Pipeline mounting rack
By designing an aluminum pipeline mounting frame with drive components, the time-consuming and labor-intensive fixing problem in the prior art is solved, and multiple pipelines are simultaneously fixed, improving installation efficiency and convenience.
Patent Information
- Application Number
- CN202420702799.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-07
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-04-07
AI Technical Summary
The existing pipeline mounting frames need to be fixed one by one when installing multiple pipelines, which is time-consuming and labor-intensive, and lacks efficient simultaneous fixing solutions.
A pipeline mounting frame including the first and second ply is designed, and the simultaneous limiting and clamping of multiple pipes is achieved through the drive assembly (casing and connecting rod), thereby improving lightweight and convenience using aluminum material. .
It realizes the simultaneous fixation of multiple pipelines, saving operating time and effort, and improving installation efficiency and convenience.
Smart Images

Figure CN222351633U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of electromechanical pipeline installation equipment, in particular to a pipeline installation frame. Background Art
[0002] Mechanical and electrical pipelines are part of mechanical and electrical engineering, mainly referring to pipelines used to transport fluid media (such as water, steam, air, gas, etc.) in buildings or facilities.
[0003] During the installation process, the electromechanical pipelines can be installed on the ceiling, and the pipeline installation frame can be used to assist the installation on the ceiling; when the pipeline installation frame is in use, the pipeline needs to be fixed on the installation frame, and then the installation frame is installed on the ceiling, so as to achieve the purpose of limiting the pipeline on the ceiling. When the pipeline is fixed on the installation frame, most installation frames include several fixing rings, and each fixing ring is provided with a clamping assembly; when in use, the pipeline is placed inside the fixing ring in sequence, and then the pipeline can be clamped in the fixing ring by the clamping assembly, so as to achieve the purpose of fixing the pipeline on the installation frame.
[0004] In the above-mentioned existing mounting frame, although it is convenient to fix the pipelines, each pipeline needs to be fixed separately, and multiple pipelines cannot be fixed on the mounting frame at the same time, so it is time-consuming and laborious to fix several pipelines. Utility Model Content
[0005] The utility model aims to provide a pipeline installation frame, which solves the problem of time-consuming and labor-intensive pipeline fixing.
[0006] The pipeline mounting frame includes a first clamping plate and a second clamping plate for clamping the pipeline; the first clamping plate is located below the second clamping plate, and the top of the first clamping plate is connected to a mounting plate for fixing to the ceiling through a fixing rod; a driving component for driving the second clamping plate to move up and down is arranged between the second clamping plate and the mounting plate.
[0007] Furthermore, a side wall between the first clamping plate and the second clamping plate is provided with a plurality of grooves for placing pipelines, and the plurality of grooves are arranged in sequence from left to right.
[0008] Furthermore, the driving assembly includes a vertically arranged sleeve, the lower end of the sleeve is rotatably connected to the top of the second clamping plate, the upper end of the sleeve is vertically provided with a connecting rod, and the upper end of the connecting rod is fixed to the bottom of the mounting plate; the outer side wall of the connecting rod is provided with an external thread, and the inner side wall of the sleeve is provided with an internal thread that is threadedly matched with the external thread.
[0009] Furthermore, the outer walls of the upper and lower ends of the connecting rod are both threaded sections, and the outer walls of the middle part are smooth; the outer diameter of the smooth section of the connecting rod is smaller than the major diameter of its threaded section; the inner wall of the upper end of the sleeve is a threaded section, and the inner walls of other parts are smooth.
[0010] Furthermore, there are two fixing rods, which are arranged left and right.
[0011] Furthermore, the second clamping plate is provided with a through hole communicating with each other up and down, the fixing rod is independently installed in the through hole, and the second clamping plate can slide up and down along the outer side wall of the fixing rod.
[0012] Furthermore, the first clamping plate is made of aluminum.
[0013] Furthermore, the second clamping plate is made of aluminum.
[0014] Compared with the prior art, the utility model has the following beneficial effects:
[0015] The utility model places a plurality of pipelines between the first clamping plate and the second clamping plate at the same time, and then under the action of the driving component, the pipelines can be simultaneously limited between the first clamping plate and the second clamping plate, so that in the process of fixing the pipelines, not only the operation time is saved, but also it is easier and more convenient; therefore, when fixing the pipelines, the purpose of saving time and labor is achieved as much as possible. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a schematic diagram of the structure of the utility model;
[0017] Figure 2 for Figure 1 Schematic diagram of the structure in which the middle sleeve moves upward and drives the second clamping plate to move upward;
[0018] Figure 3 for Figure 1 Main view structure diagram;
[0019] Figure 4 This is a state diagram used in the present utility model.
