Gravel pile filler supervision and detection device

By using a casing assembly and lifting mechanism in the testing of crushed stone piles, the problem of high friction of the probe rod in deep testing was solved, and more accurate testing results were achieved.

CN222083627UActive Publication Date: 2024-11-29CHONGQING HONGYU WATER CONSERVANCY CONSULTING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420758602.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-12
Publication Date
2024-11-29
Estimated Expiration
2034-04-12

AI Technical Summary

Technical Problem

In the testing of deep crushed stone piles, the dynamic cone penetrometer is subjected to a large frictional force, resulting in low accuracy of the test data and failing to truly reflect the quality of the crushed stone piles.

Method used

By inserting a casing assembly into the penetration channel, the friction force during the downward movement of the penetration rod is reduced through the cooperation of the first lifting mechanism and the through hammer, thus avoiding bending and deviation and improving the accuracy of the test data.

Benefits of technology

This improves the accuracy of data from deep crushed stone pile testing, accurately reflecting the quality of the crushed stone piles.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222083627U_ABST
    Figure CN222083627U_ABST
Patent Text Reader

Abstract

The utility model discloses a gravel pile filler supervising and detecting device which comprises a rack. The rod group comprises a guide rod, a hammer pad and a sounding rod which are arranged in sequence, and the hammer pad is detachably connected with the guide rod and the sounding rod; the piercing hammer is arranged on the guide rod in a sliding and sleeving manner; the first lifting mechanism is arranged at the upper end of the guide rod and slidably connected with the rack, and the first lifting mechanism is connected with the center penetrating hammer and can drive the center penetrating hammer to ascend in a reciprocating mode relative to the guide rod; and the sleeve assembly is vertically arranged at the bottom of the rack, and the sounding rod is arranged in the sleeve assembly in a penetrating mode. With the adoption of the structure, when the penetration rod enters a large depth, the sleeve assembly can be mounted and inserted into the penetration channel, so that the movement of the penetration rod is guided, the friction force borne by the side wall of the penetration rod when the penetration rod moves downwards is reduced, the penetration rod is prevented from being bent and deviated into soil between piles outside a pile hole, the accuracy of penetration detection data is improved, and the penetration detection efficiency is improved. Therefore, the quality condition of the gravel pile at a large-depth position can be truly reflected.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of gravel pile detection, in particular to a gravel pile filling supervision and detection device. Background Art

[0002] In some waterfront drawdown areas, there are soft foundations mainly composed of silty soil and silty clay with low shear resistance. If high fill treatment is required in the drawdown area, the soft foundation in the drawdown area needs to be reinforced to avoid overall instability of the soft foundation. A common reinforcement treatment method is to implement a vibro-compacted stone pile treatment project. The vibro-compacted stone pile reinforcement foundation constructed by the project can give full play to the role of the stone pile in promoting radial drainage and accelerated consolidation of the saturated soil foundation and improving various mechanical indicators of the composite foundation. After the foundation reinforcement is completed, the construction supervisor needs to test the quality of the vibro-compacted stone pile. For the stone piles that fail the test, the construction party needs to be informed in time to rework them. Common testing methods for construction supervision include heavy-duty gravity probing and ultra-heavy-duty gravity probing. During operation, the gravity probing uses a core hammer to drive the probe rod into the stone pile, and the number of hammer blows required to drive the probe rod into the stone pile every 10 cm is recorded.

[0003] During the inspection, according to the relevant geotechnical test method standards, the depth of heavy-duty dynamic probing is generally not more than 15m, and the depth of ultra-heavy-duty dynamic probing is generally not more than 20m. With the advancement of technology, the depth of gravel piles currently exceeds 70m. When using dynamic probing to detect depths above 20m, the side wall of the probing rod will be subject to great friction, and the number of hammer blows required for every 10cm of penetration of the probing rod will be too large. In addition, the probing rod is prone to bending and deformation, and shifting to the soil between the piles outside the pile hole. In this way, for the dynamic probing inspection of gravel piles at great depths, when the probing rod is lowered to a greater depth, the probing rod is subject to greater friction, resulting in lower accuracy of the inspection data, and unable to truly reflect the quality of the gravel piles at great depths. Utility Model Content

[0004] The utility model aims to provide a monitoring and testing device for gravel pile filling material, which can improve the accuracy of dynamic penetration testing data of gravel pile.

