Sleeper replacing vehicle and sleeper replacing system

By designing a car pillow replacement car that includes frame, steering frame, longitudinal shift conveyor belt, mobile operating vehicle, and lifting conveyor, it solves the problem of long -term, not flexible and complicated processes in the existing technology rail line pillow replacement process. , Achieving an efficient and flexible pillow replacement system.

CN222390155UActive Publication Date: 2025-01-24CRCC HIGH TECH EQUIP CORP LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421015411.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-11
Publication Date
2025-01-24
Estimated Expiration
2034-05-11

AI Technical Summary

Technical Problem

The prior art has problems such as long operation time, lack of flexibility and complicated processes in the replacement of rail sleepers in track lines, and is especially not suitable for environments where a small number of old sleepers are replaced.

Method used

A pillow replacement car is designed, including frame, steering rack, longitudinal shift conveyor belt, mobile work trolley and lifting conveyor. Through the collaborative work of these components, the efficient recycling and laying of pillow pillows are realized.

Benefits of technology

This system can realize the cyclic operation of recycling old pillows and laying new pillows at the same time, improving the efficiency of pillow replacement, reducing labor costs and safety hazards, and is suitable for track lines of different sizes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222390155U_ABST
    Figure CN222390155U_ABST
Patent Text Reader

Abstract

The utility model provides a sleeper replacing vehicle and a sleeper replacing system. The sleeper replacing vehicle comprises a vehicle frame. Two bogies; the first longitudinal moving conveying belt is used for bearing and transporting new and old sleepers; the mobile operation trolley is used for clamping old pillows and laying new pillows; the lifting conveyor comprises a front lifting conveyor and a rear lifting conveyor, and the front lifting conveyor and the rear lifting conveyor are located at the positions where the front lifting conveyor and the rear lifting conveyor are in butt joint with the front end and the rear end of the first longitudinal moving conveying belt correspondingly; the movable lifters comprise the front movable lifter and the rear movable lifter which are located between the movable operation trolley and the front lifting conveyor and between the movable operation trolley and the rear lifting conveyor respectively. The device has the beneficial effects of being capable of simultaneously achieving circulating operation of recycling old pillows and laying new pillows, high in pillow replacement efficiency and high in space utilization rate. The method is suitable for the technical field of railway line maintenance.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of railway line maintenance and repair, and in particular to a sleeper replacement vehicle and a sleeper replacement system. Background Art

[0002] At present, the sleeper replacement operations on old rail lines mainly use two methods: large sleeper replacement trains and simple sleeper replacement equipment composed of small excavators and multi-functional sleeper grabbing devices.

[0003] Large sleeper-changing trains use two sets of devices for laying new sleepers and recycling old sleepers, which increases the manufacturing cost and the length of the sleeper-changing equipment. Sleepers need to be frequently transported between the sleeper storage vehicle and the sleeper-changing vehicle. The entire operation line is relatively long, large in size, and difficult to park. It is suitable for track line operation areas that require a large number of old rails to be replaced. However, the operation takes a long time and is inflexible, so it is not suitable for a small number of old sleepers to be replaced.

[0004] The simple sleeper replacement equipment composed of a small excavator and a multifunctional sleeper grabbing device has a short operation line and high flexibility, but it can only replace old sleepers over a short distance at a time, and new and old sleepers need to be transported frequently, which has a very low operation efficiency. In addition, during the sleeper replacement process, the new sleepers need to be placed on both sides of the roadbed in the operation area, and the replaced old sleepers also need to be temporarily placed on both sides of the roadbed, and then the replaced old sleepers need to be uniformly recycled, which increases labor costs and safety hazards. Utility Model Content

[0005] In order to solve one of the above-mentioned technical defects, the present application provides a sleeper replacement vehicle and a sleeper replacement system.

