Charging device for tunnel blasting

By adopting slidingly connected push rod and fill block structure in the tunnel blasting device, the problem of bending and cumbersome construction of the explosion cable is solved, and more efficient transfer of explosives and leads is achieved, reducing failures and construction time during construction .

CN221959394UActive Publication Date: 2024-11-05SINOHYDRO BUREAU 12 CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420469574.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-11
Publication Date
2024-11-05
Estimated Expiration
2034-03-11

AI Technical Summary

Technical Problem

Traditional tunnel blasting devices have poor effectiveness in protecting detonation cables, resulting in the detonation cables that may be bent, there is explosion resistance during construction, and the construction is cumbersome and slow.

Method used

A charging device including a first main pipe and a push rod is designed to transfer explosives or leads into the blasting hole through a slidingly connected push rod, reduce the possibility of leads folding and disengagement by using fill blocks and push plates, and Adapt to different lengths of leads by driving the pad.

Benefits of technology

It effectively reduces the folding and disengagement of leads during the transfer process, improves the convenience and efficiency of construction, and avoids the occurrence of over-excavation of the hole bottom and under-excavation of the hole.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221959394U_ABST
    Figure CN221959394U_ABST
Patent Text Reader

Abstract

The utility model discloses a charging device for tunnel blasting, and relates to the technical field of tunnel blasting construction, the charging device comprises a first main pipe for charging, the end of the first main pipe is open, a partition plate is fixed in the first main pipe, and the bottom of the first main pipe is slidably connected with a push rod. The construction method has the effect of improving the construction efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of tunnel blasting construction, and in particular to a charging device for tunnel blasting. Background Art

[0002] The tunnel perimeter eye is a circle of light blasting holes arranged along the contour line of the tunnel face for controlling tunnel excavation. Its charging structure directly affects the control of tunnel over-excavation and under-excavation. Traditional perimeter eyes generally adopt continuous charging at the bottom of the hole or intermittent charging with simple bamboo strips. During blasting, due to the concentration of charging at the bottom of the hole, the explosive energy cannot be evenly distributed during blasting, resulting in serious over-excavation at the bottom of the hole and "hanging" under-excavation at the hole mouth. When simple bamboo strips are used for connection, the binding is difficult and the construction is cumbersome, the construction is slow and the explosion refusal phenomenon is serious.

[0003] In the process of realizing the above application, the inventors found that there are at least the following problems in this technology: the existing device is less effective in protecting the detonating cord, and the detonating cord may bend after entering the blasting hole, which may lead to detonation failure and inconvenience the construction process. Utility Model Content

[0004] In order to facilitate the construction process, the present application provides a charging device for tunnel blasting.

[0005] The present application provides a charging device for tunnel blasting that adopts the following technical solution:

[0006] A charging device for tunnel blasting comprises a first main pipe for charging, wherein the end of the first main pipe is open, a partition plate is fixed inside the first main pipe, and a push rod is slidably connected to the bottom of the first main pipe.

[0007] By adopting the above technical solution, a push rod is slidably connected to the bottom of the first main pipe. During use, the first tube body is loaded with explosives and the first tube body is inserted into the blasting hole. The explosives or guide wire in the first main pipe is transferred to the blasting hole by controlling the movement of the push rod. Since the first main pipe is rigidly arranged, the possibility of the guide wire being folded and damaged during the transfer process is reduced.

[0008] Optionally, a pushing plate is fixed to the end of the pushing rod, and a first through hole is formed on the side wall of the first main pipe, and the first through hole is communicated with the space where the pushing plate is located.

[0009] By adopting the above technical solution, during use, charge is loaded through the first through hole. After the charge is loaded, the push plate is driven to move by controlling the push rod. Since the diameter of the push plate is larger than the diameter of the push rod, it is convenient to push the guide wire and the like to move during the construction process.

[0010] Optionally, a second through hole is opened on the side wall of the first main pipe and the second through hole is symmetrical with the first through hole about the end surface of the partition plate, a filling tube is fixed to the side wall of the first main pipe and the filling tube is connected with the second through hole, and a plurality of filling blocks are placed in the filling tube.