[0005] To achieve the above-mentioned purpose, a gravel pile filling supervision and detection device is provided, which includes: a frame; a rod group, including a guide rod, a hammer pad and a sounding rod arranged in sequence, and the hammer pad is detachably connected to the guide rod and the sounding rod respectively; a core hammer slidably sleeved on the guide rod; a first lifting mechanism, which is arranged at the upper end of the guide rod and is slidably connected to the frame, the first lifting mechanism is connected to the core hammer and can drive the core hammer to reciprocate and rise relative to the guide rod; a casing assembly, which is vertically arranged at the bottom of the frame, and the sounding rod is penetrated by the casing assembly.

[0006] According to the gravel pile filling supervision and detection device, the frame includes a base frame, guide columns and a top frame connected in sequence from bottom to top, the base frame has a first mounting layer and a second mounting layer arranged up and down, the first mounting layer and the second mounting layer have coaxially arranged through holes, and the first lifting mechanism is slidably sleeved on the guide columns.

[0007] According to the gravel pile filling supervision and detection device, the casing assembly includes a first flange sleeve, a second flange sleeve and a casing section, the first flange sleeve is inserted into the through hole on the first mounting layer, the second flange sleeve is inserted into the through hole on the second mounting layer, the upper end of the casing section has an external thread head, and the lower end has an internal thread hole that cooperates with the external thread head, the casing section is inserted into the second flange sleeve, and the external thread head at the upper end of the casing section is connected to the inner side of the first flange sleeve.

[0008] According to the gravel pile filling supervision and detection device, the height of the external thread head is smaller than the height of the first flange sleeve; the width of the hammer head is larger than the inner cavity height of the first flange sleeve.

[0009] According to the gravel pile filling supervision and detection device, the first lifting mechanism includes a mounting frame, a first motor, a turntable, a connecting rod, a pull rope and a pull sleeve, the mounting frame is slidably arranged on the frame, the first motor is arranged on the top of the mounting frame, and the first motor is connected to the turntable, the edge of the turntable is rotatably connected to one end of the connecting rod, the other end of the connecting rod passes through the mounting frame and is connected to the pull rope, the end of the pull rope is connected to the pull sleeve, and a handle rod is transversely arranged on the core hammer, and a pull sleeve is provided on the rotating sleeve on the handle rod.

[0010] According to the gravel pile filling supervision and detection device, the first motor is configured as a dual-axis motor, and the turntable, connecting rod, pull rope, pull sleeve and handle rod are configured as two groups and are disposed on both sides of the first motor.

[0011] According to the gravel pile filling supervision and detection device, the mounting frame is provided with a through slot, and the lower end of the turntable extends into the through slot.

[0012] According to the gravel pile filling supervision and detection device, it also includes a second lifting mechanism, which includes a second motor, a reel, a traction rope and a lifting frame. The second motor is arranged on the top of the frame, the reel is connected to the second motor, the traction rope is wound around the reel, the lifting frame is connected to the first lifting mechanism, and the top of the lifting frame has a hanging hole, and the end of the traction rope is provided with a hook that cooperates with the hanging hole.

[0013] Beneficial effect: With the above-mentioned structure, when the sounding rod is lowered to a greater depth, a casing assembly can be installed and inserted into the sounding channel to guide the movement of the sounding rod, thereby reducing the friction force on the side wall of the sounding rod when the sounding rod moves downward and avoiding the sounding rod from bending and deviating into the soil between piles outside the pile hole, thereby improving the accuracy of the sounding detection data and truly reflecting the quality of the gravel pile at a great depth.

[0014] Additional aspects and advantages of the present invention will be given in part in the following description, and in part will become apparent from the following description, or will be learned through the practice of the present invention. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] The utility model is further described below in conjunction with the accompanying drawings and embodiments;

[0016] Figure 1 This is a structural diagram of an embodiment of the utility model when performing dynamic probing;

[0017] Figure 2 This is a structural diagram of the embodiment of the utility model when the sleeve assembly is installed;

[0018] Figure 3 is a structural diagram of the casing assembly;

[0019] Figure 4 It is a side view of the lifting frame and the first motor. DETAILED DESCRIPTION

[0020] This section will describe in detail the specific embodiments of the utility model. The preferred embodiments of the utility model are shown in the accompanying drawings. The purpose of the accompanying drawings is to supplement the description of the text part of the specification with graphics, so that people can intuitively and vividly understand each technical feature and the overall technical solution of the utility model, but it cannot be understood as a limitation on the protection scope of the utility model.

