Anti-floating reinforcement cage for rotary excavating pile under complex geological conditions
The anti-floating steel cage for rotary piles addresses floating issues through reinforced structures and detachable components, enhancing stability and ease of assembly, while allowing real-time monitoring of floating conditions.
Patent Information
- Application Number
- CN202420066225.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-01-11
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2034-01-11
AI Technical Summary
The steel cage in rotary drilling piles often floats during construction due to inadequate fixation, upward concrete forces, and buoyancy issues, especially in complex geological conditions, affecting project quality.
An anti-floating steel cage design featuring pile longitudinal reinforcements, annular reinforcing stirrups, pile spiral stirrups, reinforcing inner supports, and cross inner members, with detachable connections and benchmarks to prevent floating, and a cross internal component to resist upward forces.
The design effectively reduces steel cage floating, allows easy assembly and disassembly, and provides real-time evaluation of floating conditions, ensuring stable pile construction.
Smart Images

Figure CN222120213U_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of rotary drilling piles, and in particular to an anti-floating steel cage for rotary drilling piles under complex geological conditions. Background Art
[0002] The rotary drilling hole is formed by rotating a barrel with a valve at the bottom to crush the rock and soil, and directly load it into the drill bucket. The drill bit is then lifted out of the hole by the drilling rig lifting device and telescopic drill rod to unload the soil. This cycle is repeated continuously, and the soil is continuously taken and unloaded until the designed bottom elevation of the hole is reached.
[0003] During the bored pile pouring process, the steel cage often floats up, ranging from a few centimeters to tens of centimeters in mild cases to several meters or even completely floated up in severe cases, which is very harmful to the quality of the project. The reasons are:
[0004] The upper end of the steel cage is not fixed firmly at the hole. When the guide tube is lifted, it is easy to be caught by the guide tube and lifted together, causing the steel cage to float.
[0005] During the concrete pouring process, when the concrete surface reaches the bottom of the steel cage, due to the shallow depth of the conduit and the relatively large amount of concrete poured, the concrete returns too fast, generating a large upward force, thereby lifting the conduit and the steel cage up;
[0006] When there is a fine sand layer in the ground, if the mud density is too low, the collapsed fine sand will be spread on the concrete surface, thus forming a cushion layer with a certain thickness to cushion the steel cage. As the concrete surface rises, it will also lift the steel cage up.
[0007] Based on the above problems, this application proposes a new technical solution. Utility Model Content
[0008] In order to reduce the floating of the steel cage during the construction of rotary piles, the present application provides an anti-floating steel cage for rotary piles under complex geological conditions.
[0009] The present application provides an anti-floating steel cage for rotary piles under complex geological conditions, which adopts the following technical solution:
[0010] An anti-floating steel cage for rotary excavated piles under complex geological conditions, comprising pile longitudinal reinforcement, annular reinforcing stirrups, pile spiral stirrups, reinforcing inner supports, a pole and a cross inner member, wherein the pile longitudinal reinforcements are multiple and parallel to each other, the annular reinforcing stirrups are multiple and axially distributed, the multiple pile longitudinal reinforcements are arranged around the annular reinforcing stirrups and the pile longitudinal reinforcements are fixed to the annular reinforcing stirrups;
[0011] The pile spiral hoop reinforcement is arranged spirally around the outside of a plurality of pile longitudinal reinforcements and fixed to the pile longitudinal reinforcements, and the reinforcing inner support is located inside the circular contour surrounded by the plurality of pile longitudinal reinforcements and fixed to the pile longitudinal reinforcements;
[0012] The pole is parallel to the pile longitudinal reinforcement and one end of the pole is detachably connected to the end of the pile longitudinal reinforcement or detachably connected to the annular reinforcing stirrup near the end of the pile longitudinal reinforcement, and the other end extends outward;
[0013] The reinforcing inner support comprises a center seat, a screw and a support head. The screw is multiple and evenly distributed around the center seat. The screw is threadedly connected to the center seat. A bayonet for clamping the longitudinal reinforcement of the pile is formed on the support head. The support head is rotatably connected to the end of the screw away from the center seat.
[0014] The cross inner member is detachably connected to the annular reinforcing stirrup located at the bottom.
