Support for power pipeline

By designing a power pipe bracket with annular channel and hoop to separate the control cable and power cable, the maintenance difficulties caused by mixed laying of cables in outdoor occasions are solved, and maintenance efficiency is improved and costs are reduced.

CN222147124UActive Publication Date: 2024-12-10POWERCHINA HUADONG ENG CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420761056.8
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-12
Publication Date
2024-12-10
Estimated Expiration
2034-04-12

AI Technical Summary

Technical Problem

When there is a lack of cable trench conditions in outdoor occasions, the power pipe brackets on the market will be mixed with control cables and power cables, making it difficult for maintenance personnel to distinguish during maintenance, which increases the maintenance time and difficulty.

Method used

Design a power pipe bracket, including a bracket assembly, an annular channel, a first hoop and a cover plate, laying a control cable through the annular channel, the first hoop and the second hoop are used to fix the power cable, and use the cover plate and the support assembly Form protection to achieve the separation of cables for easy maintenance.

Benefits of technology

By separating the control cable and power cable, the maintenance convenience of maintenance personnel is improved, the inspection time is saved, and the structure can be flexibly adjusted and has low cost.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222147124U_ABST
    Figure CN222147124U_ABST
Patent Text Reader

Abstract

The utility model relates to a support for a power pipeline. The utility model is suitable for the technical field of power pipeline erection. The technical problem to be solved by the utility model is to provide the bracket for the power pipeline. According to the technical scheme, the support for the power pipeline is characterized in that the support comprises a support assembly which is provided with a plurality of annular channels at intervals, and the annular channels are used for laying control cables; the first tension band is connected to the support assembly, and the first tension band is used for laying a power cable; the cover plate can be matched with the support assembly to protect the power pipeline; and the second tension band is connected to the cover plate, and the second tension band can be clamped with the first tension band and is used for fixing the power pipeline.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of electric power pipeline erection, in particular to a bracket for electric power pipelines. Background Art

[0002] Electrical cables and optical cables are usually laid in cable trenches, cable bridges or buried underground. However, in some outdoor places, the conditions for laying cable trenches are not available. In this case, the cables are usually laid in plastic pipes or steel pipes, and then supported by brackets or hung along the wall as power pipelines.

[0003] At present, most of the power pipeline supports used in the market lay control cables and power cables together in the same bridge for the convenience of installation. When maintenance is needed, it becomes difficult to find the control cables, which causes maintenance personnel to spend more time on investigation, which is not conducive to maintenance and repair. Utility Model Content

[0004] The technical problem to be solved by the utility model is: to provide a bracket for a power pipeline in view of the above-mentioned existing problems.

[0005] The technical solution adopted by the utility model is: a bracket for power pipelines, characterized in that it includes:

[0006] A bracket assembly, on which a plurality of annular channels are arranged at intervals, and the annular channels are used for laying control cables;

[0007] A first hoop, connected to the bracket assembly, the first hoop being used for laying power cables;

[0008] A cover plate, which can cooperate with the bracket assembly to protect the power pipeline;

[0009] The second hoop is connected to the cover plate, and the second hoop can be engaged with the first hoop to fix the power pipeline.

[0010] Through the above technical means, the annular channel on the bracket assembly is used to set up the power pipeline with the control cable passing through it. The first hoop and the second hoop cooperate to fix and support the power pipeline with the power cable passing through it. The cover plate cooperates with the bracket assembly to protect the power pipeline, so that the power cable and the control cable are separated from each other, which is convenient for inspection and maintenance.

[0011] In some embodiments, the bracket assembly includes supporting side plates, a cross beam, annular support blocks, and support columns. The supporting side plates are connected to both ends of the cross beam, a plurality of annular support blocks are spaced apart on the cross beam, the first hoop is connected to the cross beam, the annular support blocks are connected to the support columns, and the support columns on both sides of the first hoop can cooperate to provide lateral support to the first hoop.

[0012] In some embodiments, the cross beam and the annular support block, and the annular support block and the support column are connected by welding.

[0013] In some embodiments, the height D of the support column is the same as the radius of the first hoop.

[0014] In some embodiments, the first hoop can be engaged with the first hoop, so that the bracket assembly can achieve multi-level splicing.

[0015] The beneficial effects of the utility model are:

[0016] 1. Through the annular channel inside the annular support block in the bracket assembly, the power pipeline with the control cable is laid by using the annular channel. The power cable has a thicker outer diameter than the control cable. The first hoop and the second hoop cooperate to fix the power pipeline with the power cable, so that the power pipeline of the control cable and the power cable are separated, which is convenient for the later maintenance of the cables in the power pipeline on the bridge, improves the maintenance convenience of maintenance personnel, and saves the troubleshooting time of maintenance personnel.

