Steel pipe pile hoisting, driving and sinking positioning guide frame
By designing an adjustable multi-layer interlaced stacked steel structure guide frame, the positioning problem of steel pipe piles under water and high working conditions is solved, precise pile sinking and flexible installation are achieved, adapting to the needs of different pile diameters, and improving the Positioning accuracy and flexibility in use.
Patent Information
- Application Number
- CN202420613621.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-27
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2034-03-27
AI Technical Summary
The existing steel pipe pile positioning guide frame is not suitable for sinking pile construction under water and high-altitude operating conditions where the construction platform is limited. The positioning plate has a large weight, is complex in production, and the positioning hole cannot be adjusted, which limits its scope of use.
A steel structure guide frame with multiple layers of interlaced stacks is designed, including an adjustable intermediate cavity guide frame, which is fixed to the construction platform by expansion bolts, suitable for different pile diameters, and a protective layer is laid on the structure to prevent Wear.
It realizes accurate positioning and sinking of steel pipe piles under water and high-altitude operating conditions, reduces the requirements of the construction platform, simplifies the installation process, is suitable for a variety of pile diameters, and improves positioning accuracy and use flexibility.
Smart Images

Figure CN221989319U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of construction engineering construction devices, in particular to a steel pipe pile hanging and sinking pile positioning guide frame. Background Art
[0002] Steel pipe piles have the characteristics of high strength and high rigidity. Compared with concrete piles, they are light in weight and easy to construct. They are commonly used pile foundation structures and are widely used in docks, bridges and other fields.
[0003] Usually, the construction methods of steel pipe piles include hammer pile driving and vibration pile driving. During the construction process, the positioning of steel pipe piles is particularly important, which determines the accuracy of pile driving. On-site construction often encounters limited pile driving conditions, which do not meet the construction requirements of large-scale pile driving equipment with high pile driving accuracy. There are situations where steel pipe piles are hoisted and driven into piles. At this time, it is difficult to position and control the accuracy of steel pipe piles. In order to ensure the accuracy of pile driving, some positioning devices for steel pipe pile driving have gradually emerged, among which the device disclosed in the Chinese patent application (CN214460401 U) is the most representative. The device sets a positioning plate on the foundation, and a plurality of positioning holes are opened on the positioning plate. The steel pipe piles to be positioned pass through the positioning holes and sink into the foundation of the pile position. The verticality of the steel pipe pile is controlled not to exceed the preset value by the distance between the side wall of the positioning hole and the steel pipe pile. This device can fix the positions of multiple piles at the same time, thereby improving the accuracy of steel pipe pile driving.
[0004] However, since the positioning plate is a whole plate with large size and certain weight, it requires high lifting capacity of lifting equipment, which is not convenient for on-site construction. The circular top hole on the positioning plate requires high precision of the hole-opening equipment and a complicated manufacturing process. The construction platform has high requirements. The positioning plate must be fixed on a stable and spacious construction platform. It is suitable for pile sinking construction under soil foundation or steel platform conditions, but not suitable for pile sinking construction under water or high-altitude working conditions with limited construction platform. At the same time, the positioning hole cannot be changed or is not easy to adjust, which greatly limits the use of the positioning plate. Summary of the invention
[0005] In view of this, the utility model provides a steel pipe pile hoisting and pile sinking positioning guide frame, which solves the problem that the steel pipe pile positioning guide frame in the prior art is not suitable for pile sinking construction under water or high-altitude working conditions where the construction working platform is limited.
[0006] The utility model solves the above problems through the following technical means:
[0007] The utility model discloses a steel pipe pile hanging and driving pile positioning guide frame, comprising a guide frame with an intermediate cavity formed by a plurality of steel structures, wherein the plurality of steel structures are at least in a two-layer staggered stacked structure, wherein the steel structure of the upper layer is installed astride two adjacent steel structures of the lower layer, and is an installation structure that can be adjusted back and forth along the center line of the two steel structures of the lower layer, and the end of the steel structure of the bottom layer is provided with a positioning hole for passing an expansion bolt to fix the whole on a construction platform.
[0008] Preferably, the diameter of the middle cavity is 10-30 mm larger than the pile diameter.
[0009] Preferably, the steel structure is a channel steel, and the web of the upper steel structure is connected and installed with the flange plate of the lower steel structure. Compared with the connection between flange plates, the contact area is larger and the installation connection is more secure.
[0010] Preferably, the steel structure is any one of I-beam, H-beam or angle steel.
[0011] Preferably, the steel structure of the lower layer is connected to the steel structure of the upper layer by any one of welding connection, bolt connection, clamping ring connection and mortise and tenon connection.
[0012] As a further improvement of the above technical solution, a protective layer is applied on the steel structure outside the intermediate cavity.
[0013] Preferably, the protective layer is linen evenly spread with butter.
