Engineering building scaffold

By integrating sliding, transmission, connection and collection mechanisms on the construction rack, the difficulty of collecting construction garbage is solved, and the problem of dim construction environment is solved through lighting, achieving efficient garbage collection and convenient construction results.

CN221957155UActive Publication Date: 2024-11-05QINGHAI CHANGRONG PROJECT MANAGEMENT GRP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202323462889.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2023-12-19
Publication Date
2024-11-05
Estimated Expiration
2033-12-19

AI Technical Summary

Technical Problem

When construction is carried out on the construction rack, it is difficult to collect construction waste and occupy space, affecting construction operations.

Method used

An engineering construction frame is designed, using a combination of sliding mechanism, transmission mechanism, connection mechanism and collection mechanism to achieve efficient garbage collection, and lighting lamps are installed on the top of the railing to provide construction ambient lighting.

Benefits of technology

It realizes efficient collection and convenience of construction operations, avoids the obstacles to construction operations by garbage, and provides lighting support in dim environments.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221957155U_ABST
    Figure CN221957155U_ABST
Patent Text Reader

Abstract

The utility model discloses an engineering building scaffold which comprises a base, a plurality of locking universal wheels are arranged at the bottom of the base, a plurality of electric telescopic rods are fixedly installed at the top of the base, a supporting plate is fixedly installed at the telescopic ends of the electric telescopic rods together, and a handrail is fixedly installed at the top of the supporting plate. A rectangular frame is fixedly installed on the supporting plate in a penetrating mode, a limiting plate is fixedly installed at the bottom of the supporting plate, a collecting mechanism is arranged on the limiting plate, the top of the collecting mechanism abuts against the bottom of the supporting plate, a connecting mechanism is fixedly installed on the side wall of the collecting mechanism, and a transmission mechanism is arranged at the bottom of the supporting plate. The transmission mechanism is connected with the connecting mechanism in an engaged mode, and a sliding mechanism is slidably connected to the rectangular frame. The construction waste collecting device is reasonable in structural design, can collect generated construction waste during construction operation, and does not hinder construction operation of operators.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of engineering construction, in particular to an engineering construction frame. Background Art

[0002] The construction frame is a kind of equipment widely used in the field of construction. During construction, a frame structure construction frame can be formed by assembling multiple construction frame horizontal bars and multiple construction frame vertical bars, which is convenient for construction workers to stand and construct.

[0003] In the prior art, when construction is carried out on a construction scaffold, a lot of construction waste will be generated. Due to the high height of the construction scaffold, the waste cannot be discarded at will. During construction, the operators will carry trash cans to collect the garbage. However, placing the trash cans on the construction scaffold will take up a lot of space, which is easy to hinder the construction of the operators. For this reason, we designed an engineering construction scaffold to solve the above problems. Utility Model Content

[0004] The utility model aims to solve the problems in the prior art and proposes an engineering construction frame.

[0005] In order to achieve the above purpose, the utility model adopts the following technical solutions:

[0006] An engineering construction frame comprises a base, a plurality of locking universal wheels are provided at the bottom of the base, a plurality of electric telescopic rods are fixedly installed at the top of the base, a support plate is fixedly installed at the telescopic ends of the plurality of electric telescopic rods, a railing is fixedly installed at the top of the support plate, a rectangular frame is fixedly installed through the support plate, a limit plate is fixedly installed at the bottom of the support plate, a collecting mechanism is provided on the limit plate, the top of the collecting mechanism is abutted against the bottom of the support plate, a connecting mechanism is fixedly installed on the side wall of the collecting mechanism, a transmission mechanism is provided at the bottom of the support plate, the transmission mechanism is meshedly connected to the connecting mechanism, a sliding mechanism is slidably connected to the rectangular frame, and the sliding mechanism is meshedly connected to the transmission mechanism.

[0007] Preferably, the collecting mechanism comprises two sliding rods which are slidably connected to the limiting plate, and a collecting frame is fixedly installed on the ends of the two sliding rods. A bottom plate is provided in the collecting frame, and a plurality of springs are fixedly connected between the side walls of the collecting frame and the side walls of the limiting plate.

[0008] Preferably, the connection mechanism comprises a fixing frame fixedly mounted on the side wall of the collecting frame, and a second rack is fixedly mounted on the end of the fixing frame.