[0006] According to a first aspect of the present application, there is provided a sleeper replacement vehicle, comprising:

[0007] Frame;

[0008] Two bogies are respectively arranged at two ends of the bottom of the frame;

[0009] A first longitudinal conveyor belt, arranged above the frame, for carrying and transporting new and old sleepers;

[0010] A mobile operation trolley is arranged below the frame and can move longitudinally along the frame to clamp old pillows and lay new pillows;

[0011] A lifting conveyor, comprising a front lifting conveyor and a rear lifting conveyor respectively arranged at the front and rear ends of the frame, the front lifting conveyor and the rear lifting conveyor respectively being located at positions docking with the front and rear ends of the first longitudinal conveyor belt, and being used to convey the recycled old pillows to the first longitudinal conveyor belt, and to transfer the new pillows on the first longitudinal conveyor belt;

[0012] The mobile lift is arranged at the bottom of the frame, including a front mobile lift and a rear mobile lift, which are respectively located between the mobile working vehicle and the front lifting conveyor and the rear lifting conveyor. The mobile lift is used to transfer the old sleepers clamped and placed on the track by the mobile working vehicle to the front lifting conveyor, and to grab the new sleepers on the rear lifting conveyor and place them on the track for the mobile working vehicle to clamp and lay.

[0013] Preferably, the lifting conveyor comprises:

[0014] A guide frame, arranged on the frame;

[0015] A second longitudinal conveyor belt;

[0016] The movable frame is connected to the second longitudinal conveyor belt and is connected to the guide frame through a first lifting drive component. The first lifting drive component drives the movable frame to drive the second longitudinal conveyor belt to move from top to bottom to the first working position A and the second working position B; the first working position A corresponds to the position of the first longitudinal conveyor belt, and the second working position B corresponds to the position of the corresponding mobile elevator.

[0017] More preferably, a first running track is provided on the frame at a position close to the mobile lift, and the first running track is provided along the length direction of the frame;

[0018] The mobile lift comprises:

[0019] A first running component, which is adapted to the first running track, so that the first running component can drive the entire mobile lift to move along the setting direction of the first running track;

[0020] A telescopic frame is arranged below the first running component, and a second lifting driving component is arranged on the telescopic frame, and the second driving component drives the telescopic frame to extend and retract in the vertical direction;

[0021] The sleeper gripper is arranged below the telescopic frame and located on the side close to the corresponding lifting conveyor. It is used to grab the old sleepers clamped by the mobile working trolley and placed on the track, and then transport them to the front lifting conveyor, and grab the new sleepers transported by the rear lifting conveyor and place them on the track for the mobile working trolley to clamp and lay them; both ends of the sleeper gripper are provided with folding parts for lateral limitation of the grabbed sleepers.

[0022] More preferably, the telescopic frame comprises: at least two support frames sequentially sleeved from outside to inside;

[0023] The top of the support frame arranged at the outermost layer is connected to the first running component; the sleeper gripper is connected to the bottom of the support frame arranged at the innermost layer;

[0024] Among the two adjacent support frames, lifting grooves are provided on the inner sides of the support frame located on the outer layer, and lifting protrusions are provided on the outer sides of the support frame located on the inner layer. The two lifting grooves are respectively matched with the two lifting protrusions, so that the support frame located on the inner side is lifted and lowered along the setting direction of the lifting grooves on the support frame located on the outer side.

[0025] More preferably, the mobile operation vehicle comprises:

[0026] The driver's cab has an operating table inside;

[0027] A second running component disposed above the driver's cab, which is adapted to the first running track, so that the second running component can drive the driver's cab to move along the setting direction of the first running track;

[0028] A working arm, one end of which is connected to the driver's cab, and the other end of which is provided with a clamping portion and a scraper. The working arm is provided with a working drive component, and the working end of the working drive component is respectively connected to the clamping portion and the scraper, and the operating table is electrically connected to the working drive component.

[0029] More preferably, a swivel support portion is provided between the driver's cab and the second running member, so that the driver's cab can swivel relative to the second running member.

[0030] More preferably, the swivel support portion swivels by 180° each time.

