Construction method for embedding and reinforcing water stop sleeve

By setting up a support device during the pre-embedding of the water stop casing, using high-strength waterproofing glue for sealing, and using reinforced steel mesh, the poor waterproofing effect and insufficient structural stability in the traditional water stop casing installation method are solved. The problem is to achieve a close bonding and effective sealing between the water stop casing and the concrete structure.

CN119411829APending Publication Date: 2025-02-11NANJING NANBU ROAD & BRIDGE ENG CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411860921.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-12-17
Publication Date
2025-02-11

AI Technical Summary

Technical Problem

It is difficult to ensure the close bond between the water stop casing and the concrete structure during construction, effective sealing and long-term structural stability, resulting in poor waterproofing and structural safety.

Method used

By setting up an embedded support device during construction, ensure the stable and fixed water stop casing; reserve matching space on both sides of the water stop casing and sealing with high-strength waterproof glue; reinforcement is used on the outside to strengthen it to strengthen Structural stability and compressive strength; finally, pour concrete into reserved voids to ensure close integration with the water stop casing.

Benefits of technology

The close integration and effective sealing between the water stop casing and the concrete structure is achieved, the waterproofing effect and structural stability are enhanced, and the later maintenance costs and risks are reduced.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119411829A_ABST
    Figure CN119411829A_ABST
Patent Text Reader

Abstract

The invention discloses a construction method for embedding and reinforcing a water stop sleeve, which relates to the technical field of constructional engineering and comprises the following steps: determining the embedding position and size of the water stop sleeve according to a design drawing and site conditions; an embedded supporting device is arranged, and the water stop sleeve is stably fixed to a preset position; gaps matched with the water stop sleeve are reserved in the concrete structure on the two sides of the water stop sleeve; the periphery of the water stop sleeve is sealed by using a high-strength waterproof sizing material; reinforcement treatment is conducted on the outer portion of the water stop sleeve; and concrete is poured into the reserved gap, and the pre-burying process is completed. A series of detailed construction steps are provided, tight combination and effective sealing of the water stop sleeve and the concrete structure in the pre-embedding process are guaranteed, the sleeve is reinforced, the structural stability and compressive strength of the sleeve are enhanced, no leakage between the water stop sleeve and the concrete structure is guaranteed through sealing treatment of the high-strength waterproof sizing material, and the sealing effect is good. And the waterproof effect is enhanced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of building engineering, and in particular to a construction method for pre-embedded reinforcement of a water-stopping sleeve. Background Art

[0002] Waterstop sleeves are common waterproof components in construction projects. They are mainly used for pre-embedded concrete structures. They provide waterproof seals for pipes passing through walls and ground to prevent moisture from penetrating through the pores of the pipes. Waterstop sleeves are widely used in underground projects, tunnels, water supply and drainage pipe systems and other places, and are usually required to have high waterproof performance and structural stability.

[0003] The traditional installation method of water-stop sleeves is usually to bury them by opening reserved holes. The subsequent waterproofing and reinforcement measures are relatively simple, mainly relying on the waterproof performance of the sleeve itself. However, in actual construction, the quality of the concrete structure around the water-stop sleeve, the sealing between the sleeve and the structure, and the reinforcement measures often cannot meet the strict waterproofing requirements, which can easily cause leakage problems between the water-stop sleeve and the surrounding structure, affecting the overall waterproofing effect and structural safety. Therefore, how to ensure the close connection between the water-stop sleeve and the concrete structure, effective waterproof sealing and long-term structural stability has become an important challenge in construction. Summary of the invention

[0004] In order to solve the above technical problems, a construction method for pre-embedded reinforcement of water-stop casing is provided. This technical solution solves the above problems.

[0005] In order to achieve the above purpose, the technical solution adopted by the present invention is:

[0006] A construction method for pre-embedded reinforcement of a water-stop casing, comprising:

[0007] Determine the embedded position and size of the water-stop casing according to the design drawings and on-site conditions;

[0008] During the structural construction process, a pre-buried support device is provided to stably fix the water-stop sleeve at the predetermined position;

[0009] Reserve gaps matching the water-stop sleeves in the concrete structure on both sides of the water-stop sleeves, and keep the gap sizes consistent;

[0010] Use high-strength waterproof rubber to seal around the water-stop sleeve to ensure the sealing effect between the water-stop sleeve and the structure;

[0011] The outside of the water-stop casing is reinforced with steel mesh to enhance the structural stability and compressive strength of the water-stop casing;

[0012] Pour concrete into the reserved gap, ensure it is tightly integrated with the structure around the water stop sleeve, and complete the embedding process.