[0009] Preferably, the transmission mechanism comprises two fixing plates fixedly mounted on the bottom of the support plate, a gear is rotatably connected between the two fixing plates, and the gear is meshingly connected with the second rack.

[0010] Preferably, the sliding mechanism comprises a pull rod slidably connected in the rectangular frame, a first rack is fixedly mounted on the bottom end of the pull rod, and the first rack is meshingly connected with the gear.

[0011] Preferably, a plurality of lighting lamps are fixedly mounted on the top of the railing.

[0012] Compared with the prior art, the utility model has the following beneficial effects:

[0013] 1. Through the setting of sliding mechanism, transmission mechanism, connecting mechanism and collecting mechanism, it can collect the generated construction waste during construction operation without hindering the construction operation of the operator.

[0014] 2. By setting up multiple lighting lamps on the top of the railing, when working in a dim environment, turn on the lighting lamps on the top of the railing to provide lighting for the operator, making it convenient for the operator to carry out construction.

[0015] In summary, the utility model has a reasonable structural design, can collect the generated construction waste during construction operations, and will not hinder the construction operations of operators. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] Figure 1 This is a first-view structural diagram of the construction frame of the engineering building proposed by the utility model;

[0017] Figure 2 A second perspective structural diagram of the construction frame of the engineering building proposed by the utility model;

[0018] Figure 3 It is a schematic diagram of the structure of the collection mechanism;

[0019] Figure 4 is a schematic diagram of the connection between the gear, the first rack and the second rack;

[0020] Figure 5 for Figure 2 A magnified view of the structure in Figure 2.

[0021] In the figure: 1 base, 2 locking universal wheel, 3 electric telescopic rod, 4 support plate, 5 railing, 6 lighting lamp, 7 collection frame, 8 rectangular frame, 9 pull rod, 10 fixed frame, 11 limit plate, 12 sliding rod, 13 spring, 14 fixed plate, 15 gear, 16 first rack, 17 second rack, 18 bottom plate. DETAILED DESCRIPTION

[0022] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all of the embodiments.

[0023] Reference Figure 1-5 The engineering construction frame includes a base 1, a plurality of locking universal wheels 2 are arranged at the bottom of the base 1, a plurality of electric telescopic rods 3 are fixedly installed on the top of the base 1, a support plate 4 is fixedly installed on the telescopic ends of the plurality of electric telescopic rods 3, a railing 5 is fixedly installed on the top of the support plate 4, a plurality of lighting lamps 6 are fixedly installed on the top of the railing 5, and when working in a dim environment, the lighting lamps 6 on the top of the railing 5 are turned on to provide lighting for the operator, so as to facilitate the operator to carry out construction, and a rectangular frame 8 is fixedly installed through the support plate 4, supporting A limiting plate 11 is fixedly installed at the bottom of the plate 4, and a collecting mechanism is provided on the limiting plate 11. The top of the collecting mechanism is against the bottom of the supporting plate 4. The collecting mechanism includes two sliding rods 12 that penetrate and slide on the limiting plate 11. The ends of the two sliding rods 12 are jointly fixedly installed with a collecting frame 7. A bottom plate 18 is provided in the collecting frame 7. The bottom plate 18 in the collecting frame 7 is detachable. When it is necessary to clean the garbage in the collecting frame 7, the operator can remove the bottom plate 18 from the collecting frame 7 for cleaning. A plurality of springs 13 are fixedly connected between the side walls of the collecting frame 7 and the side walls of the limiting plate 11.

[0024] The side wall of the collecting mechanism is fixedly mounted with a connecting mechanism, the connecting mechanism comprises a fixing frame 10 fixedly mounted on the side wall of the collecting frame 7, and a second rack 17 is fixedly mounted on the end of the fixing frame 10;

[0025] A transmission mechanism is provided at the bottom of the support plate 4, and the transmission mechanism is meshed and connected with the connecting mechanism. The transmission mechanism includes two fixed plates 14 fixedly mounted on the bottom of the support plate 4, and a gear 15 is rotatably connected between the two fixed plates 14, and the gear 15 is meshed and connected with the second rack 17;

[0026] A sliding mechanism is slidably connected to the rectangular frame 8, and the sliding mechanism is meshed with the transmission mechanism. The sliding mechanism includes a pull rod 9 slidably connected in the rectangular frame 8, and a first rack 16 is fixedly installed on the bottom end of the pull rod 9. The first rack 16 is meshed with the gear 15. Through the setting of the sliding mechanism, the transmission mechanism, the connecting mechanism and the collecting mechanism, it can collect the generated construction waste during the construction operation without hindering the construction operation of the operator.

