Novel vertical laminated slab assembly type horizontal warehouse structure
The new vertical laminated plate assembly structure solves the problems of insufficient air tightness and thermal insulation of the existing bungalow warehouse, achieves higher warehouse performance and lower construction costs, and simplifies the installation process.
Patent Information
- Application Number
- CN202420442183.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-07
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2034-03-07
AI Technical Summary
Due to poor masonry quality, the existing one-story warehouses have insufficient air tightness and thermal insulation performance, affecting the quality and safety of grain storage.
Adopting a new vertical laminated plate prefabricated structure, including cast-in-place cup foundation, foundation joists, racking columns, retaining walls, wall crown beams and roof double T-plates, prefabricated in the factory and assembled on site, and connected by bolts and sprayed concrete technology to form a laminated plate structure with closely spaced separated joints.
It improves the air tightness and thermal insulation of the warehouse, simplifies the structure and installation process, reduces material consumption and construction costs, shortens the construction period, and reduces the number of waterproofing times.
Smart Images

Figure CN221920462U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of flat warehouses, and in particular relates to a novel vertically laminated plate assembled flat warehouse structure. Background Art
[0002] The most common storage warehouse in grain storage is the bungalow warehouse. At present, the bungalow warehouse in the existing technology usually adopts brick-built enclosure walls, and the bricks are connected by mortar; the bungalow warehouse in the existing technology often has poor masonry quality and insufficient mortar saturation due to the lack of skilled workers, and cracks are easily generated between bricks, which affects the air tightness and thermal insulation performance of the warehouse body, and affects the quality and safety of stored grain. Utility Model Content
[0003] The technical problem to be solved by the utility model is: in view of the shortcomings of the existing technology, a new type of vertical composite plate assembled bungalow warehouse structure is provided, which has a simple structure, is easy to install and maintain, can improve the air tightness and thermal insulation of the warehouse body, and thus ensure the quality and safety of stored grain.
[0004] The technical solution adopted by the utility model to solve the above technical problems is:
[0005] A novel vertical composite plate assembled bungalow warehouse structure mainly comprises: a cast-in-place cup-mouth foundation 01, a foundation joist 02, a frame column 03, a retaining wall 04, a door opening joist, a wall top crown beam 06, and a roof double T-plate 07; the cast-in-place cup-mouth foundation 01 is pre-buried with multiple, and the tops of two adjacent cast-in-place cup-mouth foundations 01 are connected with prefabricated foundation joists 02, the frame columns 03 are provided with multiple and all are inserted on the corresponding cast-in-place cup-mouth foundations 01, a retaining wall 04 is inserted between two adjacent frame columns 03, and a door opening joist is also provided between the frame columns 03 located on both sides of the bungalow warehouse, the retaining wall 04 is composed of multiple wall panel units vertically overlapped, the top of the frame column 03 is provided with a wall top crown beam 06, and the top of the top crown beam 06 is provided with multiple roof double T-plates 07 in sequence in the horizontal direction.
[0006] Preferably, the prefabricated foundation support beam 02 is a simply supported beam with a rectangular cross-section, and the cast-in-place cup-mouth foundation 01 includes a foundation base plate 011, a cup mouth 012 is provided in the middle of the foundation base plate 011, a cup wall 013 is provided on the outer circle of the cup mouth 012, and a plurality of connecting bolts 014 are preset in the cup wall 013.
[0007] Preferably, the foundation joist 02 includes a joist body 023 , and vertical connection holes 021 are provided at both ends of the joist body 023 corresponding to the positions of the connection bolts 014 in the cast-in-place cup-shaped foundation 01 , and a joist groove 022 adapted to the thickness of the enclosing wall 04 is provided on the upper surface of the joist body 023 .
[0008] Preferably, the frame column 03 is a rectangular cross-section concrete column, and the frame column 03 includes a frame column body 035. Both sides of the frame column body 035 are provided with embedded channel steels 032 that are compatible with the thickness of the retaining wall 04. The bottom of the frame column body 035 is inserted into the corresponding cast-in-place cup-mouth foundation 01, and the frame column body 035 is located at a preset height above the cast-in-place cup-mouth foundation 01 and is laterally provided with tension bolt holes 031.