[0031] Preferably, the second lifting drive component includes at least one steel wire rope, a motor winch arranged on the top of the outermost support frame and a pulley arranged on the innermost support frame, and the number and position of the pulleys correspond one-to-one to the steel wire rope; one end of the steel wire rope is wound around the motor winch, and the other end of the steel wire rope is connected to the corresponding pulley.

[0032] Preferably, the second longitudinal conveyor belt is extended toward one end close to the corresponding mobile elevator.

[0033] According to a second aspect of the present application, a sleeper replacement system is provided, comprising a power vehicle and at least one sleeper replacement vehicle as described in any one of the above items connected to the power vehicle.

[0034] The sleeper replacement vehicle in the present application can accommodate a mobile work vehicle and a mobile lift below. The front mobile lift transfers the old sleepers that the mobile work vehicle clamps and places on the track to the front lift conveyor, and then transports the old sleepers to the front end of the first longitudinal conveyor belt (the first longitudinal conveyor belt rotates backward during this process); at the same time, the new sleepers stored on the rear end of the first longitudinal conveyor belt are transported to the track in turn through the rear lift conveyor and the rear mobile lift, so that the mobile work vehicle can clamp and lay them to the required position. The sleeper replacement vehicle provided in the present application has a simple structure and a reasonable design. It can simultaneously realize the cyclic operation of recycling old sleepers and laying new sleepers, and the sleeper replacement efficiency is relatively high. The first longitudinal conveyor belt is used to carry and transport old sleepers and new sleepers, with high space utilization, small size, easy parking and more flexible use, avoiding the complicated process of grabbing and replacing the new sleepers placed on both sides of the track, and then placing the replaced old sleepers on both sides of the track, and then centrally recycling the old sleepers in the prior art, which can further improve the working efficiency. The arrangement of two bogies at the bottom of the frame makes the structure of the entire sleeper replacement vehicle more stable and facilitates the separate maintenance of the sleeper replacement vehicle.

[0035] Other features and advantages of the present application will be described in the following description, and partly become apparent from the description, or understood by practicing the present application. The purpose and other advantages of the present application can be realized and obtained by the contents indicated in the written description and the accompanying drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] The drawings described herein are used to provide a further understanding of the present application and constitute a part of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute an improper limitation on the present application. In the drawings:

[0037] Figure 1 A schematic diagram of the structure of a sleeper replacement vehicle provided in this application;

[0038] Figure 2 A schematic diagram of the structure of the lifting conveyor provided for this application;

[0039] Figure 3 A schematic diagram of the connection structure between the second longitudinal conveyor belt and the movable frame provided in the present application;

[0040] Figure 4 A side view of the front mobile lift provided for this application;

[0041] Figure 5 A front view of the mobile lift provided for this application;

[0042] Figure 6 A schematic diagram of the structure of the mobile operation vehicle provided for this application;

[0043] In the figure:

[0044] 1 is a frame, 2 is a bogie, 3 is a first longitudinal conveyor belt, 4 is a mobile operating trolley, 5 is a lifting conveyor, 6 is a mobile lift, 7 is a first running track, 41 is a driver's cab, 42 is a second running component, 43 is an operating arm, 44 is a slewing support part, 51 is a guide frame, 52 is a second longitudinal conveyor belt, 53 is a mobile frame, 61 is a first running component, 62 is a telescopic frame, 63 is a sleeper gripper, 431 is a clamping part, 432 is a scraper, and 621 is a supporting frame. DETAILED DESCRIPTION

[0045] In order to make the technical solutions and advantages in the embodiments of the present application more clearly understood, the exemplary embodiments of the present application are further described in detail below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present application, rather than an exhaustive list of all the embodiments. It should be noted that the embodiments in the present application and the features in the embodiments can be combined with each other without conflict.

[0046] In the present application, the length direction of the sleeper replacement vehicle is the longitudinal direction, the height direction of the sleeper replacement vehicle is the vertical direction, and the width direction of the sleeper replacement vehicle is the transverse direction.

