Building construction supporting hanging bracket

By designing a construction support hanger that includes flat bars, semi-circular hoops, and connecting rods, and utilizing the cooperation of tension springs and hinge rods, the pipes are automatically fixed after being lifted, solving the problems of inconvenient and laborious installation in existing technologies, and improving construction efficiency and safety.

CN222085360UActive Publication Date: 2024-11-29仵小强
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420900333.9
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-28
Publication Date
2024-11-29
Estimated Expiration
2034-04-28

AI Technical Summary

Technical Problem

Existing pipe supports and hangers have high requirements for space and site during installation, resulting in inconvenience, inefficiency and labor-intensive installation, especially since pipes need to be laid horizontally or lifted before assembly, which affects construction efficiency.

Method used

Design a building construction support hanger, including a flat bar, a semi-circular hoop, and a connecting rod structure. Through the cooperation of tension springs and hinge rods, the pipe can be automatically fixed in the semi-circular hoop after being lifted. The interaction between the telescopic rod and the hinge rod is used to achieve rapid fixing. Combined with bolts and shock-absorbing springs, stability and installation efficiency are improved.

Benefits of technology

It achieves more convenient, efficient and labor-saving pipe installation, and improves construction efficiency and safety through automatic fixing and shock absorption functions.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222085360U_ABST
    Figure CN222085360U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of pipeline supports, and particularly relates to a building construction supporting hanging bracket which comprises a flat rod and a semicircular hoop, after an assembled device is fixed on a roof through the flat rod, a telescopic rod is lengthened to the longest, so that the telescopic rod generates upward supporting force on a movable block, at the moment, hinge rods on the two sides incline downwards towards one side of the movable block, and the movable block is fixed through the semicircular hoop. The tension of the extension spring enables the movable block to bear downward pressure which is confronted with the supporting force of the telescopic rod, then the semicircular hoops on the two sides can be kept in an open state, then the pipeline is moved upwards to be arranged in the semicircular hoops on the two sides, and the movable nail is jacked upwards. When the telescopic rods and the extension springs do not generate a confrontation effect any more when the telescopic rods and the extension springs exceed a horizontal state, so that the extension springs release tension to drive the semicircular hoops on the two sides to be automatically and mutually spliced and wrap the periphery of the pipeline, and first insertion rods can penetrate through first insertion grooves and then are clamped by insertion blocks in the movement process of the semicircular hoops; therefore, the bottom end of the semicircular hoop is locked and fixed, and the installation is more convenient, efficient and labor-saving.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of pipeline supports, and in particular relates to a supporting hanger for building construction. Background Art

[0002] With the rapid development of my country's economy, the requirements for urban beautification and power supply safety are also increasing. There are more and more large-scale buildings. In large-scale buildings, various pipelines must be installed, including air conditioning, fire protection, water supply, electricity, communication and heating, etc. In construction, professional pipe supports and hangers are used to place and lay various pipelines. When using existing pipe supports and hangers, it is necessary to horizontally pass the pipeline through the installed supports and hangers to fix the pipeline, or to lift the pipeline upward and fix the pipeline by manually assembling the supports and hangers. However, the former has high requirements for space and site, making it inconvenient to place the pipeline, while the latter requires the assembly or installation of the supports and hangers in conjunction with the lifted pipeline, which makes the installation difficult and inefficient, which leads to inconvenient, inefficient and laborious installation. Utility Model Content

[0003] The utility model provides a construction support hanger, which can directly fix the pipeline after it is hoisted into place, thereby solving the problem that when using the existing pipeline support hanger, the pipeline needs to be horizontally inserted into the installed support hanger to fix the pipeline, or the pipeline is hoisted upward and then the pipeline is fixed by manually assembling the support hanger. However, the former has high requirements on space and site, which makes it inconvenient to place the pipeline, while the latter requires the assembly or installation of the support hanger in conjunction with the hoisted pipeline, which makes the installation difficult and inefficient, thereby causing the problem of inconvenient, low-efficiency and laborious installation.

