Inverted well wall supporting structure

By using a reinforcement measure of multi-layer steel frame and double-layer steel mesh combined with connecting bars, oblique braces and anchors in the inverted well wall structure, the problem of well chamber collapse is solved, and construction safety is improved and the support of the well chamber interior wall is improved. Effect.

CN221990369UActive Publication Date: 2024-11-12RANKEN RAILWAY CONSTR GROUP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420319398.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-02-20
Publication Date
2024-11-12
Estimated Expiration
2034-02-20

AI Technical Summary

Technical Problem

The existing inverted well wall structure often collapses due to inadequate protection of the well chamber interior wall, causing safety hazards.

Method used

A multi-layer steel frame is used to combine a double-layer steel mesh structure, and reinforced by connecting ribs, oblique braces and anchors, forming an overall support structure with higher strength, enhancing the protective effect of the well room interior wall.

Benefits of technology

Effectively prevent the well chamber from collapse, improve construction safety, enhance the support effect on the inner wall of the vertical shaft, and ensure the stability and safety of the construction process.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN221990369U_ABST
    Figure CN221990369U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of groove construction, and particularly discloses an upside-down hanging well wall supporting structure which comprises a vertical shaft, a lock mouth ring beam is arranged on the upper portion of the vertical shaft, a plurality of layers of steel frames are sequentially arranged in the vertical shaft at intervals in the vertical direction, and the shape of the steel frames is consistent with the shape of the inner contour of the vertical shaft. A reinforcing mesh is laid on the inner wall of the vertical shaft, the reinforcing mesh comprises an inner-layer reinforcing mesh and an outer-layer reinforcing mesh, and the steel frame is located between the inner-layer reinforcing mesh and the outer-layer reinforcing mesh. The protection effect on the inner wall of the well chamber can be improved, and the well chamber is prevented from collapsing.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of trench construction, in particular to an inverted well wall supporting structure. Background Art

[0002] The relocation of municipal underground pipelines is complicated. Various pipelines are staggered and mutually restricted. Since the pipelines have been rebuilt many times and the reconstruction construction methods are inconsistent, the burial depths are inconsistent, which increases the difficulty of pipeline relocation construction. The large deviation between the actual position of the pipeline and the designed position increases the uncertainty of construction. Therefore, before relocating the pipeline, a reasonable relocation construction plan must be determined in combination with design data, geological survey data and excavation conditions to ensure construction quality.

[0003] The inverted well wall is a well-like excavation and support method that is made of a combination of locking ring beams, grilles, anchor rods, shotcrete and other processes. It is excavated and supported from top to bottom, and has the advantages of flexible process, safety and reliability, high efficiency, low cost, and little impact on surrounding pipelines and the environment. It is particularly suitable for foundation pit excavation construction with narrow construction sites and great influence from existing buildings, roads and pipelines.

[0004] However, the inverted well wall structure in the prior art often suffers from well chamber collapse due to inadequate protection of the well chamber inner wall, which creates certain safety hazards. Utility Model Content

[0005] The utility model provides an inverted well wall supporting structure, which aims to improve the protection effect on the inner wall of the well chamber and prevent the well chamber from collapsing.

[0006] The utility model is realized through the following technical scheme: an inverted shaft wall support structure, comprising a vertical shaft, a locking ring beam is arranged at the upper part of the vertical shaft, and multiple layers of steel frames are arranged in sequence along the vertical direction in the vertical shaft, and the shape of the steel frames is consistent with the inner contour shape of the vertical shaft; the inner wall of the vertical shaft is paved with a steel mesh, and the steel mesh includes an inner steel mesh and an outer steel mesh, and the steel frame is located between the inner steel mesh and the outer steel mesh.

[0007] Compared with the prior art, the utility model has the following advantages and beneficial effects: the multi-layer steel frame combined with the double-layer steel mesh structure provided in the present solution can improve the supporting effect on the inner wall of the shaft, prevent the shaft chamber from collapsing, and enhance the safety of construction.

[0008] Furthermore, a plurality of connecting ribs are connected between vertically adjacent steel frames, and the plurality of connecting ribs are distributed at intervals along the circumference of the steel frames.

