Divide the tower top cross beam into standard section, transition section, reinforcement section, cross brace section and column cap section; assemble the tower top cross beam as a whole and hoist it to the installation site;
[0062] ②, install the tower to the column cap section, and then install three distribution beams on the column cap section along the longitudinal direction of the bridge (the connection between the column cap section and the distribution beam is specifically that the top plate in the column cap section and the bottom steel plate in the distribution beam are connected to each other by full welding); specifically, the distribution beam is configured as a box beam force-bearing assembly formed by welding steel plates of different specifications and models;
[0063] ③. Connect the top plate in the distribution beam and the other bottom plates in the tower top cross beam by full penetration welding to complete the installation of the tower top cross beam;
[0064] ④. Level the tower top beam; Specifically, before the tower top is capped, since there may be a 1-2CM length deviation at each column head position of the tower frame, it is necessary to use a level to measure the elevation of each column head, and take the highest column head elevation as the standard, and add pads to the remaining column heads to make the elevation of each column head reach the same horizontal height. Since the cable towers on both sides are located at the central axis of the cable tower and are in a parallel state, the center point position and elevation of the distribution beam are measured using a total station to ensure that the tower top beam is placed in a vertical position relative to the distribution beam during installation. If there is an elevation error during installation, use the same method to add pads under the tower top beam;
[0065] ⑤. Install the limit baffle and wind cable on the tower top beam in sequence to complete the installation of the stable structure.
[0066] S2.2, install the sliding structure and the power structure;
[0067] ①. Install the slideway on the tower top beam; specifically, the slideway is set as a steel box structure formed by welding steel plates, and a limit device is set on the slideway, and a sliding slideway is welded on the sliding surface of the slideway, and homemade paraffin grease is applied on the sliding slideway to ensure that the friction coefficient of the slideway surface is less than 0.15; at the same time, in order to ensure that the cable crane load-bearing cable system can be positioned at any time during transverse movement, a triangular limit wedge block is set on the sliding slideway to position the saddle and prevent the saddle from moving;
[0068] ② Assemble the sliding trolley, polytetrafluoroethylene plate and limiting pulley to form a sliding assembly;
[0069] ③. Install a stainless steel slideway that matches the sliding slideway at the bottom of the sliding assembly, and apply paraffin oil on the stainless steel slideway for lubrication;
[0070] ④. Using a set of threaded holes reserved at the bottom of the sliding trolley, string two pieces of 7.5-meter-long fine-rolled rebars and one piece of 8-meter-long fine-rolled rebar (the fine-rolled rebar is part of the jack-fine-rolled rebar tensioning equipment) together through the connecting sleeve, and then put the fine-rolled nuts on both sides of the sliding trolley. Then, the two ends of the fine-rolled rebar pass through the suturing plate and the jack reaction seat in the jack-fine-rolled rebar tensioning setting, and then install the hydraulic jack. It should be noted that when installing the hydraulic jacks at both ends of the tower top beam, the inner core of the jack at one end must be in the jacking state, and the other end must remain stationary. At the same time, install the fine-rolled nuts on the outside of the jacks at both ends. As a result, the inner core of the jack in the jacking state of the sliding trolley falls back to retract and release the finely rolled threaded steel and tighten the finely rolled nut (the threaded steel needs to reserve a length to facilitate tensioning, retracting and moving the saddle), and the jack at the other end begins to lift and tension the threaded steel and loosen the finely rolled nut. When the sliding trolley is moving horizontally, it is necessary to pay attention to manually turning the position of each finely rolled nut in time to prevent the saddle set on the sliding trolley from being stuck and affecting the horizontal movement. However, the nut should not be turned too far when turning. If the saddle suddenly slides when moving from the middle of the beam to the edge, the rear anchor and the rock saddle will present a mechanism similar to that of a slingshot. Therefore, in order to ensure the limit, the finely rolled nut cannot move too much at one time. When the saddle moves horizontally to the predetermined position, the nut is tightened to fix the position of the saddle and the hydraulic jack.
[0071] As a further embodiment of the present invention, after the heavy-load lateral movement system is installed by the above construction method, the following heavy-load lateral movement examples are performed through trial lifting and actual lifting:
[0072] Before the trial lifting, the trial lifting platform and the test lifting object are placed in the lifting position, and the saddle transverse flat car is moved horizontally to the corresponding lifting point without load. During the trial lifting, 50%, 100% and 110% of the maximum lifting weight of the steel pipe arch rib of 104.2T are tested. After loading step by step, the test objects of different weights are subjected to load transverse movement tests 30m in front of the Guiyang bank tower, in the middle of the span, and 20m in front of the Pingtang bank tower.
[0073] The test results show that the lateral tower deviation is within 1cm when the load is lateral, the lateral movement is smooth with low friction, and the tensioning force of the jack-finished rolled rebar tensioning equipment is small. It also verifies the feasibility of the lateral movement of the load, good stability, high safety performance, strong economy, simple operation, convenient and fast, and can be widely used.
