High-strength aluminum alloy anchoring structure

Through the design of anchor rod and round table structure with high-strength aluminum alloy material, the stability and pull-out resistance of anchor rods under external force are solved, and more efficient on-site installation and longer service life are achieved.

CN222043899UInactive Publication Date: 2024-11-22TIANJIN UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420635833.4
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-29
Publication Date
2024-11-22
Estimated Expiration
Not applicable · inactive patent

AI Technical Summary

Technical Problem

Existing anchor bolts are prone to anchor damage under the action of external forces, which are difficult to repair, insufficient connection performance, low pull-out resistance, inconvenient on-site installation, low assembly efficiency, easy to rust, and poor applicability.

Method used

The anchor rod and round table structure is designed using high-strength aluminum alloy material. A hook is installed at the lower end of the anchor rod, and nuts are arranged on the upper and lower ends of the round table and threaded connections between the anchor rods. The round table is composed of two parts, fixed by bolts, and reserved holes are added to enhance the pull-off resistance. Adopt prefabricated structure to improve on-site installation efficiency.

Benefits of technology

It significantly improves the connection performance and pull-out resistance of the anchor structure, simplifies the on-site installation process, reduces the risk of rust, and improves the installation efficiency and service life.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222043899U_ABST
    Figure CN222043899U_ABST
Patent Text Reader

Abstract

The utility model provides a high-strength aluminum alloy anchoring structure which effectively solves the problems that an existing anchoring structure is not firm, the connection performance needs to be improved, the pulling resistance is insufficient, the anchoring structure is not suitable for field assembly, and the assembly degree is insufficient. According to the technical scheme, the anchor rod comprises an anchor rod body, a hook is arranged at the lower end of the anchor rod body, a circular truncated cone is arranged on the anchor rod body and located on the upper side of the hook, and nuts sleeving the anchor rod body are arranged above and below the circular truncated cone and connected with the anchor rod body through threads and abut against the upper end face and the lower end face of the circular truncated cone; the circular truncated cone is composed of two parts, the two parts of the circular truncated cone are separated along the axis of the circular truncated cone, and the two parts of the circular truncated cone are fixed together through a plurality of bolts; the prefabricated anchor bolt is ingenious in structure, the connecting performance of the anchoring structure can be greatly enhanced, the shear resistance of the concrete tenon is greatly improved to improve the overall pulling resistance of the anchor bolt, and meanwhile the field installation efficiency can be greatly improved by adopting the prefabricated structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of concrete bridge anchoring, in particular to a high-strength aluminum alloy anchoring structure. Background Art

[0002] Anchor bolts are often used to anchor the main load-bearing components of concrete bridges. As a commonly used fastener, anchor bolts are easily damaged by external forces and are difficult to repair, which requires improving their anchoring capacity during design. At the same time, considering the working environment of anchor bolts, the existing anchor bolt structure is not reliable, the connection performance is insufficient, and the pull-out resistance needs to be improved. At the same time, the existing anchor bolt structure is not easy to fine-tune during on-site installation and use, and the installation or assembly efficiency is low. The applicability problem of conventional anchor bolts caused by rust needs to be solved urgently.

[0003] A high-strength aluminum alloy anchoring structure is now provided, which can greatly enhance the connection performance at the anchoring structure, greatly improve the shear resistance of the concrete tenon to improve the overall pull-out resistance of the anchor bolt, and at the same time, the use of an assembled structure can greatly improve the on-site installation efficiency. Utility Model Content

[0004] In view of the above situation, in order to overcome the defects of the prior art, the utility model provides a high-strength aluminum alloy anchoring structure, which effectively solves the problems of the existing anchoring structure being unreliable, the connection performance needs to be improved, the pull-out resistance is insufficient, it is not suitable for on-site assembly, and the degree of assembly is insufficient.