[0004] To achieve the above purpose, the utility model provides the following technical solutions: a construction support hanger, comprising a flat rod and a semicircular hoop, the flat rod supporting two groups of horizontally sliding connecting rods, the semicircular hoop having two groups and being symmetrically spliced ​​and distributed, the semicircular hoop having a first protrusion and a second protrusion formed integrally at the top and bottom ends of the outer arc surface, the two connecting rods being symmetrically inclined and the bottom ends of the two connecting rods being fixed with a protrusion one located on the same side, the flat rod being provided with a fixed block located in the middle and two tension springs located on both sides of the fixed block, the two ends of the tension spring being respectively connected to the fixed block and the connecting rod, a movable block being provided below the fixed block, the movable block being downwardly connected with a movable nail, the movable nail The movable block is hinged with two sets of mutually symmetrical hinge rods on both sides and between the two protruding blocks 1. The movable block and the flat rod are connected to two telescopic rods on the front and back sides. A plug rod 1 is horizontally fixed on the protruding block 2 on one side, and a slot 1 and an installation slot that are perpendicular to each other are horizontally penetrated on the protruding block 2 on the other side. The plug rod 1 and the slot 1 are arranged correspondingly, and a small spring and an insert block are sequentially arranged on the bottom surface of the installation slot. The upper end of the insert block is provided with an inclined surface matching the plug rod 1, and the plug rod 1 is provided with a notch matching the upper end of the insert block. The hinge rod is inclined downward toward one side of the movable block, the telescopic rod is extended to the longest, and the spacing between the two protruding blocks 2 is greater than the inner diameter of the semicircular hoop.

[0005] The beneficial effects of the utility model are as follows: the pre-assembled device as a whole is installed by fixing the flat rod at a fixed point on the roof, and the telescopic rod is stretched to its longest length, so that it generates an upward supporting force on the movable block. At this time, the hinge rods on both sides are tilted downward toward one side of the movable block, and the connecting rod is driven by the pulling force of the tension spring to drive the protrusions on both sides to squeeze the hinge rods on both sides inward, so that the hinge rods generate downward pressure on the movable block, which is in opposition to the supporting force of the telescopic rod, so that the semicircular hoops on both sides can remain in an open state, and then the pipe is moved upward and placed in the semicircular hoops on both sides. During the process, the pipe will automatically push up the movable nails, so as to drive the hinge rods on both sides to rotate upward and exceed the horizontal state. The telescopic rod and the tension spring no longer produce mutual resistance, so the tension spring releases the tension to drive the semicircular hoops on both sides to automatically splice each other and wrap around the periphery of the pipe, and during the movement of the semicircular hoop, the insertion rod will pass through the slot and then be stuck by the insertion block, so as to lock and fix the bottom end of the semicircular hoop. The above structure realizes more convenient, efficient and labor-saving installation.

[0006] In order to fix the telescopic rod vertical support on the flat rod and the movable block;

[0007] As a further improvement of the above technical solution: three protrusions are fixed to the front and rear sides of the middle of the flat rod and the front and rear sides of the movable block respectively, and each of the three protrusions fixes the end of the telescopic rod.

[0008] The beneficial effect of this improvement is that the telescopic rod is vertically supported and fixed on the flat rod and the movable block through the protrusion three.

[0009] To fix the whole device;

[0010] As a further improvement of the above technical solution: a suspension rod is respectively passed through the left and right ends of the flat rod, a support block is fixed to the bottom end of the suspension rod, a mounting plate is fixed to the top end of the suspension rod, and a plurality of bolts are arranged on the mounting plate.

[0011] The beneficial effect of this improvement is that the mounting plate is fixed to the roof by bolts, and then the flat rod is lifted by two sets of suspension rods and supporting blocks, and then the device is fixed to the roof as a whole.

[0012] In order to achieve the purpose of buffering and shock absorption;

[0013] As a further improvement of the above technical solution: the suspension rod slides vertically on the end of the flat rod, and a shock-absorbing spring is arranged on the periphery of each suspension rod, the upper end of the shock-absorbing spring abuts the mounting plate and the lower end abuts the upper surface of the flat rod.

[0014] The beneficial effect of this improvement is that the shock absorbing spring can achieve the effect of buffering and shock absorption.

[0015] In order to facilitate the normal sliding connection between the flat rod and the connecting rod;

[0016] As a further improvement of the above technical solution: the flat rod is a C-shaped steel with an opening downward and both the front and rear ends are bent horizontally inward, and a roller is provided at the top end of the connecting rod to penetrate and rotate front and back, and the roller is arranged to roll left and right inside the flat rod.

