Edge widening structure for old pavement reconstruction
By repairing, woven and implanting link bars on old cement pavement, laying rubber asphalt stress absorption layer and asphalt concrete layer, the problems of waste pollution and unsolid connections in traditional transformation methods are solved, and the stress resistance of the pavement is improved and the durability of the overall structure.
Patent Information
- Application Number
- CN202323670095.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2023-12-29
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2033-12-29
AI Technical Summary
Traditional old cement pavement renovation methods have problems such as waste pollution, waste of resources and poor connections, resulting in uneven structure and reduced durability.
The old cement pavement is prepared with repair and woven treatment, and the widened section is laid and the link bar is implanted to cover the rubber asphalt stress absorption layer and the asphalt concrete layer, combining the mortar masonry layer and the bending pull-resistant concrete layer to form a connection between the buffered flexible pavement and the rigid base layer.
It improves the stress resistance of the pavement and the firmness and durability of the overall structure, reduces the problems of unsolid connections and uneven structures, and extends the service life of the pavement.
Smart Images

Figure CN222024814U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of road construction engineering, and in particular to a structure for widening the edge of an old road surface during reconstruction. Background Art
[0002] At present, in the field of engineering construction, the need to renovate old cement pavements to improve pavement performance and service life is becoming increasingly prominent. Traditional construction methods mainly include the removal and re-paving of old cement pavements, usually transforming them into asphalt pavements in order to improve the strength and durability of the pavement. However, this traditional renovation method has a series of problems in practical application.
[0003] First of all, the demolition of old cement pavement will generate a lot of waste, causing environmental pollution and waste of resources. The treatment of these wastes requires additional costs and resources, and also has an adverse impact on the surrounding environment.
[0004] Secondly, the traditional reconstruction method often faces problems such as loose connection and uneven structure in the process of connecting the new and old pavements. Due to the difference between the new and old materials, the connection parts are prone to cracking and breaking, which reduces the stability and durability of the overall structure. Summary of the invention
[0005] The main purpose of this application is to provide a structure for widening the edge of an old road surface reconstruction to solve the problem.
[0006] In order to achieve the above-mentioned purpose, according to one aspect of the present application, a structure for widening the edge of an old road surface reconstruction is provided.
[0007] The edge widening structure for the reconstruction of the old road surface according to the present application includes: a repaired and roughened old cement road, a widening section laid at the edge of the old cement road and flush with the end surface of the old cement road, connecting reinforcements connected between the old cement road and the widening section, a rubber asphalt stress absorption layer laid on the old cement road and the widening section, and an asphalt concrete layer laid on the rubber asphalt stress absorption layer; the widening section includes: a mortared stone layer and a flexural tensile concrete layer laid in sequence from bottom to top.
[0008] Furthermore, the old cement road comprises: an old graded crushed stone functional layer and an old cement stabilized crushed stone subbase layer laid in sequence from bottom to top and a repaired and roughened old concrete pavement layer; connecting bars are connected in the old concrete pavement layer and the flexural tensile concrete layer.
[0009] Furthermore, the connecting ribs are of threaded steel bars.
[0010] Furthermore, a concrete hardened shoulder is paved at the edge of the widened section, and the concrete hardened shoulder includes: a concrete hardened layer laid on the mortar masonry layer and connected to the flexural tensile concrete layer, the rubber asphalt stress absorption layer and the edge of the asphalt concrete layer, and shoulder earthing connected to the mortar masonry layer and the edge of the concrete hardened layer; wherein the concrete hardened layer is flush with the upper end surface of the asphalt concrete layer.
[0011] Furthermore, the flexural tensile strength of the flexural tensile concrete layer is 4.5 MPa.
[0012] Furthermore, the rubber asphalt stress absorbing layer includes: rubber asphalt, and crushed stones spread after spraying the rubber asphalt.
[0013] Furthermore, the spreading amount of rubber asphalt is 1.2-1.6 kg / m2; the spreading amount of crushed stone is 6-8 kg / m2.