[0009] Beneficial effect: The setting of the connecting reinforcement in this solution can connect adjacent steel frames into a whole, which can further improve the supporting effect on the inner wall of the shaft.

[0010] Furthermore, the connecting ribs include inner connecting ribs and outer connecting ribs, and the inner connecting ribs and the outer connecting ribs are respectively located on the inner side and the outer side of the steel frame.

[0011] Beneficial effect: In this scheme, the inner connecting reinforcement and the outer connecting reinforcement form a double-layer connecting reinforcement structure, which can form a stronger whole with the steel frame and has a better supporting effect on the inner wall of the shaft.

[0012] Furthermore, the steel frame as a whole is composed of multiple sections of steel sections spliced ​​together.

[0013] Beneficial effect: In this solution, the steel frame is formed by splicing multiple sections of steel, which is convenient for transportation to the site for assembly.

[0014] Furthermore, both ends of the steel section are connected with connecting steel plates, the two sections of the steel section spliced ​​to each other are connected to each other through the connecting steel plates, and the two connecting steel plates connected to each other are fixed by fasteners.

[0015] Beneficial effects: In this solution, the two ends of the steel sections that are spliced ​​to each other are connected and fixed by the connecting steel plates at the ends, so that it is convenient to connect the two connecting steel plates by fasteners to achieve connection between adjacent steel sections.

[0016] Furthermore, a pad is provided between the two interconnected connecting steel plates.

[0017] Beneficial effect: The setting of the pad can improve the tightness of the connection between two adjacent steel sections.

[0018] Furthermore, the steel frame is a double-layer I-beam structure.

[0019] Beneficial effect: Such arrangement can improve the strength of the steel frame.

[0020] Furthermore, a plurality of anchor rods are driven around the shaft of the vertical shaft, and the plurality of anchor rods are distributed vertically and circumferentially along the shaft of the vertical shaft.

[0021] Beneficial effect: The setting of the anchor rods in this scheme can reinforce the soil around the shaft.

[0022] Furthermore, the plurality of anchor rods are arranged in a plum blossom shape, and the anchor rods are tilted downward.

[0023] Beneficial effects: This solution can make the anchor rods evenly distributed and can improve the reinforcement strength of the soil.

[0024] Furthermore, the corners of the steel frame are connected with diagonal braces, and the middle of the steel frame is connected with a transverse brace.

[0025] Beneficial effect: The setting of diagonal braces and transverse braces in this scheme can further improve the support strength and effect of the shaft wall. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] The drawings described herein are used to provide a further understanding of the embodiments of the present utility model, constitute a part of this application, and do not constitute a limitation of the embodiments of the present utility model. In the drawings:

[0027] Figure 1 It is a cross-sectional schematic diagram of the shaft support structure in the embodiment of the utility model;

[0028] Figure 2 It is the general assembly drawing of the primary support steel frame of the vertical shaft and the plan view of the connection reinforcement arrangement in the embodiment of the utility model;

[0029] Figure 3 This is a diagram of the assembly nodes of the section steel frame in the embodiment of the utility model;

[0030] Figure 4 It is a plan layout diagram of the shaft support structure in the embodiment of the utility model;

[0031] Figure 5 It is a schematic diagram of the installation of grouting anchor rods according to an embodiment of the utility model.

[0032] Marks and corresponding parts names in the attached drawings:

[0033] Vertical shaft 101, locking ring beam 1, intercepting ditch 2, diagonal brace 3, transverse brace 301, existing water distribution pipe 4, existing rainwater pipe 5, anchor rod 6, existing hot water pipe 7, steel frame 8, outer layer connecting reinforcement 9, inner layer connecting reinforcement 10, bolt 11, connecting steel plate 12, pad 13, eyelet 14, natural gas pipe 15. DETAILED DESCRIPTION

[0034] In order to make the purpose, technical solutions and advantages of the utility model more clearly understood, the utility model is further described in detail below in conjunction with embodiments and drawings. The schematic implementation manner of the utility model and its description are only used to explain the utility model and are not intended to limit the utility model.

