Quick assembly type downward drift filling device

By using components such as main filling pipes, three-way pipelines and gate valves in the downward-coming feeding device, the problems of insufficient filling pump pressure and complex construction are solved, and the rapid and efficient filling and top connection are achieved, ensuring the safe production and filling of mines. Stability of the process.

CN222010283UActive Publication Date: 2024-11-15CHINA MINMETALS CHANGSHA MINING RES INST
View PDF 0 Cites 2 Cited by

Patent Information

Application Number
CN202420811375.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-18
Publication Date
2024-11-15
Estimated Expiration
2034-04-18

AI Technical Summary

Technical Problem

The existing downward-directional filling device is difficult to achieve efficient filling and top-mounted connections due to the limited filling pump pressure, difficult filling pipe movement, complex construction and high cost, which affects the safety of mine production.

Method used

A fast-assembled downward-direction filling device is designed, and fast and efficient filling operations are achieved by setting up components such as main filling pipes, three-way pipelines, elbow pipelines, straight pipelines, pipeline brackets and gate valves to achieve rapid and efficient filling operations and improve filling connections. Top-up ratio and ensure firm assembly connection and stability of material delivery through threaded flanges and check valves.

Benefits of technology

It realizes fast and efficient filling operations, improves the filling top rate, simplifies the assembly process, enhances the stability and reliability of the overall structure, ensures safe production in the mine, and avoids material reflux through precise control of the filling process. and leakage risk.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222010283U_ABST
    Figure CN222010283U_ABST
Patent Text Reader

Abstract

The utility model provides a fast assembly type downward drift filling device which is arranged in a drift, and the drift comprises a first layer and a second layer which are sequentially arranged from top to bottom. The downward drift filling device comprises a first filling device arranged on the first layer; the first filling device comprises a first top pipeline and a first bottom pipeline which are respectively arranged at the top and the bottom of the first layer, and a third three-way pipeline which is respectively communicated with the main filling pipe, the first top pipeline and the first bottom pipeline which are arranged in the roadway; the first top pipeline comprises a straight pipeline and a second three-way pipeline which are alternately connected, and the output end of the second three-way pipeline is communicated with the goaf of the first layer; the first bottom pipeline comprises a straight pipeline and a first three-way pipeline which are alternately connected, and the output end of the first three-way pipeline is communicated with the second layer. The fast assembly type downward drift filling device provided by the utility model improves the filling roof-contacted rate through assembly of the prefabricated parts, layered filling and multi-pipeline control.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of mining and filling by a mine access method, in particular to a fast-assembly type downward access filling device. Background Art

[0002] The downward approach filling mining method mainly uses tunnel excavation to recover the ore body, and is mainly suitable for underground mining of high-grade ores under unstable rock conditions. The approach size is often small, and the filling process is simple. The general process is: laying artificial false roof - building filling retaining wall - pumping paste slurry. The filling connection rate is extremely high in downward approach filling mining, and filling connection is an important factor to ensure safe production. A low connection rate will affect the overall strength of the artificial false roof, which is very unfavorable for the safe recovery of the lower ore body.

[0003] At present, the main method of the access filling and top connection device is to set up a filling pipeline before building the retaining wall, first fill the middle part of the mining area, and then gradually draw out the pipeline to fill the rest of the area, which is called backward filling. The method adopted by this device severely limits the pressure of the filling pump, which makes it difficult for the filling paste to be completely connected with the top plate; and the filling pipe is difficult to move, and the timing of movement is also difficult to grasp. The patent with publication number CN114046176B discloses an access method mining area filling and top connection device and method, in which at least three filling branches of different lengths are arranged at the top of the access route to realize multi-point material discharge, and the top connection status is judged by the overflow pipe. The disadvantage of this method is still that the filling pump pressure cannot be too high, and it is impossible to judge whether the top connection is successful far away from the overflow port, and secondary filling and top connection cannot be performed. The patent with publication number CN114909176A provides a method for connecting the roof of a long and deep empty field, which requires the construction of a filling hole above the mine room and the fixing of the pipeline with a metal bracket. The method adopted by the device is complex to construct, has high labor intensity, and has a high cost.