[0014] Furthermore, the asphalt concrete layer includes: a lower layer of medium-grained asphalt concrete and an upper layer of fine-grained asphalt concrete.
[0015] Furthermore, the lower layer of the medium-grained asphalt concrete is medium-grained asphalt concrete AC-16C, and the layer thickness of the lower layer of the medium-grained asphalt concrete is 4.5 cm.
[0016] Furthermore, the upper layer of the fine-grained asphalt concrete is fine-grained SBS modified asphalt concrete AC-13, and the thickness of the upper layer of the fine-grained asphalt concrete is 3.5 cm.
[0017] In the embodiment of the present application, after the old cement road is completely repaired and roughened, connecting reinforcement is implanted to connect the widened section, and then a rubber asphalt stress absorption layer is laid on the old cement road and the widened section, thereby achieving the purpose of buffering the stress between the flexible pavement and the rigid base layer, thereby achieving the technical effects of improving the stress resistance of the pavement, improving the firmness and durability of the overall structure, and thus solving the related technical problems caused by directly paving the widened section of the old cement concrete pavement. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The drawings constituting a part of this application are used to provide a further understanding of this application, so that other features, purposes and advantages of this application become more obvious. The schematic embodiment drawings and their descriptions of this application are used to explain this application and do not constitute an improper limitation on this application. In the drawings:
[0019] Figure 1 It is a structural schematic diagram of the edge widening structure for old road reconstruction according to an embodiment of the present application.
[0020] Reference numerals
[0021] 1. Old cement road, 11. Old graded crushed stone functional layer, 12. Old cement stabilized crushed stone subbase, 13. Old concrete pavement layer, 2. Widening section, 21. Mortared stone layer, 22. Flexural tensile concrete layer, 3. Connecting bars, 4. Rubber asphalt stress absorption layer, 5. Asphalt concrete layer, 51. Medium-grained asphalt concrete lower layer, 52. Fine-grained asphalt concrete upper layer, 6. Concrete hardened shoulder, 61. Concrete hardened layer, 62. Shoulder earthing. DETAILED DESCRIPTION
[0022] In order to enable those skilled in the art to better understand the solution of the present application, the technical solution in the embodiments of the present application will be clearly and completely described below in conjunction with the drawings in the embodiments of the present application. Obviously, the described embodiments are only part of the embodiments of the present application, not all of the embodiments. Based on the embodiments in the present application, all other embodiments obtained by ordinary technicians in this field without creative work should fall within the scope of protection of the present application.
[0023] It should be noted that the terms "first", "second", etc. in the specification and claims of the present application and the above-mentioned drawings are used to distinguish similar objects, and are not necessarily used to describe a specific order or sequential order. It should be understood that the data used in this way can be interchanged where appropriate, so that the embodiments of the present application described here. In addition, the terms "including" and "having" and any of their variations are intended to cover non-exclusive inclusions, for example, a process, method, system, product or device comprising a series of steps or units is not necessarily limited to those steps or units clearly listed, but may include other steps or units that are not clearly listed or inherent to these processes, methods, products or devices.
[0024] In this application, the terms "upper", "lower", "left", "right", "front", "back", "top", "bottom", "inner", "outer", "middle", "vertical", "horizontal", "lateral", "longitudinal" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the drawings. These terms are mainly used to better describe the utility model and its embodiments, and are not used to limit the indicated devices, elements or components to have a specific orientation, or to be constructed and operated in a specific orientation.
[0025] In addition, some of the above terms may be used to express other meanings in addition to indicating orientation or positional relationship. For example, the term "on" may also be used to express a certain dependency or connection relationship in some cases. For those skilled in the art, the specific meanings of these terms in this utility model can be understood according to specific circumstances.
[0026] In addition, the terms "installed", "set", "provided with", "connected", "connected", and "socketed" should be understood in a broad sense. For example, it can be a fixed connection, a detachable connection, or an integral structure; it can be a mechanical connection, or an electrical connection; it can be a direct connection, or an indirect connection through an intermediate medium, or it can be an internal connection between two devices, elements, or components. For those of ordinary skill in the art, the specific meanings of the above terms in this utility model can be understood according to specific circumstances.