[0017] The beneficial effect of this improvement is that the roller rolls inside the flat rod, which facilitates the normal sliding of the end of the connecting rod on the flat rod and facilitates the translation of the connecting rod under the pulling force of the tension spring.

[0018] In order to facilitate long-term stable support of the pipeline;

[0019] As a further improvement of the above technical solution: the movable block is threadedly connected to the movable nail, a fixing column vertically penetrates the fixed block, the top of the fixing column penetrates the flat rod upward and is threadedly connected to a locking nut, the fixing column is provided with an internal thread matching the movable nail, a second insertion rod is horizontally fixed on the first protrusion on one side, and a second slot is horizontally penetrated on the first protrusion on the other side, the second insertion rod and the second slot are arranged correspondingly, the second insertion rod horizontally penetrates the second slot and extends to the outside and is threadedly connected to a nut, and the first insertion rod horizontally penetrates the slot one and extends to the outside and is threadedly connected to a nut.

[0020] The beneficial effect of this improvement is as follows: after the movable block is moved up and close to the fixed column, it is threadedly connected to the movable block and the fixed column through the movable nail, and then the movable block is restricted on the flat rod. The movable block is fixed, which can not only reinforce and support the semicircular hoop and the pipe, but also is more conducive to the two semicircular hoops to maintain a tight splicing for a long time, and then the pipe can be clamped and supported stably for a long time. The second plug rod is restricted in the second slot by the nut, and the first plug rod is further firmly restricted in the first slot by the nut, so that the upper and lower ends of the two semicircular hoops are tightly fixed together, which is convenient for maintaining the clamping and support of the pipe stably for a long time.

[0021] In order to adapt to pipes of different diameters;

[0022] As a further improvement of the above technical solution: the middle parts of the two semicircular hoops are threadedly connected with adjusting pieces, the adjusting pieces pass through the semicircular hoops and are connected to an arc-shaped clamping plate on the inner side, the arc-shaped clamping plate is coaxially arranged with the semicircular hoops, and the end of the adjusting piece is rotatably arranged on the arc-shaped clamping plate.

[0023] The beneficial effect of this improvement is that the pipe is clamped by the arc-shaped clamping plates on both sides, and the distance between the two arc-shaped clamping plates is adjusted by rotating the adjusting piece to drive the arc-shaped clamping plates to move horizontally, so that pipes with different diameters can be clamped and fixed.

[0024] The parts not involved in the device are the same as those in the prior art or can be implemented by using the prior art. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0026] Figure 1 Axonometric view of the appearance structure of the utility model Figure 1 ;

[0027] Figure 2 Axonometric view of the appearance structure of the utility model Figure 2 ;

[0028] Figure 3 This is a front view of the appearance structure of the utility model;

[0029] Figure 4 It is a cross-sectional view of the overall structure of the utility model;

[0030] Figure 5 It is a partial structural schematic diagram of the utility model;

[0031] In the figure: 1. flat rod; 11. fixed block; 12. tension spring; 2. connecting rod; 21. roller; 3. semicircular hoop; 31. protrusion one; 32. protrusion two; 33. plug rod one; 331. missing slot; 34. slot one; 35. installation slot; 36. small spring; 37. plug block; 38. plug rod two; 39. slot two; 4. movable block; 41. movable nail; 42. fixing column; 43. locking nut; 5. hinge rod; 6. telescopic rod; 61. protrusion three; 7. suspension rod; 71. support block; 72. installation plate; 73. shock-absorbing spring; 8. adjustment piece; 81. arc splint. DETAILED DESCRIPTION