[0015] Optionally, the internal component of the cross includes a block, a short arm, a cross arm and a diagonal brace, the cross arm is located on the inner side of a circular contour surrounded by a plurality of pile longitudinal reinforcements, one end of the short arm is hinged to the outer end of the cross arm and is perpendicular to the plane where the cross arm is located, the block is penetrated by the short arm and is slidingly connected, the outer side of the block is concave to form a second C-shaped bayonet in an end view, the second bayonet abuts against annular stiffening stirrups, the end of the short arm away from the cross arm is fixed with a stop plate, one end of the diagonal brace fixes the short arm, and the other end is fixed to the end of the cross arm close to the short arm and is inclined, and the strength of the diagonal brace is less than that of the cross arm.
[0016] Optionally, the cross arm is a metal structural arm, and the diagonal support rod is plastic.
[0017] Optionally, the length of the lower edge of the second bayonet is greater than the length of the upper edge.
[0018] Optionally, an anti-slip sleeve is fixed on the screw rod, and the anti-slip sleeve is located between the center seat and the support head.
[0019] Optionally, a lifting lug is fixed on the annular stiffening stirrup located at the top, and the lifting lug is multiple and distributed circumferentially along the annular stiffening stirrup.
[0020] Optionally, a double C clamp tube is also included, wherein the double C clamp tube is viewed from the end as two C-shaped tubes that are connected to each other and diverge from each other, and the lower end or the upper end of the pile longitudinal reinforcement is inserted into an opening of the double C clamp tube.
[0021] In summary, the present application includes at least one of the following beneficial technical effects:
[0022] 1) The reinforced inner support can be used to support the steel cage to reduce the problem of collapse and deformation. At the same time, because the support head at the end of the screw supports the annular reinforcing stirrups, and the screw thread is connected to the center seat, when the steel cage is piled in the later stage, it can be quickly disassembled by slightly turning the screw.
[0023] 2) There is a benchmark at the end of the steel cage. During the concrete pouring process, the floating condition of the steel cage can be evaluated by observing the movement of the benchmark;
[0024] 3) There is a cross internal component at the bottom of the steel cage, which can withstand the downward impact force exerted by the concrete during the pouring process. This will increase the resistance when the steel cage floats up, which can help the steel cage not to float. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 is a schematic diagram of the end view structure of the present application;
[0026] Figure 2 It is a front view of the internal components of the cross of the present application;
[0027] Figure 3 It is a structural schematic diagram of the double C-cage tube of the present application.
[0028] Explanation of the reference numerals in the accompanying drawings: 1. Pile longitudinal reinforcement; 2. Circumferential stiffening stirrups; 21. Lifting ears; 3. Pile spiral stirrups; 4. Stiffening inner support; 41. Center seat; 42. Screw; 421. Anti-slip sleeve; 43. Support head; 5. Marking pole; 6. Cross internal component; 61. Block; 62. Short arm; 63. Cross arm; 64. Diagonal support rod; 65. Stop plate; 7. Double C clamp tube. DETAILED DESCRIPTION
[0029] The following is combined with Figure 1-3 This application is described in further detail.
[0030] The embodiment of the present application discloses an anti-floating steel cage for rotary piles under complex geological conditions.
[0031] Reference Figure 1-2 The anti-floating steel cage for rotary excavated piles under complex geological conditions includes pile longitudinal reinforcement 1, annular reinforcing stirrups 2, pile spiral stirrups 3, reinforcing inner supports 4, benchmarks 5 and cross internal components 6.
[0032] In this embodiment, the oil stains and scale rust on the surface of the steel bars must be cleaned before use; if overlap arc welding is used for the steel bar joints, single-sided welding should be adopted; the stressed steel bar welding or binding joints should be set at places with smaller internal forces and staggered, and the steel bar joints in the same section shall not exceed 50% of the total; for binding joints, the distance between the two joints shall not be less than 1.3 times the overlap length.
[0033] There are multiple pile longitudinal bars 1 that are parallel to each other, and the multiple pile longitudinal bars 1 are distributed in a circumferential direction; the annular reinforcing stirrups 2 are annular and there are multiple annular reinforcing stirrups 2 that are distributed along the length direction of the pile longitudinal bars 1, and the annular reinforcing stirrups 2 are located on the inner side of the multiple pile longitudinal bars 1 and the two are tied and fixed with wire. The pile spiral stirrups 3 are arranged spirally around the outer side of the multiple pile longitudinal bars 1 and are fixed to the pile longitudinal bars 1.