[0047] Figure 1 A schematic diagram of the structure of a sleeper replacement vehicle provided in this application, such as Figure 1 As shown, in order to solve the above problems, a sleeper replacement vehicle is provided in an embodiment of the present application, comprising:

[0048] Frame 1;

[0049] Two bogies 2 are respectively arranged at two ends of the bottom of the frame 1;

[0050] A first longitudinal conveyor belt 3 is arranged above the frame 1 and is used to carry and transport new and old sleepers;

[0051] A mobile operation trolley 4 is arranged below the frame 1 and can move longitudinally along the frame 1 to clamp old pillows and lay new pillows;

[0052] The lifting conveyor 5 comprises a front lifting conveyor and a rear lifting conveyor respectively arranged at the front and rear ends of the frame 1, the front lifting conveyor and the rear lifting conveyor are respectively located at the positions docking with the front and rear ends of the first longitudinal conveyor belt 3, and are used to convey the recycled old pillows to the first longitudinal conveyor belt 3, and transfer the new pillows on the first longitudinal conveyor belt 3;

[0053] The mobile lift 6 is arranged at the bottom of the frame 1, including a front mobile lift and a rear mobile lift, which are respectively located between the mobile working vehicle 4 and the front lifting conveyor and the rear lifting conveyor. It is used to transfer the old sleepers clamped and placed on the track by the mobile working vehicle 4 to the front lifting conveyor, and to grab the new sleepers on the rear lifting conveyor and place them on the track for the mobile working vehicle 4 to clamp and lay.

[0054] The sleeper replacement vehicle in the present application can accommodate a mobile work vehicle and a mobile lift below. The front mobile lift transfers the old sleepers that the mobile work vehicle clamps and places on the track to the front lift conveyor, and then transports the old sleepers to the front end of the first longitudinal conveyor belt (the first longitudinal conveyor belt rotates backward during this process); at the same time, the new sleepers stored on the rear end of the first longitudinal conveyor belt are transported to the track in turn through the rear lift conveyor and the rear mobile lift, so that the mobile work vehicle can clamp and lay them to the required position. The sleeper replacement vehicle provided in the present application has a simple structure and a reasonable design. It can simultaneously realize the cyclic operation of recycling old sleepers and laying new sleepers, and the sleeper replacement efficiency is relatively high. The first longitudinal conveyor belt is used to carry and transport old sleepers and new sleepers, with high space utilization, small size, easy parking and more flexible use, avoiding the complicated process of grabbing and replacing the new sleepers placed on both sides of the track, and then placing the replaced old sleepers on both sides of the track, and then centrally recycling the old sleepers in the prior art, which can further improve the working efficiency. The arrangement of two bogies at the bottom of the frame makes the structure of the entire sleeper replacement vehicle more stable and facilitates the separate maintenance of the sleeper replacement vehicle.

[0055] Furthermore, the second longitudinal conveyor belt 52 is extended toward one end close to the corresponding mobile elevator 6, so as to facilitate the clamping of the sleepers by the rear mobile elevator, and facilitate the second longitudinal conveyor belt of the front lifting conveyor to take over the old sleepers on the front mobile elevator, so that the transfer of sleepers between the second longitudinal conveyor belt and the mobile elevator is smoother, and there will be no problem of sleepers slipping, which is safer and the operation effect is more stable.

[0056] Figure 2 The structural diagram of the lifting conveyor provided for this application is as follows, Figure 3 The schematic diagram of the connection structure between the second longitudinal conveyor belt and the mobile frame provided in this application is as follows: Figure 2 and Figure 3 As shown, further,

[0057] The lifting conveyor 5 comprises:

[0058] A guide frame 51 is provided on the vehicle frame 1;

[0059] A second longitudinal conveyor belt 52;

[0060] The movable frame 53 is connected to the second longitudinal conveyor belt 52, and is connected to the guide frame 51 through a first lifting drive component. The first lifting drive component drives the movable frame 53 to drive the second longitudinal conveyor belt 52 to move from top to bottom to the first working position A and the second working position B; the first working position A corresponds to the position of the first longitudinal conveyor belt 3, and the second working position B corresponds to the position of the corresponding mobile elevator 6.

