Work plan management method and device based on intelligent management and control platform

Through the automated management method of the intelligent control platform, the problems of inefficient manual operation and confusion in data statistics in the existing technology are solved, and efficient execution and real-time monitoring of work plans are achieved.

CN119624178APending Publication Date: 2025-03-14GUANGDONG DIANWANG GONGSI YUNFU POWER SUPPLY BUREAU
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202411706893.1
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-11-26
Publication Date
2025-03-14

AI Technical Summary

Technical Problem

In the prior art, work plan management relies on manual operations, is inefficient, error-prone, and data statistics are chaotic, making real-time control of work dynamics impossible.

Method used

The work plan management method based on the intelligent control platform is adopted, and through functions such as automatic acquisition, verification, splitting and dynamic adjustment, the entire process is achieved from annual plan to monthly plan and then to Sunday plan.

Benefits of technology

It significantly improves the execution efficiency of work plans, reduces data errors, optimizes the planning management process, provides reliable guarantees for intelligent work plan management and control, and realizes real-time monitoring of work dynamics.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119624178A_ABST
    Figure CN119624178A_ABST
Patent Text Reader

Abstract

The invention provides a work plan management method and device based on an intelligent management and control platform. The method comprises the following steps: firstly, obtaining an annual work plan, generating a preliminary target file through an automatic importing function, then setting rules according to the work field and category, carrying out verification and error correction on the target file, generating a corrected monthly plan file, then correcting the monthly plan through a temporary work plan, and forming a final weekly and daily work plan. And the completion progress is visually displayed in real time. According to the application, automatic proofreading, automatic splitting and automatic issuing of the annual plan are realized through the intelligent management and control platform, and the corresponding port is set for workers to modify the monthly plan and add the temporary plan, so that automation of planning and overall planning is realized, and the problem that in the prior art, all work planning, distribution and overall planning work are completed manually, and the working efficiency is high is solved. The efficiency is low and the accuracy is difficult to guarantee.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of plan management, and in particular to a work plan management method based on an intelligent management and control platform, a work plan management device based on an intelligent management and control platform, a computer-readable storage medium and an intelligent management and control platform. Background Art

[0002] Effective control of the work plan of the power supply station team is the key to improving work efficiency and standardization. At present, the goal of plan management is to encourage the team to sort out the work process, clarify the task arrangement, optimize resource allocation, and reduce the interference of temporary operations on the overall work through reasonable plan proportion allocation. However, in actual management, the preparation, decomposition and execution of plans still rely on traditional manual methods, especially using Excel as the main tool for plan recording and control. Although this method is intuitive in operation, its limitations are becoming increasingly prominent as the plan level and degree of refinement increase.

[0003] Under the current model, each power supply needs to formulate an annual plan year by year, and manually split it into monthly and weekly plans, which are then handed down to the team for execution. Since the plan involves multi-dimensional classification of work categories, fields, and time, and needs to be synchronized with the data of the asset management system, this process is both time-consuming and labor-intensive, and prone to errors. In the feedback link, the completion of the plan needs to be manually sorted and submitted by the team members, and then manually summarized and counted by the administrator. Various types of data are scattered and the operation is complicated, resulting in low efficiency in the execution and feedback of the plan, and it is impossible to achieve real-time control of work dynamics. In addition, statistical analysis is still based on tables, lacks an intuitive display method, and cannot quickly generate analysis reports for decision-making reference.

[0004] In the existing technology, plan management relies on manual operation, which is inefficient, error-prone, and has chaotic data statistics. Manual screening and synchronization of asset data increases the risk of errors and affects management decisions. The lack of effective tracking and analysis tools cannot support the optimization and monitoring of plan execution, and a more efficient and accurate solution is urgently needed. Summary of the invention

[0005] The main purpose of this application is to provide a work plan management method based on an intelligent management and control platform, a work plan management device based on an intelligent management and control platform, a computer-readable storage medium and an intelligent management and control platform, so as to at least solve the problem in the prior art that all work planning, allocation and coordination work is completed manually, which is inefficient and difficult to ensure accuracy.

[0006] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a work plan management method based on an intelligent management and control platform is provided, including: obtaining a first work plan through a preset interface of the intelligent management and control platform, the first work plan being an annual work plan for a preset area, the first work plan including the execution month, execution team, work field, work category and work content of each work project; mapping the first work plan into an EXCEL file through an automatic import function to obtain a first target file; determining multiple target rules based on the work field and the work category, and verifying and correcting the corresponding first target file based on each of the target rules to obtain a second target file, and multiple target rules The rules include file specifications and corresponding correction methods for different work areas and work categories; based on the second target file, the file is split according to the execution month and the work area to obtain multiple third target files, and the third target file includes the monthly work plan of the preset area; the second work plan is obtained, and based on the second work plan, the third target file is corrected through the automatic import function to obtain a fourth target file, and the second work plan is a temporary work plan for the preset area; based on the fourth target file, the third work plan is released, and the completion progress of the third work plan is displayed in real time and visualized, and the third work plan is a Sunday work plan for the preset area.

[0007] Optionally, through the automatic import function, the first work plan is mapped into an EXCEL file to obtain a first target file, including: performing a pre-verification based on the first work plan, the pre-verification including field integrity check, data format check and logic error check; if the pre-verification fails, issuing a first alarm message, the first alarm message is used to prompt the staff to correct the first work plan; if the pre-verification passes, obtaining a preset template and mapping the fields in the first work plan to the corresponding positions in the preset template to obtain the first target file.

[0008] Optionally, based on each of the target rules, the corresponding first target file is verified and corrected to obtain a second target file, including: parsing the target rules, extracting a preset file format in the target rules, matching the first target file based on the preset file format, and determining that a first preset condition is satisfied when the match passes; parsing the target rules, extracting a preset logical association in the target rules, matching the first target file based on the preset logical association, and determining that a second preset condition is satisfied when the match passes; parsing the target rules, extracting a preset threshold in the target rules, matching a value in the first target file based on the preset threshold, and determining that a third preset condition is satisfied when the match passes; when the first preset condition, the second preset condition and the third preset condition are all satisfied, determining that the first target file has passed the verification, and determining the first target file as the second target file.

[0009] Optionally, based on each of the target rules, the corresponding first target file is checked and corrected to obtain a second target file, and the method further includes: when the first preset condition is not met, marking the first target file according to the target format in the first target file and the preset file format to record the location and type of the file format error, calling the file format mapping rule in the target rule based on the type of the file format error, and correcting the first target file according to the file format mapping rule; when the second preset condition is not met, marking the first target file according to the target logical relationship in the first target file and the preset logical association to record the location and type of the logical relationship error, calling the target rule based on the type of the logical relationship error The first preset correction method in the target rule is used, and the first target file is corrected according to the first preset correction method, the context data in the first target file is retrieved based on the location of the logical relationship error, semantic analysis is performed based on the context data, and the first target file is corrected; when the third preset condition is not satisfied, the first target file is marked according to the target value in the first target file and the preset threshold to record the location and type of the abnormal value error, the second preset correction method in the target rule is retrieved based on the type of the abnormal value error, and the first target file is corrected according to the second preset correction method, the context value is retrieved based on the location of the abnormal value error, and the first target file is corrected based on the context value.

[0010] Optionally, the second target file is split according to the execution month and the work field to obtain multiple third target files, including: splitting the second target file based on the work field to obtain multiple fourth target files; splitting the fourth target file according to the execution month to obtain multiple third target files.

[0011] Optionally, the method further includes: publishing a fourth work plan in the first target file based on the first target file; and publishing a fifth work plan in the third target file based on the third target file.

[0012] Optionally, after publishing the third work plan based on the fourth target file, the method further includes: after the third work plan is completed, synchronizing the third work plan with the asset domain system.