[0011] By adopting the above technical solution, a filling tube is fixed to the side wall of the first main pipe and is connected to the second through hole. A plurality of filling blocks are placed in the filling tube. The filling blocks in the filling tube can enter the blasting hole through the first main pipe. The filling blocks are in a compressed state in the first main pipe and abut against the inner wall of the blasting hole after entering the blasting hole, thereby reducing the possibility of the guide wire detaching from the blasting hole.

[0012] Optionally, a blocking rod for pushing the filling block is slidably disposed at the bottom of the first main pipe, a blocking block is fixed to the end of the blocking rod, and the blocking block and the pushing plate are symmetrically disposed about the partition plate.

[0013] By adopting the above technical solution, the blocking rod is driven to move, thereby driving the blocking block to move, so as to facilitate pushing the filling block into the blasting hole.

[0014] Optionally, the end of the filling tube facing away from the first main tube is opened, a push rod is slidably arranged inside the filling tube, and a buffer pad is fixed to the side wall of the push rod.

[0015] By adopting the above technical solution, the filling block in the filling tube can be transferred to the first tube body by pushing the push rod, thereby facilitating the construction process.

[0016] Optionally, a positioning rod is detachably provided at the end of the first main pipe, a positioning hole for penetrating the positioning rod is formed at the end of the first main pipe, and the positioning rod is slidably connected to an inner side wall of the positioning hole.

[0017] By adopting the above technical solution, since the positioning rod is slidably connected to the inner wall of the positioning hole, during the construction process, the length of the positioning rod extending outside the positioning hole can be adjusted by adjusting the length of the positioning rod in the positioning hole. The positioning rod abuts against the inner bottom of the blasting hole, thereby reducing the possibility of the first main pipe directly abutting against the inner wall of the blasting hole, resulting in the inability to transfer the guide wire, etc. into the blasting hole.

[0018] Optionally, a movement guide surface for facilitating the movement of the first main pipe is formed at the end of the first main pipe.

[0019] By adopting the above technical solution, a movement guide surface is provided at the end of the first main pipe, so that the first main pipe is conveniently inserted into the blasting hole.

[0020] Optionally, a driving pad is fixed to the side wall of the push plate, and a plurality of driving protrusions are fixed to the side wall of the driving pad.

[0021] By adopting the above technical solution, when the guide wire is too long, the protruding side wall is driven to contact the side wall of the guide wire. Due to the presence of the driving pad, the friction between the driving pad and the side wall of the guide wire can also drive the guide wire to move, which is convenient for adapting to guide wires of different lengths.

[0022] In summary, the present application includes at least one of the following beneficial technical effects:

[0023] 1. A push rod is slidably connected to the bottom of the first main pipe. During use, the first pipe body is loaded with explosives and inserted into the blasting hole. The explosives or guide wires in the first main pipe are transferred to the blasting hole by controlling the movement of the push rod. Since the first main pipe is rigidly arranged, the possibility of folding and damage of the guide wires during the transfer process is reduced;

[0024] 2. When the guide wire is too long, the side wall of the protrusion is driven to contact the side wall of the guide wire. Due to the presence of the driving pad, the friction between the driving pad and the side wall of the guide wire can also drive the guide wire to move, which is convenient for adapting to guide wires of different lengths. At the same time, due to the presence of the filling block, the guide wire will not slip outside the blasting hole. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] Figure 1 It is a schematic diagram of the main structure of an embodiment of the present application.

[0026] Figure 2 It is a cross-sectional view of the positions of the first through hole and the second through hole.

[0027] Description of reference numerals:

[0028] 1. First main pipe; 2. Partition plate; 3. Push rod; 4. First through hole; 5. Second through hole; 6. Filling pipe; 7. Filling block; 8. Sealing rod; 9. Sealing block; 10. Push rod; 11. Buffer pad; 12. Positioning rod; 13. Positioning hole; 14. Motion guide surface; 15. Driving pad; 16. Driving protrusion; 17. Push plate. DETAILED DESCRIPTION

[0029] The following is combined with Figure 1-2 This application is described in further detail.

