Pre-vacuumizing device and helium detection testing equipment
By using a pre-vacuum device to be tested before the helium detection and testing device to be tested, the problem of long test cycle and low accuracy in the detection of long pipe diameter and large pipelines is solved, and the existing helium detection and testing device is solved, thus achieving the problem of long-term and low-accuracy testing device. More efficient testing and longer equipment life.
Patent Information
- Application Number
- CN202420708254.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-08
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2034-04-08
AI Technical Summary
The existing helium testing and testing devices cannot operate normally when detecting long pipe diameters and large pipes, and the test cycle is long, resulting in reduced accuracy of the test results and short service life.
Design a pre-vacuum device, and perform pre-vacuum processing on the pipeline to be tested through a pre-vacuum pump and a pre-vacuum pipeline until the pre-set vacuum pressure is reached, and then the helium detection device is used to ensure the accuracy of the test results and the equipment. service life.
It shortens the helium test cycle, improves working efficiency, extends the service life of the helium test device, and ensures the accuracy of the test results.
Smart Images

Figure CN222066984U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of semiconductors, in particular to a pre-vacuuming device and helium detection and testing equipment. Background Art
[0002] Most of the process gases used in the semiconductor manufacturing process are hazardous, so the process gas delivery needs to be tested for safety to test whether the pipeline meets the airtightness requirements. For the above test, helium detection test devices are often used in the prior art to detect the pipeline sealing.
[0003] At present, due to the large amount of process gas, there are pipelines with long paths and large diameters. Existing helium detection test devices may not operate normally or have long test cycles when testing them, resulting in reduced accuracy of test results, potential dangers, and reduced service life of the test device.
[0004] Therefore, there is an urgent need for a pre-vacuum device and a helium detection test equipment to solve the above technical problems. Utility Model Content
[0005] One purpose of the utility model is to provide a pre-vacuum device, which can assist the helium detection test device to perform tests accurately, shorten the test cycle, improve work efficiency, extend the service life of the helium detection device, and ensure the accuracy of the test results.
[0006] To achieve this purpose, the utility model adopts the following technical solutions:
[0007] The pre-vacuum device is used to pre-vacuum the pipeline to be tested before the helium detection device detects the pipeline to be tested; the pre-vacuum device includes:
[0008] A pre-vacuum pump is used to pre-vacuum the pipeline to be tested;
[0009] A pre-pumping pipeline, wherein the first port of the pre-pumping pipeline is connected to the output pipe of the pre-pumping vacuum pump, and the second port of the pre-pumping pipeline is detachably connected to the pipeline to be tested;
[0010] The pre-pumping control valve is arranged on the pre-pumping pipeline. The pre-pumping control valve is used to open or close the pre-pumping pipeline to connect or disconnect the pre-pumping vacuum pump and the pipeline to be tested.
[0011] Optionally, the output pipe of the pre-vacuum pump is provided with a first flange, the first port of the pre-vacuum pipeline is provided with a second flange, and the first flange and the second flange are sealed and connected.
[0012] Optionally, the pre-pumping pipeline is a hose.
[0013] Optionally, the pre-pumping control valve is a solenoid control valve, a manual control valve or a pneumatic control valve.
[0014] Optionally, it further comprises a connecting pipeline, the connecting pipeline is connected to the pipeline to be tested, and the connecting pipeline, the pre-pumping pipeline and the helium detection device are connected via a three-way pipe.
[0015] Optionally, a vacuum pressure gauge is provided on the above-mentioned connecting pipeline to detect the pressure of the above-mentioned pipeline to be tested.
[0016] Optionally, the pre-vacuum device further comprises a mobile trolley, and the pre-vacuum pump, the pre-vacuum pipeline and the pre-vacuum control valve are all arranged on the mobile trolley.
[0017] Optionally, the moving trolley is provided with a handle for pushing and pulling the moving trolley.
[0018] Another object of the utility model is to provide a helium detection test device, which can shorten the test cycle, improve work efficiency, extend the service life of the helium detection device, and ensure the accuracy of the test results.
[0019] To achieve this purpose, the utility model adopts the following technical solutions:
[0020] The helium detection test equipment comprises a helium detection device and a pre-vacuum device as described in any of the above schemes, wherein both the helium detection device and the pre-vacuum device can be connected to the pipeline to be tested.
[0021] Optionally, the output end of the helium detection device is connected to a helium detection pipeline, the helium detection pipeline is connected to the pipeline to be tested, and a helium detection control valve is provided on the helium detection pipeline, and the helium detection control valve is used to open or close the helium detection pipeline to connect or disconnect the helium detection device and the pipeline to be tested.
