Prestressed pile driving equipment for river bank reinforcement
By using the first punching and then filling piles with piles in the river bank reinforcement equipment, the problem of collision damage of traditional pile driving equipment is solved, and the pile quality and equipment life are improved.
Patent Information
- Application Number
- CN202323394170.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-13
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2033-12-13
AI Technical Summary
Traditional river bank reinforcement prestressed pile driving equipment is prone to damage caused by collision when driving piles, especially when there are pebbles in the soil, resulting in a decline in pile quality.
A prestressed pile pile driving equipment was designed, using pile driving pipe and twisted dragon structure. The pile driving pipe was driven by hydraulic cylinder and motor to first punch holes, and then fill piles. The soil and pebbles in the twisted dragon were shaken out after punching holes. , avoid collision between the cylinder and the pebbles during pile driving.
It effectively avoids collision and damage between the column and pebbles during pile driving, and improves the quality of pile driving and the service life of the equipment.
Smart Images

Figure CN221972365U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of prestressed pile driving, and in particular relates to a prestressed pile driving device for reinforcing river bank. Background Art
[0002] Prestressed piles, also known as precast concrete piles, are prefabricated in a prefabricated component processing plant. After curing and reaching the designed strength, they are transported to the construction site, driven into the soil with a pile driver, and then the cap beam foundation is poured on the top of the pile. The concrete grade used for reinforced concrete precast piles should not be lower than 300#. The diameter of the force-bearing steel bars of the pile should not be less than 12 mm, and generally 4 to 8 main bars are configured. In order to resist hammering and penetrate the soil layer, the stirrups should be denser at the top and tip of the pile, and the main bars at the tip of the pile should be bent up and welded to a core rod. Reinforced concrete precast piles have the advantages of simple production, high strength, high rigidity and can be made into various cross-sectional shapes. It is a widely used pile type.
[0003] At present, the conventional prestressed pile driving equipment used for river bank reinforcement is generally composed of a pile hammer, a pile frame and ancillary equipment. When driving piles, the pile body is continuously struck by the pile hammer to embed it into the ground. However, there are often pebbles in the soil beside the river bank. When driving piles, the conventional pile driver may cause the pebbles to collide with the pile body, causing damage to the pile body, thereby affecting the piling work. Based on this, the utility model applies for designing a prestressed pile driving equipment for river bank reinforcement. Utility Model Content
[0004] In order to solve the above problems existing in the prior art, the utility model provides a prestressed pile driving device for river bank reinforcement, which has the characteristic of preventing the column from colliding with pebbles in the river bank soil during piling and thus causing damage.
[0005] To achieve the above-mentioned purpose, the utility model provides the following technical solutions: a prestressed pile driving device for river bank reinforcement, comprising a bottom frame and a pile driving structure, the pile driving structure comprising a connecting block, a flower shaft rod is rotatably mounted on the bottom of the connecting block, a first pulley is fixedly mounted on the outer surface of the flower shaft rod, a pile driving pipe is fixedly mounted on the bottom of the flower shaft rod, the pile driving pipe is composed of a small column and a large column, and teeth are provided on the bottom, fixing rods are fixedly mounted on both sides of the outer surface of the pile driving pipe, a first motor is fixedly mounted inside the fixing rod, and an output shaft of the first motor is fixedly mounted on the bottom of the fixing rod. A first rotating rod is fixedly installed at the end, an eccentric cam is fixedly installed on the outer surface of the first rotating rod, support plates are fixedly installed on both sides of the top of the piling pipe, one end of the two first rotating rods is rotatably connected to the support plate, sliding grooves are provided on both sides of the interior of the piling pipe, and the two sliding grooves are slidably connected to the support plate, a filling slot column is fixedly installed inside the piling pipe, a spring is fixedly installed inside the filling slot column, a connecting rod is fixedly installed on the bottom of the spring, a fixing plate is fixedly installed on the outer surface of the connecting rod, and a auger is welded on the outer surface of the fixing plate.
