Prefabricated part structure for installing distribution box in masonry

By using structures such as concrete pouring layers and mortar joints in the installation of the distribution box, the fixation and gap filling between the distribution box and the masonry are achieved, which solves the problem of structural damage and gaps during the installation of the distribution box and improves the reliability of the installation. and density.

CN221929047UActive Publication Date: 2024-10-29GREENTOWN REAL ESTATE CONSTR & MANAGEMENT GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202323660333.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-29
Publication Date
2024-10-29
Estimated Expiration
2033-12-29

AI Technical Summary

Technical Problem

In the existing technology, when the distribution box is installed in masonry, secondary openings are required, which may cause damage to the structure of the lintel and distribution box, and the gap between the distribution box and the masonry can easily cause the wall to crack.

Method used

The prefabricated structure is adopted, and the lintels and distribution boxes are fixed together through the concrete pouring layer. They are integrally formed before opening holes to avoid structural damage, and the concrete pouring layer and mortar joints are used to ensure that the gaps are dense.

Benefits of technology

It effectively avoids structural damage caused by secondary openings, reduces the gap between the distribution box and the masonry, improves the reliability and compactness of the installation, and prevents wall cracking.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221929047U_ABST
    Figure CN221929047U_ABST
Patent Text Reader

Abstract

The utility model discloses a prefabricated part structure for installing a distribution box in a masonry, which belongs to the field of building masonry and comprises a distribution box body, a lintel is installed on the upper side of the distribution box body, a concrete pouring layer is arranged outside the distribution box body, and the lintel and the distribution box body are fixed through the concrete pouring layer in a pouring mode. An electromechanical pipeline hole communicated with the power distribution box body is formed in the lintel, the lintel and the power distribution box body are fixed together through the concrete pouring layer to achieve integral forming, then a prefabricated part is perforated, and due to the fact that the lintel and the power distribution box body are fixed through concrete in the perforating process, reliability is good, the structure is not prone to being damaged in the perforating process, and the problem that in the prior art, the cost is high is solved. The problems that when the distribution box is installed in a masonry, a lintel needs to be perforated for the second time, so that the lintel and the distribution box structure are possibly damaged, and a gap between the distribution box and the masonry is prone to causing wall cracking are solved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the field of building masonry, in particular to a prefabricated component structure for installing a distribution box in masonry. Background Art

[0002] When a conventional indoor distribution box is buried in a masonry structure, a groove will be reserved at the corresponding position; because the box size is greater than 30cm, a lintel needs to be set above the distribution box. After the box is buried and installed, a hole is opened on the lintel to install the pipes entering and exiting the distribution box, and a secondary hole needs to be opened above the lintel; after the box and pipes are installed, fine stone concrete is used to fill the gap between the distribution box and the masonry.

[0003] There are many quality risks when using this installation method. The large number of electromechanical pipes entering and exiting the distribution box often damages the structural lintel during the secondary opening. The large gap between the masonry and the distribution box causes the gap to be loose, which can easily cause cracks in the wall at the distribution box location.

[0004] For example, the "A distribution box lintel and distribution system" disclosed in the Chinese patent literature has a publication number of CN211548376U, which includes a beam body, a through hole is provided on the beam body, a mounting block adapted to the through hole is provided in the through hole, the mounting block is connected to the beam body, and at least one through pipe is provided through the mounting block. The disadvantage of this patent is that the lintel and the distribution box structure are easily damaged during the opening process of the lintel, and at the same time, when the distribution box is installed, the gap between the lintel and the masonry is easy to cause the gap to be not dense, thereby causing the wall to crack. Utility Model Content

[0005] The utility model aims to overcome the problem in the prior art that when a distribution box is installed in masonry, a secondary hole needs to be drilled in the lintel, which may cause damage to the lintel and the distribution box structure, and the gap between the distribution box and the masonry easily causes wall cracks. A prefabricated structure for installing a distribution box in masonry is provided. During the prefabrication process, the hole in the lintel is drilled to avoid structural damage caused by the secondary hole drilling, and the gap between the distribution box and the masonry can be reduced.

[0006] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0007] The utility model discloses a prefabricated structure in which a distribution box is installed in a masonry, comprising a distribution box body, a lintel installed on the upper side of the distribution box body, a concrete pouring layer provided on the outside of the distribution box body, the lintel and the distribution box body are cast and fixed by the concrete pouring layer, and a mechanical and electrical pipeline hole connected to the distribution box body is provided in the lintel.