[0021] In the description of the present invention, it should be understood that descriptions involving orientation, such as up, down, front, back, left, right, etc., indicating orientations or positional relationships, are based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present invention.

[0022] In the description of the present utility model, "greater than", "less than", "exceed" etc. are understood as not including the number itself, and "above", "below", "within" etc. are understood as including the number itself. If there is a description of "first" or "second", it is only used for the purpose of distinguishing the technical features, and cannot be understood as indicating or implying the relative importance or implicitly indicating the number of the indicated technical features or implicitly indicating the order of the indicated technical features.

[0023] In the description of the present invention, unless otherwise clearly defined, terms such as setting, installing, connecting, etc. should be understood in a broad sense, and technicians in the relevant technical field can reasonably determine the specific meanings of the above terms in the present invention based on the specific content of the technical solution.

[0024] Reference Figure 1-4 A gravel pile filling supervision and detection device includes a frame 10, a rod group 20, a core hammer 30, a first lifting mechanism 40, a sleeve assembly 50 and a second lifting mechanism 60. The rod group 20 includes a guide rod 21, a hammer pad 22 and a feeler rod 23 arranged in sequence. The hammer pad 22 is detachably connected to the guide rod 21 and the feeler rod 23 in a threaded fitting manner. The feeler rod 23 adopts a structure of multiple sequential splicing, and its splicing length is determined according to the required depth of the feeler detection. The feeler rod 23 located at the bottom is installed with a cone head 24, and the width of the cone head 24 is greater than the diameter of the feeler rod 23. The core hammer 30 is slidably sleeved on the guide rod 21. The first lifting mechanism 40 is arranged at the upper end of the guide rod 21 and is slidably connected to the frame 10. The first lifting mechanism 40 is connected to the core hammer 30 and can drive the core hammer 30 to reciprocate and rise relative to the guide rod 21. The sleeve assembly 50 is vertically arranged at the bottom of the frame 10 , and the feeler rod 23 passes through the sleeve assembly 50 .

[0025] During operation, the core hammer 30 is driven to rise by the first lifting mechanism 40, and then the core hammer 30 falls and strikes the hammer pad 22, so that the feeler rod 23 and the cone head 24 are moved downward along the gravel pile for sounding, and during the sounding process, a sounding channel for accommodating the feeler rod 23 is formed on the gravel pile; when the depth of the feeler rod 23 being lowered is shallow (for example, the depth of the feeler rod 23 being lowered into the gravel pile does not exceed 15m during heavy-duty power sounding, and the depth of the feeler rod 23 being lowered into the gravel pile does not exceed 20m during super-heavy-duty power sounding), it can be adopted without installing the casing assembly 50; when the feeler rod 23 is lowered into a greater depth, the casing assembly 50 is installed, and the casing assembly 50 is inserted into the sounding channel to guide the movement of the feeler rod 23, reduce the friction force on the side wall of the feeler rod 23 when it moves downward, and avoid the feeler rod 23 from bending and deviating to the soil between the piles outside the pile hole, so as to improve the accuracy of the sounding detection data and truly reflect the quality of the gravel pile at a great depth.

[0026] In this embodiment, the frame 10 includes a base frame 11, a guide column 12 and a top frame 13 connected in sequence from bottom to top. The base frame 11 has a first mounting layer 111 and a second mounting layer 112 arranged up and down. The first mounting layer 111 and the second mounting layer 112 have coaxially arranged through holes, and the first lifting mechanism 40 is slidably mounted on the guide column 12.