[0004] In view of this, it is necessary to design an improved downward approach stope filling device to solve the above problems. Utility Model Content

[0005] The utility model aims to provide a fast-assembly type downward entry filling device. Through the pre-embedding and fast assembly of the device, fast and efficient filling operation can be achieved, the filling connection rate can be improved, and the safe production of the mine can be ensured.

[0006] In order to achieve the above-mentioned purpose of the utility model, the utility model provides a quick-assembly downward route filling device, characterized in that: the downward route filling device is arranged in the route, and the route includes a first layer and a second layer arranged in sequence from top to bottom; the downward route filling device includes a first filling device arranged in the first layer; the first filling device includes a first top pipe and a first bottom pipe respectively arranged at the top and bottom of the first layer, and a third three-way pipe respectively connected to the main filling pipe, the first top pipe, and the first bottom pipe arranged in the tunnel; the first top pipe includes a straight pipe and a second three-way pipe alternately connected, and the output end of the second three-way pipe is connected to the goaf of the first layer; the first bottom pipe includes a straight pipe and a first three-way pipe alternately connected, and the output end of the first three-way pipe is connected to the second layer.

[0007] As a further improvement of the present invention, in the first filling device, a second gate valve is provided at one end of the third three-way pipe connected to the first bottom pipe.

[0008] As a further improvement of the present invention, a first gate valve is provided at one end of the third three-way pipeline connected to the first top pipeline.

[0009] As a further improvement of the present invention, the third three-way pipe is connected to the first top pipe through an elbow pipe.

[0010] As a further improvement of the present invention, a check valve is provided at the output end of the second three-way pipeline.

[0011] As a further improvement of the utility model, the elbow pipeline, the straight pipeline and the three-way pipeline are all provided with threaded flanges.

[0012] As a further improvement of the present invention, the first filling device further comprises a pipe support, and the straight pipe in the first top pipe is fixed to the top of the first layer through the pipe support.

[0013] As a further improvement of the present invention, the lower part of the pipe support is fixed to the bottom of the first layer, the upper part of the pipe support is provided with at least one fixing hole, and the straight pipe in the first top pipe passes through a fixing hole of the pipe support.

[0014] As a further improvement of the present invention, the downward inlet filling device also includes a second filling device arranged in the second layer, the inlet also includes a third layer arranged below the second layer, the second filling device includes a second bottom pipe arranged at the bottom of the second layer, and a main filling pipe connected to the second bottom pipe; the second bottom pipe includes a straight pipe and a first three-way pipe alternately connected, and the output end of the first three-way pipe is connected to the third layer.

[0015] As a further improvement of the present invention, a third gate valve is provided at the connecting end of the main filling pipe and the second bottom pipe.

[0016] The beneficial effects of the utility model are:

[0017] 1. The utility model provides a quick-assembly downward entry filling device, which is applied between different layers by setting up components such as a main filling pipe, a three-way pipe, an elbow pipe, a straight pipe, a pipe support, and a gate valve. This structural design enables the device to perform filling operations quickly and efficiently, avoiding the complexity and time consumption of traditional on-site construction, making the entire filling process faster and more efficient. By setting up a pipe support to support the straight pipe at the top of the layer, the filling top connection rate is improved to ensure safe production in the mine.

[0018] 2. The utility model provides a quick assembly type downward inlet filling device. By arranging threaded flanges in the elbow pipe and the straight pipe, this design ensures that the components can be quickly and firmly connected. This design not only simplifies the assembly process, so that the components can be assembled together quickly and smoothly, but also enhances the stability and reliability of the overall structure, thereby improving the use efficiency and safety of the device.

[0019] 3. The utility model provides a quick-assembly downward inlet filling device that is equipped with multiple filling pipes, gate valves and check valves, which realizes precise control of the filling process. This design can flexibly adjust the filling speed and flow rate of each pipe according to actual needs, ensuring that the filling material is evenly and stably delivered to the target area. At the same time, the use of gate valves and check valves effectively avoids the risk of material backflow and leakage, and improves the safety and efficiency of the filling operation. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 The utility model is a schematic diagram of the installation of a filling pipeline in the quick-assembly downward inlet filling device provided by the utility model.