[0008] In this solution, the lintel and the distribution box are fixed together by a concrete pouring layer to achieve one-piece molding, and then the prefabricated parts are drilled. Since the two are fixed by concrete when drilling, the reliability is good, and the drilling process is not likely to cause structural damage. In addition, since a concrete pouring layer is provided on the outside of the distribution box, the size of the cast prefabricated parts can be determined according to the space between the masonry for installing the distribution box, and it is not easy to produce excessive gaps between the distribution box and the masonry due to the size of the distribution box.

[0009] Preferably, the outer side of the concrete pouring layer is connected to the masonry through mortar joints.

[0010] Preferably, the width of the lintel is greater than the width of the distribution box.

[0011] Preferably, the concrete pouring layer includes a spacing layer. The spacing layer is located between the lintel and the distribution box. The concrete in the spacing layer can improve the connection strength between the lintel and the distribution box, and avoid damage to the bonding surface between the lintel and the distribution box.

[0012] Preferably, the lintel and the outer side of the power distribution box are connected by angle brackets, so that the lintel and the power distribution box can be pre-fixed, thereby ensuring that the relative position of the lintel and the power distribution box is not easily misaligned during the pouring of the concrete pouring layer.

[0013] Preferably, a supplementary pouring hole is installed in the concrete pouring layer, the feed inlet of the supplementary pouring hole is located on the side of the concrete pouring layer facing the outside of the masonry, and the discharge outlet of the supplementary pouring hole is located on the left or right side of the concrete pouring layer. If there is still a certain gap between the side wall and the masonry after the prefabricated parts are installed in the masonry, the gap can be filled through the supplementary pouring hole.

[0014] Preferably, a detachable plug is provided at the feed inlet of the supplementary pouring hole, and the plug can improve the density between the masonry and the distribution box body, thereby avoiding the cracking of the wall.

[0015] Preferably, the feed inlet of the supplementary pouring hole is provided with an internal thread, and the press plug is provided with an external thread matching the internal thread.

[0016] Therefore, the utility model has the following beneficial effects: (1) during the prefabrication process, the holes in the lintel are opened to avoid structural damage caused by secondary opening, and the gap between the distribution box and the masonry can be reduced; (2) the lintel and the distribution box can be pre-fixed to avoid the relative position misalignment of the two during the pouring process; (3) when there is a gap between the prefabricated part and the masonry, the gap can be filled by supplementary pouring. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1It is a structural schematic diagram of a main viewing direction of the first embodiment of the utility model.

[0018] Figure 2 It is a schematic diagram of the structure of the first embodiment of the utility model in a top view.

[0019] Figure 3 It is a structural schematic diagram of a main viewing direction of the second embodiment of the utility model.

[0020] Figure 4 It is a structural schematic diagram of a main viewing direction of the third embodiment of the utility model.

[0021] In the figure: distribution box body 1 lintel 2 concrete pouring layer 3 mortar joint 4 masonry 5 spacing layer 6 corner code 7 supplementary pouring hole 8 feed inlet 9 discharge outlet 10. DETAILED DESCRIPTION

[0022] The present invention will be further described below in conjunction with the accompanying drawings and specific implementation methods.

[0023] Embodiment 1, as Figure 1-2 As shown, a prefabricated structure in which a distribution box is installed in a masonry 5 includes a distribution box body 1, a lintel 2 is installed on the upper side of the distribution box body 1, a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the lintel 2 and the distribution box body 1 are cast and fixed by the concrete pouring layer 3, and a mechanical and electrical pipeline hole connected to the distribution box body 1 is provided in the lintel 2. The width of the lintel 2 is greater than the width of the distribution box body 1.

[0024] According to the "Code for Acceptance of Construction Quality of Masonry Structure Engineering", a lintel 2 should be set on the upper part of the opening with a width exceeding 300mm. Under normal circumstances, the distribution box body piping needs to pass through the lintel 2. In order to ensure that the lintel 2 is aligned with the hole on the distribution box, it is necessary to drill holes after the lintel 2 is installed on the distribution box body 1, and the drill bit for drilling holes needs to continuously pass through the lintel 2 and the upper side of the distribution box body 1, which can easily cause the lintel 2 to deform. In this scheme, the lintel 2 and the distribution box are fixed together by a concrete pouring layer 3 to achieve one-piece molding, and then the prefabricated parts are opened. Since the two are fixed by concrete when opening the holes, the reliability is good, and the opening process is not easy to cause structural damage. In addition, since a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the size of the cast prefabricated parts can be determined according to the space between the masonry 5 for installing the distribution box, and it is not easy to cause excessive gaps between the distribution box body 1 and the masonry 5 due to the size problem of the distribution box body 1. The electromechanical conduit holes are used to arrange electromechanical circuits so that the electrical components in the distribution box are connected to the pipelines in the masonry 5 .