[0006] As an optimal technical solution for a prestressed pile driving device for river bank reinforcement according to the utility model, triangular support plates are fixedly installed on both sides of the outer surface of the bottom frame, a back frame is welded and installed on one side of the two triangular support plates, and a top cover is welded on one side of the outer surface of the back frame.
[0007] As a preferred technical solution of the prestressed pile driving equipment for river bank reinforcement of the utility model, a hydraulic cylinder is fixedly installed inside the top cover, and one end of the telescopic rod of the hydraulic cylinder is fixedly connected to the connecting block.
[0008] As a preferred technical solution of the prestressed pile driving equipment for river bank reinforcement of the utility model, a movable groove is provided inside the back frame, and two sliding rods are fixedly installed inside the movable groove.
[0009] As a preferred technical solution of the prestressed pile driving equipment for river bank reinforcement of the utility model, a driving structure is slidably mounted on the outer surface of the two sliding rods, and the driving structure includes a fixed block.
[0010] As an optimal technical solution for a prestressed pile driving device for river bank reinforcement of the utility model, a second motor is fixedly installed at the bottom of the fixed block, a second rotating rod is fixedly installed at one end of the output shaft of the second motor, and a second pulley is fixedly installed on the outer surface of the second rotating rod.
[0011] As an optimal technical solution for a prestressed pile driving device for river bank reinforcement of the utility model, a belt is sleeved on the outer surface of the second pulley, the belt is sleeved on the first pulley, a connecting long rod is fixedly installed on the top of the fixed block, and the connecting long rod is fixedly connected to the connecting block.
[0012] Compared with the prior art, the beneficial effects of the utility model are:
[0013] 1. When the utility model is in use, the device is moved to the piling position by the pile driving structure and the driving structure before piling. At this time, the pile driving pipe is rotated and moved downward by the driving of the hydraulic cylinder and the driving structure, so that the drilling work can be started. At the same time, due to the setting of the auger, the soil or pebbles wrapped inside the pile driving pipe can be moved into the auger. After the drilling is completed, the pile driving pipe is reset. At this time, the two first rotating rods can be driven by the driving of the first motors on both sides to respectively drive the eccentric cams to rotate, so that the support plate can slide in the sliding groove, and then the spring drives the connecting rod to shake up and down, and the second motor is reversed to shake off the soil and pebbles in the auger. At this time, the pile filling work can be carried out in the opened hole. This structure breaks the working principle of traditional hammering and uses the order of drilling first and then piling, so as to avoid the damage caused by the collision between the column and pebbles or other stones during the piling process, thereby improving the quality of piling.
[0014] 2. When the utility model is in use, through the hydraulic cylinder and the driving structure, the telescopic rod can drive the connecting block to move up and down through the drive of the hydraulic cylinder, so that the piling pipe reaches the required depth, and the second motor drives the second rotating rod to rotate and the flower axis rod drives the piling pipe to rotate at high speed through the belt, so that the piling pipe can perform drilling work. BRIEF DESCRIPTION OF THE DRAWINGS
[0015] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0016] Figure 1 This is a schematic diagram of the appearance structure of the utility model;
[0017] Figure 2 This is a schematic diagram of the sliding rod structure of the utility model;
[0018] Figure 3 This is a schematic diagram of the driving structure of the utility model;
[0019] Figure 4 This is a schematic diagram of the piling structure of the utility model;
[0020] Figure 5 It is a schematic diagram of the auger structure of the utility model.