[0030] The present application embodiment discloses a charging device for tunnel blasting. Figure 1 and Figure 2The charging device for tunnel blasting includes a first main pipe 1, which is used to load explosives or guide wires, etc. The end of the first main pipe 1 is open, and a push hole is opened at the bottom of the first main pipe 1. The push hole penetrates the bottom of the first main pipe 1 along the axis direction of the first main pipe 1. A push rod 3 is passed through the push hole, and the push rod 3 can slide in the push hole along the axis direction of the first main pipe 1, that is, the push rod 3 is slidably connected to the bottom of the first main pipe 1. A partition plate 2 is fixed to the inner side wall of the first main pipe 1 by bolts. The partition plate 2 divides the interior of the first main pipe 1 into two parts. The partition plate 2 is used to reduce the internal space of the first main pipe 1, thereby reducing the possibility of a large shaking amplitude of the explosive or the guide wire in the first main pipe 1.

[0031] Reference Figure 1 and Figure 2 A push plate 17 is fixed to the end of the part of the push rod 3 placed inside the first main pipe 1 by an integral molding method, and a first through hole 4 is opened on the side wall of the first main rod. The first through hole 4 penetrates the side wall of the first main pipe 1 and connects the first through hole 4 with the space where the push plate 17 is located. Material can be loaded at the first through hole 4, and at the same time, the side wall of the push plate 17 does not contact the inner wall of the first main pipe 1, so the movement of the push plate 17 will not affect the loading process. During filling, the guide wire can be placed on the end face of the push plate 17 to control the movement of the push rod 3, thereby driving the movement of the guide wire to complete the filling.

[0032] Reference Figure 1 and Figure 2 A second through hole 5 is provided on the side wall of the first main pipe 1. The second through hole 5 is symmetrical with the first through hole 4 about the end face of the partition plate 2. At the same time, the second through hole 5 passes through the side wall of the first main pipe 1. The diameter of the second through hole 5 is larger than the diameter of the first through hole 4. A filling tube 6 is fixed to the side wall of the first main pipe 1 by bolts. The axial direction of the filling tube 6 is perpendicular to the axial direction of the first main pipe 1. At the same time, the interior of the filling tube 6 is connected with the second through hole 5, so that the filling tube 6 is connected with the interior of the first main pipe 1. A plurality of filling blocks 7 are placed in the filling tube 6. In this embodiment, the filling blocks 7 are made of sponge material and are in a compressed state in the filling blocks 7. The end of the filling tube 6 away from the first main pipe 1 is opened, and a push rod 10 is slidably arranged in the filling tube 6. The push rod 10 can slide in the filling tube 6 along the axial direction of the filling tube 6. A buffer pad 11 is fixed to the side wall of the push rod 10 by bonding. The buffer pad 11 is made of rubber material. The buffer pad 11 contacts the inner side wall of the filling tube 6 and the buffer pad 11 and the inner side wall of the filling tube 6 are interference fit, so that the friction between the two is relatively large. The push rod 10 will not slide when not affected by external force, and the filling block 7 in the filling pipe 6 can be transferred to the first main pipe 1 by controlling the movement of the push rod 10 .

[0033] Reference Figure 1 and Figure 2A blocking hole is provided at the bottom of the first main pipe 1, and the blocking hole penetrates the first main pipe 1 along the axial direction of the first main pipe 1. A blocking rod 8 is inserted in the blocking hole, and the blocking rod 8 can slide in the blocking hole along the axial direction of the first main pipe 1, that is, the blocking rod 8 is slidably arranged at the bottom of the first main pipe 1, and the blocking rod 8 is used to push the filling block 7 to move in the first main pipe 1 and push it to the outside of the first main pipe 1. Since the filling block 7 is in a compressed state, the filling block 7 can be stretched to fix the guide wire in the hole without damaging the guide wire. A blocking block 9 is fixed at the end of the blocking rod 8 by an integrated molding method. The blocking block 9 and the pushing plate 17 are symmetrically arranged about the partition plate 2. The blocking block 9 can be driven to move by controlling the movement of the blocking rod 8, thereby pushing the filling block 7 to move.

