Tunnel large pipe shed positioning device under unfavorable geology

By using a combined device of steel support frames and seamless positioning steel pipes in the broken surrounding rock area, the problems of long construction period of positioning walls and offset steel pipes were solved, and the construction period was shortened and quality assurance was achieved.

CN221920995UActive Publication Date: 2024-10-29SINOHYDRO BUREAU 5
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420029991.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-01-05
Publication Date
2024-10-29
Estimated Expiration
2034-01-05

AI Technical Summary

Technical Problem

In areas with broken surrounding rock, shallow burials, or areas with complex geological conditions, the construction process of positioning walls is complicated and the construction period is long. Moreover, the seamless steel pipe may shift after concrete vibration, affecting the quality of drilling.

Method used

Design a positioning device for large tunnel pipe sheds under adverse geology, including steel support frames and seamless positioning steel pipes laid out along the direction of the tunnel. It is connected through arc-shaped positioning cavities and fixed bolts to ensure the correct positioning of the steel pipes. Shotcrete is used to replace traditional Concrete construction, simplifying the process.

Benefits of technology

It effectively shortens the construction cycle, reduces construction time and safety hazards, avoids the problem of seamless steel pipe offset, and ensures construction quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221920995U_ABST
    Figure CN221920995U_ABST
Patent Text Reader

Abstract

The utility model relates to the field of water-power engineering underground cavern construction devices, and discloses a tunnel large pipe shed positioning device under unfavorable geology, which comprises a plurality of steel support frames, the steel supporting frame comprises a plurality of single-truss supporting frames arranged in the tunnel direction, and the heights of the single-truss supporting frames are sequentially increased in the tunnel direction. The plurality of single-truss support frames are connected into a whole through horizontal connecting rods; the positioning plate is uniformly bent to form a plurality of arc-shaped positioning cavities facing the outer side of the single-truss support frame; a plurality of seamless positioning steel pipes are further included, and a single seamless steel pipe is connected with all the single-truss supporting frames in a hooping mode. According to the device, after the steel supporting frame is erected, concrete is sprayed to manufacture the positioning spraying and mixing wall, traditional conventional concrete construction is replaced, the steps of concrete and the like are omitted, and the construction period is effectively shortened; the fixing plate can be pre-connected with the single-truss supporting frame outside the tunnel, the construction time in the tunnel is further shortened, the construction time is saved, and meanwhile potential safety hazards are reduced.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of underground cavern construction devices for hydropower projects, in particular to a large pipe shed positioning device for a tunnel under poor geology. Background Art

[0002] Pumped storage power stations are mainly composed of upper and lower reservoirs and underground caverns. Large pipe shed construction is mainly used in underground cavern construction. It is a technical measure to prevent the collapse of the tunnel body and the entrance and exit sections and ensure safety during the construction period.

[0003] In recent years, with the development and construction of clean energy, the hydropower industry has become increasingly prosperous, and large pipe shed construction technology has been gradually applied to the treatment of landslides in hydraulic tunnels. The first key process in the construction of large pipe sheds is the construction of guide walls. Conventional guide wall construction is to support the formwork to embed the guide pipe in the concrete wall, which occupies the linear construction period and is extremely unfavorable for the rapid treatment of landslides. At the same time, when large-section tunnel excavation encounters broken surrounding rock areas, shallow buried areas or areas with complex geological conditions, if the conventional positioning wall construction process is followed, the process is complicated and the construction period is long. Long-term construction under complex geology will pose a great safety hazard. In addition, the existing pre-buried seamless steel pipes are usually tied with steel wire ropes. There is a deflection of the seamless steel pipes in the vibration process after pouring concrete, which leads to poor drilling quality in the later stage.

[0004] To this end, a large pipe shed positioning device for tunnels under poor geological conditions is proposed, which can greatly shorten the construction period of the positioning wall, reduce the construction procedures, and ensure the construction quality. Utility Model Content

[0005] The technical problem solved by the utility model is that the existing positioning wall construction technology has the problem of complicated construction process and too long construction period when encountering broken surrounding rock sections, shallow buried sections or sections with complex geological conditions during large-section tunnel excavation, and the existing positioning seamless steel pipe may have the problem of deviation due to concrete vibration.