[0005] The technical solution is to include an anchor rod, a hook is arranged at the lower end of the anchor rod, a truncated table is arranged on the anchor rod, the truncated table is located on the upper side of the hook, nuts are arranged above and below the truncated table and are sleeved on the anchor rod, the nut is connected to the anchor rod through threads, and the nut abuts against the upper and lower end surfaces of the truncated table; the truncated table is composed of two parts, the two parts of the truncated table are separated along the axis of the truncated table, and the two parts of the truncated table are fixed together by multiple bolts.

[0006] Furthermore, a plurality of reserved holes are provided on the two parts of the truncated table, and bolts are passed through the reserved holes to fix the two parts of the truncated table together.

[0007] Furthermore, the truncated platform is provided with horizontal holes, which penetrate through the truncated platform.

[0008] The utility model has an ingenious structure, can greatly enhance the connection performance at the anchoring structure, greatly improve the shear resistance of the concrete tenon to improve the overall pull-out resistance of the anchor bolt, and at the same time the use of an assembled structure can greatly improve the on-site installation efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0009] Figure 1 It is an overall schematic diagram of the utility model.

[0010] Figure 2It is a front sectional view of the utility model.

[0011] Figure 3 It is a side sectional view of the utility model.

[0012] Figure 4 It is a top sectional view of the utility model.

[0013] Figure 5 It is a bottom sectional view of the utility model. DETAILED DESCRIPTION

[0014] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings.

[0015] Depend on Figures 1 to 5 It is given that the utility model includes an anchor rod 1, a hook 2 is arranged at the lower end of the anchor rod 1, a frustum 3 is arranged on the anchor rod 1, the frustum 3 is located on the upper side of the hook 2, nuts 4 which are sleeved on the anchor rod 1 are arranged above and below the frustum 3, the nuts 4 are connected to the anchor rod 1 through threads, and the nuts 4 are abutted against the upper and lower end surfaces of the frustum 3; the frustum 3 is composed of two parts, the two parts of the frustum 3 are separated along the axis of the frustum 3, and the two parts of the frustum 3 are fixed together by multiple bolts.

[0016] A plurality of reserved holes 5 are provided on the two parts of the truncated platform 3 , and bolts are passed through the reserved holes 5 to fix the two parts of the truncated platform 3 together.

[0017] In order to increase the pull-out resistance, a horizontal hole 6 is provided on the truncated cone 3 , and the hole 6 passes through the truncated cone 3 .

[0018] It is worth noting that in this solution, a high-strength aluminum alloy structure is adopted as the whole, which is not easy to rust during long-term use and has high material strength. At the same time, the hook 2 is offset against the bottom surface of the cone 3, which can reduce the probability of the anchor bolt being directly pulled out during the anti-pull-out process and increase the service life of the anchor bolt.

[0019] In this solution, the side of the truncated cone 3 is provided with a through hole 6, which can strengthen the connection performance between the anchor rod 1 and the sleeve of the truncated cone 3 after the anchor structure is installed and poured with concrete. After the truncated cone 3 is spliced ​​and poured with concrete, when the concrete is dense, the gaps in the multiple positioning holes 6 reserved thereon will also be filled with concrete after the steel wire or rivet is inserted, and the holes 6 reserved in the middle will form through concrete tenons, that is, the concrete strengthens the splicing effect of the steel wire or rivet on the truncated cone 3, and also plays a certain positioning role on the spliced ​​truncated cones 3 on both sides, reducing the risk of displacement of the truncated cones 3 on both sides in different directions and misalignment, thereby causing anchor failure. At the same time, the opening in the middle of the truncated cone 3 can effectively avoid the up and down movement caused by insufficient friction between the anchor rod 1 and the reserved hole 5 when the threads of the upper and lower nuts 4 or the threads of the anchor rod 1 are damaged, because the truncated cone 3 and the anchor rod 1 are simply spliced ​​together through the reserved vertical holes 6 and the upper and lower positioning nuts 4. That is, after the middle reserved hole 5 is poured with concrete, the friction between the concrete and the middle anchor rod 1 is much greater than the friction between the anchor rod 1 and the aluminum alloy reserved hole 5, which plays a role in strengthening the connection between the anchor rod 1 and the truncated cone 3.