[0021] In the figure: 1. bottom frame; 2. back frame; 3. top cover; 4. hydraulic cylinder; 5. piling structure; 51. connecting block; 52. first pulley; 53. flower shaft rod; 54. piling pipe; 55. sliding groove; 56. support plate; 57. fixing rod; 58. first motor; 59. first rotating rod; 510. eccentric cam; 511. filling slot column; 512. spring; 513. connecting rod; 514. fixing plate; 515. auger; 6. triangular support plate; 7. moving groove; 8. sliding rod; 9. driving structure; 91. fixing block; 92. second motor; 93. second rotating rod; 94. second pulley; 95. belt; 96. connecting long rod. DETAILED DESCRIPTION
[0022] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0023] Example 1
[0024] See also Figure 1-5 The utility model provides the following technical solutions: a prestressed pile driving device for river bank reinforcement, comprising a bottom frame 1 and a pile driving structure 5, the pile driving structure 5 comprising a connecting block 51, a flower shaft rod 53 is rotatably mounted at the bottom of the connecting block 51, a first pulley 52 is fixedly mounted on the outer surface of the flower shaft rod 53, a pile driving pipe 54 is fixedly mounted at the bottom of the flower shaft rod 53, the pile driving pipe 54 is composed of a small column and a large column, and teeth are provided at the bottom, fixed rods 57 are fixedly mounted on both sides of the outer surface of the pile driving pipe 54, a first motor 58 is fixedly mounted inside the fixed rod 57, and a first rotating rod 59 is fixedly mounted on one end of the output shaft of the first motor 58 An eccentric cam 510 is fixedly installed on the outer surface of the first rotating rod 59, support plates 56 are fixedly installed on both sides of the top of the piling pipe 54, one end of the two first rotating rods 59 is rotatably connected to the support plate 56, sliding grooves 55 are provided on both sides of the interior of the piling pipe 54, and the two sliding grooves 55 are slidably connected to the support plate 56, a filling slot column 511 is fixedly installed inside the piling pipe 54, a spring 512 is fixedly installed inside the filling slot column 511, a connecting rod 513 is fixedly installed on the bottom of the spring 512, a fixing plate 514 is fixedly installed on the outer surface of the connecting rod 513, and a screw dragon 515 is welded on the outer surface of the fixing plate 514.
[0025] Example 2
[0026] See also Figure 1-3The utility model provides the following technical solution: triangular support plates 6 are fixedly installed on both sides of the outer surface of the bottom frame 1, a back frame 2 is welded and installed on one side of the two triangular support plates 6, and a top cover 3 is welded on one side of the outer surface of the back frame 2. A hydraulic cylinder 4 is fixedly installed inside the top cover 3, and one end of the telescopic rod of the hydraulic cylinder 4 is fixedly connected to the connecting block 51. A moving groove 7 is opened inside the back frame 2, and two sliding rods 8 are fixedly installed inside the moving groove 7.
[0027] The two triangular support plates 6 make the back frame 2 and the bottom frame 1 more stable. The driving structure 9 can slide between the two sliding rods 8 so that the driving structure 9 can always keep level with the pile driving structure 5. The hydraulic cylinder 4 can drive the telescopic rod to drive the connecting block 51 to move up and down, so that the pile driving pipe 54 reaches the required depth.
[0028] Example 3
[0029] See also Figure 3 The utility model provides the following technical solution: a driving structure 9 is slidably mounted on the outer surface of the two sliding rods 8, and the driving structure 9 includes a fixed block 91. A second motor 92 is fixedly mounted on the bottom of the fixed block 91, a second rotating rod 93 is fixedly mounted on one end of the output shaft of the second motor 92, and a second pulley 94 is fixedly mounted on the outer surface of the second rotating rod 93. A belt 95 is sleeved on the outer surface of the second pulley 94, and the belt 95 is sleeved on the first pulley 52. A connecting long rod 96 is fixedly mounted on the top of the fixed block 91, and the connecting long rod 96 is fixedly connected to the connecting block 51.
[0030] The second motor 92 drives the second rotating rod 93 to rotate, and the flower shaft rod 53 drives the piling pipe 54 to rotate at high speed through the belt 95.