[0009] Preferably, the enclosure wall 04 uses multiple sections of vertical composite plates, which are sequentially inserted into the embedded channel steel 032 of the bent column 03 from bottom to top. After the vertical composite plates are mortared, the composite layers use close-jointed separation joints. The cast-in-place side is constructed after the roof components are hoisted.
[0010] Preferably, the door opening support beam adopts a rectangular cross-section concrete beam with a shallow groove on it to facilitate the installation of the upper composite plate, and the steel bars on both sides are exposed; a section of concrete beam with the same cross-section is prefabricated in the factory at the corresponding position of the adjacent frame column 03, and the steel bars are exposed; the steel bars on both sides are connected by a double spiral sleeve first-level joint with on-site wet connection; and then the concrete is poured.
[0011] Preferably, each section of the wall panel unit of the retaining wall 04 includes a laminated layer 041 and a cast-in-place layer 042, a steel truss 046 is provided in the laminated layer 041, a grouting groove 043 and reserved steel bars 044 are provided at the joint of the wall panel units in the laminated layer 041, an additional steel mesh 045 for the cast-in-place layer is provided between the laminated layer 041 and the cast-in-place layer 042, and a cast-in-place layer steel mesh 047 is provided on the outside of the cast-in-place layer 042.
[0012] Preferably, the wall top crown beam 06 includes a crown beam body 062 with a gutter, and the crown beam body 062 with a gutter is provided with a plurality of reserved connection holes 061. The wall top crown beam 06 is fixedly connected to the top of the frame column 03 by cooperating with the reserved steel bars 036 at the top of the frame column 03 through the reserved connection holes 061.
[0013] Preferably, the wall top crown beam 06 is provided with a plurality of reserved connection holes 061, and the wall top crown beam 06 is fixedly connected to the top of the frame column 03 by cooperating with the column top reserved steel bars 036 at the top of the frame column 03 through the reserved connection holes 061; a parapet is provided above the edge of the wall top crown beam 06 on both sides of the bungalow warehouse.
[0014] Preferably, a plurality of beam top embedded parts 063 are provided on the upper surface of the wall top crown beam 06 , and the roof double T-plate 07 is installed above the wall top crown beam 06 through the beam top embedded parts 063 .
[0015] The specific installation process is as follows:
[0016] First, the bent column 03 is prefabricated in the factory, transported to the site, hoisted and inserted into the cast-in-place cup foundation 01, and concrete is poured to seal the cup. During the solidification of the cup concrete, a temporary connection anchor plate 033 is set between the cup and the bent column to ensure safety.
[0017] Further, the foundation joist 02 is installed, and the reserved holes of the foundation joist are passed through the reserved anchor bolts at the cup mouth and fixed by grouting;
[0018] Furthermore, vertical composite panels of the enclosure wall 04 are inserted into the inner grooves of the embedded angle steels on the sides of the bent columns 03 from bottom to top;
[0019] Further, the door opening joist 05 is installed. The door opening top plate joist needs to be temporarily arranged with vertical support. The joist is hoisted, and the column and joist longitudinal reinforcement are connected with a double spiral sleeve (first-level joint), and concrete is poured; then the remaining composite panels of the upper enclosure wall 04 are installed;
[0020] Furthermore, the top beam 06 of the wall is hoisted, and the reserved hole of the top beam of the wall is aligned with the steel bars leaking from the bent column, and the hole is sealed with grouting;
[0021] Further, the double T-plates 07 of the roof are hoisted, and the double T-plates are arranged in sequence along the eaves wall. After hoisting, they are welded and fixed to the crown beams on the top of the wall, and the joints are sealed with grouting;
[0022] Finally, arrange the steel mesh on the side of the cast-in-place layer of the retaining wall 04 and carry out shotcrete construction.