[0013] Preferably, determining the embedded position and size of the water stop sleeve according to the design drawings and on-site conditions specifically includes:

[0014] Review the design drawings to obtain the type, quantity, installation location, size requirements and embedded depth of the water-stop casing;

[0015] Check the position of the water stop sleeve according to the requirements in the design drawings and building regulations;

[0016] Conduct on-site surveys according to design drawings to measure the specific dimensions of the construction area, the location of structures, and the conditions of embedded pipes, steel bars, and walls;

[0017] Check whether there are any obstacles in the space at the construction site, ensure that the waterproof sleeve can be embedded in the designated position and does not conflict with other structures, and determine the final embedded position of the waterproof sleeve;

[0018] According to the specifications of the water-stop sleeve provided in the design drawings, measure the outer diameter of the pipeline to ensure that the size of the selected water-stop sleeve can adapt to the predetermined pipeline;

[0019] Determine the size of the reserved hole according to the outer diameter of the water-stop sleeve, and determine the depth of the embedded hole and the length of the embedded sleeve according to the waterproof requirements of the structure;

[0020] According to the elevation data in the design drawings, clarify the upper and lower elevations of the embedded water-stop casing to avoid misalignment during construction;

[0021] Use a laser level to set the center line position of the waterstop sleeve according to the design drawings, and mark it on the structure. Mark the specific embedded position of the waterstop sleeve on the on-site working surface, and mark the size, elevation and direction data.

[0022] Preferably, during the structural construction process, the embedded support device is provided to stably fix the water-stop sleeve at a predetermined position, specifically including:

[0023] Check the water-stop sleeve and embedded position. Before setting up the support device, confirm the specification, model, embedded position and elevation of the water-stop sleeve to ensure that the water-stop sleeve is consistent with the design requirements;

[0024] Prepare the materials required for the support device according to the size and construction requirements of the water stop sleeve, including steel support frames, temporary support parts, cable ties and fixing clips;

[0025] Determine the support of the water-stop sleeve, mark the installation position of the support frame near the embedded position of the structure, and ensure that the fixed position of the support frame and the water-stop sleeve are consistent with the design drawings;

[0026] Use steel tie bands to firmly connect the water-stop sleeve to the support frame. After the support device is installed, use a level and total station to calibrate the position and elevation of the water-stop sleeve to ensure that it is in the predetermined designed position.

[0027] Preferably, reserving a gap matching the water-stopping sleeve in the concrete structure on both sides of the water-stopping sleeve and maintaining the gap size consistent specifically includes:

[0028] Check the verticality and horizontality of the water stop sleeve to ensure that its fixed position in the structure meets the construction requirements and that the horizontal deviation is controlled within 5mm and the vertical deviation is controlled within 5mm;

[0029] Temporarily use steel bars for reinforcement, use binding steel bars to fix the water stop sleeve and surrounding structures, and ensure that the gap between the water stop sleeve and the poured concrete is within 10mm to 30mm;

[0030] Before pouring concrete, the support device should be inspected and accepted.

[0031] Preferably, the sealing treatment using high-strength waterproof rubber around the water-stopping sleeve to ensure the sealing effect between the water-stopping sleeve and the structure specifically includes:

[0032] Clean the interface area between the water stop sleeve and the concrete structure, and remove dust, oil, debris and loose materials on the surface;

[0033] Check the contact surface between the waterproof sleeve and the concrete to ensure that there are no cracks or irregular gaps between the waterproof sleeve and the concrete structure. If there are any defects, repair them;

[0034] Choose appropriate high-strength waterproof adhesive according to project needs, including polyurethane waterproof adhesive, epoxy resin waterproof adhesive and acrylic waterproof adhesive;

[0035] Calculate the amount of adhesive based on the adhesive dosage calculation formula, mix the adhesive in proportion, and evenly apply the mixed waterproof adhesive to the gap between the water stop sleeve and the concrete structure. Use a spray tool to apply the adhesive to the entire contact surface and ensure that the thickness is consistent. The applied adhesive covers the entire contact area.