[0031] Working principle and use process of the utility model: In the process of using the utility model, before piling, the device is moved to the piling position, and the telescopic rod is driven by the hydraulic cylinder 4 to drive the connecting block 51 to move up and down, so that the piling pipe 54 reaches the required depth. At the same time, the second motor 92 is driven to rotate the second rotating rod 93 and the belt 95 is used to drive the piling pipe 54 to rotate at a high speed, so that the piling pipe 54 can be punched. When punching, due to the setting of the auger 515 , the soil or pebbles wrapped inside the pile driving pipe 54 can be moved to the auger 515. After the drilling is completed, the pile driving pipe 54 is reset. At this time, the two first rotating rods 59 can respectively drive the eccentric cams 510 to rotate through the driving of the first motors 58 on both sides, thereby allowing the support plate 56 to slide in the sliding groove 55, and then the spring 512 drives the connecting rod 513 to swing up and down, and cooperate with the reversal of the second motor 92 to shake off the soil and pebbles in the auger 515, and then pile filling work can be carried out in the opened hole.
[0032] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.
Claims
1. A prestressed pile driving device for river bank reinforcement, comprising a bottom frame (1) and a pile driving structure (5), characterized in that: The piling structure (5) comprises a connecting block (51), a flower shaft rod (53) is rotatably mounted at the bottom of the connecting block (51), a first pulley (52) is fixedly mounted on the outer surface of the flower shaft rod (53), a piling pipe (54) is fixedly mounted at the bottom of the flower shaft rod (53), the piling pipe (54) is composed of a small column and a large column, and has teeth at the bottom, fixed rods (57) are fixedly mounted on both sides of the outer surface of the piling pipe (54), a first motor (58) is fixedly mounted inside the fixed rod (57), a first rotating rod (59) is fixedly mounted on one end of the output shaft of the first motor (58), and an eccentric cam (510) is fixedly mounted on the outer surface of the first rotating rod (59), Support plates (56) are fixedly installed on both sides of the top of the pile driving pipe (54), one end of the two first rotating rods (59) is rotatably connected to the support plates (56), sliding grooves (55) are provided on both sides of the interior of the pile driving pipe (54), and the two sliding grooves (55) are slidably connected to the support plates (56), a filling slot column (511) is fixedly installed inside the pile driving pipe (54), a spring (512) is fixedly installed inside the filling slot column (511), a connecting rod (513) is fixedly installed at the bottom of the spring (512), a fixing plate (514) is fixedly installed on the outer surface of the connecting rod (513), and a screw dragon (515) is welded and installed on the outer surface of the fixing plate (514).
2. The prestressed pile driving equipment for river bank reinforcement according to claim 1, characterized in that: Triangular support plates (6) are fixedly mounted on both sides of the outer surface of the bottom frame (1), a back frame (2) is welded to one side of the two triangular support plates (6), and a top cover (3) is welded to one side of the outer surface of the back frame (2).
3. The prestressed pile driving equipment for river bank reinforcement according to claim 2, characterized in that: A hydraulic cylinder (4) is fixedly installed inside the top cover (3), and one end of the telescopic rod of the hydraulic cylinder (4) is fixedly connected to the connecting block (51).
4. The prestressed pile driving equipment for river bank reinforcement according to claim 2, characterized in that: A movable groove (7) is provided inside the back frame (2), and two sliding rods (8) are fixedly installed inside the movable groove (7).
5. The prestressed pile driving equipment for river bank reinforcement according to claim 4, characterized in that: A driving structure (9) is slidably mounted on the outer surfaces of the two sliding rods (8), and the driving structure (9) comprises a fixing block (91).
6. The prestressed pile driving equipment for river bank reinforcement according to claim 5, characterized in that: A second motor (92) is fixedly mounted on the bottom of the fixed block (91), a second rotating rod (93) is fixedly mounted on one end of the output shaft of the second motor (92), and a second pulley (94) is fixedly mounted on the outer surface of the second rotating rod (93).
7. The prestressed pile driving equipment for river bank reinforcement according to claim 6, characterized in that: The outer surface of the second pulley (94) is sleeved with a belt (95), and the belt (95) is sleeved with the first pulley (52). A connecting rod (96) is fixedly installed on the top of the fixed block (91), and the connecting rod (96) is fixedly connected to the connecting block (51).