[0027] It should be noted that, in the absence of conflict, the embodiments and features in the embodiments of the present application can be combined with each other. The present application will be described in detail below with reference to the accompanying drawings and in combination with the embodiments.
[0028] like Figure 1 As shown, the present application relates to a structure for widening the edge of an old road surface reconstruction, comprising: an old cement road 1, a widening section 2, connecting ribs 3, a rubber asphalt stress absorbing layer 4 and an asphalt concrete layer 5. The old cement road 1 is first repaired and roughened, and then the connecting ribs 3 are implanted inwardly at the edge of the old cement road 1, and then the widening section 2 is constructed at the edge of the old cement road 1. When the surfaces of the old cement road 1 and the widening section 2 are flush, the rubber asphalt stress absorbing layer 4 and the asphalt concrete layer 5 are constructed on the surfaces of the old cement road 1 and the widening section 2. In the embodiment of the present application, after the old cement road 1 is completely repaired and roughened, the connecting ribs 3 are implanted to connect the widening section 2, and then the rubber asphalt stress absorbing layer 4 is laid on the old cement road 1 and the widening section 2, so as to achieve the purpose of buffering the stress between the flexible road surface and the rigid base layer, thereby achieving the technical effects of improving the stress resistance of the road surface, improving the firmness and durability of the overall structure, and thus solving the related technical problems caused by directly laying the widening section on the old cement concrete road surface.
[0029] In this embodiment, the old cement road 1 includes: an old graded crushed stone functional layer 11, an old cement stabilized crushed stone base layer 12 and a repaired and roughened old concrete pavement layer 13 are sequentially laid from bottom to top; the old cement pavement is treated, and new cement slabs are poured on the structures with defects such as broken plate corners and broken plates, and cracks are grouted. After the old pavement is repaired, it is roughened to ensure that the newly constructed widened section 2 can be better connected with the old cement road 1, so as to improve the stability of the connection, thereby achieving beneficial effects such as improving the quality and durability of the overall road surface.
[0030] Furthermore, the thickness of the old graded crushed stone functional layer 11 is 15 cm, the thickness of the old cement stabilized crushed stone base layer 12 is 18 cm, and the thickness of the old concrete pavement layer 13 is 20 cm; the layered design of 15 cm, 18 cm and 20 cm helps to balance the functions of each layer, reasonably distribute the load, avoids the problems that may be caused by excessive or insufficient thickness of each layer, makes the overall structure more balanced, and improves the compression resistance and durability of the pavement.
[0031] In this embodiment, the widening section 2 includes: a mortar masonry layer 21 and a flexural tensile concrete layer 22 laid sequentially from bottom to top; wherein, the thickness of the mortar masonry layer 21 is 25 cm, which provides a stable foundation support for the widening section 2, which helps to disperse the load, reduce the squeeze on the underlying soil, and improve the stability of the overall structure; the thickness of the flexural tensile concrete layer 22 is 20 cm; and the flexural tensile strength of the flexural tensile concrete layer 22 is 4.5 MPa, indicating that it has good bending resistance, making it more able to withstand traffic loads, increasing the overall stability of the widening section 2, helping to reduce the risk of structural deformation and damage, and improving the safety of the road surface.
[0032] In this embodiment, the connecting rib 3 is The threaded steel bars, the connecting bars 3 are implanted in the center of the old concrete pavement layer 13 and the flexural tensile concrete layer 22. The larger diameter and surface thread design increase the connection strength between the connecting bars 3 and the old concrete pavement 13 and the flexural tensile concrete layer 22, ensuring a stronger connection, reducing the risk of crack expansion, improving the stability and durability of the overall structure, and extending the service life of the pavement.