[0021] Figure 2 The utility model provides a schematic diagram of the first three-way pipe in the quick assembly type downward inlet filling device.

[0022] Figure 3 A schematic diagram of a second three-way pipe of the quick-assembly downward inlet filling device provided by the utility model.

[0023] Figure 4 A schematic diagram of the third three-way pipeline and the first gate valve and the second gate valve of the quick-assembly downward inlet filling device provided by the utility model.

[0024] Figure 5 A schematic diagram of a straight pipe pipeline of a quick-assembly downward inlet filling device provided by the utility model.

[0025] Figure 6 A schematic diagram of an elbow pipe of a quick-assembly downward inlet filling device provided by the utility model.

[0026] Figure 7 A schematic diagram of a pipe support of a quick-assembly downward-inlet filling device provided by the utility model.

[0027] Reference numerals

[0028] 1-first layer; 2-second layer; 3-third layer; 4-straight pipe; 51-first three-way pipe; 52-second three-way pipe; 53-third three-way pipe; 6-main filling pipe; 7-elbow pipe; 8-pipe support; 81-fixing hole; 9-first gate valve; 10-second gate valve; 11-third gate valve; 12-artificial false bottom; 13-main transport lane. DETAILED DESCRIPTION

[0029] In order to make the purpose, technical solutions and advantages of the present invention more clear, the present invention is described in detail below with reference to the accompanying drawings and specific embodiments.

[0030] It should also be noted that, in order to avoid obscuring the present invention due to unnecessary details, only structures and / or processing steps closely related to the scheme of the present invention are shown in the accompanying drawings, while other details that are not closely related to the present invention are omitted.

[0031] In addition, it should be noted that the terms "comprises", "includes" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, article or apparatus that includes a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or apparatus.

[0032] Please refer to Figure 1-Figure 7The utility model provides a quick-assembly downward route filling device, characterized in that: the downward route filling device is arranged in the route, and the route includes a first layer 1 and a second layer 2 arranged in sequence from top to bottom; the downward route filling device includes a first filling device arranged in the first layer 1; the first filling device includes a first top pipe and a first bottom pipe respectively arranged at the top and bottom of the first layer 1, and a third three-way pipe 53 respectively connected with the main filling pipe 6 arranged in the tunnel, the first top pipe, and the first bottom pipe; the first top pipe includes a straight pipe 4 and a second three-way pipe 52 connected alternately, and the output end of the second three-way pipe 52 is connected to the goaf of the first layer 1; the first bottom pipe includes a straight pipe 4 and a first three-way pipe 51 connected alternately, and the output end of the first three-way pipe 51 is connected to the second layer 2, and gate valves are also installed at both ends of the third three-way pipe. The third three-way pipe 53 and the elbow pipe 7 are both arranged in the main transport lane 13. Such arrangement enables the second three-way pipe 52 to be located at the top of the first layer 1. When the first layer 1 is filled, the filling end of the filling material is located at the top of the first layer 1. The first three-way pipe 51 is located at the top of the second layer 2. When the second layer 2 is filled, the filling end of the filling material is located at the top of the first layer 1, thereby improving the filling top connection rate.

[0033] Please refer to Figure 2-Figure 4 In the first filling device, the end of the third three-way pipe 53 connected to the first bottom pipe is provided with a second gate valve 10. The end of the third three-way pipe 53 connected to the first top pipe is provided with a first gate valve 9. Such a configuration can enhance the operational flexibility of the filling device and accurately control the filling of different layers.

[0034] The third three-way pipe 53 is connected to the first top pipe through the elbow pipe 7. A check valve is provided at the output end of the second three-way pipe 52. The elbow pipe 7, the straight pipe 4 and the three-way pipe are all provided with threaded flanges. Such a configuration can prevent the backflow of the filling material in the pipe and improve the stability of the system. The straight pipe 4 and the elbow pipe 7 provided with threaded flanges can be quickly connected and disassembled. The elbow pipe 7 and the straight pipe 4 can flexibly adjust the direction and branching of the pipe to adapt to different mine layouts and filling requirements.

