Sludge solidification grouting construction system
Through the sludge curing grouting construction system, mineral-based soft soil cementitious materials are used, which solves the problems of long construction cycle, high cost and poor structural strength of the foundation curing in the sludge zone under cement solidification method, and achieves rapid, low cost and high strength Sludge curing effect.
Patent Information
- Application Number
- CN202420743566.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-11
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-11
AI Technical Summary
In the prior art, the foundation curing of the silt zone adopts cement solidification method, resulting in a long construction period, high cost and poor structural strength, which is easy to be damaged in subsequent construction.
The sludge solidification grouting construction system is adopted, including agitating units, storage units, batching units, pumping units and leveling and compacting units, and mineral-based soft soil cementitious materials are used to replace silicate cement, and by controlling the raw material ratio and The stirring method ensures uniform distribution, achieving rapid curing and high strength.
It shortens the construction cycle, reduces costs, improves the structural strength of the silt zone, reduces environmental impact and energy consumption, saves 30% investment costs compared with traditional cement slurry grouting construction, and improves the durability after curing.
Smart Images

Figure CN222065474U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of sludge solidification, in particular to a sludge solidification grouting construction system. Background Art
[0002] Silt solidification treatment refers to fixing harmful substances in silt in the structure through physical, chemical or biological methods, so that it no longer has fluidity and permeability, thereby achieving the purpose of reducing pollution and protecting the environment. When carrying out road construction in silt areas, it is necessary to solidify the foundation of the silt area to ensure the normal construction of the road.
[0003] At present, the main method for solidifying the foundation of the silt zone is to excavate a hole in the silt zone and then pour cement so that the foundation of the silt zone can be solidified after the cement solidifies. Under the above solidification method, although the solidification of the silt zone foundation can be achieved, the use of cement to solidify the silt zone foundation will not only make the solidification construction period of the silt zone foundation longer and the construction cost higher, but also make the structural strength of the silt zone foundation after solidification poor, which is easy to be damaged in the subsequent construction process. Utility Model Content
[0004] 1. Technical issues to be resolved
[0005] The technical problem to be solved by the utility model is to provide a sludge solidification grouting construction system in view of the current status of the prior art.
[0006] (II) Technical solution
[0007] The utility model is realized through the following technical scheme: the utility model proposes a sludge solidification grouting construction system, including a stirring unit, a material storage unit, a batching unit, a pumping unit and a leveling and compacting unit, wherein the stirring unit is mainly used to stir the mud pumped to the solidification position to ensure the uniform distribution of the solidified mud; the material storage unit is mainly used to store the mud raw materials and gel materials for solidification; the batching unit is mainly used to configure the solidified mud; the pumping unit is mainly used to transport the configured solidified mud to the construction site; the leveling and compacting unit is mainly used to level and compact the solidified sludge area.
[0008] Furthermore, the material storage unit includes a main material bin and an auxiliary material bin.
[0009] By adopting the above technical solution, the main material bin is mainly used to store the main raw materials for sludge solidification, and the auxiliary material bin is mainly used to store the gel material that assists the main material of sludge solidification in solidification.
[0010] Furthermore, the batching unit includes an air compressor and a mixing bin, wherein the mixing bin is located below the main bin and the auxiliary bin, and the batching unit is connected to the pumping unit through a pipeline.
[0011] By adopting the above technical solution, the ratio of the raw materials for sludge solidification can be controlled by controlling the opening and closing of the main silo and the auxiliary silo, so as to prepare the final grouting raw materials in the mixing silo.
[0012] Furthermore, the pumping unit mainly uses a solidifying material conveying pump to convey the solidifying slurry.
[0013] By adopting the above technical solution, the raw materials for sludge solidification can be conveniently transported to the sludge area under the action of the pumping unit.
[0014] Furthermore, the stirring unit is an amphibious stirring device, and the stirring head of the stirring unit extends into the sludge solidification position.
[0015] By adopting the above technical solution, the stirring unit is mainly used to ensure the uniform distribution of the solidifying material in the mud area.
[0016] Furthermore, the leveling and compacting unit includes an excavator, a bulldozer and a vibratory roller.
[0017] By adopting the above technical solution, the leveling and compacting unit is mainly used to level and compact the upper side of the solidified silt zone to ensure normal road construction.