[0006] In order to solve the above technical problems, the technical solution adopted by the utility model is: a large pipe shed positioning device for a tunnel under poor geological conditions, comprising a plurality of steel support frames arranged along the direction of the tunnel;

[0007] The steel support frame includes a plurality of single support frames arranged along the tunnel direction, and the heights of the single support frames are successively increased along the tunnel direction; the plurality of single support frames are connected by horizontal connecting rods arranged along the tunnel direction;

[0008] The steel support frame also includes a positioning plate arranged on the outer side of the single support frame by a plurality of fixing bolts, the positioning plate matches the shape of the outer edge of the single support frame, and the positioning plate is evenly bent to have a plurality of arc-shaped positioning cavities facing the outer side of the single support frame;

[0009] The steel support frame also includes a plurality of seamless positioning steel pipes arranged along the tunnel direction, and a single seamless steel pipe is connected to all single support frames of the steel support frame by means of an arc-shaped positioning cavity.

[0010] Particularly, a plurality of horizontal connecting rods are provided, and the horizontal connecting rods are evenly distributed on the inner wall of the single support frame.

[0011] Particularly, the single-frame support frame includes vertical sections on both sides and an arc section on the top, and the vertical section and the arc section are connected by a fixed connecting plate.

[0012] Furthermore, the positioning plate covers the entire arc segment and part of the vertical segment.

[0013] Compared with the prior art, the utility model has the following advantages and beneficial effects: the utility model replaces the traditional conventional concrete construction by erecting a steel support frame and then spraying concrete to make a positioning spray-mixed wall, eliminating the need for concrete and other strong steps, and effectively shortening the construction period; in addition, the fixed plate can also be pre-connected with a single support frame outside the tunnel, further shortening the construction time in the tunnel, saving construction time and reducing safety hazards. At the same time, by pre-positioning the seamless steel pipe with the positioning plate, the deflection of the seamless steel pipe pre-buried in the prior art due to the concrete vibration process can be effectively avoided, and the problem of substandard hole quality caused by the deflection of the drilling rig in the later drilling process can be avoided, effectively ensuring the construction quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] Figure 1 It is a cross-sectional structural schematic diagram of the device of the utility model.

[0015] Figure 2 It is a schematic diagram of the cross-sectional structure of the device of the utility model along the tunnel direction.

[0016] Figure 3 for Figure 1 Enlarged structural diagram at A in the middle.

[0017] The meanings of the numbers in the figure are: single-frame support frame—1; horizontal connecting rod—2; positioning plate—3; arc-shaped positioning cavity—31; fixing bolt—4; seamless positioning steel pipe—5; fixed connecting plate—6. DETAILED DESCRIPTION

[0018] The following will clearly and completely describe the technical solutions in the embodiments of the utility model in conjunction with the accompanying drawings in the embodiments of the utility model, so as to have a further understanding of the concept of the utility model, the technical problems solved, the technical features constituting the technical solutions and the technical effects brought about.

[0019] like Figure 1 to Figure 3As shown, the utility model is a tunnel large pipe shed positioning device under bad geological conditions, comprising a plurality of steel support frames arranged along the tunnel direction;

[0020] The steel support frame includes a plurality of single support frames 1 arranged along the tunnel direction, and the height of the single support frames 1 increases in sequence along the tunnel direction; the plurality of single support frames 1 are connected by a horizontal connecting rod 2 arranged along the tunnel direction;

[0021] The steel support frame also includes a positioning plate 3 arranged on the outside of the single support frame 1 through a plurality of fixing bolts 4, the positioning plate 3 matches the shape of the outer edge of the single support frame 1, and the positioning plate 3 is evenly bent to have a plurality of arc-shaped positioning cavities 31 facing the outside of the single support frame 1;

[0022] The steel support frame also includes a plurality of seamless positioning steel pipes 5 arranged along the tunnel direction, and a single seamless positioning steel pipe is connected to all single support frames 1 of the steel support frame through an arc-shaped positioning cavity 31 .