[0020] The names of the components in the figure are: 1, mounting plate 2, fixing rod 3, first clamping plate 4, second clamping plate 5, sleeve 6, connecting rod. DETAILED DESCRIPTION
[0021] The present invention is further described below through specific embodiments in conjunction with the accompanying drawings, but the present invention is not limited thereto. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
[0022] Example
[0023] A pipeline installation frame described in this embodiment, such as Figure 1 , Figure 2 and Figure 3 As shown, it comprises a first clamping plate 3 and a second clamping plate 4 for clamping pipelines, wherein the first clamping plate 3 is located below the second clamping plate 4; when the first clamping plate 3 and the second clamping plate 4 are produced, preferably, the sizes thereof are consistent; when in use, a plurality of pipelines are placed between the first clamping plate 3 and the second clamping plate 4 at the same time;
[0024] like Figure 1 As shown, the top of the first clamping plate 3 is connected to a mounting plate 1 for fixing to the ceiling through a fixing rod 2; when the fixing rod 2 is fixed, its top is fixed to the bottom of the mounting plate 1, and its bottom is fixed to the top of the first clamping plate 3; thus, the fixing rod 2 connects the mounting plate 1 and the first clamping plate 3 together; when the mounting plate 1 is specifically fixed to the ceiling, it can be fixed to the ceiling by welding, or a plurality of threaded holes can be opened on the mounting plate 1, and then the mounting plate 1 can be fixed to the ceiling by driving screws into the threaded holes;
[0025] like Figure 1 and Figure 2 As shown, a sleeve 5 is vertically arranged between the second clamping plate 4 and the mounting plate 1, and the lower end of the sleeve 5 is rotatably connected to the top of the second clamping plate 4, and a connecting rod 6 is vertically arranged on the upper end of the sleeve 5, and the upper end of the connecting rod 6 is fixed to the bottom of the mounting plate 1; the outer wall of the connecting rod 6 is provided with an external thread, and the inner wall of the sleeve 5 is provided with an internal thread that is threadedly matched with the external thread; this section of the scheme as a whole constitutes a driving assembly for driving the second clamping plate 4 to move up and down; when the rotary connection is specifically implemented, a blind hole can be opened at the top of the second clamping plate 4, a bearing is installed in the blind hole, the outer ring of the bearing is fixed in the blind hole, and the lower end of the sleeve 5 is fixed to the inner ring of the bearing, so that the sleeve 5 can rotate on the second clamping plate 4 without driving the second clamping plate 4 to rotate, thereby realizing a rotary connection; at the same time, because the outer side of the connecting rod 6 is threadedly matched with the inner side of the sleeve 5, and the connecting rod 6 is fixed to the bottom of the mounting plate 1, when the sleeve 5 is rotated through the thread, it can move up and down along the connecting rod 6, and during the upward movement of the sleeve 5, as shown in FIG. Figure 2 In the middle position, the sleeve 5 can drive the second clamping plate 4 to move upward, so that a gap can be left between the first clamping plate 3 and the second clamping plate 4, and then multiple pipelines with the same size can be placed between the first clamping plate 3 and the second clamping plate 4 at the same time; then when the sleeve 5 moves downward along the connecting rod 6, it can drive the second clamping plate 4 to move downward, and when the bottom of the second clamping plate 4 contacts multiple pipelines, multiple pipelines can be clamped between the first clamping plate 3 and the second clamping plate 4 at the same time; thereby saving time and effort in the process of clamping the pipelines;
[0026] In the specific implementation process, the interior of the connecting rod 6 in the driving assembly can be a hollow structure, thereby saving production costs;
[0027] like Figure 1 and Figure 2 As shown, the outer walls of the upper and lower ends of the connecting rod 6 are both threaded sections, and the outer wall of the middle part is smooth; the outer diameter of the smooth section of the connecting rod 6 is smaller than the major diameter of its threaded section; the inner wall of the upper end of the sleeve 5 is a threaded section, and the inner walls of other parts are smooth; because the outer diameter of the smooth section of the connecting rod 6 is smaller than the major diameter of its threaded section, the threaded section and the smooth section of the connecting rod 6 can be moved into the sleeve 5; during the movement, when the thread of the sleeve 5 moves to the threaded section at the lower end of the connecting rod 6, the sleeve 5 drives the second clamping plate 4 to move downward, and the pipeline is clamped between the first clamping plate 3 and the second clamping plate 4; when the thread of the sleeve 5 moves to the threaded section at the upper end of the connecting rod 6, The second clamping plate 4 is lifted upward, and a gap for placing the pipeline is left between the first clamping plate 3 and the second clamping plate 4; by only setting the threaded sections at the two ends of the connecting rod 6, when the lower end of the connecting rod 6 passes through the threaded section on the sleeve 5, the smooth section in the middle part of the connecting rod 6 can slide quickly in the sleeve 5, thereby increasing the speed of the sleeve 5 moving upward or downward, thereby increasing the speed of the second clamping plate 4 moving upward or downward; if the outer side wall of the connecting rod 6 is provided with external threads, it takes a certain amount of time to screw the sleeve 5 on the connecting rod 6, so the above design can save operation time, has certain practicality, and saves time and effort during operation;
[0028] like Figure 1 and Figure 4 As shown, a side wall between the first clamping plate 3 and the second clamping plate 4 is provided with a plurality of grooves for placing pipelines, and the plurality of grooves are arranged in sequence from left to right; a side wall between the first clamping plate 3 and the second clamping plate 4 is respectively the top of the first clamping plate 3 and the bottom of the second clamping plate 4; the grooves are all semicircular arc structures that are connected front to back, and when the grooves on the first clamping plate 3 and the grooves on the second clamping plate 4 are in contact, a circular structure is formed between the two grooves, and the rear pipeline is placed in the circle formed by the two grooves; the diameter of the circular structure formed between each two grooves can be different in size, so that it is convenient to place pipelines of different thicknesses and sizes; because a plurality of grooves are provided, multiple pipelines can be placed in the grooves; through the design of the grooves, the contact surface between the pipeline and the first clamping plate 3 and the second clamping plate 4 can be increased, so that the pipeline can be placed more stably between the first clamping plate 3 and the second clamping plate 4;
[0029] Further preferably, the plurality of grooves are arranged at equal intervals from left to right. The equal interval design not only facilitates the management of the pipeline, but also saves a certain amount of material.