[0034] The above arrangement can constitute the main body of the steel cage.
[0035] Reference Figure 1 The reinforcing inner support 4 is located inside the circular contour surrounded by the plurality of pile longitudinal bars 1 and is fixed to the pile longitudinal bars 1. The function of the reinforcing inner support 4 is to support the steel cage to prevent it from collapsing and deforming when it is not in use.
[0036] During construction: the lifting of the steel cage on site is directly connected and lowered by a crane. The lifting points are set at two places on the top layer of annular stiffening stirrups of each section of the steel cage, arranged symmetrically, for a total of four. The lifting points can be lifting ears 21; the lifting ears 21 are made of round steel and welded to the corresponding annular stiffening stirrups 2. As the steel cage is continuously extended, the weight of the steel cage is increasing. In order to avoid the deformation of the steel cage during lifting, a special hanger is set at the top of the steel cage. When the steel cage is lowered into place, wait until the upper lifting bar is centered, then loosen the hook and hang the lifting bar on the shoulder pole beam across the top of the pile hole casing, and weld the lifting bar to the shoulder pole, and the shoulder pole to the casing. The construction sequence of the steel cage is lifting-positioning-connection-lowering.
[0037] The lowering process is as follows: lift the connected frame, pull out the shoulder pole beam, slowly lower it, and repeat the above process; during the lowering process, the reinforcing inner support 4 in the steel cage needs to be removed to prevent obstruction and hooking of the concrete pouring conduit; after the steel cage is lowered into place, the hanging rod and the shoulder pole, and the shoulder pole and the casing are welded and fixed to prevent the steel cage from floating up and sinking when pouring concrete. When fixing, the center of the steel cage should be adjusted in the opposite direction according to the deviation of the steel casing so that the center of the steel cage coincides with the center of the pile.
[0038] According to the above process, it can be known that the reinforced inner support 4 needs to be disassembled in the later stage. Therefore, if it is fixed by steel bar welding, bundling, etc., it is relatively laborious and inconvenient to dismantle; for this reason, in the present embodiment, the reinforced inner support 4 is configured to include: a center seat 41, a screw rod 42 and a support head 43; the screw rod 42 is multiple (such as: 3) and is evenly distributed around the center seat 41, and the screw rod 42 is threadedly connected to the center seat 41; a bayonet 1 for clamping the pile longitudinal reinforcement 1 is formed on the support head 43, and the support head 43 is rotatably connected to the end of the screw rod 42 away from the center seat 41.
[0039] When in use, the staff first clamps a support head 43 with a certain pile longitudinal reinforcement 1, and then adjusts the length of other screw rods 42 so that the support head 43 at the end can be clamped with other corresponding pile longitudinal reinforcements 1 to achieve the internal support effect; when it needs to be dismantled, it is only necessary to shorten one or two screw rods 42 to remove it, so the operation is relatively fast and easy when lowering the steel cage.
[0040] In order to facilitate the rotation of the screw rod 42 and prevent the palm from being scratched, an anti-slip cover 421 is fixed on the screw rod 42 . The anti-slip cover 421 may be a rubber cover and is located between the central seat 41 and the support head 43 .
[0041] The above-mentioned benchmark 5 can be directly made of steel bars, which are parallel to the pile longitudinal reinforcement 1 and one end of which is connected to the upper end of the pile longitudinal reinforcement 1 in a bundled manner or detachably connected to the annular reinforcing stirrup 2 close to the upper end of the pile longitudinal reinforcement 1, and the other end extends outward.
[0042] When pouring concrete, the mud density should be controlled between 1.15 and 1.25. If the density is too large, the buoyancy on the steel cage will increase, and a thicker laitance will be formed on the concrete surface. When the concrete surface rises, the laitance will wrap the steel cage and float upward.
[0043] The benchmark 5 leaks out of the mud surface. When the benchmark 5 is found to float up during the pouring process, it also means that the steel cage has floated up. At this time, measures must be taken immediately to restore the floating steel cage to its original position.