[0022] Beneficial effects of the utility model:
[0023] The utility model provides a pre-vacuum device and a helium detection test equipment. When performing a helium detection test on a pipeline to be tested with a large pipeline diameter and a long pipeline, the pre-vacuum pipeline is first connected to the pipeline to be tested, and the pre-vacuum control valve is opened. At this time, the helium detection device and the pipeline to be tested are not connected; the pre-vacuum pump is opened to pre-vacuum the pipeline to be tested until a preset vacuum pressure is reached, the pre-vacuum pump and the pre-vacuum control valve are closed, and the helium detection device is connected to the pipeline to be tested. The helium detection device determines whether the vacuum pressure value meets the requirements, and if so, a helium detection is performed; if not, the helium detection device vacuums the pipeline to be tested until the required vacuum pressure value is met, and then a helium detection is performed. By setting a pre-vacuum device and using the pre-vacuum pump to pre-vacuum the pipeline to be tested with a fast and high-power process, not only can the test rate in the helium detection process be reduced, but also the vacuuming time of the helium detection device is greatly reduced, the use time of the helium detection device is reduced, and the service life of the helium detection device is increased. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is an axonometric diagram of a pre-vacuuming device provided in a specific embodiment of the utility model;
[0025] Figure 2 It is a structural schematic diagram of a helium detection test device provided by a specific implementation mode of the utility model.
[0026] In the figure:
[0027] 10. Pre-vacuum pump; 11. First flange; 12. Output pipe;
[0028] 20. Pre-extraction pipeline; 21. Second flange;
[0029] 30. Pre-pumping control valve;
[0030] 40. Mobile trolley; 41. Handle; 42. Carrying platform; 43. Wheels;
[0031] 50. Connecting pipeline; 60. Vacuum pressure gauge;
[0032] 210. Helium detection device; 220. Helium detection pipeline; 230. Helium detection control valve; 300. Pipeline to be tested. DETAILED DESCRIPTION
[0033] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It is to be understood that the specific embodiments described herein are only used to explain the present invention, rather than to limit the present invention. It should also be noted that, for ease of description, only the parts related to the present invention, rather than all structures, are shown in the accompanying drawings.
[0034] In the description of the present invention, unless otherwise clearly specified and limited, the terms "connected", "connected", and "fixed" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0035] In the present utility model, unless otherwise clearly specified and limited, a first feature being "above" or "below" a second feature may include that the first and second features are in direct contact, or may include that the first and second features are not in direct contact but are in contact through another feature between them. Moreover, a first feature being "above", "above" and "above" a second feature includes that the first feature is directly above and obliquely above the second feature, or simply indicates that the first feature is higher in level than the second feature. A first feature being "below", "below" and "below" a second feature includes that the first feature is directly below and obliquely below the second feature, or simply indicates that the first feature is lower in level than the second feature.
[0036] In the description of this embodiment, the terms "upper", "lower", "right", etc., are based on the directions or positions shown in the drawings, and are only for the convenience of description and simplified operation, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation of the present invention. In addition, the terms "first" and "second" are only used to distinguish in the description and have no special meaning.
[0037] Refer to the following Figure 1 and Figure 2 The pre-vacuum device provided by the utility model is described in detail with reference to embodiments.
[0038] Please refer to Figure 1 and Figure 2 The present embodiment provides a pre-vacuuming device, which is used to pre-vacuum the pipeline 300 before the helium detection device 210 detects the pipeline 300 to accelerate the vacuum treatment in the pipeline 300 to improve the helium detection speed of the helium detection device 210.
[0039] Please refer to Figure 1 and Figure 2Specifically, the pre-vacuum device includes a pre-vacuum pump 10, a pre-vacuum pipeline 20 and a pre-vacuum control valve 30. The pre-vacuum pump 10 is used to perform pre-vacuum treatment on the pipeline to be tested 300; the first port of the pre-vacuum pipeline 20 is connected to the output pipe 12 of the pre-vacuum pump 10, and the second port of the pre-vacuum pipeline 20 is detachably connected to the pipeline to be tested 300; the pre-vacuum control valve 30 is arranged on the pre-vacuum pipeline 20, and the pre-vacuum control valve 30 is used to open or close the pre-vacuum pipeline 20 to connect or disconnect the pre-vacuum pump 10 and the pipeline to be tested 300.
