Splicing joint of steel plate composite shear wall
By using the steel steel beams and base piles in the splicing node of the steel plate scissors, and the problem of high operating difficulty and safety risks of the existing welding fixed method through the splicing gushing plate and the bolt connection method connected to the steel plate. More efficient construction process.
Patent Information
- Application Number
- CN202421219100.9
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-31
- Publication Date
- 2025-01-24
- Estimated Expiration
- 2034-05-31
AI Technical Summary
The existing steel plate combination shear wall is fixed by welding, with high operating requirements and safety risks, and is also very labor-intensive and inefficient.
The steel plate shear wall splicing node is adopted. The steel plate shear wall structure is provided between the steel beams and the base piles, and the splicing gusset and connecting steel plate are connected to the welding fixation.
Reduce the difficulty and safety risks, reduce the workload and time, and improve the construction efficiency.
Smart Images

Figure CN222390700U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the technical field of steel plate combined shear wall splicing, in particular to a steel plate combined shear wall splicing node. Background Art
[0002] At present, steel structures are increasingly used in the field of building structure technology. Various new steel structures are constantly emerging and have been applied in the engineering field. The number is also increasing, and it has broad prospects. Its main advantages are: compared with concrete building structures, it has better applicability and feasibility. For example, it reduces the volume of components and increases the usable space; reduces the deadweight of the structure, reduces or completely eliminates the formwork and support required for construction; reduces embedded parts and improves seismic performance; facilitates construction and shortens construction period;
[0003] In actual engineering applications, due to the limitations of factors such as the length of steel plate component production, transportation, and even the space of the construction site, the problem of splicing steel plate walls is inevitable in engineering construction. The current conventional solution to this problem is to weld and splice different wall sections at the construction site. This solution has the advantages of direct butt joint of steel plates, good continuity of steel walls, and a simple and smooth appearance at the joints. However, this solution also has its obvious shortcomings, which are mainly manifested in: the welding process has high skill requirements for operators, and the uneven operating levels of different operators affect the stability of welding quality, posing a large quality hazard, and welding is an operation with live open flames, and there are certain safety risks in construction operations; in addition, in high-rise or super-high-rise buildings, steel plate walls are usually spliced once per floor or once every two floors, which directly leads to a huge amount of seam welding work to be completed, which is labor-intensive and time-consuming, poorly economical, and inefficient. Utility Model Content
[0004] The technical problem to be solved by the utility model is that the existing steel plate combined shear wall is generally fixed to the steel frame structure by welding. This installation method has high requirements on the operators, is accompanied by certain risks, and has the problem of huge workload.
[0005] In order to solve the above problems, the technical solution adopted by the utility model is a steel plate combined shear wall splicing node, including two I-beam cross beams and two I-beam foundation piles, the two I-beam cross beams are welded and fixed between the two I-beam foundation piles, a steel plate shear wall structure is arranged between the two I-beam cross beams and the two I-beam foundation piles, a splicing buckle plate is arranged between the edge of the steel plate shear wall structure and the I-beam cross beams and the I-beam foundation piles, and a plurality of connecting steel plates are fixed on one side of the splicing buckle plate.
[0006] As a further solution of the utility model: the steel plate shear wall structure includes a steel plate wall body, a circular connecting plate is welded on the outside of the steel plate wall body, and a number of reinforcing ribs are vertically staggered and fixed on both sides of the steel plate wall body. The structure needs to be welded in advance before assembly.
[0007] As a further solution of the utility model: the connecting steel plate is located between two reinforcing ribs so as to make the connecting steel plate fit tightly with the steel plate wall body.
[0008] As a further solution of the utility model: a plurality of through connection holes are opened on the side of the splicing gusset plate, and a connection through hole is opened on the side of the connecting steel plate to facilitate connection with the I-beam crossbeam and the I-beam foundation pile.
[0009] As a further solution of the utility model: circular holes are opened on the sides of the I-beam crossbeam and the I-beam foundation pile at the through-connecting holes, and connecting circular holes are opened on the sides of the steel plate wall body at the connecting through holes.
[0010] As a further solution of the utility model: the through-connecting hole and the circular hole are connected and fixed by fastening bolts and nuts, and the connecting through hole and the connecting circular hole are connected and fixed by fastening long bolts and nuts.
[0011] As a further solution of the utility model: the through-connecting hole is in the shape of a long slot, so as to adapt to I-beam beams or I-beam foundation piles of different widths.