[0023] Compared with the prior art, the utility model has the following main advantages:
[0024] 1. The utility model provides a new type of vertical composite plate assembled bungalow warehouse structure, which replaces the traditional brickwork method by reasonably setting the positions and connection forms of the cast-in-place cup foundation, foundation support beams, frame columns, enclosure walls, wall top crown beams and roof double T-plates, and can effectively improve the air tightness and thermal insulation of the warehouse body, and the overall structure is simple and easy to install and maintain;
[0025] 2. The main structure of the utility model adopts a large number of factory prefabricated parts, which saves a lot of on-site processes, improves the degree of on-site mechanized construction, reduces the amount of manual construction, and is conducive to safe construction;
[0026] 3. The enclosure wall of the utility model adopts a composite plate structure, which can give full play to the compressive strength of concrete and the tensile strength of steel bars, reduce material consumption, and reduce warehouse construction costs;
[0027] 4. According to the current general regulations, the traditional brick wall enclosure wall needs to be waterproofed twice, while the assembled concrete structure of the utility model only needs one waterproofing, which further saves the cost;
[0028] 5. The utility model adopts a large number of bolt connectors for fixed connection, which can save installation and disassembly time and shorten the warehouse construction period. BRIEF DESCRIPTION OF THE DRAWINGS
[0029] Figure 1 It is an overall schematic diagram of a novel vertical composite board assembled flat warehouse in an embodiment of the utility model;
[0030] Figure 2 It is a plan layout diagram of the cast-in-place cup mouth foundation of a bungalow warehouse in the embodiment of the utility model;
[0031] Figure 3 It is a structural diagram of the cast-in-place cup mouth foundation in the embodiment of the utility model;
[0032] Figure 4 It is a plan view of the flat warehouse frame columns and the surrounding walls in the embodiment of the utility model;
[0033] Figure 5 It is a partial enlarged view of the frame columns and the surrounding wall of the bunk house in the embodiment of the utility model;
[0034] Figure 6 It is a schematic diagram of the connection between the foundation joist and the cast-in-place cup foundation in the embodiment of the utility model;
[0035] Figure 7 This is a schematic diagram of the connection between the rack column and the cast-in-place cup foundation in the embodiment of the utility model;
[0036] Figure 8 It is a cross-sectional view of the enclosure wall in the embodiment of the utility model;
[0037] Fig. 9 It is a schematic diagram of the connection between the wall top crown beam and the frame column in the embodiment of the utility model.
[0038] In the figure: 01-cast-in-place cup-mouth foundation, 011-foundation bottom plate, 012-cup mouth, 013-cup wall, 014-connecting bolts; 02-foundation joist, 021-vertical connection hole, 022-joist pressure groove, 023-joist beam body; 03-frame column, 031-tension bolt hole, 032-embedded channel steel, 033-temporary connection anchor plate, 034-tension bolt, 035-frame column body, 036- Reserved steel bars at the top of the column; 04-retaining wall, 041-overlapping layer, 042-cast-in-place layer, 043-tongue and groove, 044-reserved steel bars at the overlapped layer, 045-additional steel mesh at the cast-in-place layer, 046-reinforcement trusses at the overlapped layer, 047-reinforcement mesh at the cast-in-place layer; 05-parapet; 06-crown beam at the top of the wall, 061-reserved connection holes, 062-crown beam with gutter, 063-embedded parts at the top of the beam; 07-double T-plate on the roof. DETAILED DESCRIPTION
[0039] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the utility model and are not used to limit the utility model. In addition, the technical features involved in each embodiment of the utility model described below can be combined with each other as long as they do not conflict with each other.
[0040] It should be pointed out that, according to the needs of implementation, the various steps / components described in this application can be split into more steps / components, and two or more steps / components or partial operations of steps / components can be combined into new steps / components to achieve the purpose of the present utility model.
[0041] Embodiment 1: This embodiment provides a novel vertical composite plate assembled flat warehouse structure, such as Figures 1 to 9 As shown, it mainly includes: a cast-in-place cup-mouth foundation 01, a foundation joist 02, a frame column 03, a retaining wall 04, a door opening joist, a wall top crown beam 06, and a roof double T-plate 07; the cast-in-place cup-mouth foundation 01 is pre-buried with multiple, and the tops of two adjacent cast-in-place cup-mouth foundations 01 are connected with prefabricated foundation joists 02, the frame columns 03 are provided with multiple and all are inserted on the corresponding cast-in-place cup-mouth foundations 01, a retaining wall 04 is inserted between two adjacent frame columns 03, and a door opening joist is also provided between the frame columns 03 located on both sides of the bungalow warehouse, the retaining wall 04 is composed of multiple wall panel units vertically overlapped, the top of the frame column 03 is provided with a wall top crown beam 06, and the top of the top crown beam 06 is provided with multiple roof double T-plates 07 in sequence in the horizontal direction.