[0035] like Figure 1 As shown, this embodiment provides an inverted shaft wall support structure, including a vertical shaft 101. A locking ring beam 1 is provided at the upper portion of the vertical shaft 101. The locking ring beam 1 of the vertical shaft 101 has an outer contour size of 11×8m, a ring beam width of 1.2m, a height of 1m, and C30 cast-in-place concrete. Connecting bars of a grid steel frame 8 are reserved in the ring beam. The connecting bars are made of C22 steel bars and are arranged at intervals of 1m.

[0036] A ditches 2 is excavated outside the locking ring beam 1 for collecting and draining water. Existing water distribution pipes 4, existing rainwater pipes 5, existing hot water pipes 7 and natural gas pipes 15 are arranged outside the vertical shaft 101 and pass through the vertical shaft 101.

[0037] Multiple layers of steel frames 8 are arranged in sequence along the vertical direction in the shaft 101. The shape of the steel frames 8 is consistent with the inner contour of the shaft 101. In this embodiment, the steel frames 8 are rectangular frame structures. The inner wall of the shaft 101 is paved with steel meshes, which include an inner steel mesh and an outer steel mesh. The steel frame 8 is located between the inner steel mesh and the outer steel mesh.

[0038] A plurality of connecting ribs are connected between the vertically adjacent steel frames 8, and the plurality of connecting ribs are spaced apart along the circumference of the steel frames 8. In this embodiment, the connecting ribs are welded and fixed to the steel frames 8, and the connecting ribs include inner connecting ribs 10 and outer connecting ribs 9. Figure 2 As shown, the inner connecting ribs 10 and the outer connecting ribs 9 are located on the inner side and the outer side of the steel frame 8 respectively.

[0039] Combination Figure 2 and Figure 3 As shown, the steel frame 8 is composed of multiple sections of steel sections connected to each other, which can reduce the transportation volume, facilitate transportation, and facilitate on-site installation and construction. In this embodiment, the steel frame 8 is a double-layer I-beam structure, that is, the steel frame 8 of this embodiment adopts I-22B double-piece I-beams with a vertical spacing of 0.5m / 0.7m. The steel frame 8 is formed into a whole by two layers of I-beam structures, which can improve the overall strength of the steel frame 8, thereby improving the support force on the inner side of the shaft 101.

[0040] In this embodiment, connecting steel plates 12 are connected to both ends of the steel section. The two sections of the steel section that are spliced ​​together are connected to each other through the connecting steel plates 12. The two connecting steel plates 12 that are connected to each other are fixed by fasteners. In this embodiment, the fasteners are bolts 11. Between the adjacent steel sections at both ends, through holes are opened on the two connecting steel plates 12, and the two connecting steel plates 12 are fixed by inserting bolts 11 into the through holes, so that the two adjacent steel sections can be connected and fixed. In this embodiment, in order to improve the stability of the connection between the steel sections, a pad 13 is further provided between the two connecting steel plates 12 that are connected to each other. The pad 13 is a rubber pad 13. The setting of the pad 13 can make the two connecting steel plates 12 that are connected to each other more tightly connected, thereby improving the strength of the connection between the adjacent steel sections.

[0041] Combination Figure 1 and Figure 4 As shown, in order to prevent the formation from collapsing, multiple Hollow grouting anchor 6 is used to reinforce the soil. (Q355) The design value of pull-out resistance is 50kn, the ultimate pull-out resistance of the rod body is 180KN, the fracture elongation of the anchor rod 6 is not less than 16%, the strength grade of the cement slurry stone body between the anchor rod 6 and the hole wall is M30, and multiple anchor rods 6 are distributed vertically and circumferentially along the shaft 101. Figure 5As shown, the anchor rods 6 are driven with an annular spacing of 2.0m and a vertical spacing of 0.75. Multiple anchor rods 6 are arranged in a plum blossom shape, and the anchor rods 6 are all tilted downward. In this embodiment, the downward tilt angle of the anchor rods 6 is 10-15. The driving angle of the anchor rods 6 is adjusted according to the on-site conditions to avoid existing pipelines. In this embodiment, each anchor rod is driven once, and a pneumatic gun is used to drive it in. The pipe wall of the shaft 101 is staggered and drilled every 100-200mm to form eyelets 14 for driving the anchor rods 6. The diameter of the eyelets 14 is 6-8mm.