[0013] According to another aspect of the present application, a work plan management device based on an intelligent management and control platform is provided, the device comprising: an acquisition unit, used to acquire a first work plan through a preset interface of the intelligent management and control platform, the first work plan being an annual work plan for a preset area, the first work plan including the execution month, execution team, work field, work category and work content of each work project; a first processing unit, used to map the first work plan into an EXCEL file through an automatic import function to obtain a first target file; a second processing unit, used to determine a plurality of target rules based on the work field and the work category, and to verify and correct the corresponding first target file based on each of the target rules to obtain a second target file, wherein the plurality of target rules include The system includes file specifications for different work areas and work categories and corresponding correction methods; a third processing unit is used to split the second target file according to the execution month and the work area to obtain multiple third target files, and the third target file includes the monthly work plan of the preset area; a fourth processing unit is used to obtain the second work plan, and based on the second work plan, the third target file is corrected by the automatic import function to obtain the fourth target file, and the second work plan is a temporary work plan for the preset area; a publishing unit is used to publish the third work plan based on the fourth target file, and to display the completion progress of the third work plan in real time. The third work plan is a Sunday work plan for the preset area.

[0014] According to another aspect of the present application, a computer-readable storage medium is provided, wherein the computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute any one of the methods described.

[0015] According to another aspect of the present application, an intelligent management and control platform is provided, comprising: one or more processors, a memory, and one or more programs, wherein the one or more programs are stored in the memory and are configured to be executed by the one or more processors, and the one or more programs include methods for executing any one of the described methods.

[0016] Apply the technical solution of this application to realize the automated management of work plans through an intelligent management and control platform. First, obtain the annual work plan and generate a preliminary target file through the automatic import function, then set rules according to the work field and category, verify and correct the target file, generate a revised monthly plan file, and then revise the monthly plan through a temporary work plan to form a final Sunday work plan, and visualize the completion progress in real time. This application is set to realize automatic proofreading, automatic splitting and automatic publishing of the annual plan through an intelligent management and control platform, and set corresponding ports for staff to modify the monthly plan and add temporary plans, realizing the automation of planning and coordination, and solving the problem that all work planning, allocation and coordination work are completed manually in the prior art, which is inefficient and difficult to ensure accuracy. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A hardware structure block diagram of a mobile terminal for work plan management based on an intelligent management and control platform provided in an embodiment of the present application is shown;

[0018] Figure 2 A flow chart of a work plan management method based on an intelligent management and control platform provided according to an embodiment of the present application is shown;

[0019] Figure 3 A structural block diagram of a work plan management device based on an intelligent management and control platform provided according to an embodiment of the present application is shown.

[0020] The above drawings include the following reference numerals:

[0021] 102, processor; 104, memory; 106, transmission device; 108, input and output devices. DETAILED DESCRIPTION

[0022] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.

[0023] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.

[0024] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.

[0025] As introduced in the background technology, the planning management in the prior art relies on manual operation, which is inefficient, error-prone, and has chaotic data statistics. Manual screening and synchronization of asset data increases the risk of errors and affects management decisions. The lack of effective tracking and analysis tools cannot support the optimization and monitoring of plan execution. In order to solve the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy, the embodiments of the present application provide a work plan management method based on an intelligent management and control platform, a work plan management device based on an intelligent management and control platform, a computer-readable storage medium and an intelligent management and control platform.

[0026] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the accompanying drawings in the embodiments of the present invention.

[0027] The method embodiments provided in the embodiments of the present application can be executed in a mobile terminal, a computer terminal or a similar computing device. Taking running on a mobile terminal as an example, Figure 1 1 is a hardware structure block diagram of a mobile terminal of a work plan management method based on an intelligent management and control platform according to an embodiment of the present invention. Figure 1 As shown, the mobile terminal may include one or more ( Figure 1Only one is shown in the figure) a processor 102 (the processor 102 may include but is not limited to a processing device such as a microprocessor MCU or a programmable logic device FPGA) and a memory 104 for storing data, wherein the mobile terminal may also include a transmission device 106 and an input / output device 108 for communication functions. It can be understood by those skilled in the art that Figure 1 The structure shown is for illustration only and does not limit the structure of the mobile terminal. Figure 1 More or fewer components as shown, or with Figure 1 Different configurations are shown.

[0028] The memory 104 can be used to store computer programs, for example, software programs and modules of application software, such as the computer program corresponding to the work plan management method based on the intelligent management and control platform in the embodiment of the present invention. The processor 102 executes various functional applications and data processing by running the computer program stored in the memory 104, that is, the above method is realized. The memory 104 may include a high-speed random access memory, and may also include a non-volatile memory, such as one or more magnetic storage devices, flash memory, or other non-volatile solid-state memory. In some examples, the memory 104 may further include a memory remotely arranged relative to the processor 102, and these remote memories can be connected to the mobile terminal via a network. Examples of the above-mentioned network include but are not limited to the Internet, an intranet, a local area network, a mobile communication network, and a combination thereof. The transmission device 106 is used to receive or send data via a network. The above-mentioned specific examples of the network may include a wireless network provided by a communication provider of the mobile terminal. In one example, the transmission device 106 includes a network adapter (Network Interface Controller, referred to as NIC), which can be connected to other network devices through a base station so as to communicate with the Internet. In one example, the transmission device 106 may be a radio frequency (RF) module, which is used to communicate with the Internet wirelessly.

[0029] In this embodiment, a work plan management method based on an intelligent management and control platform is provided and runs on a mobile terminal, a computer terminal or a similar computing device. It should be noted that the steps shown in the flowchart of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and although the logical order is shown in the flowchart, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0030] Figure 2 Flowchart of the work plan management method based on the intelligent management and control platform according to the embodiment of the present application. Figure 2As shown, the method comprises the following steps:

[0031] Step S201, obtaining a first work plan through a preset interface of the intelligent management and control platform, the first work plan being an annual work plan for a preset region, and the first work plan including the execution month, execution team, work field, work category, and work content of each work item;

[0032] Specifically, the annual work plan for the preset area is obtained through the preset interface of the intelligent management and control platform, including the execution month, execution team, work field, work category and work content of the work project. For example, in the annual work plan of a power supply station, power equipment inspection is required in January, and it is designated to be performed by Team A. It belongs to the "equipment maintenance" work field and the "inspection" work category, and the work content is "transformer equipment inspection". Through the automatic acquisition function, the rapid summary and centralized management of the annual work plan is realized, avoiding data omissions and errors that may be caused by manual entry, and laying a reliable data foundation for the subsequent plan decomposition.

[0033] Step S202, mapping the first work plan into an EXCEL file through an automatic import function to obtain a first target file;

[0034] Specifically, through the automatic import function of the platform, the first work plan is mapped into a structured Excel file to generate the first target file. For example, the above annual plan is imported by classifying by team and month, and the Excel file can automatically generate the header and data content according to "work area-category-month". The unified format of the Excel file facilitates the storage, management and processing of the plan data; the automation of the import process significantly reduces the manual operation steps, improves efficiency, and reduces the complexity of data processing.

[0035] Step S203, determining a plurality of target rules based on the work field and the work category, and performing verification and error correction on the corresponding first target file based on each target rule to obtain a second target file, wherein the plurality of target rules include file specifications and corresponding correction methods for different work fields and work categories;

[0036] Specifically, the second target file refers to a plan file generated based on the first target file (the original annual plan data after import) through the verification and error correction function of the intelligent management and control platform. The second target file is more complete and standardized in content and structure than the first target file, ensuring the accuracy and consistency of the data. It is the basic file for subsequent plan splitting and execution. Furthermore, target rules are set based on work areas and work categories. For example, for the "inspection" category in the "equipment maintenance" field, the rules require that work tasks must specify the equipment number and inspection time. The platform verifies and corrects the first target file according to these rules to generate a second target file. For example, if a record lacks an equipment number, the system automatically prompts to complete it or correct it according to the rules. Through the automatic verification of target rules, the integrity and accuracy of the plan data are ensured, which solves the problems of omissions and errors that are prone to occur in traditional manual inspections and improves the standardization of plans.