[0036] After each layer is applied, ensure that the adhesive is fully cured before applying the next layer. The thickness of the coating is 1 to 2 mm.

[0037] After applying the adhesive, you can use a scraper to compact the adhesive so that it fits more closely to the contact surface between the waterproof casing and the concrete. After applying, check the joints to ensure that there are no missed areas or uneven areas.

[0038] Determine the curing time according to the type of waterproof adhesive used and the construction environment. Do not disturb the mobile waterproof casing during the curing period to ensure that the adhesive is completely cured.

[0039] Keep the environment dry during the curing period. After curing is completed, check the sealing effect of the waterproof adhesive and conduct a waterproof test through a pressure water test.

[0040] Preferably, the calculation of the amount of rubber material based on the rubber material amount calculation formula specifically includes:

[0041] The calculation formula for the amount of rubber is:

[0042]

[0043] Where V is the volume of the waterproof rubber, D O The outer diameter of the water-stopping casing, D I is the inner diameter of the water-stopping casing, h is the thickness of the applied rubber, that is, the width of the gap between the casing and the concrete;

[0044] The compound is configured based on the volume of the waterproof compound.

[0045] Preferably, the reinforcement treatment is performed on the outside of the water-stopping sleeve, and a steel mesh is used for reinforcement to enhance the structural stability and compressive strength of the water-stopping sleeve, specifically including:

[0046] According to the outer diameter size and design requirements of the water-stop casing, make a steel mesh, install it around the outside of the water-stop casing, and ensure that there is a 50-100mm gap between the mesh and the casing;

[0047] After installing the steel mesh, pour the concrete. When pouring, make sure that the concrete can fully cover the steel mesh and fill all gaps;

[0048] Use a vibrator to compact the concrete, ensuring that the steel mesh is completely wrapped in the concrete to avoid voids and honeycomb structures;

[0049] After the concrete is poured, it is cured for 7 to 14 days.

[0050] Preferably, check the construction quality of the reinforced part to ensure that the steel mesh is in the correct position, check the arrangement of the steel mesh, the pouring quality of the concrete, and the connection between the water stop sleeve and the concrete, and waterproof the reinforced part.

[0051] Preferably, the concrete is poured into the reserved gap to ensure close integration with the structure around the water stop sleeve, and the pre-embedding process specifically includes:

[0052] When the concrete strength reaches more than 70% of the design strength, the formwork is removed and the concrete surface is checked after removal to confirm that there is no damage or defect.

[0053] Check whether the concrete surface is flat and smooth, without obvious bubbles, cracks and voids. After the curing period, conduct a strength test on the concrete;

[0054] After the concrete pouring is completed, the construction acceptance is carried out to check whether the entire pre-embedded process meets the design requirements and the tightness of the water stop sleeve and the surrounding structure.

[0055] Preferably, the construction acceptance specifically includes:

[0056] Review construction records, including concrete pouring time, strength grade, mix ratio and construction technology, check construction plans and design drawings to ensure that the materials, processes and methods used are consistent with design requirements;

[0057] Check the installation of formwork, support and water-stop sleeve to ensure that the installation direction, elevation and size of the sleeve meet the design requirements, especially the combination requirements of the outer contact surface of the sleeve and the surrounding structure;

[0058] Check whether the water stop sleeve has any deviation or deformation to ensure that it is firmly installed and will not move during the concrete pouring process;

[0059] If there are marks on the sleeve, check whether the marks are consistent with the design requirements to ensure that it is correctly positioned;

[0060] Check the combination of concrete and waterproof sleeve, and use measuring tools to check whether the gap between waterproof sleeve and surrounding structure is uniform;

[0061] Check whether the concrete pouring surface is flat, use instruments to check whether there are bubbles, and ensure that the concrete is tightly combined with the casing to prevent water seepage;

[0062] Check the quality and density of concrete, check the concrete curing and strength, verify the concrete curing records, and conduct concrete strength testing by taking samples on site after the curing period;

[0063] Record the construction process and inspection results, and prepare an acceptance report, which includes the installation position, size and tightness inspection results of the water stop sleeve.