[0061] In the present application, the first lifting drive component can drive the mobile frame to drive the second longitudinal conveyor belt to move to the first working position A and the second working position B respectively, so as to realize the sleeper transmission between the second longitudinal conveyor belt and the first longitudinal conveyor belt and the mobile lift. Since the stroke of each working position is fixed, it can be moved according to the cycle, which is flexible and convenient to use, does not require human intervention, saves manpower and cost, reduces the occurrence of failures, and has higher working efficiency; and there is no need to set up sensors and other detection components, which improves the stability of operation.

[0062] Figure 4 Side view of the front mobile lift provided for this application, Figure 5 The front view of the mobile lift provided for this application, such as Figure 4-Figure 5 As shown, Figure 4 The direction indicated by the middle arrow is the direction of sleeper lifting. Figure 5 The direction indicated by the middle arrow is the direction of the sleeper closing.

[0063] A first running track 7 is provided on the frame 1 at a position close to the mobile lift 6, and the first running track 7 is provided along the length direction of the frame 1;

[0064] The mobile lift 6 comprises:

[0065] A first running component 61, which is adapted to the first running track 7, so that the first running component 61 can drive the entire mobile lift 6 to move along the setting direction of the first running track 7;

[0066] The telescopic frame 62 is arranged below the first running component 61, and the telescopic frame 62 is provided with a second lifting driving component, and the second driving component drives the telescopic frame 62 to extend and retract in the vertical direction;

[0067] The sleeper gripper 63 is arranged below the telescopic frame 62 and is located on the side close to the corresponding lifting conveyor 5. It is used to grab the old sleepers clamped and placed on the track by the mobile operation trolley 4, and then transport them to the front lifting conveyor. It is used to grab the new sleepers transported by the rear lifting conveyor and place them on the track for the mobile operation trolley 4 to clamp and lay. Both ends of the sleeper gripper 63 are provided with folding parts, which are used to lateral limit the two ends of the grabbed sleepers. The folding parts can realize the automatic centering function of the sleepers, avoid the interference of the sleepers with other parts during the transportation process, and are more convenient and safe.

[0068] In the present application, since there is a distance difference between the lifting conveyor and the clamping part of the mobile working vehicle in the longitudinal and vertical directions, the mobile lifting device arranged between the two needs to realize the longitudinal and vertical transportation of the sleepers. The first running component can move along the running track, thereby driving the telescopic frame and the sleeper gripper to move longitudinally, and the telescopic frame can be telescoped vertically, so that the sleepers transported on the sleeper gripper can be adjusted vertically. The sleeper gripper is located on the side close to the corresponding lifting conveyor, which is convenient for clamping the old sleepers that the mobile working vehicle clamps and places on the track, and then directly placing the old sleepers on the second longitudinal conveyor belt of the front lifting conveyor; and it is convenient to directly clamp the new sleepers on the rear lifting conveyor, and then transport them to the track close to the mobile working vehicle. Interference with other components is avoided during the operation, which is more convenient. The travel of the telescopic frame at each working position is also fixed, so it can be moved in a cycle. It is flexible and convenient to use and does not require human intervention, saving manpower and costs, reducing the occurrence of failures, and improving working efficiency. There is no need to set up sensors and other detection components, which improves working stability.

[0069] Furthermore, the telescopic frame 62 includes: at least two support frames 621 which are sequentially sleeved from the outside to the inside;

[0070] The top of the support frame 621 disposed on the outermost layer is connected to the first running member 61; the sleeper gripper 63 is connected to the bottom of the support frame 621 disposed on the innermost layer;

[0071] Among the two adjacent support frames 621, lifting grooves are set on the inner sides of the support frame 621 located on the outer layer, and lifting protrusions are set on the outer sides of the support frame 621 located on the inner layer. The two lifting grooves are respectively matched with the two lifting protrusions, so that the support frame 621 located on the inner side is lifted and lowered along the setting direction of the lifting grooves on the support frame 621 located on the outer side.