[0037] Step S204, splitting the second target file according to execution month and work field to obtain a plurality of third target files, wherein the third target files include monthly work plans for preset regions;

[0038] Specifically, based on the second target file, the third target file is automatically split into monthly plans according to the execution month and work area. For example, the equipment maintenance task in January is split into the transformer inspection task of Team A and the cable line inspection task in February. The platform automatically splits the plan from annual to monthly, which simplifies the workload of managers, eliminates the possible association errors during manual splitting, and improves the efficiency of plan management.

[0039] Step S205, obtaining a second work plan, and modifying the third target file through an automatic import function based on the second work plan to obtain a fourth target file, wherein the second work plan is a temporary work plan for a preset area;

[0040] Specifically, the second work plan (temporary work plan) is obtained, and it is merged and revised with the third target file (monthly plan) through the automatic import function. For example, due to a sudden failure, an emergency maintenance task for a certain power equipment needs to be temporarily added. The system can include the temporary task in the monthly plan and mark it as a "temporary task". The platform provides a dynamic adjustment function, allowing managers to flexibly respond to sudden tasks, ensure the timeliness and accuracy of the monthly plan, and reduce the tedious operations of plan adjustment.

[0041] Step S206: Release a third work plan based on the fourth target file, and visualize the completion progress of the third work plan in real time. The third work plan is a Sunday work plan for a preset area.

[0042] Specifically, based on the fourth target file (revised monthly plan), the Sunday plan is released, and the completion of the plan is displayed in real time through the platform's visualization function. For example, a chart shows that the task completion rate for a certain week is 80%, of which 10% are deferred tasks and 70% are completed tasks. After the Sunday plan is released, the tasks are clearly distributed to each team; through the visual progress display, managers can intuitively understand the execution of the plan, which is convenient for timely adjustments and decisions.

[0043] Through this embodiment, the present application provides a work plan management method based on an intelligent management and control platform, which realizes the automated management of the entire process from annual plan to monthly plan to Sunday plan through functions such as automatic acquisition, verification, splitting and dynamic adjustment. The platform introduces a target rule engine to ensure the integrity and accuracy of the plan data; the automatic splitting function reduces manual operations and improves efficiency; the flexible temporary plan adjustment function meets the management needs of emergency tasks; the visual progress display enables managers to control the completion of tasks in real time and provide data support for scientific decision-making. Compared with traditional manual operations, the method of the present application significantly improves work efficiency, reduces data errors, optimizes the plan management process, and provides reliable guarantees for intelligent work plan management and control. It solves the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy.

[0044] As a possible implementation method, the first work plan is mapped into an EXCEL file through an automatic import function to obtain a first target file, including the following steps:

[0045] Step S301, performing a pre-check based on the first work plan, the pre-check including field integrity check, data format check and logic error check;

[0046] Specifically, data pre-verification is performed first. The pre-verification is intended to ensure the integrity, standardization and accuracy of the first work plan, including field integrity check, data format check and logical error check. For example, the platform will verify whether the required fields (such as execution month, execution team, work area and work content) are filled in completely; verify whether the date field conforms to the standard format (such as YYYY-MM-DD), whether the numeric field is a valid value; and check the logical relationship, such as the time conflict of the tasks of the same team or the matching of the work content with the responsibilities of the execution team. If a record in the plan lacks key fields or the format does not meet the requirements (such as the execution month is empty or the date format is wrong), the platform will capture these problems in time.

[0047] Step S302: If the pre-check fails, a first alarm message is issued, and the first alarm message is used to prompt the staff to revise the first work plan;

[0048] Specifically, if the pre-verification fails, the platform will issue the first alarm message to prompt the staff to correct the plan data. The alarm message clearly points out the problem and provides correction suggestions, such as "The execution team is empty, please add information" or "The execution month exceeds the annual range, please adjust to January to December." The implementation of this function provides timely feedback to the staff, reduces the risk of plan failure caused by data errors, and significantly improves the efficiency of plan preparation.

[0049] Step S303, when the pre-check is passed, obtain the preset template and map the fields in the first work plan to the corresponding positions in the preset template to obtain the first target file.

[0050] Specifically, when the pre-verification passes, the platform will automatically call the preset EXCEL template, map the fields in the first work plan to the corresponding positions in the template, and finally generate the first target file. The mapping process ensures the standardization and availability of the plan data, laying a data foundation for subsequent plan splitting and verification. The template fields can be flexibly configured according to the management needs of different regions or power supply stations. For example, if a power supply station needs to conduct special statistics on equipment inspection tasks, the platform will automatically fill in the relevant information into specific columns of the template.

[0051] Through the above steps, the intelligent import, data verification and template processing of the first work plan were realized, which brought significant beneficial effects. First, the pre-verification function effectively ensured the integrity, accuracy and logical consistency of the data, avoiding plan execution deviations caused by missing or incorrect data; the alarm prompt function further reduced the burden of manual inspection, provided clear correction guidance for staff, and improved work efficiency; finally, the template mapping function improved the compatibility and sharing of plan data through standardized processing methods, and provided strong technical support for the subsequent automatic splitting, verification and synchronization of work plans based on the intelligent management and control platform.

[0052] As a possible implementation, checking and correcting the corresponding first target file based on each target rule to obtain a second target file includes the following steps:

[0053] Step S401, parsing the target rule, extracting the preset file format in the target rule, matching the first target file based on the preset file format, and determining that the first preset condition is satisfied if the match passes;

[0054] Specifically, the platform will parse the preset file format in the target rule and match the first target file. In this process, the platform verifies whether the file complies with the specifications of field naming, column header order and data type. For example, for the annual plan file submitted by the power supply station, the platform requires the "month" field to be in pure digital format, the "shift" field to be a fixed value drop-down box, and the "work area" and "work category" to be filled in according to the prescribed business classification. If the file format does not meet the requirements, the platform will mark the error location and provide correction suggestions.

[0055] Step S402, parsing the target rule, extracting the preset logical association in the target rule, matching the first target file based on the preset logical association, and determining that the second preset condition is satisfied if the match passes;

[0056] Specifically, the platform parses the logical associations in the target rules and checks the logical consistency between the fields in the first target file. For example, if a work task belongs to the field of "equipment maintenance", the "work category" must be "equipment inspection" or "fault handling" and should not be marked as "customer service". If a logical conflict occurs, the platform will automatically identify and generate prompt information to remind staff to adjust unreasonable field matching. Through this logical verification, the platform effectively avoids configuration errors in the planning process and removes potential obstacles to the execution of actual tasks.

[0057] Step S403, parsing the target rule, extracting the preset threshold in the target rule, matching the value in the first target file based on the preset threshold, and determining that the third preset condition is satisfied if the match passes;

[0058] Specifically, the platform performs a match check on the numerical fields in the first target file based on the preset thresholds parsed from the target rules. For example, for the setting of task duration, the platform requires that its range is between 1 and 31 days; for the number of people assigned to a team, it cannot exceed the specified upper limit. If the duration of a record exceeds 31 days or the number of people in a team exceeds the limit, the platform will immediately issue a warning message and generate specific correction suggestions to ensure that the planned data meets the established requirements.

[0059] Step S404: when the first preset condition, the second preset condition and the third preset condition are all satisfied, it is determined that the first target file has passed the verification, and the first target file is determined as the second target file.

[0060] Specifically, when the first target file meets the preset conditions in terms of file format, logical association and numerical threshold, the platform determines that the file has passed the verification and generates the second target file. The second target file is a standardized data file that has undergone strict verification and automated error correction. It has the characteristics of standardized format, rigorous logic and reasonable content, and can be directly used for subsequent monthly and Sunday plan splitting and release.

[0061] It can be seen that this application has significantly improved the accuracy and efficiency of annual work plan data processing through the target rule analysis and multi-level verification functions of the intelligent management and control platform. The platform realizes all-round verification from data format specification to logical association verification to numerical rationality check, solving the problems of low efficiency and easy omission of errors in traditional manual review methods.