[0027] The casing assembly 50 includes a first flange sleeve 51, a second flange sleeve 52 and a casing section 53. The first flange sleeve 51 is inserted into the through hole on the first mounting layer 111, the second flange sleeve 52 is inserted into the through hole on the second mounting layer 112, and the second flange sleeve 52 is detachably connected to the second mounting layer 112 by bolts. The upper end of the casing section 53 has an external thread head 531, and the lower end has an internal thread hole 532 that matches the external thread head 531. The casing section 53 is inserted into the second flange sleeve 52, and the external thread head 531 at the upper end of the casing section 53 is connected to the inner side of the first flange sleeve 51. The casing section 53 adopts a multi-jointed structure, and the joint length is determined according to the depth of insertion into the sounding channel. Specifically, the joint length can be determined in the following manner: the lower part of the sounding rod 23 extends out of the casing assembly 50, and the height difference between the lower end of the casing assembly 50 and the cone head 24 does not exceed 15-20m.

[0028] When the casing assembly 50 needs to be installed, the hammer pad 22 is first hammered to make it drop to a lower position, and then the hammer pad 22 is separated from the sounding rod 23, and the guide rod 21 and the first lifting mechanism 40 are moved up to a higher position, and the second flange sleeve 52 is first set on the second installation layer 112, and the casing section 53 is passed through the second flange sleeve 52 and inserted into the sounding channel, and the first flange sleeve 51 is installed on the upper end of the casing section 53. The hammer pad 22 moves down to abut the casing assembly 50, and the core hammer 30 is lifted by the first lifting mechanism 40, and the core hammer 30 is used to drop and hammer to drive the casing assembly 50 into the sounding channel. In this way, based on the above structure, the first lifting mechanism 40 and the core hammer 30 can be used to drive the casing assembly 50 into the sounding channel, and there is no need to set up a separate driving component to drive the casing assembly 50, which can simplify the device structure.

[0029] The height of the external thread head 531 is smaller than the height of the first flange sleeve 51, so that the core hammer 30 can hit the first flange sleeve 51 when falling, avoiding the external thread head 531 from being deformed and damaged.

[0030] In this embodiment, the first lifting mechanism 40 includes a mounting frame 41, a first motor 42, a rotating disk 43, a connecting rod 44, a pull rope 45 and a pull sleeve 46. The mounting frame 41 is slidably arranged on the guide column 12, the first motor 42 is arranged on the top of the mounting frame 41, and the first motor 42 is connected to the rotating disk 43, the edge of the rotating disk 43 is rotatably connected to one end of the connecting rod 44, the other end of the connecting rod 44 passes through the mounting frame 41 and is connected to the pull rope 45, the end of the pull rope 45 is connected to the pull sleeve 46, and the core hammer 30 is transversely provided with a handle bar 31, and the handle bar 31 is rotatably provided with the pull sleeve 46. The above structure can adopt the following working mode: the first motor 42 drives the rotating disk 43 to rotate, so as to pull the core hammer 30 upward through the connecting rod 44 and the pull rope 45, and then the first motor 42 is powered off to release the core hammer 30 freely, and after the core hammer 30 hits the hammer pad 22, the first motor 42 is powered on to continue to drive the rotating disk 43 to rotate.

[0031] The upward position of the core piercing hammer 30 can be detected by a travel switch / limit switch matched with the core piercing hammer 30, and the travel switch / limit switch is connected to the controller of the first motor 42, so as to control the power-off time of the first motor 42. In addition, a pull rope 45 is provided between the connecting rod 44 and the pull sleeve 46, and the connecting rod 44 is not directly connected to the core piercing hammer 30 to prevent the rebound generated by the core piercing hammer 30 hitting the hammer pad 22 from impacting the connecting rod 44.

[0032] The first motor 42 is a dual-axis motor, and the rotating disk 43, the connecting rod 44, the pull rope 45, the pull sleeve 46 and the handle bar 31 are all arranged in two groups, and are arranged on both sides of the first motor 42. The core hammer 30 can be lifted stably through this structure.

[0033] In this embodiment, the mounting frame 41 has a through slot 411, the lower end of the rotating disk 43 extends into the through slot 411, and the connecting rod 44 is also inserted into the through slot 411. By accommodating the rotating disk 43 through the through slot 411, the layout height of the rotating disk 43 and the first motor 42 can be reduced.