[0017] 2. This structure can be made using flat steel, steel bars and other materials at the construction site. It is easy to obtain materials, has low cost, and can be flexibly adjusted according to site conditions. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 It is a schematic diagram of the structure of this application.

[0019] Description of reference numerals:

[0020] 1. Support side plate; 2. Crossbeam; 3. Annular support block; 4. Support column; 5. First hoop; 6. Second hoop; 7. Cover plate.

[0021] This specification includes references to "one embodiment" or "an embodiment." The appearance of the phrase "in one embodiment" or "in an embodiment" does not necessarily refer to the same embodiment. The particular features, structures or characteristics may be combined in any suitable manner consistent with the present disclosure.

[0022] The term "comprising" is open ended. As used in the appended claims, the term does not exclude additional structures or steps.

[0023] "First," "second," etc. As used herein, these terms act as labels for the nouns that precede them and do not imply any type of ordering (e.g., spatial, temporal, logical, etc.). DETAILED DESCRIPTION

[0024] In order to enable those skilled in the art to better understand the technical solution of the present utility model, the technical solution of the present utility model is further described below in conjunction with specific embodiments.

[0025] Combination Figure 1 As shown, this embodiment is a bracket for a power pipeline, including a bracket assembly, a first hoop 5, a cover plate 7 and a second hoop 6. The bracket assembly includes a supporting side plate 1, a crossbeam 2, an annular support block 3 and a supporting column 4. The two ends of the crossbeam 2 are connected to the supporting side plates 1. The supporting side plates 1 are provided with connecting holes. The supporting side plates 1 can be used to fix the entire structure on a wall or a hanger bracket. The crossbeam 2 is provided with annular support blocks 3 at intervals along the axial direction. The middle part of the annular support block 3 is provided with an annular channel. The annular channel can be used to set up a power pipeline with a control cable.

[0026] A plurality of first hoops 5 are connected to the crossbeam 2 at intervals in the axial direction, and support columns 4 corresponding to the first hoops 5 are connected to the annular support block 3, and the support columns 4 on both sides of the first hoops 5 can provide lateral support to the first hoops 5. A plurality of second hoops 6 are connected to the cover plate 7, and convex portions for connection are provided at both ends of the first hoops 5, and the first hoops 5 can be engaged with the second hoops 6 through the convex portions, thereby fixing the power pipeline through which the power cable is passed, and at the same time, the cover plate 7 can cooperate with the bracket assembly to form protection for the power pipeline.

[0027] The power cable is laid by the cooperation of the first hoop 5 and the second hoop 6, and the control cable is laid using the middle part of the annular support block 3, so that the power pipelines of the control cable and the power cable are separated, which is convenient for the later inspection of the cables in the power pipelines on the bridge and improves the inspection convenience of maintenance personnel.

[0028] Furthermore, the height D of the support column 4 is the same as the radius of the first hoop 5 .

[0029] In some embodiments, the cross beam 2 and the annular support block 3, the annular support block 3 and the support column 4, the cross beam 2 and the first hoop 5, and the cover plate 7 and the second hoop 6 are all connected by welding.

[0030] In some embodiments, the first hoops 5 can also be engaged with each other, so that a plurality of bracket assemblies form a multi-level splicing of the power pipeline.

[0031] The above are all preferred embodiments of the present utility model, and are not intended to limit the protection scope of the present utility model. Therefore, any equivalent changes made based on the structure, shape, and principle of the present utility model should be included in the protection scope of the present utility model.

Claims

1. A bracket for a power pipeline, characterized in that: include: A bracket assembly, on which a plurality of annular channels are arranged at intervals, and the annular channels are used for laying control cables; A first hoop (5) connected to the support assembly, wherein the first hoop (5) is used for laying power cables; A cover plate (7) capable of cooperating with the bracket assembly to protect the power pipeline; The second hoop (6) is connected to the cover plate (7), and the second hoop (6) can be engaged with the first hoop (5) to fix the power pipeline.

2. The bracket for electric power pipeline according to claim 1, characterized in that: The support assembly comprises a supporting side plate (1), a cross beam (2), an annular support block (3), and a support column (4); the supporting side plates (1) are connected to both ends of the cross beam (2); a plurality of annular support blocks (3) are arranged at intervals on the cross beam (2); the first hoop (5) is connected to the cross beam (2); the annular support block (3) is connected to the support column (4); and the support columns (4) on both sides of the first hoop (5) can cooperate to provide lateral support to the first hoop (5).

3. The bracket for electric power pipeline according to claim 2, characterized in that: The cross beam (2) and the annular support block (3), and the annular support block (3) and the support column (4) are connected by welding.

4. The bracket for electric power pipeline according to claim 2, characterized in that: The height (D) of the support column (4) is the same as the radius of the first hoop (5).

5. The bracket for electric power pipeline according to claim 1, characterized in that: The first hoop (5) can be engaged with the first hoop (5), so that the bracket assembly can achieve multi-level splicing.