[0062] As a possible implementation, checking and correcting the corresponding first target file based on each target rule to obtain the second target file also includes the following steps:

[0063] Step S501, when the first preset condition is not satisfied, marking the first target file according to the target format and the preset file format in the first target file to record the location and type of the file format error, calling the file format mapping rule in the target rule based on the type of the file format error, and correcting the first target file according to the file format mapping rule;

[0064] Specifically, the platform verifies the file format of the first target file based on the target rules. If the file format does not meet the preset conditions, the platform will record the specific error location and error type through marking, and call the file format mapping rules in the target rules for error correction according to the type of file format error. For example, if the date format of a field does not meet the preset requirements (such as the format of "2024-11-01" becomes "2024 / 11 / 01"), the platform will automatically correct it to a format that meets the regulations to ensure data normalization. Through this step, the platform can not only quickly discover format problems, but also automatically correct them, thereby greatly improving the efficiency of data processing.

[0065] Step S502, when the second preset condition is not met, the first target file is marked according to the target logical relationship and the preset logical association in the first target file to record the location and type of the logical relationship error, the first preset correction method in the target rule is retrieved based on the type of the logical relationship error, and the first target file is corrected according to the first preset correction method, the context data in the first target file is retrieved based on the location of the logical relationship error, semantic analysis is performed based on the context data, and the first target file is corrected;

[0066] Specifically, the platform will verify the logical relationship. If the second preset condition is not met, the platform will mark the error position and type in the file according to the target logical relationship and the preset logical association in the first target file, and call the preset correction method in the target rule to correct the error. For example, if there is a logical mismatch between the "work area" and the "work category" of a certain work task (such as the "equipment maintenance" category is mistakenly marked as the "customer service" field), the platform will automatically call the corresponding correction method and correct the logical error based on the context data in the file. By performing semantic analysis on the context, the platform can intelligently identify and correct errors to ensure the logical consistency of the file.

[0067] Step S503, when the third preset condition is not met, the first target file is marked according to the target value and the preset threshold in the first target file to record the location and type of the abnormal value error, the second preset correction method in the target rule is called based on the type of the abnormal value error, and the first target file is corrected according to the second preset correction method, the context value is called based on the location of the abnormal value error, and the first target file is corrected based on the context value.

[0068] Specifically, the platform verifies the values ​​in the file. If the third preset condition is not met (for example, the value exceeds the set reasonable range), the platform will mark the location and type of the abnormal value error, and call the numerical correction method in the target rule to correct the error. For example, if the working hours of a team exceed the set maximum value, the platform will automatically detect and correct it. Through further analysis based on contextual values, the platform can ensure the accuracy and rationality of the data and reduce the possibility of manual intervention.

[0069] Through the above steps, the automated execution significantly improves the efficiency of the work plan formulation and review process, reduces manual intervention, reduces the incidence of human errors, and improves the accuracy of the work plan. The platform's verification and error correction mechanism ensures the high quality of the data, so that the generated second target file can be seamlessly applied to the subsequent work plan decomposition and execution, providing a reliable foundation for the management of the entire work plan.

[0070] As a possible implementation method, the second target file is split according to the execution month and work area to obtain multiple third target files to ensure efficient management and accurate execution of the work plan. The implementation of this step can finely decompose the work plan, making each task more specific and clear, and facilitating subsequent execution and supervision. It includes the following steps:

[0071] Step S601, splitting the second target file based on the work domain to obtain a plurality of fourth target files;

[0072] Specifically, the platform first splits the second target file according to the work field. For example, if the second target file contains multiple work fields, such as power maintenance, equipment maintenance, customer service, etc., the platform will split the data into multiple files according to these fields. For example, tasks related to power maintenance will be split into a separate file, and tasks related to equipment maintenance will be split into another file to ensure that tasks in each field can be managed and executed independently. This step makes the tasks in each work field more focused, making it easier for relevant personnel to arrange work and allocate resources by field.

[0073] Step S602, splitting the fourth target file according to the execution month to obtain a plurality of third target files.

[0074] Specifically, the platform further splits each fourth target file according to the execution month to generate multiple third target files. Each target file corresponds to the work plan for a specific month to ensure that the work tasks match the actual execution time. For example, the platform splits the tasks in the field of "power maintenance" into monthly work plan files, and allocates and arranges specific tasks and goals for each month. In this way, the platform can ensure that the work plan for each month is more detailed and specific, making it easier for the execution team to perform tasks according to the time nodes.

[0075] It can be seen that by splitting the second target file based on work areas and execution months, the platform can break down complex annual work plans into specific monthly plans and ensure that tasks in each work area are managed independently. This splitting method not only improves the pertinence and execution of the work plan, but also enables managers to more accurately grasp the specific work arrangements for each area and month, avoiding redundancy and confusion in the plan.

[0076] As a possible implementation manner, the method further includes the following steps:

[0077] Step S701, publishing the fourth work plan in the first target file based on the first target file;

[0078] Specifically, the platform will publish the fourth work plan to the relevant execution team in a formal form based on the relevant data in the first target file, such as work areas, execution teams, work content, and time nodes. For example, the platform may publish the tasks and arrangements in the field of "power maintenance" as a specific work plan, clarify the personnel allocation and task objectives of the execution team, and ensure that the work can be carried out according to the predetermined plan. This step plays an important role in ensuring the execution of the annual plan, and can help managers and the execution team clarify the work content and objectives of each stage.

[0079] Step S702: Publish the fifth work plan in the third target file based on the third target file.

[0080] Specifically, the platform publishes the fifth work plan based on the third target file. This process further refines the monthly or temporary work plan to ensure that each quarterly or monthly task can be arranged and executed in detail at the weekly or even daily level. The platform publishes a specific fifth work plan based on the task information in the third target file, and clearly allocates tasks to each team according to time nodes. Through this refined work plan release, the platform can ensure that the execution team has clear work goals at each stage, and can monitor the execution of tasks in real time and make timely adjustments.

[0081] It can be seen that by publishing the fourth work plan in the first target file and the fifth work plan in the third target file, the platform can ensure the gradual refinement and hierarchical management of the work plan, thereby improving the accuracy and execution efficiency of the work plan. This phased release of the work plan can help each team clarify its responsibilities and tasks, and avoid execution deviations caused by unclear information or unclear plans.

[0082] As a possible implementation manner, after issuing the third work plan based on the fourth target file, the method further includes:

[0083] After the third work plan is completed, the third work plan is synchronized with the asset domain system.

[0084] Specifically, once the third work plan is completed, the platform will automatically export relevant work data, including work content, execution time, resources and tools used, and match this data with the asset data in the asset domain system. The platform will synchronize this information to the asset domain system based on preset rules and data formats to ensure that the asset data in the system is updated synchronously with the actual work progress. For example, after completing the maintenance task of a certain equipment, the platform will transmit the maintenance status, maintenance time, spare parts used and other information of the equipment to the asset domain system to ensure that the asset management system can accurately reflect the current status of the equipment.

[0085] It can be seen that by synchronizing the third work plan with the asset domain system, the platform can achieve close integration of work plans and asset management, and improve the data consistency and accuracy between work tasks and asset management. This mechanism not only reduces manual intervention and data entry errors, but also automatically updates the information in the asset management system, improving the real-time and accuracy of asset data.

[0086] In order to enable those skilled in the art to more clearly understand the technical solution of the present application, the implementation process of the work plan management method based on the intelligent management and control platform of the present application will be described in detail below in combination with specific embodiments.

[0087] This embodiment relates to a specific work plan management method based on an intelligent management and control platform, including the following steps:

[0088] Step S1: Formulate an annual plan. At the beginning of the year, each power supply station formulates a work plan for each field of the year based on work needs and actual conditions, and specifies the working months and execution teams in the work plan, and clarifies the work content and work requirements for subsequent monthly plans and Sunday plans.