[0018] Furthermore, the discharge pipe of the pumping unit is located at the stirring head of the stirring unit.
[0019] By adopting the above technical solution, it is possible to ensure that the sludge solidification material is precisely sprayed to the grouting position.
[0020] (III) Beneficial effects
[0021] Compared with the prior art, the utility model has the following beneficial effects:
[0022] In order to solve the problem that the current method of solidifying the foundation of the silt zone is mainly to pour cement after digging a hole in the silt zone, so that the foundation of the silt zone can be solidified after the cement solidifies, although the solidification of the silt zone foundation can be achieved under the above solidification method, the use of cement to solidify the silt zone foundation will not only make the solidification construction period of the silt zone foundation longer and the construction cost higher, but also make the structural strength of the silt zone foundation after solidification and molding poor, and it is easy to be damaged in the subsequent construction process. The utility model adopts mineral-based soft soil cementitious materials instead of silicate cement as the soft soil solidification material when used, which effectively It reduces environmental impact and energy consumption, and the mineral-based soft soil cementitious material slurry has a water seepage rate of 0 and an expansion rate greater than 1% (with micro-expansion). It is resistant to chloride ion and sulfate ion corrosion and meets the application requirements of different types of soil. At the same time, high-performance mineral-based cementitious materials overcome the problems of water seepage and large shrinkage of cement materials, and the fast curing speed can shorten the construction period. More than 80% of the soil is original state, with low cost and less transportation cost. Therefore, the grouting construction period can be shortened. Compared with traditional cement slurry grouting construction, it can save about 30% of investment costs. At the same time, the structural strength of the silt zone after grouting is much greater than the strength of the cement after solidification, and it is not easy to be damaged during later construction. BRIEF DESCRIPTION OF THE DRAWINGS
[0023] Figure 1 It is a structural frame diagram of the sludge solidification grouting construction system of the utility model.
[0024] The following are the descriptions of the reference numerals:
[0025] 1. Material storage unit; 2. Batching unit; 3. Pumping unit; 4. Mixing unit; 5. Leveling and compacting unit. DETAILED DESCRIPTION
[0026] In order to make the purpose, technical solution and advantages of the utility model more clear, the utility model is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described here are only used to explain the utility model and are not used to limit the utility model.
[0027] like Figure 1As shown, the sludge solidification grouting construction system in this embodiment includes a stirring unit 4, a storage unit 1, a batching unit 2, a pumping unit 3 and a leveling and compacting unit 5, wherein the stirring unit 4 is mainly used to stir the mud pumped to the solidification position to ensure the uniform distribution of the solidified mud; the storage unit 1 is mainly used to store the solidification mud raw materials and gel materials, and the storage unit 1 includes a main material bin and an auxiliary material bin, wherein the main material bin is mainly used to store the main raw materials for sludge solidification, and the auxiliary material bin is mainly used to store the gel materials that assist the sludge solidification main materials in solidification; the batching unit 2 is mainly used to configure the solidified mud, and the ratio of the raw materials for sludge solidification can be controlled by controlling the opening and closing of the main material bin and the auxiliary material bin, so as to obtain the final grouting raw materials in the mixing bin; the pumping unit 3 is mainly used to transport the configured solidified mud to the construction site; the leveling and compacting unit 5 is mainly used to level and compact the solidified sludge area.
[0028] like Figure 1 As shown, in this embodiment, the batching unit 2 includes an air compressor and a mixing bin, wherein the mixing bin is located below the main bin and the auxiliary bin, and the batching unit 2 is connected to the pumping unit 3 through a pipeline. The pumping unit 3 mainly uses a solidifying material conveying pump to realize the conveying of solidified mud. Under the action of the pumping unit 3, the raw materials for sludge solidification can be conveniently conveyed to the sludge area. The stirring unit 4 is an amphibious stirring equipment, and the stirring head of the stirring unit 4 extends into the sludge solidification position. The stirring unit 4 is mainly used to ensure the uniform distribution of the solidifying materials in the sludge area.
[0029] like Figure 1 As shown, in this embodiment, the leveling and compacting unit 5 includes an excavator, a bulldozer and a vibratory roller. The leveling and compacting unit 5 is mainly used to level and compact the upper side of the solidified silt zone to ensure the normal construction of the road. The discharge pipe of the pumping unit 3 is located at the mixing head of the mixing unit 4, which can ensure the precise injection of the silt solidification material to the grouting position.