[0032] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0033] Example 1

[0034] See also Figure 1-Figure 5The utility model provides the following technical solutions: a construction support hanger, comprising a flat rod 1 and a semicircular hoop 3, wherein the flat rod 1 supports two sets of horizontally sliding connecting rods 2, wherein the semicircular hoop 3 has two sets and is symmetrically spliced ​​and distributed, wherein the semicircular hoop 3 is integrally formed with a convex block 1 31 and a convex block 2 32 at the top and bottom ends of the outer arc surface, respectively, wherein the two connecting rods 2 are symmetrically inclined and the bottom ends are both fixed with a convex block 1 31 located on the same side, wherein the flat rod 1 is provided with a fixed block 11 located in the middle and two tension springs 12 located on both sides of the fixed block 11, wherein the two ends of the tension spring 12 are respectively connected to the fixed block 11 and the connecting rod 2, wherein the fixed block A movable block 4 is provided below 11, and the movable block 4 is connected with a movable nail 41 downwardly. The movable block 4 is hinged with two sets of mutually symmetrical hinge rods 5 between the two protrusions 31 on both sides. The movable block 4 and the flat rod 1 are connected with two telescopic rods 6 on the front and rear sides. A plug rod 33 is horizontally fixed on the protrusion 32 on one side, and a slot 34 and a mounting slot 35 are horizontally penetrated through the protrusion 32 on the other side. The plug rod 33 and the slot 34 are correspondingly arranged. The bottom surface of the mounting slot 35 is sequentially provided with a small spring 36 and a plug block 37 upwardly. The upper end of the plug block 37 is provided with an inclined The inclined surface, the insertion rod 1 33 is provided with a notch 331 which cooperates with the upper end of the insertion block 37, the hinge rod 5 is tilted downward toward the side of the movable block 4, the telescopic rod 6 is extended to the longest, and the distance between the two protrusions 2 32 is greater than the inner diameter of the semicircular hoop 3. The pre-assembled device is installed as a whole by fixing the flat rod 1 to the roof at a fixed point, and the telescopic rod 6 is stretched to the longest so that it exerts an upward support force on the movable block 4. At this time, the hinge rods 5 on both sides are tilted downward toward the side of the movable block 4, and the connecting rod 2 is driven by the tension of the tension spring 12 to drive the protrusions 1 31 on both sides to squeeze the hinge rods 5 on both sides inward, so that the hinge rod 5 exerts downward pressure on the movable block 4, and The supporting force of the telescopic rod 6 is antagonistic, so that the semicircular hoops 3 on both sides can remain in the open state, and then the pipe is moved upward and placed in the semicircular hoops 3 on both sides. During the process, the pipe will automatically push up the movable nail 41, and then drive the hinge rods 5 on both sides to rotate upward and exceed the horizontal state. When the telescopic rod 6 and the tension spring 12 no longer produce mutual resistance, the tension spring 12 releases the tension to drive the semicircular hoops 3 on both sides to automatically splice each other and wrap around the outer periphery of the pipe, and during the movement of the semicircular hoop 3, the insertion rod 1 33 will pass through the slot 1 34 and be stuck by the insertion block 37, thereby locking and fixing the bottom end of the semicircular hoop 3. The above structure makes installation more convenient, efficient and labor-saving. The front and rear sides of the middle part of the flat rod 1 and the front and rear sides of the movable block 4 are respectively fixed with protrusions 3 61, and each of the protrusions 3 61 fixes the end of the telescopic rod 6; the telescopic rod 6 is vertically supported and fixed on the flat rod 1 and the movable block 4 through the protrusions 3 61.The left and right ends of the flat rod 1 are respectively penetrated by a suspension rod 7, a support block 71 is fixed to the bottom end of the suspension rod 7, a mounting plate 72 is fixed to the top end of the suspension rod 7, and a plurality of bolts are arranged on the mounting plate 72; the mounting plate 72 is fixed to the roof by bolts, and then the flat rod 1 is lifted by two sets of suspension rods 7 and support blocks 71, and then the whole device is fixed to the roof. The suspension rod 7 slides vertically at the end of the flat rod 1, and a shock absorbing spring 73 is arranged on the periphery of each suspension rod 7, the upper end of the shock absorbing spring 73 abuts against the mounting plate 72 and the lower end abuts against the upper surface of the flat rod 1; the shock absorbing spring 73 achieves the effect of buffering and shock reduction. The flat rod 1 is a C-shaped steel with an opening set downward and both the front and rear ends are bent horizontally inward. A roller 21 is provided at the top end of the connecting rod 2 to penetrate and rotate front and back. The roller 21 is set to roll left and right inside the flat rod 1. The roller 21 rolls inside the flat rod 1, which facilitates the normal sliding of the end of the connecting rod 2 on the flat rod 1 and facilitates the translation of the connecting rod 2 under the tension of the tension spring 12. The movable block 4 is threadedly connected with the movable nail 41, and a fixing column 42 is vertically penetrated on the fixed block 11. The top of the fixing column 42 penetrates the flat rod 1 upward and is threadedly connected with a locking nut 43. The fixing column 42 is provided with an internal thread that matches the movable nail 41. A plug rod 2 38 is horizontally fixed on the protrusion 1 31 on one side, and a slot 2 39 is horizontally penetrated on the protrusion 1 31 on the other side. The plug rod 2 38 and the slot 2 39 are correspondingly arranged. The plug rod 2 38 horizontally penetrates the slot 2 39 and extends to the outside to be threadedly connected with a nut. The plug rod 1 33 horizontally penetrates the slot 1 34 and extends to the outside to be threadedly connected with Nut; after the movable block 4 is moved up and close to the fixed column 42, it is threadedly connected with the movable block 4 and the fixed column 42 through the movable nail 41, and then the movable block 4 is restricted on the flat rod 1. The movable block 4 is fixed, which can not only reinforce and support the semicircular hoop 3 and the pipeline, but also is more conducive to the two semicircular hoops 3 to maintain a close splicing for a long time, and thus to clamp and support the pipeline stably for a long time. The plug rod 2 38 is restricted in the slot 2 39 by the nut, and the plug rod 1 33 is further firmly restricted in the slot 1 34 by the nut, so that the upper and lower ends of the two semicircular hoops 3 are tightly fixed together, which is convenient for maintaining the clamping and support of the pipeline stably for a long time. The middle parts of the two semicircular hoops 3 are both threadedly connected with an adjusting piece 8, which passes through the semicircular hoop 3 and is connected to an arc-shaped clamping plate 81 on the inner side. The arc-shaped clamping plate 81 is coaxially arranged with the semicircular hoop 3, and the end of the adjusting piece 8 is rotatably arranged on the arc-shaped clamping plate 81; the pipeline is clamped by the arc-shaped clamping plates 81 on both sides, and the distance between the two arc-shaped clamping plates 81 is adjusted by rotating the adjusting piece 8 to drive the arc-shaped clamping plate 81 to move horizontally, so that pipelines with different diameters can be clamped and fixed.