[0064] Compared with the prior art, the present invention has the following beneficial effects:

[0065] The present invention proposes a construction method for pre-embedded reinforcement of a water-stopping sleeve. Through a series of meticulous construction steps, the water-stopping sleeve is ensured to be tightly combined with the concrete structure and effectively sealed during the pre-embedded process, and the sleeve itself is reinforced to enhance its structural stability and compressive strength. BRIEF DESCRIPTION OF THE DRAWINGS

[0066] Figure 1 It is a step flow framework diagram of the present invention. DETAILED DESCRIPTION

[0067] The following description is used to disclose the present invention so that those skilled in the art can implement the present invention. The preferred embodiments described below are only examples, and those skilled in the art may think of other obvious variations.

[0068] Reference Figure 1 As shown, a construction method for pre-embedded reinforcement of a water-stop casing comprises:

[0069] Step 1:

[0070] Review the design drawings to obtain the type, quantity, installation location, size requirements and embedded depth of the water-stop casing;

[0071] Check the position of the water stop sleeve according to the requirements in the design drawings and building regulations;

[0072] Conduct on-site surveys according to design drawings to measure the specific dimensions of the construction area, the location of structures, and the conditions of embedded pipes, steel bars, and walls;

[0073] Check whether there are any obstacles in the space at the construction site, ensure that the waterproof sleeve can be embedded in the designated position and does not conflict with other structures, and determine the final embedded position of the waterproof sleeve;

[0074] According to the specifications of the water-stop sleeve provided in the design drawings, measure the outer diameter of the pipeline to ensure that the size of the selected water-stop sleeve can adapt to the predetermined pipeline;

[0075] Determine the size of the reserved hole according to the outer diameter of the water-stop sleeve, and determine the depth of the embedded hole and the length of the embedded sleeve according to the waterproof requirements of the structure;

[0076] According to the elevation data in the design drawings, clarify the upper and lower elevations of the embedded water-stop casing to avoid misalignment during construction;

[0077] Use a laser level to set the center line position of the waterstop sleeve according to the design drawings, and mark it on the structure. Mark the specific embedded position of the waterstop sleeve on the on-site working surface, and mark the size, elevation and direction data.

[0078] Determine the embedded position and size of the water-stop casing according to the design drawings and on-site conditions;

[0079] Step 2:

[0080] Check the water-stop sleeve and embedded position. Before setting up the support device, confirm the specification, model, embedded position and elevation of the water-stop sleeve to ensure that the water-stop sleeve is consistent with the design requirements;

[0081] Prepare the materials required for the support device according to the size and construction requirements of the water stop sleeve, including steel support frames, temporary support parts, cable ties and fixing clips;

[0082] Determine the support of the water-stop sleeve, mark the installation position of the support frame near the embedded position of the structure, and ensure that the fixed position of the support frame and the water-stop sleeve are consistent with the design drawings;

[0083] Use steel tie bands to firmly connect the water-stop sleeve to the support frame. After the support device is installed, use a level and total station to calibrate the position and elevation of the water-stop sleeve to ensure that it is in the predetermined designed position.

[0084] Step 3:

[0085] Check the verticality and horizontality of the water stop sleeve to ensure that its fixed position in the structure meets the construction requirements and that the horizontal deviation is controlled within 5mm and the vertical deviation is controlled within 5mm;

[0086] Temporarily use steel bars for reinforcement, use binding steel bars to fix the water stop sleeve and surrounding structures, and ensure that the gap between the water stop sleeve and the poured concrete is within 10mm to 30mm;

[0087] Before pouring concrete, the support device should be inspected and accepted.

[0088] Step 4:

[0089] Clean the interface area between the water stop sleeve and the concrete structure, and remove dust, oil, debris and loose materials on the surface;

[0090] Check the contact surface between the waterproof sleeve and the concrete to ensure that there are no cracks or irregular gaps between the waterproof sleeve and the concrete structure. If there are any defects, repair them;

[0091] Choose appropriate high-strength waterproof adhesive according to project needs, including polyurethane waterproof adhesive, epoxy resin waterproof adhesive and acrylic waterproof adhesive;

[0092] Calculate the amount of adhesive based on the adhesive dosage calculation formula, mix the adhesive in proportion, and evenly apply the mixed waterproof adhesive to the gap between the water stop sleeve and the concrete structure. Use a spray tool to apply the adhesive to the entire contact surface and ensure that the thickness is consistent. The applied adhesive covers the entire contact area.