[0030] The specific implementation process of this embodiment is as follows: when solidifying the silt zone, firstly, the water and silt in the pre-excavated pits at the construction location are discharged, and the configured solidifying raw materials are pumped into the pre-excavated pits in the silt solidification zone by the pumping unit 3, and then the silt soil is solidified by the stirring unit 4 in situ vertical up and down stirring and solidification. To ensure the uniformity of stirring, the vertical up and down stirring is performed multiple times within the solidification depth range, for no less than three cycles, and the curing agent is sprayed while stirring for the first two times. At the same time, the descending and lifting rates are controlled. If the speed is too fast, part of the silt soil will be solidified. It is difficult to mix evenly with the curing agent, and too slow a speed will cause the curing agent to aggregate and form lumps, affecting the uniformity of the solidified soil. Therefore, according to the actual situation, the operator of the on-site curing equipment can increase the number of air stirring to ensure uniform mixing. After the silt soil is solidified in situ, the surface is simply trimmed with the help of the excavator in the leveling and compacting unit 5, and then the solidified soil is cured in situ for 28 days. After the curing is completed, the bulldozer in the leveling and compacting unit 5 is used to roughly level the surface and make a road arch. Then, the vibratory roller in the leveling and compacting unit 5 is used to compact the surface to complete the silt resistance solidification construction.
[0031] By using mineral-based soft soil cementitious materials instead of silicate cement as soft soil solidification materials, environmental impact and energy consumption are effectively reduced. In addition, the slurry of mineral-based soft soil cementitious materials has a water seepage rate of 0, an expansion rate greater than 1% (with micro-expansion), and is resistant to chloride ion and sulfate ion corrosion, and can meet the application requirements of different types of soil. At the same time, high-performance mineral-based cementitious materials overcome the problems of water seepage and large shrinkage of cement materials, and the fast curing speed can shorten the construction period. More than 80% of the soil is original state, with low cost and less transportation cost. Therefore, the grouting construction period can be shortened, and the investment cost can be saved by about 30% compared with traditional cement slurry grouting construction. At the same time, the structural strength of the silt zone after grouting is much greater than the strength of the cement after solidification, and it is not easy to be damaged during later construction.
[0032] The above description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be apparent to those skilled in the art, and the general principles defined herein may be implemented in other embodiments without departing from the spirit or scope of the present invention. Therefore, the present invention will not be limited to the embodiments shown herein, but will conform to the widest scope consistent with the principles and novel features disclosed herein.
Claims
1. The silt solidification grouting construction system is characterized by: The invention comprises a stirring unit (4), a material storage unit (1), a batching unit (2), a pumping unit (3) and a leveling and compacting unit (5), wherein the stirring unit (4) is mainly used to stir the mud pumped to the solidification position to ensure the uniform distribution of the solidified mud; the material storage unit (1) is mainly used to store the mud raw materials and gel materials for solidification; the batching unit (2) is mainly used to configure the solidified mud; the pumping unit (3) is mainly used to transport the configured solidified mud to the construction site; and the leveling and compacting unit (5) is mainly used to level and compact the solidified silt zone.
2. The sludge solidification grouting construction system according to claim 1 is characterized in that: The material storage unit (1) comprises a main material bin and an auxiliary material bin.
3. The sludge solidification grouting construction system according to claim 2 is characterized in that: The batching unit (2) comprises an air compressor and a mixing bin, wherein the mixing bin is located below the main bin and the auxiliary bin, and the batching unit (2) is connected to the pumping unit (3) via a pipeline.
4. The sludge solidification grouting construction system according to claim 1 is characterized in that: The pumping unit (3) mainly uses a solidifying material conveying pump to convey the solidifying slurry.
5. The sludge solidification grouting construction system according to claim 1 is characterized in that: The stirring unit (4) is an amphibious stirring device, and the stirring head of the stirring unit (4) extends into the sludge solidification position.
6. The sludge solidification grouting construction system according to claim 1 is characterized in that: The leveling and compacting unit (5) comprises an excavator, a bulldozer and a vibratory roller.
7. The sludge solidification grouting construction system according to claim 1 is characterized in that: The discharge pipe opening of the pumping unit (3) is located at the stirring head of the stirring unit (4).