[0089] Step S2: Upload the annual plan. After confirming that the annual plan formulated by each power supply station is correct, each power supply station needs to import it into the platform through EXCEL with one click. The platform will verify and automatically correct the data according to relevant rules, based on the work field and work category, to ensure the accuracy and standardization of the data as much as possible. After the data is imported, the platform can see the relevant imported data, and can make secondary corrections and processing on the data. After confirming that the data is correct, it is necessary to publish the annual plan to form a formal annual work plan that can be executed by the team.

[0090] Step S3: Generate a monthly plan. After the annual plan is released, the platform automatically splits it into monthly plans for each month according to the month and work area of ​​the annual plan. The monthly plan can be modified and deleted, and a temporary plan can be created according to the actual situation. After ensuring that the monthly plan is accurate, the monthly plan is released. After the release, the monthly plan will officially take effect.

[0091] Step S4: Release the Sunday plan. The Sunday plan is released according to the monthly plan. Generally speaking, the source of the Sunday plan is the annual and monthly plan, so generally speaking, the Sunday plan and the annual plan are one-to-one corresponding. The Sunday plan can be specific to the work content and specific execution time. The system controls the completion of the work according to the set execution time. After the Sunday plan is released, the work tasks will be automatically distributed to each team.

[0092] Step S5: Report the Sunday plan. After the Sunday plan is released, each team can report the completion of the work plan on the platform according to the completion of the work tasks. The work completion status is divided into ongoing, completed and deferred. For deferred work tasks, the platform requires that the reason for the delay must be reported. The background can monitor the current execution status of each work task in real time, realizing real work tracking and supervision.

[0093] Step S6: Synchronize the asset domain. For completed tasks, the system will export the asset domain data synchronized with the controllable asset domain with one click. During the export process, the data of the intelligent management and control platform must correspond one-to-one with the data of the asset domain. The platform will automatically match according to relevant rules to form data that can be recognized and approved by the asset domain system, thereby realizing the synchronization of the data of the intelligent management and control platform and the data of the asset domain.

[0094] Step S7: Visual display. When the manager logs into the platform, he can intuitively see the completion status of the entire work plan. The platform displays the completion status of each power supply station's work plan, power supply station comparison chart and other required information and indicator data in the form of charts, so that the manager can understand the execution and completion status of the entire work plan at a glance.

[0095] This embodiment provides a work plan management method based on an intelligent management and control platform, which aims to improve the execution efficiency and management transparency of the work plan. By formulating, uploading and publishing annual, monthly and Sunday plans, the platform ensures that the work tasks at each stage can be accurately implemented and executed. After the data is imported, the accuracy and standardization of the work plan data are guaranteed through intelligent verification and automatic error correction functions, effectively reducing human errors. The automatic generation and adjustment of monthly plans and Sunday plans make the execution of plans more flexible and adaptable. The platform also realizes real-time monitoring of work progress. The team can report the completion of the work in real time. The management personnel can grasp the execution status of the task at any time and make timely adjustments to the deferred tasks. In addition, the platform uses the intelligent synchronization function to correspond to the data of the asset domain system one by one, ensuring the real-time and accuracy of asset management. The visual display function provides managers with a clear work plan execution status, making decision-making more efficient. Overall, this method optimizes the execution process of the work plan through intelligent management means, improves work efficiency, ensures the rational use of resources, and ensures that various tasks are completed on time and in quality.

[0096] It should be noted that the steps shown in the flowcharts of the accompanying drawings can be executed in a computer system such as a set of computer executable instructions, and that, although a logical order is shown in the flowcharts, in some cases, the steps shown or described can be executed in an order different from that shown here.

[0097] The present application embodiment also provides a kind of work plan management device based on intelligent management and control platform. It should be noted that the work plan management device based on intelligent management and control platform of the present application embodiment can be used to execute the work plan management method based on intelligent management and control platform provided by the present application embodiment. The device is used to implement the above-mentioned embodiment and preferred implementation mode, and the description has been made and will not be repeated. As used below, the term "module" can implement a combination of software and / or hardware of a predetermined function. Although the device described in the following embodiments is preferably implemented in software, the implementation of hardware, or a combination of software and hardware is also possible and conceived.

[0098] The following is an introduction to the work plan management device based on the intelligent management and control platform provided in the embodiment of the present application.

[0099] Figure 31 is a structural block diagram of a work plan management device based on an intelligent management and control platform according to an embodiment of the present application. Figure 3 As shown, the device includes: an acquisition unit 10, a first processing unit 20, a second processing unit 30, a third processing unit 40, a fourth processing unit 50 and a publishing unit 60.

[0100] The acquisition unit 10 is used to acquire a first work plan through a preset interface of the intelligent management and control platform. The first work plan is an annual work plan for a preset area. The first work plan includes the execution month, execution team, work field, work category and work content of each work project.

[0101] Specifically, the annual work plan for the preset area is obtained through the preset interface of the intelligent management and control platform, including the execution month, execution team, work field, work category and work content of the work project. For example, in the annual work plan of a power supply station, power equipment inspection is required in January, and it is designated to be performed by Team A. It belongs to the "equipment maintenance" work field and the "inspection" work category, and the work content is "transformer equipment inspection". Through the automatic acquisition function, the rapid summary and centralized management of the annual work plan is realized, avoiding data omissions and errors that may be caused by manual entry, and laying a reliable data foundation for the subsequent plan decomposition.

[0102] The first processing unit 20 is used to map the first work plan into an EXCEL file through an automatic import function to obtain a first target file;

[0103] Specifically, through the automatic import function of the platform, the first work plan is mapped into a structured Excel file to generate the first target file. For example, the above annual plan is imported by classifying by team and month, and the Excel file can automatically generate the header and data content according to "work area-category-month". The unified format of the Excel file facilitates the storage, management and processing of the plan data; the automation of the import process significantly reduces the manual operation steps, improves efficiency, and reduces the complexity of data processing.

[0104] A second processing unit 30 is used to determine a plurality of target rules based on the work field and the work category, and to verify and correct the corresponding first target file based on each target rule to obtain a second target file, wherein the plurality of target rules include file specifications and corresponding correction methods for different work fields and work categories;

[0105] Specifically, the second target file refers to a plan file generated based on the first target file (the original annual plan data after import) through the verification and error correction function of the intelligent management and control platform. The second target file is more complete and standardized in content and structure than the first target file, ensuring the accuracy and consistency of the data. It is the basic file for subsequent plan splitting and execution. Furthermore, target rules are set based on work areas and work categories. For example, for the "inspection" category in the "equipment maintenance" field, the rules require that work tasks must specify the equipment number and inspection time. The platform verifies and corrects the first target file according to these rules to generate a second target file. For example, if a record lacks an equipment number, the system automatically prompts to complete it or correct it according to the rules. Through the automatic verification of target rules, the integrity and accuracy of the plan data are ensured, which solves the problems of omissions and errors that are prone to occur in traditional manual inspections and improves the standardization of plans.

[0106] The third processing unit 40 is used to split the second target file according to the execution month and the work field to obtain a plurality of third target files, wherein the third target file includes a monthly work plan for a preset area;

[0107] Specifically, based on the second target file, the third target file is automatically split into monthly plans according to the execution month and work area. For example, the equipment maintenance task in January is split into the transformer inspection task of Team A and the cable line inspection task in February. The platform automatically splits the plan from annual to monthly, which simplifies the workload of managers, eliminates the possible association errors during manual splitting, and improves the efficiency of plan management.

[0108] The fourth processing unit 50 is used to obtain a second work plan, and to modify the third target file through an automatic import function based on the second work plan to obtain a fourth target file, wherein the second work plan is a temporary work plan for a preset area;

[0109] Specifically, the second work plan (temporary work plan) is obtained, and it is merged and revised with the third target file (monthly plan) through the automatic import function. For example, due to a sudden failure, an emergency maintenance task for a certain power equipment needs to be temporarily added. The system can include the temporary task in the monthly plan and mark it as a "temporary task". The platform provides a dynamic adjustment function, allowing managers to flexibly respond to sudden tasks, ensure the timeliness and accuracy of the monthly plan, and reduce the tedious operations of plan adjustment.