[0093] The calculation formula for the amount of rubber is:

[0094]

[0095] Where V is the volume of the waterproof rubber, D O The outer diameter of the water-stopping casing, D I is the inner diameter of the water-stopping casing, h is the thickness of the applied rubber, that is, the width of the gap between the casing and the concrete;

[0096] Configure the adhesive based on the volume of the waterproof adhesive;

[0097] After each layer is applied, ensure that the adhesive is fully cured before applying the next layer. The thickness of the coating is 1 to 2 mm.

[0098] After applying the adhesive, you can use a scraper to compact the adhesive so that it fits more closely to the contact surface between the waterproof casing and the concrete. After applying, check the joints to ensure that there are no missed areas or uneven areas.

[0099] Determine the curing time according to the type of waterproof adhesive used and the construction environment. Do not disturb the mobile waterproof casing during the curing period to ensure that the adhesive is completely cured.

[0100] Keep the environment dry during the curing period. After curing is completed, check the sealing effect of the waterproof adhesive and conduct a waterproof test through a pressure water test.

[0101] Step 5:

[0102] According to the outer diameter size and design requirements of the water-stop casing, make a steel mesh, install it around the outside of the water-stop casing, and ensure that there is a distance of 50 to 100 mm between the mesh and the casing;

[0103] After installing the steel mesh, pour the concrete. When pouring, make sure that the concrete can fully cover the steel mesh and fill all gaps;

[0104] Use a vibrator to compact the concrete, ensuring that the steel mesh is completely wrapped in the concrete to avoid voids and honeycomb structures;

[0105] After the concrete is poured, it is cured for 7 to 14 days.

[0106] Preferably, check the construction quality of the reinforced part to ensure that the steel mesh is in the correct position, check the arrangement of the steel mesh, the pouring quality of the concrete, and the connection between the water stop sleeve and the concrete, and waterproof the reinforced part.

[0107] Step 6:

[0108] When the concrete strength reaches more than 70% of the design strength, the formwork is removed and the concrete surface is checked after removal to confirm that there is no damage or defect.

[0109] Check whether the concrete surface is flat and smooth, without obvious bubbles, cracks and voids. After the curing period, conduct a strength test on the concrete;

[0110] After the concrete pouring is completed, the construction acceptance is carried out to check whether the entire pre-embedded process meets the design requirements and the tightness of the water stop sleeve and the surrounding structure.

[0111] Construction acceptance specifically includes:

[0112] Review construction records, including concrete pouring time, strength grade, mix ratio and construction technology, check construction plans and design drawings to ensure that the materials, processes and methods used are consistent with design requirements;

[0113] Check the installation of the formwork, support and water-stop sleeve to ensure that the installation direction, elevation and size of the sleeve meet the design requirements, especially the combination requirements of the outer contact surface of the sleeve and the surrounding structure;

[0114] Check whether the water stop sleeve has any deviation or deformation to ensure that it is firmly installed and will not move during the concrete pouring process;

[0115] If there are marks on the sleeve, check whether the marks are consistent with the design requirements to ensure that it is correctly positioned;

[0116] Check the combination of concrete and waterproof sleeve, and use measuring tools to check whether the gap between waterproof sleeve and surrounding structure is uniform;

[0117] Check whether the concrete pouring surface is flat, use instruments to check whether there are bubbles, and ensure that the concrete is tightly combined with the casing to prevent water seepage;

[0118] Check the quality and density of concrete, check the concrete curing and strength, verify the concrete curing records, and conduct concrete strength testing by taking samples on site after the curing period;

[0119] Record the construction process and inspection results, and prepare an acceptance report, which includes the installation position, size and tightness inspection results of the water stop sleeve.

[0120] In summary, the advantages of the present invention are:

[0121] The sealing treatment with high-strength waterproof adhesive ensures that there is no leakage between the water-stop sleeve and the concrete structure, which enhances the waterproof effect and prevents moisture from penetrating through the joints.

[0122] The waterproof casing is reinforced with steel mesh or steel skeleton to enhance the structural stability and compressive strength of the casing, avoiding the influence of external pressure during construction or later use;

[0123] During the construction process, high-precision measuring tools such as laser level and total station are used to ensure that the embedded position and elevation of the water-stop casing meet the design requirements and reduce the adverse consequences caused by construction deviations;

[0124] Strictly control the size of the gap around the water-stop sleeve and the density of the concrete pouring to ensure the construction quality, avoid the appearance of concrete honeycomb structure or voids, and further ensure the strength and waterproofness of the structure;

[0125] Through reasonable reinforcement and sealing treatment, leakage or deformation between the water-stop sleeve and the concrete can be effectively prevented, thereby reducing possible maintenance costs and risks in the later stage. The entire construction method is carried out strictly in accordance with the design drawings and building specifications, which helps to ensure the tightness of the water-stop sleeve and the surrounding structure and that various technical requirements during the construction process meet the standards, thereby ensuring the quality of the project.