[0074] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A heavy-load traverse system of a sliding boat type in a cable hoisting system, characterized in that: The heavy-load transverse movement system comprises a stable structure arranged on a tower in a pulley-type saddle cable hoisting system, a sliding structure (4) connected to the stable structure, and a power structure (5) for driving the sliding structure (4) to slide relative to the stable structure; the stable structure comprises a tower top cross beam (1) and a wind cable (3); the sliding structure (4) comprises a slideway, a sliding trolley (4.1), a polytetrafluoroethylene plate (4.3) and a limit pulley; the power structure (5) is configured as a jack-finished rolled threaded steel tensioning device; The process of constructing the heavy-load traverse system is as follows: Step 1: Preliminary preparation: Process each component of the heavy-load lateral movement system separately; Step 2: Install the heavy-load lateral movement system; S2.1, install a stable structure; ① Divide the tower top cross beam into standard section, transition section, reinforcement section, cross brace section and column cap section; assemble the tower top cross beam as a whole and hoist it to the installation site; ② Install the tower frame to the column cap section, and then install at least one distribution beam on the column cap section along the longitudinal direction of the bridge; ③. Use full penetration welding to connect the top plate and standard section, the top plate and transition section, the top plate and reinforcement section, and the top plate and cross bracing section in the distribution beam to complete the installation of the tower top beam; ④. Use the total station to level the tower top beam; ⑤. Install the limit baffle and wind cable on the tower top beam in sequence to complete the installation of the stable structure; S2.2, install the sliding structure; ①. Install the slideway on the top beam of the tower; ② Assemble the sliding trolley, polytetrafluoroethylene plate and limiting pulley to form a sliding assembly; ③. Install a stainless steel slideway that matches the sliding slideway at the bottom of the sliding assembly, and apply paraffin oil on the stainless steel slideway for lubrication to complete the installation of the sliding structure; S2.3, install the power structure; Using a set of threaded holes reserved at the bottom of the sliding trolley, the fine-rolled threaded steel in the jack-fine-rolled threaded steel tensioning equipment is installed on the fine-rolled nuts through the connecting sleeves and then installed on both sides of the sliding trolley; then the two ends of the fine-rolled threaded steel are respectively passed through the connecting plates and jack reaction seats in the jack-fine-rolled threaded steel tensioning device and then installed on the hydraulic jacks; the installation of the power structure is completed.
2. The heavy-load traverse system according to claim 1, characterized in that: The stable structure is provided with two groups respectively connected to the two towers; The sliding structures (4) are arranged in two groups corresponding to the two groups of stable structures respectively; The power structure (5) is provided with two groups which are respectively arranged in one-to-one correspondence with the two groups of sliding structures (4).
3. The heavy-load traverse system according to claim 2, characterized in that: A single group of the stabilizing structure comprises a tower top cross beam (1), a limit baffle (2) and a wind cable (3); the tower top cross beam (1) is installed on the upper end surface of the tower in the pulley-type saddle cable hoisting system; the limit baffle (2) is arranged on the side of the tower top cross beam (1); one end of the wind cable (3) is hinged to the single-piece tower through a wire rope jack, and the other end of the wind cable (3) is connected to the ground anchor through a hook pulley.
4. The heavy-load traverse system according to claim 3, characterized in that: The limit baffles (2) are provided with two pieces respectively arranged on two mutually parallel side surfaces of the tower top cross beam (1); the two limit baffles (2) are both extended along the length direction of the tower top cross beam (1); one end of the two limit baffles (2) is connected to the upper end surface of the tower top cross beam (1); and the other ends of the two limit baffles (2) are both extended in the height direction in a direction away from the tower top cross beam (1).
5. The heavy-load traverse system according to claim 3, characterized in that: A reinforcement rib group is also provided between the single-piece limit baffle plate and the tower top cross beam (1), and the single-piece reinforcement rib group is provided with a plurality of pieces which are arranged at intervals from each other along the extension direction of the limit baffle plate (2).
6. The heavy-load traverse system according to claim 3, characterized in that: The two wind cables (3) respectively arranged in the two groups of the stable structures are arranged in an "eight" shape relative to each other, and the angle between the two wind cables (3) is set to be 45°-60°.
7. The heavy-load traverse system according to any one of claims 3 to 6, characterized in that: A single set of the sliding structure (4) is installed on the upper end surface of the tower top cross beam (1), and the single set of the sliding structure (4) includes a slideway, a sliding trolley (4.1), a polytetrafluoroethylene plate (4.3) and a limiting pulley; The slideway is arranged on the upper end surface of the tower top crossbeam (1); The sliding trolley (4.1) is slidably mounted on the slideway, and the sliding trolley (4.1) is connected to the power structure (5).