[0042] Furthermore, the prefabricated foundation support beam 02 is a simply supported beam with a rectangular cross-section, and the cast-in-place cup-mouth foundation 01 includes a foundation base plate 011, a cup mouth 012 is provided in the middle of the foundation base plate 011, a cup mouth 012 is provided on the outer circle of the cup mouth 012, and a plurality of connecting bolts 014 are preset in the cup wall 013.
[0043] Furthermore, the foundation joist 02 includes a joist body 023 , and vertical connection holes 021 are provided at both ends of the joist body 023 corresponding to the positions of the connection bolts 014 in the cast-in-place cup-shaped foundation 01 , and a joist groove 022 adapted to the thickness of the enclosing wall 04 is provided on the upper surface of the joist body 023 .
[0044] Furthermore, the frame column 03 is a rectangular cross-section concrete column, and the frame column 03 includes a frame column body 035. Both sides of the frame column body 035 are provided with embedded channel steels 032 that are compatible with the thickness of the retaining wall 04. The bottom of the frame column body 035 is inserted into the corresponding cast-in-place cup-mouth foundation 01, and the frame column body 035 is located at a preset height above the cast-in-place cup-mouth foundation 01 and is horizontally provided with tension bolt holes 031.
[0045] Furthermore, the enclosure wall 04 uses multiple sections of vertical composite plates, which are sequentially inserted into the embedded channel steel 032 of the bent column 03 from bottom to top. After the vertical composite plates are mortared, the composite layers use close-jointed separation joints. The cast-in-place side is constructed after the roof components are hoisted.
[0046] Furthermore, the door opening support beam adopts a rectangular cross-section concrete beam with a shallow groove on it to facilitate the installation of the upper composite plate, and the steel bars on both sides are exposed; a section of concrete beam with the same cross-section is prefabricated in the factory at the corresponding position of the adjacent frame column 03, and the steel bars are exposed; the steel bars on both sides are connected by a double spiral sleeve first-level joint with on-site wet connection; and then the concrete is poured.
[0047] Furthermore, each wall panel unit section of the retaining wall 04 includes a laminated layer 041 and a cast-in-place layer 042, a steel truss 046 is provided in the laminated layer 041, a grouting groove 043 and reserved steel bars 044 are provided at the joint of the wall panel units in the laminated layer 041, an additional steel mesh of the cast-in-place layer 045 is provided between the laminated layer 041 and the cast-in-place layer 042, and a cast-in-place layer steel mesh 047 is provided on the outer side of the cast-in-place layer 042.
[0048] Furthermore, the wall top crown beam 06 is provided with a plurality of reserved connection holes 061, and the wall top crown beam 06 is fixedly connected to the top of the frame column 03 through the reserved connection holes 061 in cooperation with the column top reserved steel bars 036 at the top of the frame column 03; a parapet is provided above the edge of the wall top crown beam 06 on both sides of the bungalow warehouse.
[0049] Furthermore, a plurality of beam top embedded parts 063 are provided on the upper surface of the wall top crown beam 06 , and the roof double T-plate 07 is installed above the wall top crown beam 06 through the beam top embedded parts 063 .
[0050] Embodiment 2: This embodiment provides a novel vertical composite slab assembled bungalow warehouse structure, wherein the cast-in-place cup-mouth foundation 01 adopts an eccentric cast-in-place cup-mouth foundation, specifically including a foundation bottom plate 011, a cup mouth 012, a cup wall 013, and connecting bolts 014, wherein the foundation bottom plate 011 is eccentric to the outside of the warehouse to utilize the column axial force to balance part of the bending moment to reduce the foundation cross section; the frame column 03 is inserted into the cup mouth 012, and after positioning, quick-setting fine stone concrete is poured into the cup mouth to fix the frame column 03 to form the embedded end of the frame column 03; during the stage when the strength of the quick-setting fine stone concrete increases, temporary fixing measures are required to ensure the safety of the frame column 03 during this period; connecting bolts 014 are arranged on the cup wall 013, and the connecting bolts 014 are used to temporarily fix the frame column 03 and also to fix the prefabricated foundation support beam 02.
[0051] Furthermore, the prefabricated foundation support beam 02 is a simply supported beam with a rectangular cross-section, and circular holes are provided at both ends thereof, facing the connecting bolts 014 provided on the cup wall 013. After the holes and the connecting bolts 014 are connected, the holes are grouted and fixed.