[0023] In a certain embodiment of the utility model, the single-frame support frame is spliced ​​and welded with HW150 steel, and the steel support frame stands on the foundation of the pipe shed positioning wall formed by pouring concrete at the bottom of the tunnel. The positioning plate 3 and the single-frame support frame 1 are connected by fixing bolts 4 to form a support structure that matches the shape of the tunnel. The spacing between each single-frame support frame 1 is the same, and they are arranged inside the positioning spray-mixed wall. The purpose of gradually increasing the height of the single-frame support frame 1 arranged along the tunnel direction is to reserve an external insertion angle of about 5°, which is convenient for fixing the inclination angle of the seamless positioning steel pipe 5 in the later stage.

[0024] As a preferred embodiment, a plurality of horizontal connecting rods 2 are provided, and the horizontal connecting rods 2 are evenly distributed on the inner wall of the single-frame support frame 1 .

[0025] In this embodiment, a plurality of horizontal connecting rods 2 are provided to ensure the connection strength of the steel support frame and to ensure that each horizontal connecting rod 2 is subjected to uniform force in the tunnel direction.

[0026] As a preferred embodiment, the single-frame support frame 1 includes vertical sections on both sides and an arc section on the top, and the vertical section and the arc section are connected by a fixed connecting plate 6.

[0027] In this embodiment, the function of the fixed connecting plate 6 is to facilitate the splicing of the single-frame support frame 1. At the same time, the use of the fixed connecting plate 6 to connect the vertical section and the arc section can ensure that only one specification of arc section is required, and replacing the vertical sections of different heights can ensure that the height of the single-frame support frame 1 is gradually increased.

[0028] As a further embodiment, the positioning plate 3 covers the entire arc segment and part of the vertical segment.

[0029] In this embodiment, by covering the entire arc section and part of the vertical section of the positioning plate 3, the distribution of the seamless positioning steel pipe 5 can be effectively ensured to ensure that the subsequent drilling requirements are met.

[0030] The words “connection” and “fixation” appearing in the description of the present invention may refer to fixed connection, processing and forming, welding, or mechanical connection. The specific meanings of the above terms in the present invention shall be understood according to the specific circumstances.

[0031] In the description of the present invention, the terms "center", "upper", "lower", "horizontal", "inner", "outer", etc., which indicate the orientation or position relationship, are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying a specific orientation that the device or element referred to must have, and therefore cannot be understood as a limitation on the present invention.

[0032] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model, rather than to limit it. Although the utility model has been described in detail with reference to the aforementioned embodiments, ordinary technicians in the field should understand that they can still modify the technical solutions described in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents. However, these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the utility model.

Claims

1. A tunnel large pipe shed positioning device under poor geological conditions, characterized in that: It includes several steel support frames arranged along the tunnel direction; The steel support frame comprises a plurality of single support frames (1) arranged along the tunnel direction, wherein the height of the single support frames (1) increases in sequence along the tunnel direction; the plurality of single support frames (1) are connected via a horizontal connecting rod (2) arranged along the tunnel direction; The steel support frame further comprises a positioning plate (3) arranged on the outside of the single support frame (1) by means of a plurality of fixing bolts (4); the positioning plate (3) matches the shape of the outer edge of the single support frame (1), and the positioning plate (3) is evenly bent to form a plurality of arc-shaped positioning cavities (31) facing the outside of the single support frame (1); The steel support frame also includes a plurality of seamless positioning steel pipes (5) arranged along the tunnel direction, and a single seamless positioning steel pipe (5) is connected to all the single support frames (1) of the steel support frame through an arc-shaped positioning cavity (31).

2. A tunnel large pipe shed positioning device in poor geological conditions as claimed in claim 1, characterized in that: A plurality of horizontal connecting rods (2) are provided, and the horizontal connecting rods (2) are evenly distributed on the inner wall of the single support frame (1).

3. The large pipe shed positioning device for tunnels in poor geological conditions as claimed in claim 1, characterized in that: The single-frame support frame (1) comprises vertical sections on both sides and an arc-shaped section on the top, and the vertical section and the arc-shaped section are connected via a fixed connecting plate (6).

4. A tunnel large pipe shed positioning device in poor geological conditions as claimed in claim 3, characterized in that: The positioning plate (3) covers the entire arc section and part of the vertical section.