[0040] The pre-vacuum device of this embodiment, when performing a helium detection test on a pipeline 300 to be tested with a large pipeline diameter and a long pipeline, first connects the pre-vacuum pipeline 20 with the pipeline 300 to be tested, and opens the pre-vacuum control valve 30. At this time, the helium detection device 210 is not connected to the pipeline 300 to be tested; the pre-vacuum pump 10 is turned on to perform a pre-vacuum treatment on the pipeline 300 to be tested until a preset vacuum pressure is reached, and the pre-vacuum pump 10 and the pre-vacuum control valve 30 are closed, and the helium detection device 210 is connected to the pipeline 300 to be tested. The helium detection device 210 determines whether the vacuum pressure value meets the requirement, and if so, performs a helium detection; if not, the helium detection device 210 vacuums the pipeline 300 to be tested until the required vacuum pressure value is met, and then performs a helium detection. By providing a pre-vacuum device and using the pre-vacuum pump 10 to pre-vacuum the pipeline 300 to be tested quickly and with high power, not only can the test rate in the helium detection process be reduced, but also the vacuuming time of the helium detection device 210 can be greatly reduced, the use time of the helium detection device 210 can be reduced, and the service life of the helium detection device 210 can be increased.
[0041] Optionally, the output pipe 12 of the pre-vacuum pump 10 is provided with a first flange 11, and the first port of the pre-vacuum pipeline 20 is provided with a second flange 21. The first flange 11 and the second flange 21 are sealedly connected to achieve a sealed connection between the two, thereby achieving communication between the two.
[0042] It is understandable that the output pipe 12 of the pre-vacuum pump 10 and the pre-vacuum pipeline 20 may also be connected by other connection methods, as long as the connectivity and sealing of the two are met, and no specific limitation is made here.
[0043] Furthermore, the pre-pumping control valve 30 is an electromagnetic control valve, a manual control valve or a pneumatic control valve, which can realize the driving function of opening and closing the pre-pumping pipeline 20 .
[0044] Furthermore, the pre-vacuum pipeline 20 is a hose, and the hose is provided to facilitate the placement and connection of the pre-vacuum pipeline 20, so that when the pre-vacuum device is not connected to the pipeline 300 to be tested, the pre-vacuum pipeline 20 is also easier to store instead of standing upright on the pre-vacuum pump 10, and also avoids causing pressure on the pre-vacuum pump 10.
[0045] Please continue to refer to Figure 1 and Figure 2 In this embodiment, the pre-vacuum device also includes a connecting pipeline 50, which is connected to the pipeline to be tested 300. The connecting pipeline 50, the pre-vacuum pipeline 20 and the helium detection device 210 are connected through a three-way pipe; the setting of the connecting pipeline 50 can realize the connection between the helium detection device 210 and the pre-vacuum pipeline 20 and the pipeline to be tested 300 respectively.
[0046] Furthermore, a vacuum pressure gauge 60 is provided on the connecting pipeline 50 to detect the pressure of the pipeline 300 to be tested, so that when the pre-vacuum device performs vacuum extraction on the pipeline 300 to be tested, the vacuum pressure gauge 60 can provide real-time feedback on the pressure value of the pipeline 300 to be tested, until the pressure value of the pipeline 300 to be tested reaches the standard, and then the vacuum extraction process of the pipeline 300 to be tested by the pre-vacuum device can be stopped. In addition, the vacuum pressure gauge 60 is provided on the connecting pipeline 50, which can also ensure that when the helium detection device 210 performs a subsequent detection, if the pressure value has not yet reached the standard, the helium detection device 210 will perform vacuum extraction on the pipeline 300 to be tested again, and the vacuum pressure gauge 60 can obtain the pressure value of the pipeline 300 to be tested in real time until it reaches the standard.
[0047] Please continue to refer to Figure 1 and Figure 2 In the present embodiment, the pre-vacuum device further comprises a mobile trolley 40, on which the pre-vacuum pump 10, the pre-vacuum pipeline 20 and the pre-vacuum control valve 30 are all arranged, so that the pre-vacuum device is movable. When the device is not needed, it can be pushed away or used for vacuuming other pipelines. When needed, the entire pre-vacuum device can be pushed to the corresponding helium detection device 210, which does not occupy space and is convenient for placement.
[0048] Specifically, the mobile cart 40 includes a carrying platform 42 and a plurality of wheels 43 . The plurality of wheels 43 are evenly distributed at the bottom of the carrying platform 42 . The carrying platform 42 is used to carry the pre-vacuum pump 10 , and the wheels 43 are used to move the mobile cart 40 .
[0049] Further, a handle 41 is provided on the mobile trolley 40 for pushing or pulling the mobile trolley 40. Specifically, the handle 41 is provided on one side of the carrying platform 42 to push or pull the mobile trolley 40.