[0052] Furthermore, after the prefabricated foundation joist 02 is mortared, the retaining wall 04 is arranged upwards accordingly.
[0053] Furthermore, the bent column 03 is a rectangular cross-section concrete column, with tension bolt holes 031 at its lower end and pre-buried channel steels 032 on both sides as slots for the enclosure wall 04. The longitudinal reinforcement at the top of the column leaks out and can be inserted into the reserved channel of the crown beam 06 at the top of the wall, and then grouting is performed to connect them together;
[0054] Furthermore, the bent column 03 may consider using prestressed reinforcement, arranging prestressed reinforcement on the tension side in the bin to reduce the amount of reinforcement;
[0055] Furthermore, the enclosure wall 04 uses multiple sections of vertical composite plates, which are sequentially inserted into the embedded channel steel 032 of the bent column 03 from bottom to top. After the vertical composite plates are mortared, the composite layers use close-jointed separation joints. The cast-in-place side is constructed after the roof components are hoisted.
[0056] Furthermore, the door opening support beam adopts a rectangular cross-section concrete beam with a shallow groove on it to facilitate the installation of the upper composite plate, and the steel bars on both sides are exposed; a section of concrete beam with the same cross-section is prefabricated in the factory at the corresponding position of the adjacent frame column 03, and the steel bars are exposed; the steel bars on both sides are connected by on-site wet-joined double spiral sleeves (first-level joints); and then the concrete is poured.
[0057] Furthermore, the wall top crown beam 06 adopts a rectangular cross-section concrete beam, wherein the eaves wall top crown beam 06 has a gutter on the side and a parapet on the top of the transverse gable; column reinforcement holes are reserved at the top of the crown beam 06 corresponding to the frame column 03, and after the column top is mortared, it is hoisted with the column reinforcement and grouted to be closed; embedded parts are preset at the corresponding position on the top of the crown beam 06, which are used for welding and fixing with the embedded parts of the roof double T-plate 07.
[0058] Furthermore, the double T-plates 07 of the roof are arranged horizontally, placed on the top of the wall top crown beam 06 in turn, and welded and fixed with the embedded parts preset on the top of the crown beam 06; the joints between the double T-plates are treated by grouting; after the roof components are fixed, the cast-in-place layer of the retaining wall 04 is constructed.
[0059] Furthermore, the cast-in-place layer adopts the shotcrete process, and the cast-in-place layer is finally constructed after the roof is hoisted; the composite board is 6 cm thick, with tongues and grooves on both sides, and the tongues and grooves are grouted and sealed after splicing; the composite board is arranged with prestressed tendons by pre-tensioning method to reduce the amount of steel bars; the inner side of the composite board warehouse is provided with a rough surface so as to be connected with the cast-in-place layer as a whole; steel bars are reserved at the joints of the composite boards for tying additional steel bars; additional steel bars are arranged on the inner side of the composite board warehouse at the joints to adjust and reduce the vertical difference deformation of the upper and lower boards;
[0060] Furthermore, the cast-in-place layer is reinforced with horizontal reinforcement at the turning point to avoid concrete cracking at the corner; the cast-in-place layer adopts the sprayed concrete process and can be constructed in sections and blocks at the same time, and the construction sequence is from bottom to top. After the sprayed concrete is completed, it is smoothed in time.
[0061] Furthermore, all parts of the present application that are not described in detail are the same as the prior art or are implemented using the prior art.
[0062] In summary:
[0063] 1. The utility model provides a new type of vertical composite plate assembled bungalow warehouse structure, which replaces the traditional brickwork method by reasonably setting the positions and connection forms of the cast-in-place cup foundation, foundation support beams, frame columns, enclosure walls, wall top crown beams and roof double T-plates, and can effectively improve the air tightness and thermal insulation of the warehouse body, and the overall structure is simple and easy to install and maintain;
[0064] 2. The main structure of the utility model adopts a large number of factory prefabricated parts, which saves a lot of on-site processes, improves the degree of on-site mechanized construction, reduces the amount of manual construction, and is conducive to safe construction;
[0065] 3. The enclosure wall of the utility model adopts a composite plate structure, which can give full play to the compressive strength of concrete and the tensile strength of steel bars, reduce material consumption, and reduce warehouse construction costs;
[0066] 4. According to the current general regulations, the traditional brick wall enclosure wall needs to be waterproofed twice, while the assembled concrete structure of the utility model only needs one waterproofing, which further saves the cost;
[0067] 5. The utility model adopts a large number of bolt connectors for fixed connection, which can save installation and disassembly time and shorten the warehouse construction period.