[0025] During the prefabrication and pouring process, the in and out relationship between the distribution box 1 and the concrete block needs to be strictly controlled. The side of the distribution box 1 facing the outside of the masonry 5, that is, the front side of the distribution box 1, needs to be exposed from the concrete pouring layer 3 by at least 1.5 cm. In this embodiment, the exposed distance is 2 cm, which facilitates the setting of the door hinge of the distribution box 1 and ensures that the opening of the door will not be affected.

[0026] The outer side of the concrete casting layer 3 is connected to the masonry 5 through the mortar joint 4. The mortar joint 4 refers to the mortar layer filled between the masonry 5 and the prefabricated parts when they are built into the masonry 5, that is, the seam line smeared after the mortar is bonded. The mortar joint 4 includes horizontal mortar joints 4 and vertical mortar joints 4. The mortar joints 4 are between the upper and lower sides of the distribution box and the masonry 5, and the mortar joints 4 are between the left and right sides of the distribution box and the masonry 5. When determining the outer dimensions of the concrete casting layer 3 of the prefabricated parts, the size of the reserved space between the masonry 5 and the thickness of the mortar joints 4 need to be comprehensively considered.

[0027] Embodiment 2, as Figure 3 As shown, a prefabricated structure in which a distribution box is installed in a masonry 5 includes a distribution box body 1, a lintel 2 is installed on the upper side of the distribution box body 1, a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the lintel 2 and the distribution box body 1 are cast and fixed by the concrete pouring layer 3, and a mechanical and electrical pipeline hole connected to the distribution box body 1 is provided in the lintel 2. The width of the lintel 2 is greater than the width of the distribution box body 1.

[0028] According to the "Code for Acceptance of Construction Quality of Masonry Structure Engineering", a lintel 2 should be set on the upper part of the opening with a width exceeding 300mm. Under normal circumstances, the distribution box body piping needs to pass through the lintel 2. In order to ensure that the lintel 2 is aligned with the hole on the distribution box, it is necessary to drill holes after the lintel 2 is installed on the distribution box body 1, and the drill bit for drilling holes needs to continuously pass through the lintel 2 and the upper side of the distribution box body 1, which can easily cause the lintel 2 to deform. In this scheme, the lintel 2 and the distribution box are fixed together by a concrete pouring layer 3 to achieve one-piece molding, and then the prefabricated parts are opened. Since the two are fixed by concrete when opening the holes, the reliability is good, and the opening process is not easy to cause structural damage. In addition, since a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the size of the cast prefabricated parts can be determined according to the space between the masonry 5 for installing the distribution box, and it is not easy to cause excessive gaps between the distribution box body 1 and the masonry 5 due to the size problem of the distribution box body 1. The electromechanical conduit holes are used to arrange electromechanical circuits so that the electrical components in the distribution box are connected to the pipelines in the masonry 5 .

[0029] During the prefabrication and pouring process, the in and out relationship between the distribution box 1 and the concrete block needs to be strictly controlled. The side of the distribution box 1 facing the outside of the masonry 5, that is, the front side of the distribution box 1, needs to be exposed from the concrete pouring layer 3 by at least 1.5 cm. In this embodiment, the exposed distance is 2 cm, which facilitates the setting of the door hinge of the distribution box 1 and ensures that the opening of the door will not be affected.

[0030] The outer side of the concrete casting layer 3 is connected to the masonry 5 through the mortar joint 4. The mortar joint 4 refers to the mortar layer filled between the masonry 5 and the prefabricated parts when they are built into the masonry 5, that is, the seam line smeared after the mortar is bonded. The mortar joint 4 includes horizontal mortar joints 4 and vertical mortar joints 4. The mortar joints 4 are between the upper and lower sides of the distribution box and the masonry 5, and the mortar joints 4 are between the left and right sides of the distribution box and the masonry 5. When determining the outer dimensions of the concrete casting layer 3 of the prefabricated parts, the size of the reserved space between the masonry 5 and the thickness of the mortar joints 4 need to be comprehensively considered.