[0072] The telescopic frame in the present application is formed by at least two supporting frames, wherein the number of supporting frames is determined by the displacement required to be adjusted in the vertical direction, and the practicability is high. The lifting slot and the lifting protrusion are adapted to make the lifting process smoother and the use effect better.

[0073] Furthermore, the second lifting drive component includes at least one steel wire rope, a motor winch arranged on the top of the outermost support frame 621 and a pulley arranged on the innermost support frame 621, and the number and position of the pulleys correspond one-to-one to the steel wire rope; one end of the steel wire rope is wound around the motor winch, and the other end of the steel wire rope is connected to the corresponding pulley.

[0074] Figure 6 The structural diagram of the mobile operation vehicle provided for this application is as follows: Figure 6 As shown, further, the mobile operation vehicle 4 includes:

[0075] A driver's cab 41, wherein an operating console is arranged inside;

[0076] A second running component 42 disposed above the driver's cab 41 is adapted to the first running track 7 so that the second running component 42 can drive the driver's cab 41 to move along the setting direction of the first running track 7;

[0077] The working arm 43 has one end connected to the driver's cab 41, and the other end thereof is provided with a clamping portion 431 and a scraper 432. The working arm 43 is provided with a working drive component, and the working end of the working drive component is respectively connected to the clamping portion 431 and the scraper 432, and the operating table is electrically connected to the working drive component.

[0078] Furthermore, a swivel support part 44 is provided between the driver's cab 41 and the second running member 42, so that the driver's cab 41 can swivel relative to the second running member 42. The swivel support part 44 swivels by an angle of 180° each time.

[0079] In this application, the mobile work vehicle needs to complete the grabbing of old pillows and the laying of new pillows, so a driver's cab needs to be set up, and it needs to rotate through a slewing support part to reduce the visual blind spot. The work drive component makes the operation of the clamping part and the scraper more flexible, and the grabbing of old pillows and the laying of new pillows are more precise.

[0080] In the present application, the stroke of each rotation of the slewing support part is fixed to 180°, which is convenient for replacing the position of the sleeper on the fork hook to realize cyclic replacement of the sleeper, and the operation efficiency is higher.

[0081] Specifically, in the present application, the rotation of the first longitudinal conveyor belt 3, the second longitudinal conveyor belt 52, the first lifting drive component, the second lifting drive component, the first running component 64, the second running component 42, the operating drive component, and the rotating support part 44 can be provided with driving force by any driving component such as a motor, a hydraulic motor or a pneumatic motor.

[0082] More specifically, the first lifting drive component, the second lifting drive component, and the operation drive component can be a structure selected from the group consisting of a chain, an oil cylinder, an air cylinder, and a motor winch.

[0083] More specifically, the first running track 7 and the lifting groove can be a structure selected from the group consisting of a steel rail, a guide groove, a dovetail and a guide column.

[0084] The present application also provides a sleeper replacement system, comprising a power vehicle and at least one sleeper replacement vehicle as described in any of the above items connected to the power vehicle.

[0085] Since the sleeper replacement system provided in this application includes the sleeper replacement vehicle, it can be considered that it has the same beneficial effects as the sleeper replacement vehicle, which will not be described in detail. In this application, the number of sleeper replacement vehicles can be selected according to actual use needs, which can meet the use requirements of a small number of replacements of old sleepers or a large number of replacements of old sleepers.