[0035] The first filling device further comprises a pipe support 8, through which the straight pipe 4 in the first top pipe is fixed to the top of the first layer 1. The lower part of the pipe support 8 is fixed to the bottom of the first layer 1, and the upper part of the pipe support 8 is provided with at least one fixing hole 81, through which the straight pipe 4 in the first top pipe passes. With such a configuration, a system with a stable structure and easy adjustment can be formed. The number of the fixing holes 81 can be multiple, and the straight pipe 4 passes through one fixing hole 81, and the remaining fixing holes 81 are used as spares to facilitate height adjustment.

[0036] The downward entry filling device also includes a second filling device arranged in the second layer 2, and the entry also includes a third layer 3 arranged below the second layer 2. The second filling device includes a second bottom pipe arranged at the bottom of the second layer 2 and a main filling pipe 6 connected to the second bottom pipe; the second bottom pipe includes a straight pipe 4 and a first three-way pipe 51 connected alternately, and the output end of the first three-way pipe 51 is connected to the third layer 3. The connecting end of the main filling pipe 6 and the second bottom pipe is provided with a third gate valve 11. Both ends of the second bottom pipe and the main filling pipe 6 are arranged in the main transport lane 13. With such a configuration, the filling work of the third layer 3 can be equally efficient. Through the control of the third gate valve 11, the material flow direction can be accurately adjusted to ensure the filling effect.

[0037] The working principle of the present invention is further described below in conjunction with specific embodiments:

[0038] When filling with the quick-assembly downward-entry filling device provided by the utility model, the filling method mainly includes the following steps:

[0039] (1) Processing components

[0040] The required components are processed in the workshop, including the straight pipe 4, the elbow pipe 7, the three-way pipe, the gate valve and the pipe support 8.

[0041] (2) Ore body layer

[0042] The ore body is divided into several layers from top to bottom, and each layer is divided into several approaches for mining. The mining order is from top to bottom, and each approach is divided into the first layer, the second layer and the third layer from top to bottom.

[0043] (3) Mining and assembly

[0044] The following is an example of the mining method in one route:

[0045] First, the access road at the top first layer is mined to form the first goaf area, and an artificial false bottom 12 is laid in the goaf area. Then the processed components are assembled into a filling pipeline system, and the assembly method is as follows:

[0046] Three pipe supports 8 are arranged along the access direction of the first layer, and the pipe supports 8 are embedded in the artificial false bottom 12 for fixing. The third three-way pipe 53 is connected to the main filling pipe 6 in the lane, and the first gate valve 9 and the second gate valve 10 are installed at both ends. The end with the first gate valve 9 is connected to one end of the elbow pipe 7, and the other end of the elbow pipe 7 is connected to the second three-way pipe 52. The second three-way pipe 52 is connected to the remaining second three-way pipes 52 through the straight pipe 4. The second three-way pipes 52 are arranged at intervals, and the straight pipe 4 passes through the fixing hole 81 of the pipe support 8, thereby being fixed to the top of the first layer.

[0047] (4) Filling layer

[0048] After the assembly is completed, the first gate valve 9 is opened, and the filling material flows through the main filling pipe and the second three-way pipe 52 in sequence to fill the first layer. After the first layer is filled and connected to the top, the second layer is excavated, and after the second layer is mined, an artificial false bottom 12 is laid and the filling pipe is assembled. The assembly method is:

[0049] A pipeline at the bottom of the second layer is laid, and the filling pipeline is connected to both ends of the pipeline at the bottom of the second layer. A third gate valve 11 is set at the connection point. The first three-way pipeline 51 at the bottom of the second layer is connected with several first three-way pipelines 51 through a straight pipe 4 to form a pipeline network.