[0068] The above embodiments are only used to illustrate the design ideas and features of the utility model, and their purpose is to enable those skilled in the art to understand the content of the utility model and implement it accordingly. The protection scope of the utility model is not limited to the above embodiments. Therefore, any equivalent changes or modifications made based on the principles and design ideas disclosed by the utility model are within the protection scope of the utility model.
Claims
1. A new type of vertical composite plate assembled flat warehouse structure, characterized by: The invention comprises a cast-in-place cup-mouth foundation (01), a foundation support beam (02), a frame column (03), a retaining wall (04), a wall top crown beam (06) and a roof double T-plate (07); the cast-in-place cup-mouth foundation (01) is pre-buried with a plurality of prefabricated foundation support beams (02) connected to the tops of two adjacent cast-in-place cup-mouth foundations (01); the frame column (03) is provided with a plurality of prefabricated foundation support beams (02) and all of them are inserted on the corresponding cast-in-place cup-mouth foundation (01); a retaining wall (04) is inserted between two adjacent frame columns (03); the retaining wall (04) is composed of a plurality of vertically stacked wall panel units; the top of the frame column (03) is provided with a wall top crown beam (06); the top of the top crown beam (06) is provided with a roof double T-plate (07).
2. According to claim 1, the novel vertical composite plate assembled flat warehouse structure is characterized by: The cast-in-place cup-mouth foundation (01) comprises a foundation base plate (011), a cup mouth (012) is provided in the middle of the foundation base plate (011), a cup wall (013) is provided on the outer circle of the cup mouth (012), and a plurality of connection bolts (014) are preset in the cup wall (013).
3. According to claim 2, the novel vertical composite plate assembled flat warehouse structure is characterized by: The foundation joist (02) comprises a joist beam body (023), and vertical connection holes (021) are provided at both ends of the joist beam body (023) corresponding to the positions of the connection bolts (014) in the cast-in-place cup-shaped foundation (01), and a joist pressing groove (022) adapted to the thickness of the enclosure wall (04) is provided on the upper surface of the joist beam body (023).
4. The novel vertical composite plate assembled flat warehouse structure according to claim 3 is characterized by: The frame column (03) comprises a frame column body (035), and embedded channel steels (032) matching the thickness of the surrounding wall (04) are arranged on both sides of the frame column body (035); the bottom of the frame column body (035) is inserted into the corresponding cast-in-place cup-shaped foundation (01), and the frame column body (035) is horizontally provided with tension bolt holes (031) at a preset height above the cast-in-place cup-shaped foundation (01).
5. The novel vertical composite plate assembled flat warehouse structure according to claim 1 is characterized by: Each wall panel unit section of the enclosure wall (04) comprises a laminated layer (041) and a cast-in-place layer (042); a steel truss (046) is provided inside the laminated layer (041); a grouting groove (043) and reserved steel bars (044) are provided at the joint of the wall panel units of the laminated layer (041); an additional steel mesh (045) for the cast-in-place layer is provided between the laminated layer (041) and the cast-in-place layer (042); and a steel mesh (047) for the cast-in-place layer is provided outside the cast-in-place layer (042).
6. The novel vertical composite plate assembled flat warehouse structure according to claim 1 is characterized by: The wall top crown beam (06) comprises a crown beam body (062) with a gutter, and the crown beam body (062) with a gutter is provided with a plurality of reserved connection holes (061). The wall top crown beam (06) cooperates with the column top reserved steel bars (036) at the top of the frame column (03) through the reserved connection holes (061) to be fixedly connected to the top of the frame column (03).
7. The novel vertical composite plate assembled bungalow structure according to claim 6 is characterized by: Parapet walls (05) are arranged above the edges of the top beams (06) of the walls on both sides of the bungalow.
8. The novel vertical composite plate assembled bungalow structure according to claim 6 is characterized by: The upper surface of the wall top crown beam (06) is provided with a plurality of beam top embedded parts (063), and the roof double T plate (07) is installed above the wall top crown beam (06) through the beam top embedded parts (063).