[0044] The cross inner member 6 is detachably connected to the annular reinforcing stirrup 2 located at the bottom.
[0045] A transverse cross internal member 6 is added to the bottom of the steel cage, so that the concrete has a downward impact force on the steel cage, which will increase the resistance when the steel cage floats up, and can help the steel cage not to float.
[0046] Reference Figure 2 However, when the cross internal component 6 is added to the lower part of the steel cage, it will affect the falling depth of the conduit, causing trouble for the secondary hole cleaning and increasing the thickness of the sediment at the bottom of the hole. Therefore, in the present application, the cross internal component 6 is configured to include: a block 61, a short arm 62, a cross arm 63 and a diagonal support rod 64.
[0047] The cross arm 63 is cross-shaped when viewed from above, and is located inside the circular outline surrounded by multiple pile longitudinal reinforcements 1; one end of the short arm 62 is hinged to the outer end of the cross arm 63 and is perpendicular to the plane where the cross arm 63 is located, and the hinged rotation surface is parallel to the support arm of the cross arm 63; the clamping block 61 is penetrated by the short arm 62 and is slidably connected, and the outer side of the clamping block 61, that is, the side away from the central axis of the cross arm 63, is concave to form a C-shaped clamping mouth 2 in an end view, and the clamping mouth 2 contacts the annular reinforcing stirrup 2 to be clamped in the steel cage.
[0048] The end of the short arm 62 away from the cross arm 63 is fixed with a stop plate 65, and the stop plate 65 can be a welded steel plate, which is used to prevent the short arm 62 from being separated from the cross arm 63. One end of the diagonal brace 64 fixes the short arm 62, and the other end is fixed to the end of the cross arm 63 close to the short arm 62 and is inclined. The strength of the diagonal brace 64 is smaller than that of the cross arm 63.
[0049] According to the above arrangement, the cross inner member 6 is still subject to a downward impact during concrete pouring, and the steel cage is also subject to the resistance caused by the cross inner member 6 being blocked by concrete when it wants to float up; also because the cross arm 63 can move downward, that is, the position is further downward, so the falling depth of the conduit is increased; also because the short arm 62 and the cross arm 63 are hinged, the strength of the diagonal support rod 64 is less than the cross arm 63, so when necessary, force can be applied downward directly through the conduit to break the diagonal support rod 64, that is, the short arm 62 rotates, and the cross inner member 6 is relaxed and no longer connected to the steel cage, so as to ensure that the secondary emptying can be carried out smoothly.
[0050] In this embodiment, the cross arm 63 is a metal structural arm, and the diagonal support rod 64 is plastic; the diagonal support rod 64 can be fixed to the short arm 62 and the cross arm 63 by injection molding after sample melting.
[0051] In order to make it easier for the cross inner component 6 to be separated from the steel cage after the diagonal support rod 64 is broken, the length of the lower edge of the second clamping mouth of the clamping block 61 is greater than the length of the upper edge.
[0052] Reference Figure 3 The present application also includes a double C clamp tube 7. The double C clamp tube 7 is viewed from the end as two mutually diverging C-shaped interconnected shapes, and the lower end or upper end of the pile longitudinal reinforcement 1 is inserted into an opening of the double C clamp tube 7.
[0053] Because the steel cage is made in sections according to its length and hoisted into the hole, the number and length of sections depends on the total length of the steel cage. After the steel cage is formed and passed the inspection, the first section of the steel cage is lifted by a crane, and the lifting point is located at the first stiffening hoop at the top. When hoisting the steel cage into the hole, it should be aligned with the hole diameter, kept vertical, and gently and slowly lowered into the hole. After entering the hole, it should be lowered slowly.