[0033] In this embodiment, the rubber asphalt stress absorbing layer 4 includes: rubber asphalt, and crushed stone spread after spraying the rubber asphalt; crushed stone should be spread immediately after spraying the rubber asphalt, and then rolled by a rubber-wheel roller; during spreading, the air temperature and the ground temperature must not be lower than 15°C, which helps to ensure that the rubber asphalt can be evenly laid at a suitable temperature and improve the quality and stability of the construction; the spreading amount of the rubber asphalt is 1.2-1.6 kg / m 2 The amount of crushed stone spread is 6-8 kg / m 2 , the coverage of crushed stone should reach more than 70%, and the amount of rubber asphalt spread and the coverage of crushed stone should be controlled to make the ratio of rubber asphalt absorption layer 4 more scientific and reasonable, so as to achieve better stress absorption and delay the aging of road surface. 1cm thick rubber asphalt stress absorption layer 4 is used to transition the stress of flexible asphalt concrete layer 5 and rigid cement concrete base old cement road 1 or widening section 2, so as to improve the stability of the overall road surface structure.
[0034] In this embodiment, the asphalt concrete layer 5 includes: a medium-grained asphalt concrete lower layer 51 and a fine-grained asphalt concrete upper layer 52 .
[0035] Specifically, the medium-grained asphalt concrete lower layer 51 is medium-grained asphalt concrete AC-16C, and the layer thickness of the medium-grained asphalt concrete lower layer 51 is 4.5 cm. The medium-grained asphalt concrete AC-16C is used as the lower layer, and the particle size design provides better bearing capacity, helps to disperse traffic loads, and improves the stability of the structure.
[0036] Specifically, the fine-grained asphalt concrete upper layer 52 is fine-grained SBS modified asphalt concrete AC-13, and the thickness of the fine-grained asphalt concrete upper layer 52 is 3.5 cm. It uses SBS modifier, has strong flexibility and durability, is suitable for the surface layer, and provides a smoother driving surface. Its flexibility and durability help reduce the noise generated by driving and improve driving comfort; at the same time, its good flexibility can improve the crack resistance of the asphalt concrete layer 5 and reduce the risk of cold cracks.
[0037] In this embodiment, the edge of the widening section 2 is paved with a concrete hardened shoulder 6, which includes: a concrete hardened layer 61 laid on the mortar masonry layer 21 and connected to the edges of the flexural tensile concrete layer 22, the rubber asphalt stress absorption layer 4 and the asphalt concrete layer 5, and a shoulder earthwork 62 connected to the edges of the mortar masonry layer 21 and the concrete hardened layer 61; wherein the concrete hardened layer 61 is flush with the upper end surface of the asphalt concrete layer 5. The concrete hardened shoulder 6 is arranged on the side of the fill section, which helps to provide edge support and ensure the stability of the edge of the fill section, which plays an important role in preventing the collapse and deformation of the fill slope and helps to maintain the overall stability of the road.
[0038] Specifically, the concrete hardening layer 61 is made of C25 concrete, 29 cm thick and 50 cm long; C25 concrete has a high compressive strength, so the setting of the concrete hardening layer 61 effectively improves the overall strength of the lateral end of the concrete hardened shoulder 6, reduces the deformation and damage of the concrete hardened shoulder 6, and improves its bearing capacity; the shoulder soil 62 is 0.281m 3 / m, and its slope is 1:1.5. The setting of the shoulder earthwork 62 helps to prevent soil erosion and protect the base material at the edge of the fill section; the appropriate slope optimizes the discharge of moisture, reduces the retention of moisture in the shoulder earthwork 62, reduces the erosion and damage of the shoulder earthwork 62, thereby reducing maintenance costs and extending the service life of the concrete hardened shoulder 6.
[0039] The construction steps of the structure are as follows: the old cement road 1 is first repaired and roughened, and then the connecting reinforcement 3 is implanted inwardly at the edge of the old cement road 1, and then the widening section 2 is constructed at the edge of the old cement road 1. When the surfaces of the old cement road 1 and the widening section 2 are flush, a rubber asphalt stress absorption layer 4 and an asphalt concrete layer 5 are constructed on the surfaces of the old cement road 1 and the widening section 2.