[0050] Please refer to Figure 1 and Figure 2This embodiment also provides a helium detection test equipment, which includes a helium detection device 210 and a pre-vacuum device as described in any of the above schemes. Both the helium detection device 210 and the pre-vacuum device can be connected to the pipeline 300 to be tested, so as to first pre-vacuum the pipeline 300 to be tested, and then perform the helium detection process of the helium detection device 210. By setting the pre-vacuum device, the helium detection test equipment shortens the test cycle, improves the work efficiency, prolongs the service life of the helium detection device 210, and ensures the accuracy of the test results.
[0051] Furthermore, the output end of the helium detection device 210 is connected with a helium detection pipeline 220, which is connected to the pipeline to be tested 300. A helium detection control valve 230 is provided on the helium detection pipeline 220, which is used to open or close the helium detection pipeline 220 to connect or disconnect the helium detection device 210 and the pipeline to be tested 300. By realizing the connection and disconnection between the helium detection device 210 and the pipeline to be tested 300, the helium detection control valve 230 is closed when pre-vacuuming is performed, so that the helium detection pipeline 220 is closed; when helium detection is performed, the pre-vacuuming pipeline 20 of the corresponding pre-vacuuming device is closed, so that the two do not interfere with each other and operate in coordination with each other.
[0052] Obviously, the above embodiments of the present invention are merely examples for the purpose of clearly illustrating the present invention, and are not intended to limit the implementation methods of the present invention. For those skilled in the art, various obvious changes, readjustments and substitutions can be made without departing from the scope of protection of the present invention. It is not necessary and impossible to list all implementation methods here. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention shall be included in the scope of protection of the claims of the present invention.
Claims
1. A pre-vacuum device, characterized in that: Used to perform a pre-vacuum treatment on the pipeline (300) to be tested before the helium detection device (210) detects the pipeline (300) to be tested; The pre-vacuum device comprises: A pre-vacuum pump (10) is used to perform a pre-vacuum treatment on the pipeline to be tested (300); A pre-evacuation pipeline (20), wherein a first port of the pre-evacuation pipeline (20) is connected to an output pipe (12) of the pre-evacuation vacuum pump (10), and a second port of the pre-evacuation pipeline (20) is detachably connected to the pipeline to be tested (300); A pre-pumping control valve (30) is arranged on the pre-pumping pipeline (20), and the pre-pumping control valve (30) is used to open or close the pre-pumping pipeline (20) so as to connect or disconnect the pre-pumping vacuum pump (10) and the pipeline to be tested (300).
2. The pre-vacuum device according to claim 1, characterized in that: The output pipe (12) of the pre-vacuum pump (10) is provided with a first flange (11), and the first port of the pre-vacuum pipeline (20) is provided with a second flange (21), and the first flange (11) and the second flange (21) are sealed and connected.
3. The pre-vacuum device according to claim 1, characterized in that: The pre-extraction pipeline (20) is a hose.
4. The pre-vacuum device according to claim 1, characterized in that: The pre-pumping control valve (30) is an electromagnetic control valve, a manual control valve or a pneumatic control valve.
5. The pre-vacuum device according to claim 1, characterized in that: It also comprises a connecting pipeline (50), wherein the connecting pipeline (50) is connected to the pipeline to be tested (300), and the connecting pipeline (50), the pre-extraction pipeline (20) and the helium detection device (210) are connected via a three-way pipe.
6. The pre-vacuum device according to claim 5, characterized in that: The connecting pipeline (50) is provided with a vacuum pressure gauge (60) for detecting the pressure of the pipeline to be tested (300).
7. The pre-vacuum device according to claim 1, characterized in that: The pre-vacuum device further comprises a movable trolley (40), and the pre-vacuum pump (10), the pre-vacuum pipeline (20) and the pre-vacuum control valve (30) are all arranged on the movable trolley (40).
8. The pre-vacuum device according to claim 7, characterized in that: The moving trolley (40) is provided with a handle (41) for pushing or pulling the moving trolley (40).
9. Helium detection test equipment, characterized in that, It comprises a helium detection device (210) and a pre-vacuum device as described in any one of claims 1 to 8, wherein both the helium detection device (210) and the pre-vacuum device can be connected to the pipeline (300) to be tested.
10. The helium detection test equipment according to claim 9, characterized in that: The output end of the helium detection device (210) is connected to a helium detection pipeline (220), the helium detection pipeline (220) is connected to the pipeline to be tested (300), and a helium detection control valve (230) is provided on the helium detection pipeline (220), and the helium detection control valve (230) is used to open or close the helium detection pipeline (220) so as to connect or disconnect the helium detection device (210) and the pipeline to be tested (300).