[0027] The functional principle of the utility model can be explained through the following operation modes:

[0028] When the operator needs to perform construction operations on the support plate 4, first, the operator unlocks the locking universal wheel 2, pushes the device to the construction site, and then locks the locking universal wheel 2. The operator climbs onto the support plate 4 and starts the extension of the electric telescopic rod 3. The electric telescopic rod 3 drives the operator on the support plate 4 to rise. When the rise reaches a height suitable for construction, the extension of the electric telescopic rod 3 is stopped, and construction can be carried out. When construction waste is generated during construction, the operator pulls the pull rod 9 upward, and the pull rod 9 drives the first rack 16 to move upward, and the first rack 16 drives the gear 15 to rotate, and the gear 15 drives the second rack 17 The second rack 17 slides and drives the collecting frame 7 to slide out from the bottom of the supporting plate 4 through the fixing frame 10. The top of the collecting frame 7 is separated from the obstruction of the bottom of the supporting plate 4. At this time, the operator can put the construction waste into the collecting frame 7. After the construction waste is placed, the operator releases the pull rod 9. At this time, the collecting frame 7 slides back to its original position under the tension of the spring 13. The top of the collecting frame 7 is again against the bottom of the supporting plate 4, and the pull rod 9 is also reset accordingly. When the construction is completed and the construction waste in the collecting frame 7 needs to be cleaned up, the operator removes the bottom plate 18 on the collecting frame 7 to collect and process the construction waste.

[0029] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes within the technical scope disclosed by the present invention according to the technical scheme and the utility model concept of the present invention, which should be covered by the protection scope of the present invention.

Claims

1. A construction frame for an engineering building, comprising a base (1), characterized in that: The bottom of the base (1) is provided with a plurality of locking universal wheels (2); the top of the base (1) is fixedly mounted with a plurality of electric telescopic rods (3); the telescopic ends of the plurality of electric telescopic rods (3) are fixedly mounted with a support plate (4); the top of the support plate (4) is fixedly mounted with a railing (5); a rectangular frame (8) is fixedly mounted through the support plate (4); a limiting plate (11) is fixedly mounted at the bottom of the support plate (4); a collecting mechanism is provided on the limiting plate (11); the top of the collecting mechanism abuts against the bottom of the support plate (4); the collecting mechanism comprises two sliding rods (12) which are slidably connected to the limiting plate (11); the ends of the two sliding rods (12) are fixedly mounted with a collecting frame (7); a bottom plate (18) is provided inside the collecting frame (7); a plurality of springs (18) are fixedly connected between the side walls of the collecting frame (7) and the side walls of the limiting plate (11); 13), a connecting mechanism is fixedly installed on the side wall of the collecting mechanism, and the connecting mechanism includes a fixing frame (10) fixedly installed on the side wall of the collecting frame (7), and a second rack (17) is fixedly installed on the end of the fixing frame (10). A transmission mechanism is provided at the bottom of the support plate (4), and the transmission mechanism is meshed with the connecting mechanism. The transmission mechanism includes two fixing plates (14) fixedly installed on the bottom of the support plate (4), and a gear (15) is rotatably connected between the two fixing plates (14), and the gear (15) is meshed with the second rack (17). A sliding mechanism is slidably connected on the rectangular frame (8), and the sliding mechanism is meshed with the transmission mechanism. The sliding mechanism includes a pull rod (9) slidably connected in the rectangular frame (8), and a first rack (16) is fixedly installed at the bottom end of the pull rod (9), and the first rack (16) is meshed with the gear (15).

2. The construction frame for engineering construction according to claim 1, characterized in that: A plurality of lighting lamps (6) are fixedly mounted on the top of the railing (5).

Citation Information

Cited By

  • Anti-falling construction frame for building construction

    CN224931345U