[0126] The above shows and describes the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited to the above embodiments. The above embodiments and descriptions only describe the principles of the present invention. The present invention may be subject to various changes and improvements without departing from the spirit and scope of the present invention. These changes and improvements fall within the scope of the present invention. The scope of protection claimed by the present invention is defined by the attached claims and their equivalents.

Claims

1. A construction method for pre-embedded reinforcement of a water-stop casing, characterized in that: include: Determine the embedded position and size of the water-stop casing according to the design drawings and on-site conditions; During the structural construction process, a pre-buried support device is set to stably fix the water-stop sleeve at the predetermined position; Reserve gaps matching the water-stop sleeves in the concrete structure on both sides of the water-stop sleeves, and keep the gap sizes consistent; Use high-strength waterproof rubber to seal around the water-stop sleeve to ensure the sealing effect between the water-stop sleeve and the structure; The outside of the water-stop casing is reinforced with steel mesh to enhance the structural stability and compressive strength of the water-stop casing; Pour concrete into the reserved gap, ensure it is tightly integrated with the structure around the water stop sleeve, and complete the embedding process.

2. A construction method for pre-embedded reinforcement of water-stop casing according to claim 1, characterized in that: Determining the embedded position and size of the water stop sleeve according to the design drawings and on-site conditions specifically includes: Review the design drawings to obtain the type, quantity, installation location, size requirements and embedded depth of the water-stop casing; Check the position of the water stop sleeve according to the requirements in the design drawings and building regulations; According to the design drawings, conduct on-site surveys to check whether there are any obstacles in the construction site and determine the final embedded position of the water-stop sleeve; According to the specifications of the water-stop sleeve provided in the design drawings, measure the outer diameter of the pipeline to ensure that the size of the selected water-stop sleeve can adapt to the predetermined pipeline; Determine the size of the reserved hole according to the outer diameter of the water-stop sleeve, and determine the depth of the embedded hole and the length of the embedded sleeve according to the waterproof requirements of the structure; According to the elevation data in the design drawings, clarify the upper and lower elevations of the embedded water-stop casing to avoid misalignment during construction; Use a laser level to set the center line position of the waterstop sleeve according to the design drawings, and mark it on the structure. Mark the specific embedded position of the waterstop sleeve on the on-site working surface, and mark the size, elevation and direction data.

3. A construction method for pre-embedded reinforcement of water-stop casing according to claim 2, characterized in that: The method of providing a pre-buried support device during the structural construction process to stably fix the water-stop sleeve at a predetermined position specifically includes: Check the water-stop sleeve and embedded position. Before setting up the support device, confirm the specification, model, embedded position and elevation of the water-stop sleeve to ensure that the water-stop sleeve is consistent with the design requirements; Prepare the materials required for the support device according to the size and construction requirements of the water stop sleeve, including steel support frames, temporary support parts, cable ties and fixing clips; Determine the support of the water-stop sleeve, mark the installation position of the support frame near the embedded position of the structure, and ensure that the fixed position of the support frame and the water-stop sleeve are consistent with the design drawings; Use steel tie bands to firmly connect the water-stop sleeve to the support frame. After the support device is installed, use a level and total station to calibrate the position and elevation of the water-stop sleeve to ensure that it is in the predetermined designed position.

4. A construction method for pre-embedded reinforcement of water-stop casing according to claim 3, characterized in that: The step of reserving a gap matching the water stop sleeve in the concrete structure on both sides of the water stop sleeve and maintaining the gap size consistent specifically includes: Check the verticality and horizontality of the water stop sleeve to ensure that its fixed position in the structure meets the construction requirements and that the horizontal deviation is controlled within 5mm and the vertical deviation is controlled within 5mm; Temporarily use steel bars for reinforcement, use binding steel bars to fix the water stop sleeve and surrounding structures, and ensure that the gap between the water stop sleeve and the poured concrete is within 10mm to 30mm; Before pouring concrete, the support device should be inspected and accepted.