[0110] The publishing unit 60 is used to publish a third work plan based on the fourth target file, and to visualize the completion progress of the third work plan in real time, where the third work plan is a Sunday work plan for a preset area.

[0111] Specifically, based on the fourth target file (revised monthly plan), the Sunday plan is released, and the completion of the plan is displayed in real time through the platform's visualization function. For example, a chart shows that the task completion rate for a certain week is 80%, of which 10% are deferred tasks and 70% are completed tasks. After the Sunday plan is released, the tasks are clearly distributed to each team; through the visual progress display, managers can intuitively understand the execution of the plan, which is convenient for timely adjustments and decisions.

[0112] Through this embodiment, the present application provides a work plan management device based on an intelligent management and control platform, including: an acquisition unit, a first processing unit, a second processing unit, a third processing unit, a fourth processing unit and a publishing unit. The device realizes the automated management of the entire process from annual plans to monthly plans to Sunday plans through functions such as automatic acquisition, verification, splitting and dynamic adjustment. The platform introduces a target rule engine to ensure the integrity and accuracy of the plan data; through the automatic splitting function, manual operations are reduced and efficiency is improved; the flexible temporary plan adjustment function meets the management needs of emergency tasks; the visual progress display enables managers to control the completion of tasks in real time and provide data support for scientific decision-making. Compared with traditional manual operations, it significantly improves work efficiency, reduces data errors, optimizes the plan management process, and provides reliable guarantees for intelligent work plan management and control. It solves the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy.

[0113] As a possible implementation manner, the first processing unit includes: a pre-checking module, a first alarm module and a first target module.

[0114] A pre-check module, used for performing pre-check based on the first work plan, the pre-check including field integrity check, data format check and logic error check;

[0115] Specifically, data pre-verification is performed first. The pre-verification is intended to ensure the integrity, standardization and accuracy of the first work plan, including field integrity check, data format check and logical error check. For example, the platform will verify whether the required fields (such as execution month, execution team, work area and work content) are filled in completely; verify whether the date field conforms to the standard format (such as YYYY-MM-DD), whether the numeric field is a valid value; and check the logical relationship, such as the time conflict of the tasks of the same team or the matching of the work content with the responsibilities of the execution team. If a record in the plan lacks key fields or the format does not meet the requirements (such as the execution month is empty or the date format is wrong), the platform will capture these problems in time.

[0116] A first alarm module is used to issue a first alarm message when the pre-check fails, and the first alarm message is used to prompt the staff to revise the first work plan;

[0117] Specifically, if the pre-verification fails, the platform will issue the first alarm message to prompt the staff to correct the plan data. The alarm message clearly points out the problem and provides correction suggestions, such as "The execution team is empty, please add information" or "The execution month exceeds the annual range, please adjust to January to December." The implementation of this function provides timely feedback to the staff, reduces the risk of plan failure caused by data errors, and significantly improves the efficiency of plan preparation.

[0118] The first target module is used to obtain the preset template and map the fields in the first work plan to the corresponding positions in the preset template to obtain the first target file when the pre-verification passes.

[0119] Specifically, when the pre-verification passes, the platform will automatically call the preset EXCEL template, map the fields in the first work plan to the corresponding positions in the template, and finally generate the first target file. The mapping process ensures the standardization and availability of the plan data, laying a data foundation for subsequent plan splitting and verification. The template fields can be flexibly configured according to the management needs of different regions or power supply stations. For example, if a power supply station needs to conduct special statistics on equipment inspection tasks, the platform will automatically fill in the relevant information into specific columns of the template.

[0120] As a possible implementation manner, the second processing unit includes: a first determining module, a second determining module, a third determining module and a fourth determining module.

[0121] A first determination module is used to parse the target rule, extract the preset file format in the target rule, match the first target file based on the preset file format, and determine that the first preset condition is satisfied if the match passes;

[0122] Specifically, the platform will parse the preset file format in the target rule and match the first target file. In this process, the platform verifies whether the file complies with the specifications of field naming, column header order and data type. For example, for the annual plan file submitted by the power supply station, the platform requires the "month" field to be in pure digital format, the "shift" field to be a fixed value drop-down box, and the "work area" and "work category" to be filled in according to the prescribed business classification. If the file format does not meet the requirements, the platform will mark the error location and provide correction suggestions.

[0123] A second determination module is used to parse the target rule, extract the preset logical association in the target rule, match the first target file based on the preset logical association, and determine that the second preset condition is satisfied if the match passes;

[0124] Specifically, the platform parses the logical associations in the target rules and checks the logical consistency between the fields in the first target file. For example, if a work task belongs to the field of "equipment maintenance", the "work category" must be "equipment inspection" or "fault handling" and should not be marked as "customer service". If a logical conflict occurs, the platform will automatically identify and generate prompt information to remind staff to adjust unreasonable field matching. Through this logical verification, the platform effectively avoids configuration errors in the planning process and removes potential obstacles to the execution of actual tasks.

[0125] A third determination module is used to parse the target rule, extract the preset threshold in the target rule, match the value in the first target file based on the preset threshold, and determine that the third preset condition is satisfied when the match passes;

[0126] Specifically, the platform performs a match check on the numerical fields in the first target file based on the preset thresholds parsed from the target rules. For example, for the setting of task duration, the platform requires that its range is between 1 and 31 days; for the number of people assigned to a team, it cannot exceed the specified upper limit. If the duration of a record exceeds 31 days or the number of people in a team exceeds the limit, the platform will immediately issue a warning message and generate specific correction suggestions to ensure that the planned data meets the established requirements.

[0127] The fourth determination module is used to determine that the first target file passes the verification and determines the first target file as the second target file when the first preset condition, the second preset condition and the third preset condition are all satisfied.

[0128] Specifically, when the first target file meets the preset conditions in terms of file format, logical association and numerical threshold, the platform determines that the file has passed the verification and generates the second target file. The second target file is a standardized data file that has undergone strict verification and automated error correction. It has the characteristics of standardized format, rigorous logic and reasonable content, and can be directly used for subsequent monthly and Sunday plan splitting and release.

[0129] As a possible implementation manner, the second processing unit further includes: a first error correction module, a second error correction module and a third error correction module.

[0130] A first error correction module is used to mark the first target file according to the target format and the preset file format in the first target file to record the location and type of the file format error, retrieve the file format mapping rule in the target rule based on the type of the file format error, and correct the first target file according to the file format mapping rule when the first preset condition is not satisfied;

[0131] Specifically, the platform verifies the file format of the first target file based on the target rules. If the file format does not meet the preset conditions, the platform will record the specific error location and error type through marking, and call the file format mapping rules in the target rules for error correction according to the type of file format error. For example, if the date format of a field does not meet the preset requirements (such as the format of "2024-11-01" becomes "2024 / 11 / 01"), the platform will automatically correct it to a format that meets the regulations to ensure data normalization. Through this step, the platform can not only quickly discover format problems, but also automatically correct them, thereby greatly improving the efficiency of data processing.

[0132] A second error correction module is used to mark the first target file according to the target logical relationship and the preset logical association in the first target file to record the location and type of the logical relationship error when the second preset condition is not met, call the first preset correction method in the target rule based on the type of the logical relationship error, and correct the first target file according to the first preset correction method, call the context data in the first target file based on the location of the logical relationship error, perform semantic analysis based on the context data and correct the first target file;

[0133] Specifically, the platform will verify the logical relationship. If the second preset condition is not met, the platform will mark the error position and type in the file according to the target logical relationship and the preset logical association in the first target file, and call the preset correction method in the target rule to correct the error. For example, if there is a logical mismatch between the "work area" and the "work category" of a certain work task (such as the "equipment maintenance" category is mistakenly marked as the "customer service" field), the platform will automatically call the corresponding correction method and correct the logical error based on the context data in the file. By performing semantic analysis on the context, the platform can intelligently identify and correct errors to ensure the logical consistency of the file.