[0086] Working Principle: Figure 1 The direction indicated by the arrow is the direction of replacement of the old and new sleepers)

[0087] 1. First, place the new pillows neatly on the first longitudinal conveyor belt 3; the number of new pillows to be placed can be selected according to actual needs;

[0088] 2. After the mobile operation trolley 4 moves longitudinally to the position where the pillow needs to be replaced, the old pillow is clamped and placed on the track. The front mobile elevator grabs the old pillow and moves it close to the front elevator conveyor. At this time, the second longitudinal conveyor belt of the front elevator conveyor moves to the operation position B and receives the old pillow. Then the second longitudinal conveyor belt moves to the operation position A. At this time, the first longitudinal conveyor belt 3 and the second longitudinal conveyor belt rotate backward synchronously, so that the old pillow is transported to the front end of the first longitudinal conveyor belt 3;

[0089] 3. At the same time, the second longitudinal conveyor belt of the rear lifting conveyor also rotates backward synchronously, and the new pillow at the rear end of the first longitudinal conveyor belt 3 is transported to the second longitudinal conveyor belt of the rear lifting conveyor, and the second longitudinal conveyor belt drives the new pillow from the working position A to the working position B; then the rear mobile elevator moves to a position close to the rear lifting conveyor and grabs the new pillow, and then the rear mobile elevator drives the new pillow to the position where the new pillow needs to be laid, and the new pillow is placed on the track, and the mobile operation trolley clamps and lays the new pillow;

[0090] 4. Repeat steps 2-3 above until all the old pillows in the working area are replaced with new ones, or the new pillows on the first longitudinal conveyor belt 3 are used up.

[0091] In the description of the present application, it should be understood that the terms "longitudinal", "length", "up", "down", "front", "back", "vertical", "top", "bottom", "inside", "outside", etc., indicating the orientation or position relationship, are based on the orientation or position relationship shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present application.

[0092] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is at least two, such as two, three, etc., unless otherwise clearly and specifically defined.

[0093] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection, an electrical connection, or can communicate with each other; it can be a direct connection, or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0094] Although the preferred embodiments of the present application have been described, those skilled in the art may make other changes and modifications to these embodiments once they have learned the basic creative concept. Therefore, the appended claims are intended to be interpreted as including the preferred embodiments and all changes and modifications falling within the scope of the present application.

[0095] Obviously, those skilled in the art can make various changes and modifications to the present application without departing from the spirit and scope of the present application. Thus, if these modifications and variations of the present application fall within the scope of the claims of the present application and their equivalents, the present application is also intended to include these modifications and variations.

Claims

1. A sleeper replacement vehicle, characterized in that: include: Frame (1); Two bogies (2) are respectively arranged at two ends of the bottom of the vehicle frame (1); A first longitudinal conveyor belt (3) is arranged above the vehicle frame (1) and is used for carrying and transporting new and old sleepers; A mobile operation trolley (4) is arranged below the frame (1) and can move longitudinally along the frame (1) to clamp old pillows and lay new pillows; A lifting conveyor (5), comprising a front lifting conveyor and a rear lifting conveyor respectively arranged at the front and rear ends of the frame (1), the front lifting conveyor and the rear lifting conveyor respectively being located at positions docking with the front and rear ends of the first longitudinal conveyor belt (3), and being used to convey the recycled old pillows to the first longitudinal conveyor belt (3), and to transfer the new pillows on the first longitudinal conveyor belt (3); The mobile lift (6) is arranged at the bottom of the frame (1), and comprises a front mobile lift and a rear mobile lift, which are respectively located between the mobile operation vehicle (4) and the front lift conveyor and the rear lift conveyor, and are used to transfer the old sleepers clamped by the mobile operation vehicle (4) and placed on the track to the front lift conveyor, and to grab the new sleepers on the rear lift conveyor and place them on the track for the mobile operation vehicle (4) to clamp and lay.

2. The sleeper replacement vehicle according to claim 1, characterized in that: The lifting conveyor (5) comprises: A guide frame (51) is arranged on the vehicle frame (1); A second longitudinal conveyor belt (52); The movable frame (53) is connected to the second longitudinal conveyor belt (52) and is connected to the guide frame (51) via a first lifting drive component. The first lifting drive component drives the movable frame (53) to drive the second longitudinal conveyor belt (52) to move from top to bottom to a first working position A and a second working position B; the first working position A corresponds to the position of the first longitudinal conveyor belt (3), and the second working position B corresponds to the position of the corresponding movable lift (6).