[0020] Similarly, the hole 6 described in this scheme can form a PBL shear key with the poured concrete, relying on the shear resistance of the concrete tenon inside it to improve the overall pull-out resistance of the anchor bolt. The PBL shear key mainly bears longitudinal shear force, transverse shear force and separation force, among which the longitudinal shear force and separation force are mainly borne by the concrete tenon formed in the circular opening and the through steel bars therein; the transverse shear force is borne by the perforated steel plate. After the truncated cone 3 is spliced, a through hole 6 is left in the middle thereof. After the concrete is poured, the hole 6 is filled with concrete to form a cylindrical concrete tenon. The concrete tenon is connected to the external concrete at both ends. During the pull-out resistance of the anchor rod 1, the concrete tenon is against the lower surface of the reserved hole 5 of the truncated cone 3, that is, a structure similar to the above-mentioned PBL is formed, which can resist longitudinal shear force and vertical separation force, that is, improve the pull-out resistance of the anchor bolt. At the same time, in the direction of the vertical circular hole opening, the entire truncated cone 3 also increases the contact area between the anchor bolt and the concrete, similar to the role of the vertical hole steel plate in the PBL shear key, which can resist the lateral shear force, that is, reduce the risk of the anchor bolt being pulled out due to lateral displacement.

[0021] In addition, the anchor bolt structure adopts a spliced ​​assembled truncated table 3, and a fixed hole 6 is reserved. At the same time, the anchor rod 1 and the truncated table 3 are connected by bolts. The overall structure has a small amount of on-site work and a high degree of assembly. Prefabricated parts are usually produced in a well-controlled factory environment, which can ensure the quality and accuracy of the components. By reserving the holes 6 during the prefabrication process, the position of the splicing can be ensured to be accurate, avoiding additional processing work on site. The truncated table 3 is fixed and positioned by two nuts 4, which is simple and effective, making the assembly and disassembly of the structure relatively easy, with good adjustability, and can be fine-tuned during the installation process to ensure accurate alignment and firm connection of the structure. The use of prefabricated parts reduces the time and human resources required for on-site construction, while reducing dependence on the on-site working environment. In addition, the standardized design of prefabricated parts allows them to be reused in different projects, further improving efficiency and economy. This assembly design not only improves the quality and performance of the structure, but also reduces construction costs and time, so it has broad application prospects in engineering practice.

[0022] The utility model has an ingenious structure, can greatly enhance the connection performance at the anchoring structure, greatly improve the shear resistance of the concrete tenon to improve the overall pull-out resistance of the anchor bolt, and at the same time the use of an assembled structure can greatly improve the on-site installation efficiency.

Claims

1. A high-strength aluminum alloy anchoring structure, characterized in that: The invention comprises an anchor rod (1), a hook (2) is arranged at the lower end of the anchor rod (1), a truncated platform (3) is arranged on the anchor rod (1), the truncated platform (3) is located on the upper side of the hook (2), nuts (4) which are sleeved on the anchor rod (1) are arranged above and below the truncated platform (3), the nut (4) is connected to the anchor rod (1) via threads, and the nut (4) abuts against the upper and lower end surfaces of the truncated platform (3); the truncated platform (3) consists of two parts, the two parts of the truncated platform (3) are separated along the axis of the truncated platform (3), and the two parts of the truncated platform (3) are fixed together via a plurality of bolts.

2. A high-strength aluminum alloy anchoring structure according to claim 1, characterized in that: A plurality of reserved holes (5) are provided on both parts of the truncated platform (3), and bolts are passed through the reserved holes (5) to fix the two parts of the truncated platform (3) together.

3. A high-strength aluminum alloy anchoring structure according to claim 1, characterized in that: The truncated platform (3) is provided with a horizontal hole (6), and the hole (6) passes through the truncated platform (3).