[0040] From the above description, it can be seen that the present application achieves the following technical effects: in the embodiment of the present application, after the old cement road 1 is repaired and completely roughened, connecting ribs 3 are implanted to connect the widened section 2, and then a rubber asphalt stress absorption layer 4 is laid on the old cement road 1 and the widened section 2, thereby achieving the purpose of buffering the stress between the flexible pavement and the rigid base layer, thereby achieving the technical effects of improving the stress resistance of the pavement, improving the firmness and durability of the overall structure, and thus solving the related technical problems caused by directly paving the widened section of the old cement concrete pavement.
[0041] The above description is only the preferred embodiment of the present application and is not intended to limit the present application. For those skilled in the art, the present application may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application shall be included in the protection scope of the present application.
Claims
1. A structure for widening the edge of an old road surface reconstruction, characterized in that: include: An old cement road (1) that has been repaired and roughened, a widening section (2) laid at the edge of the old cement road (1) and flush with the upper end surface of the old cement road (1), connecting bars (3) connected to the old cement road (1) and the widening section (2), a rubber asphalt stress absorption layer (4) laid on the old cement road (1) and the widening section (2), and an asphalt concrete layer (5) laid on the rubber asphalt stress absorption layer (4); the widening section (2) comprises: a mortared stone layer (21) and a flexural tensile concrete layer (22) laid in sequence from bottom to top.
2. The old road reconstruction edge widening structure according to claim 1 is characterized in that: The old cement road (1) comprises: an old graded crushed stone functional layer (11) and an old cement stabilized crushed stone subbase (12) laid in sequence from bottom to top and an old concrete pavement layer (13) that has been repaired and roughened; the linking bars (3) are connected in the old concrete pavement layer (13) and the flexural tensile concrete layer (22).
3. The old road reconstruction edge widening structure according to claim 1 is characterized in that: The connecting rib (3) is of threaded steel bars.
4. The edge widening structure for old road reconstruction according to claim 1 is characterized in that: A concrete hardened shoulder (6) is paved at the edge of the widening section (2), and the concrete hardened shoulder (6) comprises: a concrete hardened layer (61) paved on the mortared stone layer (21) and connected to the edges of the flexural tensile concrete layer (22), the rubber asphalt stress absorption layer (4) and the asphalt concrete layer (5), and a shoulder earthwork (62) connected to the edges of the mortared stone layer (21) and the concrete hardened layer (61); wherein the concrete hardened layer (61) is flush with the upper end surface of the asphalt concrete layer (5).
5. The edge widening structure for old road reconstruction according to claim 1 is characterized in that: The flexural tensile strength of the flexural tensile concrete layer (22) is 4.5 MPa.
6. The old road reconstruction edge widening structure according to claim 1 is characterized in that: The rubber asphalt stress absorbing layer (4) comprises: rubber asphalt, and crushed stones spread after spraying the rubber asphalt.
7. The old road reconstruction edge widening structure according to claim 6 is characterized in that: The amount of rubber asphalt sprayed is 1.2-1.6 kg / m 2 The amount of crushed stone spread is 6-8 kg / m 2 .
8. The old road reconstruction edge widening structure according to claim 1 is characterized in that: The asphalt concrete layer (5) comprises: a medium-grained asphalt concrete lower layer (51) and a fine-grained asphalt concrete upper layer (52).
9. The old road reconstruction edge widening structure according to claim 8, characterized in that: The medium-grained asphalt concrete lower layer (51) is medium-grained asphalt concrete AC-16C, and the layer thickness of the medium-grained asphalt concrete lower layer (51) is 4.5 cm.
10. The old road reconstruction edge widening structure according to claim 8, characterized in that: The fine-grained asphalt concrete upper layer (52) is fine-grained SBS modified asphalt concrete AC-13, and the thickness of the fine-grained asphalt concrete upper layer (52) is 3.5 cm.