[0031] The concrete pouring layer 3 includes a spacing layer 6, and the spacing layer 6 is located between the lintel 2 and the distribution box 1. The lintel 2 and the outer side of the distribution box 1 are connected by an angle code 7. The concrete in the spacing layer 6 can improve the connection strength between the lintel 2 and the distribution box 1, and avoid damage to the contact surface between the lintel 2 and the distribution box 1 after being stressed. After the spacing layer 6 is set, the lintel 2 and the distribution box 1 are in a state of being completely covered by concrete, and the reliability of their positions is also better. The angle code 7 can realize the pre-fixation of the lintel 2 and the distribution, thereby ensuring that the relative position of the lintel 2 and the distribution box 1 is not easy to be misplaced during the pouring of the concrete pouring layer 3. When the concrete pouring layer 3 is precast, the distribution box 1 and the lintel 2 need to be connected into a whole through the angle code 7, and then hoisted into the prefabricated mold. During the hoisting process, the door of the distribution box 1 is facing upward, and one side of the door is 2 cm higher than the upper part of the mold, thereby achieving the structure described above that the front side of the distribution box 1 is exposed 32 cm from the concrete casting layer.

[0032] Embodiment three, as Figure 4 As shown, a prefabricated structure in which a distribution box is installed in a masonry 5 includes a distribution box body 1, a lintel 2 is installed on the upper side of the distribution box body 1, a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the lintel 2 and the distribution box body 1 are cast and fixed by the concrete pouring layer 3, and a mechanical and electrical pipeline hole connected to the distribution box body 1 is provided in the lintel 2. The width of the lintel 2 is greater than the width of the distribution box body 1.

[0033] According to the "Code for Acceptance of Construction Quality of Masonry Structure Engineering", a lintel 2 should be set on the upper part of the opening with a width exceeding 300mm. Under normal circumstances, the distribution box body piping needs to pass through the lintel 2. In order to ensure that the lintel 2 is aligned with the hole on the distribution box, it is necessary to drill holes after the lintel 2 is installed on the distribution box body 1, and the drill bit for drilling holes needs to continuously pass through the lintel 2 and the upper side of the distribution box body 1, which can easily cause the lintel 2 to deform. In this scheme, the lintel 2 and the distribution box are fixed together by a concrete pouring layer 3 to achieve one-piece molding, and then the prefabricated parts are opened. Since the two are fixed by concrete when opening the holes, the reliability is good, and the opening process is not easy to cause structural damage. In addition, since a concrete pouring layer 3 is provided on the outside of the distribution box body 1, the size of the cast prefabricated parts can be determined according to the space between the masonry 5 for installing the distribution box, and it is not easy to cause excessive gaps between the distribution box body 1 and the masonry 5 due to the size problem of the distribution box body 1. The electromechanical conduit holes are used to arrange electromechanical circuits so that the electrical components in the distribution box are connected to the pipelines in the masonry 5 .

[0034] During the prefabrication and pouring process, the in and out relationship between the distribution box 1 and the concrete block needs to be strictly controlled. The side of the distribution box 1 facing the outside of the masonry 5, that is, the front side of the distribution box 1, needs to be exposed from the concrete pouring layer 3 by at least 1.5 cm. In this embodiment, the exposed distance is 2 cm, which facilitates the setting of the door hinge of the distribution box 1 and ensures that the opening of the door will not be affected.

[0035] The outer side of the concrete casting layer 3 is connected to the masonry 5 through the mortar joint 4. The mortar joint 4 refers to the mortar layer filled between the masonry 5 and the prefabricated parts when they are built into the masonry 5, that is, the seam line smeared after the mortar is bonded. The mortar joint 4 includes horizontal mortar joints 4 and vertical mortar joints 4. The mortar joints 4 are between the upper and lower sides of the distribution box and the masonry 5, and the mortar joints 4 are between the left and right sides of the distribution box and the masonry 5. When determining the outer dimensions of the concrete casting layer 3 of the prefabricated parts, the size of the reserved space between the masonry 5 and the thickness of the mortar joints 4 need to be comprehensively considered.