[0054] When the last circumferential reinforcing stirrup 2 is reached, the above-mentioned shoulder beam is used to penetrate the steel cage and stop it; then, the second steel cage is lifted so that its center coincides with the center of the first steel cage and the center of the pile hole, and the two steel cages are butt-jointed; at this time, the position of the double C clamp tube 7 at the lower end of the first steel cage is adjusted, and several pile longitudinal bars 1 at the lower end of the second steel cage are clamped into the other clamping port of the corresponding double C clamp tube 7 to achieve preliminary positioning and fixation, and the joint is aligned; then, due to the segmented production and section-by-section construction, the upper and lower steel cages are connected by binding joints (joint overlap rate ≤ 50%); considering the firmness of the binding joints, at least 3 longitudinal main bars are selected at the joints for single-sided welding connection, with a welding length of 10d, and at the same time, pay attention to whether the binding points of the spiral hoop of the connection section are firm. The spiral stirrups are tied and overlapped according to the requirements of the specifications, and the stirrups are spot welded on the main bars near the main bar joints (within about 1000mm) to strengthen their overlap.
[0055] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. An anti-floating steel cage for rotary piles under complex geological conditions, characterized by: The pile comprises pile longitudinal reinforcement (1), annular stiffening stirrups (2), pile spiral stirrups (3), stiffening inner supports (4), a pole (5) and a cross inner member (6), wherein the pile longitudinal reinforcement (1) is multiple and parallel to each other, the annular stiffening stirrups (2) are multiple and axially distributed, the multiple pile longitudinal reinforcements (1) are arranged around the annular stiffening stirrups (2) and the pile longitudinal reinforcements (1) are fixed to the annular stiffening stirrups (2); The pile spiral stirrups (3) are arranged spirally around the outer sides of the plurality of pile longitudinal bars (1) and are fixed to the pile longitudinal bars (1); the reinforcing inner support (4) is located inside the circular outline surrounded by the plurality of pile longitudinal bars (1) and is fixed to the pile longitudinal bars (1); The marking rod (5) is parallel to the pile longitudinal reinforcement (1) and one end of the marking rod is detachably connected to the end of the pile longitudinal reinforcement (1) or detachably connected to the annular reinforcing stirrup (2) near the end of the pile longitudinal reinforcement (1), and the other end of the marking rod extends outwards; The reinforcing inner support (4) comprises a center seat (41), a screw rod (42) and a support head (43); the screw rod (42) is multiple and evenly distributed around the center seat (41); the screw rod (42) is threadedly connected to the center seat (41); a bayonet hole 1 for clamping the pile longitudinal reinforcement (1) is formed on the support head (43); the support head (43) is rotatably connected to the end of the screw rod (42) away from the center seat (41); The cross inner component (6) is detachably connected to the annular reinforcing stirrup (2) located at the bottom.
2. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 1 is characterized in that: The cross inner member (6) comprises a clamping block (61), a short arm (62), a cross arm (63) and an oblique brace (64); the cross arm (63) is located inside a circular contour surrounded by a plurality of pile longitudinal reinforcements (1); one end of the short arm (62) is hinged to the outer end of the cross arm (63) and is perpendicular to the plane where the cross arm (63) is located; the clamping block (61) is penetrated by the short arm (62) and is slidably connected; the outer side of the clamping block (61) is concave to form a second C-shaped clamping slot in end view; the second clamping slot abuts against the annular reinforcing stirrup (2); one end of the short arm (62) away from the cross arm (63) is fixed to a stop plate (65); one end of the oblique brace (64) is fixed to the short arm (62), and the other end is fixed to one end of the cross arm (63) close to the short arm (62) and is arranged obliquely; the strength of the oblique brace (64) is smaller than that of the cross arm (63).
3. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 2 is characterized in that: The cross arm (63) is a metal structural arm, and the diagonal support rod (64) is plastic.
4. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 2 is characterized in that: The length of the lower edge of the second bayonet is greater than the length of the upper edge.
5. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 1 is characterized in that: An anti-slip sleeve (421) is fixed on the screw rod (42), and the anti-slip sleeve (421) is located between the central seat (41) and the support head (43).
6. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 1 is characterized in that: A lifting lug (21) is fixed to the annular reinforcing stirrup (2) located at the top, and the lifting lug (21) is multiple and distributed in the annular direction of the annular reinforcing stirrup (2).
7. The anti-floating steel cage for rotary piles under complex geological conditions according to claim 1 is characterized by: It also comprises a double C clamp tube (7), wherein the double C clamp tube (7) is in the shape of two mutually diverging Cs connected to each other in end view, and the lower end or the upper end of the pile longitudinal reinforcement (1) is inserted into an opening of the double C clamp tube (7).