[0034] Reference Figure 1 and Figure 2 A positioning hole 13 is provided on the end surface of the first main pipe 1 which is open, and the axial direction of the positioning hole 13 is the same as that of the first main pipe 1. A positioning rod 12 is inserted into the positioning hole 13 and the positioning rod 12 can slide in the positioning hole 13 along the axial direction of the first main pipe 1, that is, the positioning rod 12 is slidably connected to the inner wall of the positioning hole 13, and the positioning rod 12 is threadedly connected to the inner wall of the positioning hole 13. By rotating the positioning rod 12, the positioning rod 12 can be driven to slide in the positioning hole 13. By controlling the length of the part of the positioning rod 12 placed outside the positioning hole 13, the length of the first main pipe 1 penetrating into the blasting hole can be controlled. The end of the positioning rod 12 abuts against the inner bottom of the blasting hole, thereby reducing the possibility that the end of the first main pipe 1 directly abuts against the inner bottom of the blasting hole and cannot be filled; a movement guide surface 14 is provided at the end of the first main pipe 1, and the movement guide surface 14 facilitates the movement of the first main pipe 1, reducing the possibility that the first main pipe 1 and the end of the blasting hole are stuck and cannot penetrate into the blasting hole.

[0035] Reference Figure 1 and Figure 2 A driving pad 15 is fixed to the side wall of the pushing plate 17 by bonding. The driving pad 15 is made of rubber. A plurality of driving protrusions 16 are fixed to the side wall of the driving pad 15 by integral molding. The driving protrusions 16 are used to increase the friction between the pushing plate 17 and the guide wire. When the guide wire is too long, the friction between the driving pad 15 and the side wall of the guide wire can drive the guide wire to move.

[0036] The implementation principle of a charging device for tunnel blasting in an embodiment of the present application is as follows: after the explosive or the guide wire is passed through the first through hole 4, it is placed on the pushing plate 17, the first main pipe 1 is passed into the blasting hole, the pushing rod 3 is pushed, and the pushing plate 17 is driven to move, so that the explosive or the guide wire is placed in the blasting hole, and then the blocking rod 8 is pushed to drive the filling block 7 to pass through the blasting hole, and the filling block 7 abuts against the inner wall of the blasting hole, thereby reducing the possibility of the guide wire detaching from the blasting hole.

[0037] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.

Claims

1. A charging device for tunnel blasting, characterized in that: It comprises a first main pipe (1) for charging medicine, the end of the first main pipe (1) is open, a partition plate (2) is fixed inside the first main pipe (1), and a push rod (3) is slidably connected to the bottom of the first main pipe (1).

2. The charging device for tunnel blasting according to claim 1, characterized in that: A push plate (17) is fixed to the end of the push rod (3), and a first through hole (4) is opened on the side wall of the first main pipe (1), and the first through hole (4) is connected to the space where the push plate (17) is located.

3. The charging device for tunnel blasting according to claim 2, characterized in that: A second through hole (5) is provided on the side wall of the first main pipe (1), and the second through hole (5) and the first through hole (4) are symmetrical with respect to the end surface of the partition plate (2); a filling pipe (6) is fixed on the side wall of the first main pipe (1), and the filling pipe (6) is connected to the second through hole (5); and a plurality of filling blocks (7) are placed in the filling pipe (6).

4. The charging device for tunnel blasting according to claim 2, characterized in that: A blocking rod (8) for pushing the filling block (7) is slidably arranged at the bottom of the first main pipe (1), a blocking block (9) is fixed to the end of the blocking rod (8), and the blocking block (9) and the pushing plate (17) are symmetrically arranged with respect to the partition plate (2).

5. The charging device for tunnel blasting according to claim 3, characterized in that: The end of the filling tube (6) facing away from the first main tube (1) is open, a push rod (10) is slidably arranged inside the filling tube (6), and a buffer pad (11) is fixed to the side wall of the push rod (10).

6. The charging device for tunnel blasting according to claim 1, characterized in that: A positioning rod (12) is detachably provided at the end of the first main pipe (1), and a positioning hole (13) for passing the positioning rod (12) is provided at the end of the first main pipe (1), and the positioning rod (12) is slidably connected to the inner wall of the positioning hole (13).

7. The charging device for tunnel blasting according to claim 1, characterized in that: The end of the first main pipe (1) is provided with a movement guide surface (14) which facilitates the movement of the first main pipe (1).

8. The charging device for tunnel blasting according to claim 2, characterized in that: A driving pad (15) is fixed to the side wall of the push plate (17), and a plurality of driving protrusions (16) are fixed to the side wall of the driving pad (15).