[0014] It can be seen from the above technical solution that the utility model has the following beneficial effects:
[0015] The steel pipe pile hanging and pile sinking positioning guide frame of the utility model is a frame structure with at least two layers of steel structures stacked together. The two ends of the steel structure of the bottom layer can be fixed on the construction platform above the pile position to carry out steel pipe pile sinking positioning. Under water and high-altitude working conditions where the construction platform is limited, the single-end cantilever of the steel structure of the bottom layer can also be fixed and installed. It has low requirements for the construction platform and a wide range of adaptability. The distance between the steel structures of each layer is adjusted according to the pile position and the pile diameter, so as to achieve the purpose of adjusting the size of the middle cavity. It is suitable for different pile diameters, has a simple structure, is light in weight, does not require a complicated manufacturing process, and is simple and convenient to install. The multiple layers of staggered and stacked steel structures also have a certain height, which has a better enclosure effect than positioning plates. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a structural schematic diagram of the steel pipe pile hoisting and sinking pile positioning guide frame of Example 1;
[0017] Figure 2 for Figure 1 Front view of
[0018] Figure 3 It is a structural schematic diagram of the steel pipe pile hanging and sinking pile positioning guide frame of Example 2;
[0019] Figure 4 for Figure 3 Front view of.
[0020] like Figure 1-Figure 4 , steel structure-11, middle cavity-12, positioning hole-13, expansion bolt-14, upper channel steel-21, lower channel steel-22, middle cavity-23, positioning hole-24, expansion bolt-25. DETAILED DESCRIPTION
[0021] In the description of the present invention, it should be understood that the terms "center", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", etc., indicating directions or positional relationships, are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore should not be understood as a limitation on the present invention.
[0022] The terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "plurality" means two or more.
[0023] Example 1
[0024] The utility model will be described in detail below with reference to the accompanying drawings: The steel pipe pile hanging and sinking pile positioning guide frame described in this embodiment is as follows Figure 1-Figure 2 As shown, it includes a guide frame with an intermediate cavity 12 formed by a plurality of steel structures 11, and the plurality of steel structures 11 are at least in a two-layer staggered stacked structure. The upper steel structure 11 is installed across the two adjacent steel structures 11 in the lower layer, and is an installation structure that can be adjusted back and forth along the center line of the two steel structures 11 in the lower layer. The end of the steel structure 11 in the bottom layer is provided with a positioning hole 13 for passing an expansion bolt 14 to fix the whole to the construction platform.
[0025] The steel pipe pile driving and positioning guide frame described in this embodiment is a frame structure with at least two layers of steel structures 11 stacked together. The two ends of the bottom steel structure 11 can be fixed on the construction platform above the pile position to carry out steel pipe pile positioning. Under water and high-altitude working conditions where the construction platform is limited, the bottom steel structure 11 can also be cantilevered and fixed at a single end, which has low requirements for the construction platform and a wide range of adaptability. The distance between the steel structures 11 of each layer is adjusted according to the pile position and pile diameter, so as to achieve the purpose of adjusting the size of the middle cavity 12. It is suitable for different pile diameters, has a simple structure, is light in weight, does not require a complicated manufacturing process, and is simple and convenient to install. The multi-layer staggered and stacked steel structures 11 also have a certain height, which has a better enclosure effect than the positioning plate.
[0026] As a preferred implementation of this embodiment, the diameter of the middle cavity 12 is 10-30 mm larger than the pile diameter.
[0027] As a preferred implementation of this embodiment, the steel structure 11 is a channel steel, and the web of the upper steel structure 11 is connected and installed with the flange plate of the lower steel structure 11; the steel structure 11 can also be any one of an I-beam, an H-beam or an angle steel.
[0028] As a preferred implementation of this embodiment, the steel structure 11 of the lower layer is connected to the steel structure 11 of the upper layer by any connection method such as welding connection, bolt connection, clamping ring connection, and mortise and tenon connection.
[0029] As a further improvement of the above technical solution, a protective layer (not shown in the figure) is applied on the steel structure 11 outside the intermediate cavity 12 to prevent the steel pipe piles from directly contacting the positioning guide frame of the steel structure 11 and wearing the surface paint of the steel pipe piles.
[0030] As a preferred implementation manner of this embodiment, the protective layer is linen cloth evenly spread with butter.
[0031] Example 2
[0032] In this embodiment, the positioning guide frame composed of two lower channel steels 22 and two upper channel steels 21 is mainly used as an example for specific description: the steel pipe pile hanging and sinking pile positioning guide frame described in this embodiment is as follows: Figure 3 , Figure 4 As shown, it includes two lower channel steels 22 and two upper channel steels 21 which are stacked and installed in a criss-cross pattern. The two lower channel steels 22 and the two upper channel steels 21 are arranged in a "well" shape, and the intermediate cavity 23 is used to insert steel pipe piles. The webs of the two upper channel steels 21 are connected to the flange plates of the two lower channel steels 22. Positioning holes 24 are respectively opened at both ends of the lower channel steel 22 for passing expansion bolts 25 to fix the lower channel steel 22 on the construction platform.