[0042] In this embodiment Figure 2 and Figure 4 As shown, the corners of the steel frame 8 are connected with diagonal braces 3, and the middle of the steel frame 8 is connected with a transverse brace 301.

[0043] The specific implementation process is as follows:

[0044] Construction process:

[0045] Survey and set out → Construction of locking ring beam → Excavation → Installation of steel mesh → Installation of grille → Driving anchor rods and grouting → Spraying well wall → Next cycle

[0046] (1) Surveying and laying out: Before construction, the surveying team will first lay out the center or edge of the shaft using the verified precision guide points, and lay out the excavation contour line of the working shaft ring beam according to the design dimensions of the construction drawing.

[0047] (2) Construction of locking ring beam: According to the design data, the locking ring beam is accurately positioned and laid out. The locking ring beam is excavated at a slope of 1:1. The earthwork is excavated manually with the help of machinery. After the excavation reaches 200 mm above the design elevation, the bottom is picked and trimmed manually. The base is compacted according to the design requirements to ensure the molding quality and foundation bearing capacity requirements. After reaching the bottom elevation of the beam, the steel bars are tied, the formwork is erected, and the concrete is poured.

[0048] (3) Connection shaft excavation support cycle footage:

[0049] ① After the initial support of the working pit reaches the design strength, the support is erected in time. The diagonal brace adopts 25B single-piece I-beam, and a 25B single-piece I-beam cross brace is set in the middle.

[0050] ② Earth excavation can be carried out only after the concrete strength of the locking ring beam reaches 85% of the design. The working shaft body adopts step-by-step earth excavation, and the vertical excavation step distance is the same as the grid spacing. The vertical shaft is excavated by excavator in combination with manual excavation. Except for the 30cm close to the excavation edge line, which is manually cleared, the middle position is excavated by mechanical excavation. The excavation is carried out by vertical lifting. The bucket size is 1.5*1.5*2m, and it is lifted vertically by a 25t crane. After lifting to the ground soil yard, it is uniformly loaded and transported at night, and a part of the original soil is reserved for backfilling in the working shaft later. The excavation and support of the vertical shaft follows the principle of "vertical layering, partial excavation, support as excavation, and timely closure into a ring". After excavation, spray concrete is sprayed in time to close the excavation surface, and then the grid is erected to reduce stratum loss.

[0051] ③ Anchor reinforcement and grouting

[0052] To prevent ground collapse, a Hollow grouting anchor rods are used to reinforce the soil. (Q355) The design value of pull-out resistance is 50kn, the ultimate pull-out resistance of the rod body is 180KN, the anchor fracture elongation is not less than 16%, the strength grade of the cement slurry stone body between the anchor rod body and the hole wall is M30, the circumferential spacing of the anchor rods is 2.0m, the vertical spacing is 0.75, the overall arrangement is plum blossom-shaped, the downward inclination angle is 10-15°, one hit per frame, and the air gun is used for jacking. The pipe wall is staggered and drilled every 100-200mm, and the hole diameter is 6-8mm.

[0053] The grouting slurry is selected according to the geological conditions of this project and field tests. The slurry mix ratio should be determined by field tests, and the grouting pressure (0.5~1.5MPa) should be controlled according to the geological conditions to ensure that the final pressure is not greater than 0.5Mpa, and the radius of the reinforced body must not be less than 0.25m.

[0054] Grouting is mainly based on cement slurry with a water-cement ratio of 0.5 to 0.55. The slurry is mixed with P042.5 cement, and the grouting behind the primary support is carried out in multiple times: the first grouting is low-pressure grouting, the grouting pressure is 0.1 to 0.3 MPa, and the grouting liquid flows out of the orifice; the second grouting is saturated grouting, and the grouting pressure is 0.5 MPa. Before grouting, the working surface is first sealed with sprayed concrete to prevent leakage, and the accumulation in the small duct is cleaned with high-pressure air. Grouting can be single-tube or multi-tube parallel grouting. Multi-tube parallel grouting can be processed with a slurry distributor. After grouting, immediately block the orifice to prevent the slurry from flowing out.

[0055] ④ Laying of steel mesh and installation of steel grille:

[0056] The steel mesh is laid by workers on site, and the overlap length of the mesh is based on a grid.