[0134] The third error correction module is used to mark the first target file according to the target value and the preset threshold in the first target file to record the location and type of the abnormal value error when the third preset condition is not met, call the second preset correction method in the target rule based on the type of the abnormal value error, and correct the first target file according to the second preset correction method, call the context value based on the location of the abnormal value error, and correct the first target file based on the context value.

[0135] Specifically, the platform verifies the values ​​in the file. If the third preset condition is not met (for example, the value exceeds the set reasonable range), the platform will mark the location and type of the abnormal value error, and call the numerical correction method in the target rule to correct the error. For example, if the working hours of a team exceed the set maximum value, the platform will automatically detect and correct it. Through further analysis based on contextual values, the platform can ensure the accuracy and rationality of the data and reduce the possibility of manual intervention.

[0136] As a possible implementation manner, the third processing unit includes: a first splitting module and a second splitting module.

[0137] A first splitting module is used to split the second target file based on the work field to obtain a plurality of fourth target files;

[0138] Specifically, the platform first splits the second target file according to the work field. For example, if the second target file contains multiple work fields, such as power maintenance, equipment maintenance, customer service, etc., the platform will split the data into multiple files according to these fields. For example, tasks related to power maintenance will be split into a separate file, and tasks related to equipment maintenance will be split into another file to ensure that tasks in each field can be managed and executed independently. This step makes the tasks in each work field more focused, making it easier for relevant personnel to arrange work and allocate resources by field.

[0139] The second splitting module is used to split the fourth target file according to the execution month to obtain multiple third target files.

[0140] Specifically, the platform further splits each fourth target file according to the execution month to generate multiple third target files. Each target file corresponds to the work plan for a specific month to ensure that the work tasks match the actual execution time. For example, the platform splits the tasks in the field of "power maintenance" into monthly work plan files, and allocates and arranges specific tasks and goals for each month. In this way, the platform can ensure that the work plan for each month is more detailed and specific, making it easier for the execution team to perform tasks according to the time nodes.

[0141] As a possible implementation manner, the device further includes: a first publishing unit and a second publishing unit.

[0142] A first publishing unit, configured to publish a fourth work plan in the first target file based on the first target file;

[0143] Specifically, the platform will publish the fourth work plan to the relevant execution team in a formal form based on the relevant data in the first target file, such as work areas, execution teams, work content, and time nodes. For example, the platform may publish the tasks and arrangements in the field of "power maintenance" as a specific work plan, clarify the personnel allocation and task objectives of the execution team, and ensure that the work can be carried out according to the predetermined plan. This step plays an important role in ensuring the execution of the annual plan, and can help managers and the execution team clarify the work content and objectives of each stage.

[0144] The second publishing unit is used to publish the fifth work plan in the third target file based on the third target file.

[0145] Specifically, the platform publishes the fifth work plan based on the third target file. This process further refines the monthly or temporary work plan to ensure that each quarterly or monthly task can be arranged and executed in detail at the weekly or even daily level. The platform publishes a specific fifth work plan based on the task information in the third target file, and clearly allocates tasks to each team according to time nodes. Through this refined work plan release, the platform can ensure that the execution team has clear work goals at each stage, and can monitor the execution of tasks in real time and make timely adjustments.

[0146] As a possible implementation manner, the device further includes: a synchronization unit.

[0147] The synchronization unit is used to synchronize the third work plan with the asset domain system after the third work plan is completed.

[0148] Specifically, once the third work plan is completed, the platform will automatically export relevant work data, including work content, execution time, resources and tools used, and match this data with the asset data in the asset domain system. The platform will synchronize this information to the asset domain system based on preset rules and data formats to ensure that the asset data in the system is updated synchronously with the actual work progress. For example, after completing the maintenance task of a certain equipment, the platform will transmit the maintenance status, maintenance time, spare parts used and other information of the equipment to the asset domain system to ensure that the asset management system can accurately reflect the current status of the equipment.

[0149] The work plan management device based on the intelligent management and control platform includes a processor and a memory. The acquisition unit, the first processing unit, the second processing unit, the third processing unit, the fourth processing unit and the publishing unit are all stored in the memory as program units, and the processor executes the program units stored in the memory to implement corresponding functions. The modules are all located in the same processor; or, the modules are located in different processors in any combination.

[0150] The processor includes a kernel, which retrieves the corresponding program unit from the memory. One or more kernels can be set, and the kernel parameters can be adjusted to solve the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy.

[0151] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory, such as read-only memory (ROM) or flash RAM, and the memory includes at least one memory chip.

[0152] An embodiment of the present invention provides a computer-readable storage medium, which includes a stored program, wherein when the program is running, the device where the computer-readable storage medium is located is controlled to execute the work plan management method based on the intelligent management and control platform.

[0153] An embodiment of the present invention provides an intelligent management and control platform, comprising: one or more processors, a memory, and one or more programs, wherein the one or more programs are stored in the memory and are configured to be executed by one or more processors, and the one or more programs include a method for executing the above-mentioned work plan management method based on the intelligent management and control platform.

[0154] An embodiment of the present invention provides a processor, which is used to run a program, wherein the work plan management method based on the intelligent management and control platform is executed when the program is running.

[0155] An embodiment of the present invention provides a communication system, which includes a primary communication domain, a secondary communication domain processor, a memory, and a program stored in the memory and executable on the processor. When the processor executes the program, at least the above-mentioned work plan management method based on the intelligent management and control platform is implemented.

[0156] The present application also provides a computer program product, which, when executed on a data processing device, is suitable for executing a program that initializes at least the above-mentioned work plan management method based on the intelligent management and control platform.

[0157] Obviously, those skilled in the art should understand that the above modules or steps of the present invention can be implemented by a general computing device, they can be concentrated on a single computing device, or distributed on a network composed of multiple computing devices, they can be implemented by a program code executable by a computing device, so that they can be stored in a storage device and executed by the computing device, and in some cases, the steps shown or described can be executed in a different order than here, or they can be made into individual integrated circuit modules, or multiple modules or steps therein can be made into a single integrated circuit module for implementation. Thus, the present invention is not limited to any specific combination of hardware and software.

[0158] Those skilled in the art will appreciate that the embodiments of the present application may be provided as methods, systems, or computer program products. Therefore, the present application may adopt the form of a complete hardware embodiment, a complete software embodiment, or an embodiment in combination with software and hardware. Moreover, the present application may adopt the form of a computer program product implemented in one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) that include computer-usable program code.

[0159] The present application is described with reference to the flowcharts and / or block diagrams of the methods, devices (systems), and computer program products according to the embodiments of the present application. It should be understood that each process and / or box in the flowchart and / or block diagram, as well as the combination of the processes and / or boxes in the flowchart and / or block diagram, can be implemented by computer program instructions. These computer program instructions can be provided to a processor of a general-purpose computer, a special-purpose computer, an embedded processor, or other programmable data processing device to generate a machine, so that the instructions executed by the processor of the computer or other programmable data processing device generate instructions for implementing the processes in the flowchart and / or block diagram. Figure 1 A process or multiple processes and / or boxes Figure 1 A device that provides the functions specified in a block or multiple blocks.

[0160] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture including an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0161] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process in the computer or other programmable device. Figure 1 A process or multiple processes and / or boxes Figure 1 The steps for the functions specified in one or more boxes.

[0162] In a typical configuration, a computing device includes one or more processors (CPU), input / output interfaces, network interfaces, and memory.

[0163] The memory may include non-permanent memory in a computer-readable medium, random access memory (RAM) and / or non-volatile memory in the form of read-only memory (ROM) or flash RAM. The memory is an example of a computer-readable medium.