5. A construction method for pre-embedded reinforcement of water-stop casing according to claim 4, characterized in that: The sealing treatment using high-strength waterproof rubber around the water-stopping sleeve to ensure the sealing effect between the water-stopping sleeve and the structure specifically includes: Clean the interface area between the water stop sleeve and the concrete structure, and remove dust, oil, debris and loose materials on the surface; Check the contact surface between the waterproof sleeve and the concrete to ensure that there are no cracks or irregular gaps between the waterproof sleeve and the concrete structure. If there are any defects, repair them; Choose appropriate high-strength waterproof adhesive according to project needs, including polyurethane waterproof adhesive, epoxy resin waterproof adhesive and acrylic waterproof adhesive; Calculate the amount of adhesive based on the adhesive dosage calculation formula, mix the adhesive in proportion, and evenly apply the mixed waterproof adhesive to the gap between the water stop sleeve and the concrete structure. Use a spray tool to apply the adhesive to the entire contact surface and ensure that the thickness is consistent. The applied adhesive covers the entire contact area. After each layer is applied, ensure that the adhesive is fully cured before applying the next layer. The thickness of the coating is 1 to 2 mm. After applying the adhesive, you can use a scraper to compact the adhesive so that it fits more closely to the contact surface between the waterproof casing and the concrete. After applying, check the joints to ensure that there are no missed areas or uneven areas. Determine the curing time according to the type of waterproof adhesive used and the construction environment. Do not disturb the mobile waterproof casing during the curing period to ensure that the adhesive is completely cured. Keep the environment dry during the curing period. After curing is completed, check the sealing effect of the waterproof adhesive and conduct a waterproof test through a pressure water test.

6. A construction method for pre-embedded reinforcement of water-stop casing according to claim 5, characterized in that: The calculation formula for the amount of rubber material is as follows: include: The calculation formula for the amount of rubber is: Where V is the volume of the waterproof rubber, D O The outer diameter of the water-stopping casing, D I is the inner diameter of the water-stopping casing, h is the thickness of the applied rubber, that is, the width of the gap between the casing and the concrete; The compound is configured based on the volume of the waterproof compound.

7. A construction method for pre-embedded reinforcement of water-stop casing according to claim 6, characterized in that: The reinforcement treatment on the outside of the water stop sleeve, using a steel mesh for reinforcement to enhance the structural stability and compressive strength of the water stop sleeve specifically includes: According to the outer diameter size and design requirements of the water-stop casing, make a steel mesh, install it around the outside of the water-stop casing, and ensure that there is a 50-100mm gap between the mesh and the casing; After installing the steel mesh, pour the concrete. When pouring, make sure that the concrete can fully cover the steel mesh and fill all gaps; Use a vibrator to compact the concrete, ensuring that the steel mesh is completely wrapped in the concrete to avoid voids and honeycomb structures; After the concrete is poured, it is cured for 7 to 14 days.

8. A construction method for pre-embedded reinforcement of water-stop casing according to claim 7, characterized in that: Check the construction quality of the reinforced part, ensure the correct position of the steel mesh, check the layout of the steel mesh, the pouring quality of the concrete, and the connection between the water stop sleeve and the concrete, and waterproof the reinforced part.

9. A construction method for pre-embedded reinforcement of water-stop casing according to claim 8, characterized in that: The concrete is poured into the reserved gap to ensure close integration with the structure around the water stop sleeve. The pre-embedding process specifically includes: When the concrete strength reaches more than 70% of the design strength, the formwork is removed and the concrete surface is checked after removal to confirm that there is no damage or defect. Check whether the concrete surface is flat and smooth, without obvious bubbles, cracks and voids. After the curing period, conduct a strength test on the concrete; After the concrete pouring is completed, the construction acceptance is carried out to check whether the entire pre-embedded process meets the design requirements and the tightness of the water stop sleeve and the surrounding structure.

10. A construction method for pre-embedded reinforcement of water-stop casing according to claim 9, characterized in that: The construction acceptance specifically includes: Review construction records, including concrete pouring time, strength grade, mix ratio and construction technology, check construction plans and design drawings to ensure that the materials, processes and methods used are consistent with design requirements; Check the installation of formwork, support and water stop sleeve; Record the construction process and inspection results, and prepare an acceptance report, which includes the installation position, size and tightness inspection results of the water stop sleeve.