[0057] The steel frame is processed in advance, and each circumferential segment is welded with connecting steel plates and I-beams. The connecting steel plates are fixed with bolts. The vertically adjacent circumferential steel frame grids are longitudinally connected with HRB400 steel bars with a diameter of 22mm (double layers inside and outside).

[0058] After the steel frame is installed, C25 early-strength concrete is sprayed to make it dense.

[0059] The steel mesh is processed in advance and transported to the cave for installation. During installation, the steel mesh is laid close to the rock surface to be sprayed, and the concrete protective layer of the steel mesh is not less than 35mm.

[0060] ⑤ Shotcrete

[0061] C25 shotcrete is used for initial support. When spraying concrete, it is carried out in sections, slices, layers, and from bottom to top. The loose concrete and rebound materials of the previous group at the bottom are cleaned and re-sprayed in time to ensure the beauty and verticality of the shaft wall.

[0062] The inverted well wall construction method in this embodiment is well applicable to foundation pit excavation in the case of narrow construction space and complex construction environment, and has the characteristics of high safety performance, high efficiency and convenience, simple process, low construction difficulty and low cost;

[0063] This embodiment uses steel frame assembly to ensure the rigidity of the support, hollow mortar anchors to reinforce the surrounding soil, ensure the stability of the soil and pipelines, spray concrete to support the closed soil, and fill the steel to form an overall force, which ensures the force stability of the foundation pit structure and makes the shaft excavation safer and more reliable;

[0064] In this embodiment, the surrounding well chambers are backfilled with yellow sand, and grouting is used to reinforce the surrounding areas of the vertical shaft pipelines, which reduces the settlement of the surrounding pipelines during the vertical shaft excavation process and ensures the safety of the surrounding pipelines.

[0065] The specific implementation methods described above further illustrate the purpose, technical solutions and beneficial effects of the utility model in detail. It should be understood that the above description is only the specific implementation method of the utility model and is not used to limit the protection scope of the utility model. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the utility model should be included in the protection scope of the utility model.

Claims

1. An inverted shaft wall support structure, comprising a vertical shaft, wherein a locking ring beam is provided at the upper portion of the vertical shaft. It is characterized in that Multiple layers of steel frames are arranged in sequence along the vertical direction in the shaft, and the shape of the steel frames is consistent with the inner contour of the shaft; the inner wall of the shaft is paved with a steel mesh, and the steel mesh includes an inner steel mesh and an outer steel mesh, and the steel frame is located between the inner steel mesh and the outer steel mesh.

2. The inverted shaft wall support structure according to claim 1, It is characterized in that A plurality of connecting ribs are connected between vertically adjacent steel frames, and the plurality of connecting ribs are distributed at intervals along the circumference of the steel frames.

3. The inverted shaft wall support structure according to claim 2, It is characterized in that The connecting ribs include inner connecting ribs and outer connecting ribs, and the inner connecting ribs and the outer connecting ribs are respectively located on the inner side and the outer side of the steel frame.

4. An inverted shaft wall support structure according to any one of claims 1 to 3, It is characterized in that The steel frame as a whole is composed of multiple sections of steel sections connected together.

5. The inverted shaft wall support structure according to claim 4, It is characterized in that Both ends of the steel section are connected with connecting steel plates, and the two sections of the steel section spliced ​​to each other are connected to each other through the connecting steel plates, and the two connecting steel plates connected to each other are fixed by fasteners.

6. The inverted shaft wall support structure according to claim 5, It is characterized in that A pad is also provided between the two interconnected connecting steel plates.

7. An inverted shaft wall support structure according to any one of claims 1 to 3, It is characterized in that The steel frame is a double-layer I-beam structure.

8. The inverted shaft wall support structure according to claim 1, It is characterized in that A plurality of anchor rods are driven around the shaft of the vertical shaft, and the plurality of anchor rods are distributed vertically and circumferentially along the shaft of the vertical shaft.

9. The inverted shaft wall support structure according to claim 8, It is characterized in that The plurality of anchor rods are arranged in a plum blossom shape, and the anchor rods are arranged to be inclined downward.

10. The inverted shaft wall support structure according to claim 1, It is characterized in that The corners of the steel frame are connected with diagonal braces, and the middle of the steel frame is connected with a transverse brace.