[0035] The working principle and use process of this utility model:

[0036] The mounting plate 72 is fixed on the roof with bolts, and the flat rod 1 is lifted up by the hanging rod 7 and the supporting block 71 to install the pre-assembled device as a whole; and the shock absorbing spring 73 is used to achieve shock absorption and buffering.

[0037] When installing the pipeline: pull down the movable block 4 to stretch the telescopic rod 6 to the maximum, so that it generates an upward supporting force on the movable block 4. At this time, the hinge rods 5 on both sides are tilted downward toward the movable block 4, and the top of the connecting rod 2 is pulled by the tension spring 12, driving the protrusions 31 on both sides to squeeze the hinge rods 5 on both sides inward, so that the hinge rods 5 generate downward pressure on the movable block 4, which is in opposition to the supporting force of the telescopic rod 6, so that the semicircular hoops 3 on both sides can remain in the open state, and then move the pipeline upward and place it in the semicircular hoops 3 on both sides. During the process, the pipeline will automatically push up the movable nail 41, thereby driving the hinge rods 5 on both sides to rotate upward and exceed the horizontal state. The telescopic rod 6 and the tension spring The spring 12 no longer produces mutual resistance, so the tension of the connecting rod 2 by the stretching spring 12 and the rolling of the roller 21 inside the flat rod 1 make the connecting rods 2 on both sides approach each other, thereby driving the semicircular hoops 3 on both sides to automatically splice each other and wrap around the outer periphery of the pipe, and the plug rod 1 33 will pass through the slot 1 34 and be stuck by the plug block 37, so that the bottom end of the semicircular hoop 3 is locked and fixed, and then the movable nail 41 is screwed to make it threadedly connected with the movable block 4 and the fixed column 42, and the plug rod 1 33 and the plug rod 2 38 are respectively restricted in the slot 1 34 and the slot 2 39 with nuts, thereby strengthening the connection between the two semicircular hoops 3 and strengthening the supporting effect of the semicircular hoop 3.

[0038] The pipe is clamped by the arc-shaped clamping plates 81 on both sides, and the distance between the two arc-shaped clamping plates 81 is adjusted by rotating the adjusting member 8 to drive the arc-shaped clamping plates 81 to move horizontally, so that pipes with different diameters can be clamped and fixed.