[0030] like Figure 1As shown, there are two fixing rods 2, which are arranged left and right. The design of the two fixing rods 2 can improve the stability between the mounting plate 1 and the first clamping plate 3.
[0031] like Figure 1 As shown, the second clamping plate 4 is provided with a through hole communicating with each other from top to bottom, the fixing rod 2 is independently installed in the through hole, and the second clamping plate 4 can slide up and down along the outer wall of the fixing rod 2; through the design of the through hole, the second clamping plate 4 can be limited on the fixing rod 2 to prevent the second clamping plate 4 from turning over; and when the sleeve 5 drives the second clamping plate 4 to move upward, the stability of the second clamping plate 4 when moving up and down can be improved;
[0032] The first clamping plate 3 is made of aluminum, and the second clamping plate 4 is made of aluminum; aluminum has many advantages, such as light weight, high strength, easy processing, strong corrosion resistance and high hardness; therefore, in the process of moving the second clamping plate 4 up and down, the weight can be reduced, which is convenient for movement;
[0033] During specific use: when the pipeline needs to be installed, first install the mounting plate 1 on the ceiling, thereby driving the first clamping plate 3 to be limited on the ceiling, and then adjust the sleeve 5 to move upward, thereby driving the second clamping plate 4 to move upward; then place multiple pipelines in sequence between the first clamping plate 3 and the second clamping plate 4. After the placement is completed, adjust the sleeve 5 to move downward, and the sleeve 5 drives the second clamping plate 4 to move downward. During the downward movement, because the pipeline is located between the first clamping plate 3 and the second clamping plate 4 at the same time, the pipeline can be limited between the first clamping plate 3 and the second clamping plate 4 at the same time. Compared with the prior art of fixing the pipelines one by one, it is more time-saving and labor-saving, and saves operation time.
Claims
1. A pipeline installation frame, comprising a first clamping plate (3) and a second clamping plate (4) for clamping a pipeline; the first clamping plate (3) is located below the second clamping plate (4), characterized in that: The top of the first clamping plate (3) is connected to a mounting plate (1) for fixing on a ceiling via a fixing rod (2); a driving component for driving the second clamping plate (4) to move up and down is provided between the second clamping plate (4) and the mounting plate (1).
2. The pipeline installation frame according to claim 1, characterized in that: A side wall between the first clamping plate (3) and the second clamping plate (4) is provided with a plurality of grooves for placing pipelines, and the plurality of grooves are arranged in sequence from left to right.
3. The pipeline installation frame according to claim 1, characterized in that: The driving assembly comprises a vertically arranged sleeve (5), the lower end of the sleeve (5) is rotatably connected to the top of the second clamping plate (4), the upper end of the sleeve (5) is vertically arranged with a connecting rod (6), and the upper end of the connecting rod (6) is fixed to the bottom of the mounting plate (1); the outer wall of the connecting rod (6) is provided with an external thread, and the inner wall of the sleeve (5) is provided with an internal thread that is threadably matched with the external thread.
4. The pipeline installation frame according to claim 3, characterized in that: The outer walls of the upper and lower ends of the connecting rod (6) are both threaded sections, and the outer wall of the middle part is smooth; the outer diameter of the smooth section of the connecting rod (6) is smaller than the major diameter of its threaded section; the inner wall of the upper end of the sleeve (5) is a threaded section, and the inner walls of the other parts are smooth.
5. The pipeline installation frame according to claim 4, characterized in that: There are two fixing rods (2) arranged in left and right positions.
6. The pipeline installation frame according to claim 5, characterized in that: The second clamping plate (4) is provided with a through hole communicating with each other from top to bottom, the fixing rod (2) is independently installed in the through hole, and the second clamping plate (4) can slide up and down along the outer side wall of the fixing rod (2).
7. The pipeline installation frame according to claim 1, characterized in that: The first clamping plate (3) is made of aluminum.
8. The pipeline installation frame according to claim 1, characterized in that: The second clamping plate (4) is made of aluminum.