[0164] Computer readable media include permanent and non-permanent, removable and non-removable media that can be implemented by any method or technology to store information. Information can be computer readable instructions, data structures, program modules or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), static random access memory (SRAM), dynamic random access memory (DRAM), other types of random access memory (RAM), read-only memory (ROM), electrically erasable programmable read-only memory (EEPROM), flash memory or other memory technology, compact disk read-only memory (CD-ROM), digital versatile disk (DVD) or other optical storage, magnetic cassettes, magnetic disk storage or other magnetic storage devices or any other non-transmission media that can be used to store information that can be accessed by a computing device. As defined herein, computer readable media does not include temporary computer readable media (transitory media), such as modulated data signals and carrier waves.

[0165] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.

[0166] From the above description, it can be seen that the above embodiments of the present application achieve the following technical effects:

[0167] 1) The work plan management method based on the intelligent management and control platform of the present application realizes the automated management of the whole process from annual plan to monthly plan to Sunday plan through the functions of automatic acquisition, verification, splitting and dynamic adjustment. The platform introduces the target rule engine to ensure the integrity and accuracy of the plan data; the automatic splitting function reduces manual operation and improves efficiency; the flexible temporary plan adjustment function meets the management needs of emergency tasks; the visual progress display enables managers to control the completion of tasks in real time and provide data support for scientific decision-making. Compared with traditional manual operation, the method of the present application significantly improves work efficiency, reduces data errors, optimizes the plan management process, and provides reliable guarantee for intelligent work plan management and control. It solves the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy.

[0168] 2) The work plan management device based on the intelligent management and control platform of the present application includes: an acquisition unit, a first processing unit, a second processing unit, a third processing unit, a fourth processing unit and a publishing unit. The device realizes the automatic management of the whole process from annual plan to monthly plan to Sunday plan through the functions of automatic acquisition, verification, splitting and dynamic adjustment. The platform introduces a target rule engine to ensure the integrity and accuracy of the plan data; the automatic splitting function reduces manual operation and improves efficiency; the flexible temporary plan adjustment function meets the management needs of emergency tasks; the visual progress display enables managers to control the completion of tasks in real time and provide data support for scientific decision-making. Compared with traditional manual operation, it significantly improves work efficiency, reduces data errors, optimizes the plan management process, and provides reliable guarantee for intelligent work plan management and control. It solves the problem that all work planning, allocation and coordination work is completed manually in the prior art, which is inefficient and difficult to ensure accuracy.

[0169] The above are only preferred embodiments of the present application and are not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.

Claims

1. A work plan management method based on an intelligent management and control platform, characterized in that: include: Obtaining a first work plan through a preset interface of the intelligent management and control platform, the first work plan being an annual work plan for a preset region, the first work plan including the execution month, execution team, work field, work category, and work content of each work item; By using an automatic import function, the first work plan is mapped into an EXCEL file to obtain a first target file; Determine a plurality of target rules based on the work field and the work category, and perform verification and error correction on the corresponding first target file based on each of the target rules to obtain a second target file, wherein the plurality of target rules include file specifications and corresponding correction methods for different work fields and work categories; Based on the second target file, the second target file is split according to the execution month and the work field to obtain a plurality of third target files, wherein the third target files include the monthly work plan of the preset area; Acquire a second work plan, and based on the second work plan, modify the third target file through the automatic import function to obtain a fourth target file, wherein the second work plan is a temporary work plan for the preset area; A third work plan is issued based on the fourth target file, and the completion progress of the third work plan is displayed in real time and visualized, wherein the third work plan is a Sunday work plan for the preset area.

2. The method according to claim 1, characterized in that By using the automatic import function, the first work plan is mapped into an EXCEL file to obtain a first target file, including: Performing a pre-check based on the first work plan, the pre-check including field integrity check, data format check and logic error check; In the case where the pre-check fails, a first alarm message is issued, wherein the first alarm message is used to prompt the staff to revise the first work plan; When the pre-check is passed, a preset template is obtained and fields in the first work plan are mapped to corresponding positions in the preset template to obtain the first target file.

3. The method according to claim 1, characterized in that Based on each of the target rules, the corresponding first target file is verified and error corrected to obtain a second target file, including: Parsing the target rule, extracting a preset file format in the target rule, matching the first target file based on the preset file format, and determining that a first preset condition is satisfied if the match passes; Parsing the target rule, extracting a preset logical association in the target rule, matching the first target file based on the preset logical association, and determining that a second preset condition is satisfied if the match passes; Parsing the target rule, extracting a preset threshold in the target rule, matching the value in the first target file based on the preset threshold, and determining that a third preset condition is satisfied if the match passes; When the first preset condition, the second preset condition and the third preset condition are all satisfied, it is determined that the first target file has passed verification, and the first target file is determined as the second target file.

4. The method according to claim 3, characterized in that: The method further comprises: verifying and correcting the first target file corresponding to each target rule to obtain a second target file; In the case that the first preset condition is not satisfied, marking the first target file according to the target format in the first target file and the preset file format to record the location and type of the file format error, retrieving the file format mapping rule in the target rule based on the type of the file format error, and correcting the error of the first target file according to the file format mapping rule; In the case where the second preset condition is not met, the first target file is marked according to the target logical relationship and the preset logical association in the first target file to record the location and type of the logical relationship error, the first preset correction method in the target rule is retrieved based on the type of the logical relationship error, and the first target file is corrected according to the first preset correction method, the context data in the first target file is retrieved based on the location of the logical relationship error, semantic analysis is performed based on the context data, and the first target file is corrected; When the third preset condition is not met, the first target file is marked according to the target value in the first target file and the preset threshold value to record the location and type of the abnormal value error, the second preset correction method in the target rule is called based on the type of the abnormal value error, and the first target file is corrected according to the second preset correction method, the context value is called based on the location of the abnormal value error, and the first target file is corrected based on the context value.

5. The method according to claim 1, characterized in that Based on the second target file, the second target file is split according to the execution month and the work field to obtain multiple third target files, including: Splitting the second target file based on the work field to obtain a plurality of fourth target files; The fourth target file is split according to the execution month to obtain a plurality of the third target files.

6. The method according to any one of claims 1 to 5, characterized in that The method further comprises: Publishing the fourth work plan in the first target file based on the first target file; The fifth work plan in the third target file is published based on the third target file.

7. The method according to any one of claims 1 to 5, characterized in that After issuing the third work plan based on the fourth target file, the method further includes: After the third work plan is completed, the third work plan is synchronized with the asset domain system.

8. A work plan management device based on an intelligent management and control platform, characterized in that: The device comprises: An acquisition unit, configured to acquire a first work plan through a preset interface of the intelligent management and control platform, wherein the first work plan is an annual work plan for a preset region, and the first work plan includes an execution month, an execution team, a work field, a work category, and a work content of each work item; A first processing unit is used to map the first work plan into an EXCEL file through an automatic import function to obtain a first target file; A second processing unit is used to determine a plurality of target rules based on the work field and the work category, and to perform verification and error correction on the corresponding first target file based on each of the target rules to obtain a second target file, wherein the plurality of target rules include file specifications and corresponding correction methods for different work fields and work categories; A third processing unit is used to split the second target file according to the execution month and the work field to obtain a plurality of third target files, wherein the third target files include the monthly work plan of the preset area; a fourth processing unit, configured to obtain a second work plan, and to modify the third target file through the automatic import function based on the second work plan to obtain a fourth target file, wherein the second work plan is a temporary work plan for the preset area; A publishing unit is used to publish a third work plan based on the fourth target file, and to display the completion progress of the third work plan in real time and visually, wherein the third work plan is a Sunday work plan for the preset area.

9. A computer-readable storage medium, characterized in that: The computer-readable storage medium includes a stored program, wherein when the program is executed, the device where the computer-readable storage medium is located is controlled to execute the method according to any one of claims 1 to 7.

10. An intelligent management and control platform, characterized in that: include: One or more processors, a memory, and one or more programs, wherein the one or more programs are stored in the memory and are configured to be executed by the one or more processors, and the one or more programs include methods for executing any one of claims 1 to 7.