[0034] In this embodiment, the second lifting mechanism 60 includes a second motor 61, a reel 62, a traction rope 63 and a lifting frame 64. The second motor 61 is arranged on the top of the frame 10, the reel 62 is connected to the second motor 61, the traction rope 63 is wound on the reel 62, the lifting frame 64 is connected to the mounting frame 41 of the first lifting mechanism 40, the first motor 42 is located on the inner side of the lifting frame 64, the top of the lifting frame 64 has a hanging hole 641, and the end of the traction rope 63 is provided with a hook that matches the hanging hole 641. When the first lifting mechanism 40 and the guide rod need to be moved upward to assemble the feeler rod 23 and the casing section 53, the hook is hung in the hanging hole 641, and then the second motor 61 is started, and the traction rope 63 is rolled up through the reel 62, so that the lifting frame 64 can be moved upward.

[0035] The embodiments of the present invention are described in detail above in conjunction with the accompanying drawings, but the present invention is not limited to the above embodiments. Various changes can be made within the knowledge scope of ordinary technicians in the technical field without departing from the purpose of the present invention.

Claims

1. A monitoring and detection device for gravel pile filling, It is characterized in that include: frame; A rod group, comprising a guide rod, a hammer pad and a feeler rod arranged in sequence, wherein the hammer pad is detachably connected to the guide rod and the feeler rod respectively; A core hammer, slidably sleeved on the guide rod; A first lifting mechanism is arranged at the upper end of the guide rod and is slidably connected to the frame, wherein the first lifting mechanism is connected to the core piercing hammer and can drive the core piercing hammer to reciprocate and rise relative to the guide rod; The casing assembly is vertically arranged at the bottom of the frame, and the feeler rod is penetrated through the casing assembly.

2. A gravel pile filling monitoring and detection device according to claim 1, It is characterized in that The frame includes a bottom frame, a guide column and a top frame connected in sequence from bottom to top, the bottom frame has a first installation layer and a second installation layer arranged up and down, the first installation layer and the second installation layer have coaxially arranged through holes, and the first lifting mechanism is slidably sleeved on the guide column.

3. A gravel pile filling monitoring and detection device according to claim 2, It is characterized in that The sleeve assembly includes a first flange sleeve, a second flange sleeve and a sleeve joint. The first flange sleeve is inserted into the through hole on the first mounting layer, and the second flange sleeve is inserted into the through hole on the second mounting layer. The upper end of the sleeve joint has an external thread head, and the lower end has an internal thread hole that cooperates with the external thread head. The sleeve joint is inserted into the second flange sleeve, and the external thread head at the upper end of the sleeve joint is connected to the inner side of the first flange sleeve.

4. A gravel pile filling monitoring and detection device according to claim 3, It is characterized in that The height of the external thread head is smaller than the height of the first flange sleeve; the width of the hammer head is larger than the inner cavity height of the first flange sleeve.

5. A gravel pile filling monitoring and detection device according to claim 1, It is characterized in that The first lifting mechanism includes a mounting frame, a first motor, a turntable, a connecting rod, a pull rope and a pull sleeve. The mounting frame is slidably arranged on the frame, the first motor is arranged on the top of the mounting frame, and the first motor is connected to the turntable. The edge of the turntable is rotatably connected to one end of the connecting rod, and the other end of the connecting rod passes through the mounting frame and is connected to the pull rope. The end of the pull rope is connected to the pull sleeve, and a handle rod is transversely arranged on the core hammer, and a pull sleeve is rotatably sleeved on the handle rod.

6. A gravel pile filling monitoring and detection device according to claim 5, It is characterized in that The first motor is configured as a dual-axis motor, and the turntable, connecting rod, pull rope, pull sleeve and handle rod are configured as two groups and are disposed on both sides of the first motor.

7. A gravel pile filling monitoring and detection device according to claim 5, It is characterized in that The mounting frame is provided with a through slot, and the lower end of the rotating disk extends into the through slot.

8. A gravel pile filling monitoring and detection device according to any one of claims 1 to 7, It is characterized in that It also includes a second lifting mechanism, which includes a second motor, a reel, a traction rope and a lifting frame. The second motor is arranged on the top of the frame, the reel is connected to the second motor, the traction rope is wound around the reel, the lifting frame is connected to the first lifting mechanism, and the top of the lifting frame is provided with a hanging hole, and the end of the traction rope is provided with a hook that cooperates with the hanging hole.