3. The sleeper replacement vehicle according to claim 2, characterized in that: A first running track (7) is arranged on the frame (1) at a position close to the mobile lift (6), and the first running track (7) is arranged along the length direction of the frame (1); The mobile lift (6) comprises: A first running component (61) adapted to the first running track (7) such that the first running component (61) can drive the entire mobile lift (6) to move along a setting direction of the first running track (7); A telescopic frame (62) is arranged below the first running component (61), and a second lifting driving component is arranged on the telescopic frame (62), and the second driving component drives the telescopic frame (62) to extend and retract in the vertical direction; The sleeper gripper (63) is arranged below the telescopic frame (62) and is located on a side close to the corresponding lifting conveyor (5), and is used to grip the old sleepers clamped by the mobile working trolley (4) and placed on the track, and then transport them to the front lifting conveyor, and to grip the new sleepers transported by the rear lifting conveyor and place them on the track for the mobile working trolley (4) to grip and lay them; both ends of the sleeper gripper (63) are provided with a folding component for lateral limiting the gripped sleepers.

4. The sleeper replacement vehicle according to claim 3, characterized in that: The telescopic frame (62) comprises: at least two support frames (621) which are sequentially sleeved from the outside to the inside; The top of the support frame (621) arranged at the outermost layer is connected to the first running component (61); the sleeper gripper (63) is connected to the bottom of the support frame (621) arranged at the innermost layer; Among the two adjacent support frames (621), lifting grooves are provided on the inner sides of the support frame (621) located on the outer layer, and lifting protrusions are provided on the outer sides of the support frame (621) located on the inner layer. The two lifting grooves are respectively matched with the two lifting protrusions, so that the support frame (621) located on the inner side is lifted and lowered along the setting direction of the lifting grooves on the support frame (621) located on the outer side.

5. The sleeper replacement vehicle according to claim 4, characterized in that: The mobile operation vehicle (4) comprises: A driver's cab (41) having an operating console disposed therein; A second running component (42) disposed above the driver's cab (41) and adapted to the first running track (7) such that the second running component (42) can drive the driver's cab (41) to move along the setting direction of the first running track (7); A working arm (43) is connected to the driver's cab (41) at one end, and is provided with a clamping portion (431) and a scraper (432) at the other end thereof. A working drive component is provided on the working arm (43), and a working end of the working drive component is respectively connected to the clamping portion (431) and the scraper (432), and the operating platform is electrically connected to the working drive component.

6. The sleeper replacement vehicle according to claim 5, characterized in that: A slewing support portion (44) is provided between the driver's cab (41) and the second running component (42), so that the driver's cab (41) can slew relative to the second running component (42).

7. The sleeper replacement vehicle according to claim 6, characterized in that: The rotation angle of the rotary support part (44) is 180° each time.

8. The sleeper replacement vehicle according to claim 4, characterized in that: The second lifting drive component includes at least one steel wire rope, a motor winch arranged on the top of the outermost support frame (621) and a pulley arranged on the innermost support frame (621), and the number and position of the pulleys correspond one-to-one to the steel wire rope; one end of the steel wire rope is wound around the motor winch, and the other end of the steel wire rope is connected to the corresponding pulley.

9. The sleeper replacement vehicle according to claim 2, characterized in that: The second longitudinal conveyor belt (52) is extended toward one end close to the corresponding mobile elevator (6).

10. A sleeper replacement system, characterized in that: It comprises a power vehicle and at least one sleeper replacement vehicle as claimed in any one of claims 1 to 9 connected to the power vehicle.

Citation Information

Cited By

  • Sleeper replacing and transferring device and system and operation method

    CN118273173A