[0050] One end of the first three-way pipe 51 is connected to the third layer; both ends of the second layer bottom pipe are respectively connected to the main filling pipe 6 in the tunnel, and a third gate valve 11 is arranged between both ends of the second layer bottom pipe and the main filling pipe 6. The second gate valve 10 is opened, and the filling material flows through the main filling pipe and the first three-way pipe 51 in sequence to fill the second layer until the second layer is filled, and the third layer is excavated. After the mining is completed, the third gate valve 11 located on the second layer is opened to fill the third layer until the filling is completed.

[0051] To summarize, the utility model provides a rapid-assembly downward entry filling device, which, through the processing of prefabricated components and rapid on-site assembly, and the method of layered mining and filling, not only improves the construction efficiency and avoids the complexity and time consumption of traditional on-site construction, but also ensures the safety of mining work. The utility model is applied to a top-down filling scheme, which effectively fills the goaf of the lower layer by pre-burying and assembling pipes in the upper layer, significantly improving the filling connection rate, and by setting multiple filling pipes and gate valves, precise control of the filling process is achieved.

[0052] The above embodiments are only used to illustrate the technical solution of the utility model rather than to limit it. Although the utility model is described in detail with reference to the preferred embodiments, those skilled in the art should understand that the technical solution of the utility model can be modified or replaced by equivalents without departing from the spirit and scope of the technical solution of the utility model.

Claims

1. A quick-assembly downward-entry filling device, characterized in that: The downward entry filling device is arranged in the entry, and the entry includes a first layer and a second layer arranged in sequence from top to bottom; the downward entry filling device includes a first filling device arranged in the first layer; the first filling device includes a first top pipe and a first bottom pipe respectively arranged at the top and bottom of the first layer, and a third three-way pipe respectively connected to the main filling pipe, the first top pipe and the first bottom pipe arranged in the tunnel; the first top pipe includes a straight pipe and a second three-way pipe alternately connected, and the output end of the second three-way pipe is connected to the goaf of the first layer; the first bottom pipe includes a straight pipe and a first three-way pipe alternately connected, and the output end of the first three-way pipe is connected to the second layer.

2. The quick-assembly downward-entry filling device according to claim 1, characterized in that: In the first filling device, a second gate valve is provided at one end of the third three-way pipe connected to the first bottom pipe.

3. The quick-assembly downward-entry filling device according to claim 2 is characterized in that: The end of the third three-way pipeline connected to the first top pipeline is provided with a first gate valve.

4. The quick-assembly downward-entry filling device according to claim 3 is characterized in that: The third three-way pipeline is connected to the first top pipeline through an elbow pipeline.

5. The quick-assembly downward-entry filling device according to claim 1, characterized in that: A check valve is provided at the output end of the second three-way pipeline.

6. The quick-assembly downward-entry filling device according to claim 4, characterized in that: The elbow pipe, the straight pipe and the three-way pipe are all provided with threaded flanges.

7. The quick-assembly downward-entry filling device according to claim 6, characterized in that: The first filling device further comprises a pipe support, and the straight pipe in the first top pipe is fixed to the top of the first layer through the pipe support.

8. The quick-assembly downward-entry filling device according to claim 7, characterized in that: The lower part of the pipe support is fixed to the bottom of the first layer, and the upper part of the pipe support is provided with at least one fixing hole, and the straight pipe in the first top pipe passes through a fixing hole of the pipe support.

9. The quick-assembly downward-entry filling device according to claim 1, characterized in that: The downward inlet filling device also includes a second filling device arranged in the second layer, and the inlet also includes a third layer arranged below the second layer. The second filling device includes a second bottom pipe arranged at the bottom of the second layer and a main filling pipe connected to the second bottom pipe; the second bottom pipe includes a straight pipe and a first three-way pipe alternately connected, and the output end of the first three-way pipe is connected to the third layer.

10. The quick-assembly downward-entry filling device according to claim 9, characterized in that: A third gate valve is provided at the connecting end of the main filling pipe and the second bottom pipe.

Citation Information

Cited By

  • Quick assembly type downward drift filling method

    CN120830539A

  • Wave-type staggered filling mining method for high and low drift cooperative roof contact

    CN122328199A