[0039] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A construction support hanger, characterized in that: The invention comprises a flat rod (1) and a semicircular hoop (3). The flat rod (1) supports two groups of horizontally sliding connecting rods (2). The semicircular hoop (3) has two groups and is symmetrically spliced ​​and distributed. The semicircular hoop (3) is integrally formed with a first protrusion (31) and a second protrusion (32) at the top and bottom ends of the outer arc surface respectively. The two connecting rods (2) are symmetrically inclined and the bottom ends are both fixed with a first protrusion (31) located on the same side. The flat rod (1) is provided with a fixed block (11) located in the middle and two tension springs (12) located on both sides of the fixed block (11). The two ends of the tension spring (12) are respectively connected to the fixed block (11) and the connecting rod (2). A movable block (4) is provided below the fixed block (11). The movable block (4) is downwardly connected with a movable nail (41). The movable block (4) is hinged to the two protrusions (31) on both sides and has two groups of mutually left and right hinges. A right symmetrical hinge rod (5), the movable block (4) and the flat rod (1) are connected to two telescopic rods (6) at the front and rear sides. A plug rod (33) is horizontally fixed on the protrusion block (32) on one side, and a slot (34) and a mounting groove (35) are horizontally penetrated through the protrusion block (32) on the other side. The plug rod (33) and the slot (34) are arranged correspondingly. A small spring (36) and a plug block (37) are arranged upward in sequence on the bottom surface of the mounting groove (35). The upper end of the plug block (37) is provided with an inclined surface that matches the plug rod (33). The plug rod (33) is provided with a notch (331) that matches the upper end of the plug block (37). The hinge rod (5) is tilted downward toward one side of the movable block (4), the telescopic rod (6) is extended to the longest, and the distance between the two protrusion blocks (32) is greater than the inner diameter of the semicircular hoop (3).

2. A construction support hanger according to claim 1, characterized in that: The front and rear sides of the middle of the flat rod (1) and the front and rear sides of the movable block (4) are respectively fixed with three protrusions (61), and each of the three protrusions (61) fixes the end of the telescopic rod (6).

3. A construction support hanger according to claim 1, characterized in that: A suspension rod (7) is respectively provided through the left and right ends of the flat rod (1); a support block (71) is fixed to the bottom end of the suspension rod (7); a mounting plate (72) is fixed to the top end of the suspension rod (7); and a plurality of bolts are provided on the mounting plate (72).

4. A construction support hanger according to claim 3, characterized in that: The suspension rod (7) slides vertically on the end of the flat rod (1), and a shock absorbing spring (73) is arranged on the periphery of each suspension rod (7), the upper end of the shock absorbing spring (73) abuts against the mounting plate (72) and the lower end abuts against the upper surface of the flat rod (1).

5. A construction support hanger according to claim 1, characterized in that: The flat rod (1) is a C-shaped steel with an opening downward and both ends thereof are bent horizontally inwards. A roller (21) is rotatably provided through the top end of the connecting rod (2) and passes through the top end. The roller (21) is rotatably arranged in the flat rod (1) from left to right.

6. A construction support hanger according to claim 1, characterized in that: The movable block (4) is threadedly connected to the movable nail (41), a fixing column (42) vertically penetrates the fixed block (11), the top end of the fixing column (42) penetrates the flat rod (1) upwards and is threadedly connected to a locking nut (43), the fixing column (42) is provided with an internal thread matched with the movable nail (41), a second insertion rod (38) is horizontally fixed on the first protrusion (31) on one side, and a second slot (39) is horizontally penetrated on the first protrusion (31) on the other side, the second insertion rod (38) and the second slot (39) are arranged correspondingly, the second insertion rod (38) horizontally penetrates the second slot (39) and extends to the outside to be threadedly connected to a nut, and the first insertion rod (33) horizontally penetrates the first slot (34) and extends to the outside to be threadedly connected to a nut.

7. A construction support hanger according to claim 1, characterized in that: The middle parts of the two semicircular hoops (3) are both threadedly connected with an adjusting piece (8), the adjusting piece (8) passes through the semicircular hoops (3) and is connected to an arc-shaped clamping plate (81) on the inner side, the arc-shaped clamping plate (81) is coaxially arranged with the semicircular hoops (3), and the end of the adjusting piece (8) is rotatably arranged on the arc-shaped clamping plate (81).