[0036] The concrete pouring layer 3 includes a spacing layer 6, and the spacing layer 6 is located between the lintel 2 and the distribution box 1. The lintel 2 and the outer side of the distribution box 1 are connected by an angle code 7. The concrete in the spacing layer 6 can improve the connection strength between the lintel 2 and the distribution box 1, and avoid damage to the contact surface between the lintel 2 and the distribution box 1 after being stressed. After the spacing layer 6 is set, the lintel 2 and the distribution box 1 are in a state of being completely covered by concrete, and the reliability of their positions is also better. The angle code 7 can realize the pre-fixation of the lintel 2 and the distribution, thereby ensuring that the relative position of the lintel 2 and the distribution box 1 is not easy to be misplaced during the pouring of the concrete pouring layer 3. When the concrete pouring layer 3 is precast, the distribution box 1 and the lintel 2 need to be connected into a whole through the angle code 7, and then hoisted into the prefabricated mold. During the hoisting process, the door of the distribution box 1 is facing upward, and one side of the door is 2 cm higher than the upper part of the mold, thereby achieving the structure described above that the front side of the distribution box 1 is exposed 32 cm from the concrete casting layer.

[0037] The concrete casting layer 3 is also provided with a supplementary pouring hole 8, the feed port 9 of the supplementary pouring hole 8 is located on the side of the concrete casting layer 3 facing the outside of the masonry 5, and the discharge port 10 of the supplementary pouring hole 8 is located on the left or right side of the concrete casting layer 3. In this embodiment, supplementary pouring holes 8 are built into the concrete casting layers 3 on the left and right sides of the distribution box, wherein the discharge port 10 of the supplementary pouring hole 8 on the left side is located on the left side of the concrete casting layer 3, and the discharge port 10 of the supplementary pouring hole 8 on the right side is located on the right side of the concrete casting layer 3. If there is still a certain gap between the side wall and the masonry 5 after the prefabricated parts are installed in the masonry 5, the gap can be filled through the supplementary pouring hole 8. A detachable plug is provided at the feed port 9 of the supplementary pouring hole 8. An internal thread is provided at the feed port 9 of the supplementary pouring hole 8, and an external thread matching the internal thread is provided on the plug.

[0038] During the casting process of the prefabricated part, the pressure plug is hoisted together with the supplementary pouring hole 8 along with the distribution box 1 for casting, so that the supplementary pouring hole 8 is integrally formed in the prefabricated part. When supplementary pouring is required, the pressure plug is first removed, and then filler is passed into the supplementary pouring hole 8, and then the pressure plug is screwed into the feed port 9 of the supplementary pouring hole 8 through a thread, and the filler in the supplementary pouring hole 8 is compacted into the gap between the prefabricated part and the masonry 5.

Claims

1. A prefabricated structure for installing a distribution box in a masonry, comprising a distribution box body, a lintel is installed on the upper side of the distribution box body, and is characterized in that: A concrete pouring layer is provided on the outside of the distribution box body, the lintel and the distribution box body are cast and fixed by the concrete pouring layer, and an electromechanical pipeline hole communicating with the distribution box body is provided in the lintel.

2. A prefabricated structure for installing a distribution box in masonry according to claim 1, characterized in that: The outer side of the concrete pouring layer is connected with the masonry through mortar joints.

3. The prefabricated structure for installing a distribution box in masonry according to claim 1 is characterized in that: The width of the lintel is greater than the width of the distribution box.

4. The prefabricated structure for installing a distribution box in masonry according to claim 1 is characterized in that: The concrete pouring layer includes a spacing layer, and the spacing layer is located between the lintel and the distribution box body.

5. The prefabricated structure for installing a distribution box in masonry according to claim 1 is characterized in that: The lintel and the outer side of the distribution box are connected via angle brackets.

6. A prefabricated structure for installing a distribution box in masonry according to any one of claims 1 to 5, characterized in that: A supplementary pouring hole is also installed in the concrete pouring layer, the feed inlet of the supplementary pouring hole is located on the side of the concrete pouring layer facing the outside of the masonry, and the discharge outlet of the supplementary pouring hole is located on the left or right side of the concrete pouring layer.

7. A prefabricated structure for installing a distribution box in masonry according to claim 6, characterized in that: A detachable pressing plug is provided at the feeding port of the supplementary pouring hole.

8. A prefabricated structure for installing a distribution box in masonry according to claim 7, characterized in that: The feed inlet of the supplementary pouring hole is provided with an internal thread, and the press plug is provided with an external thread adapted thereto.