[0033] The steel pipe pile hanging and sinking pile positioning guide frame described in this embodiment is arranged in a "well" shape through the two lower channel steels 22 and the two upper channel steels 21. The positioning holes 24 opened at both ends of the lower channel steel 22 can be fixed at both ends or fixed by a single end cantilever through the expansion bolts 25 embedded in the positioning holes 24. The requirements for the construction platform are low. Under the conditions of water and high-altitude operations where the construction platform is limited, the guide frame can be fixed by a single-end cantilever. The guide frame has a wide range of adaptability and low requirements for the construction platform. No large-scale operation platform is required, and conventional cranes can be used for installation. It is convenient and simple, low cost, and good economic benefits. At the same time, the distance between the two lower channel steels 22 and the distance between the two upper channel steels 21 can be adjusted according to the pile position and pile diameter, so as to achieve the purpose of adjusting the size of the intermediate cavity 23, and is suitable for different pile diameters.
[0034] As a further improvement of the above technical solution, a protective layer is applied on the steel structure outside the intermediate cavity 23 to prevent the steel pipe piles from directly contacting the steel structure positioning guide frame and wearing the surface paint of the steel pipe piles.
[0035] As a preferred implementation manner of this embodiment, the protective layer is linen cloth evenly spread with butter.
[0036] The working process of the steel pipe pile hanging and sinking pile positioning guide frame described in this embodiment during the specific construction is as follows:
[0037] During installation, the surveyor first places the installation position of the positioning guide frame according to the designed pile position. The spacing from the edge of the positioning guide frame to the edge of the steel pipe pile is controlled at 20 mm. Four points are placed outside the cutting area and marked for the installation of two horizontal lower channel steels 22. Then, the expansion bolts 25 are inserted into the positioning holes 24 on the lower channel steel 22 to fix the lower channel steel 22 to the pre-determined installation position on the dock panel. Then, the position of the upper channel steel 21 is adjusted according to the diameter of the steel pipe pile and fixed to the lower channel steel 22. After installation, the protective layer (not shown in the figure) is laid on the four sides of the positioning guide frame.
[0038] When sinking piles, first use a crawler crane to lift the first section of the steel pipe pile, lift it at two points, and put it into the middle cavity 23 of the above-mentioned positioning guide frame. The steel pipe pile is inserted into the riverbed by its own weight. At the same time, the surveyor remeasures the inclination of the steel pipe pile. After the inclination is well controlled, the vibrating hammer is started to start sinking the pile. During the pile sinking process, the surveyor continuously observes the inclination of the steel pipe pile. When deviation occurs, the crane driver is notified in time to adjust the boom to ensure that the steel pipe pile is vertical. When the pile top is 1m away from the top surface of the above-mentioned positioning guide frame, the positioning guide frame is removed to facilitate the sinking of the vibrating hammer until the pile is sunk to the designed elevation.
[0039] Finally, it should be noted that the above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model has been described in detail with reference to the preferred embodiments, ordinary technicians in the field should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the purpose and scope of the technical solution of the utility model, which should be included in the scope of the claims of the utility model.
Claims
1. A steel pipe pile driving and positioning guide frame, characterized by: It includes several steel structures that surround an intermediate cavity, and the steel structures are staggered and stacked in at least two layers. The upper steel structure is installed across the two adjacent steel structures in the lower layer, and is an installation structure that can be adjusted back and forth along the center line of the two steel structures in the lower layer. The end of the bottom steel structure is provided with a positioning hole for passing expansion bolts to fix the whole to the construction platform.
2. A steel pipe pile driving and positioning guide frame according to claim 1, characterized in that: The diameter of the middle cavity is 10-30 mm larger than the pile diameter.
3. The steel pipe pile driving and positioning guide frame according to claim 1, characterized in that: The steel structure is a channel steel, and the web of the upper steel structure is connected and installed with the flange plate of the lower steel structure.
4. A steel pipe pile driving and positioning guide frame according to claim 1, characterized in that: The steel structure is any one of I-beam, H-beam or angle steel.
5. The steel pipe pile driving and positioning guide frame according to claim 1, characterized in that: The steel structure of the lower layer is connected to the steel structure of the upper layer by any one of welding connection, bolt connection, clamping ring connection and mortise and tenon connection.
6. The steel pipe pile driving and positioning guide frame according to claim 1, characterized in that: A protective layer is applied on the steel structure outside the middle cavity.
7. A steel pipe pile driving and positioning guide frame according to claim 6, characterized in that: The protective layer is linen evenly coated with butter.
Citation Information
Cited By
Steel pipe pile sinking positioning frame
CN120367211A