[0012] Compared with the prior art, the utility model has the following advantages: the utility model adds a connection method that eliminates welding and adopts bolting instead. Connection holes are opened in the I-beam and the steel plate shear wall structure in advance, and then only bolts are required for assembly. Compared with welding, it saves time and effort and has lower requirements on operators. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:
[0014] Figure 1 It is a three-dimensional diagram of the overall structure of a steel plate composite shear wall splicing node of the utility model.
[0015] Figure 2 It is a three-dimensional diagram of the structure of a splicing buckle plate and a connecting steel plate in a splicing node of a steel plate composite shear wall of the utility model.
[0016] Figure 3 The utility model is a cross-sectional view of the connection between an I-beam crossbeam, a splicing buckle plate, a connecting steel plate, and a steel plate shear wall structure in a splicing node of a steel plate composite shear wall.
[0017] Figure 4 It is an enlarged view of the A-section structure in a steel plate composite shear wall splicing node of the utility model.
[0018] In the attached figure:
[0019] 1. I-beam crossbeam; 2. I-beam foundation pile; 3. Steel plate shear wall structure; 4. Splicing gusset plate; 5. Connecting steel plate; 6. Fastening long bolts; 7. Fastening bolts; 3.1. Steel plate wall body; 3.2. Reciprocating connecting plate; 3.3. Reinforcement ribs; 4.1. Through connecting hole; 5.1. Connecting through hole. DETAILED DESCRIPTION
[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0021] The utility model provides a technical solution to solve the existing problems raised in the background technology.
[0022] Combined with Figure 1 It can be known that the structure includes two I-beam cross beams 1 and two I-beam foundation piles 2. The two I-beam cross beams 1 are welded and fixed between the two I-beam foundation piles 2. A steel plate shear wall structure 3 is arranged between the two I-beam cross beams 1 and the two I-beam foundation piles 2. A splicing gusset plate 4 is arranged between the edge of the steel plate shear wall structure 3 and the I-beam cross beam 1 and the I-beam foundation pile 2. A plurality of connecting steel plates 5 are fixed on one side of the splicing gusset plate 4.
[0023] Combined with Figure 2 It can be known that a plurality of through-connection holes 4.1 are provided on the side of the splicing gusset plate 4, and a connection through-hole 5.1 is provided on the side of the connecting steel plate 5, so as to facilitate connection with the I-beam crossbeam 1 and the I-beam foundation pile 2; the through-connection hole 4.1 is in the shape of a long slot, so as to facilitate adaptation to I-beam crossbeams 1 or I-beam foundation piles 2 of different widths;
[0024] Combined with Figure 3-4It can be known that the steel plate shear wall structure 3 includes a steel plate wall body 3.1, a circular connecting plate 3.2 is welded on the outside of the steel plate wall body 3.1, and a number of reinforcing ribs 3.3 are vertically staggered and fixed on both sides of the steel plate wall body 3.1. The structure needs to be welded in advance before it can be assembled; the connecting steel plate 5 is located between the two reinforcing ribs 3.3, so that the connecting steel plate 5 and the steel plate wall body 3.1 can be tightly fitted; the side surfaces of the I-beam crossbeam 1 and the I-beam foundation pile 2 are both provided with circular holes at the through-connecting hole 4.1, and the side surfaces of the steel plate wall body 3.1 are both provided with connecting circular holes at the connecting through-hole 5.1; the through-connecting hole 4.1 and the circular hole are connected and fixed by fastening bolts 7 and nuts, and the connecting through-hole 5.1 and the connecting circular hole are connected and fixed by fastening long bolts 6 and nuts.
[0025] The working principle of the present application is as follows: when assembling the steel plate shear wall, firstly, the through connection hole 4.1, the connecting through hole 5.1, the circular hole and the connecting circular hole are opened in advance, and the circular connecting plate 3.2 and the reinforcing rib 3.3 are welded and fixed to the steel plate wall body 3.1 in advance, and then the steel plate shear wall structure 3 is placed between the two I-beam cross beams 1 and the two I-beam foundation piles 2, and then the splicing buckle plate 4 is clamped at the contact point between the circular connecting plate 3.2 and the I-beam cross beam 1 and the I-beam foundation pile 2, and at the same time, the connecting steel plate 5 should be located between the two reinforcing ribs 3.3, and then the splicing buckle plate 4 is fixed to the I-beam cross beam 1 and the I-beam foundation pile 2 by tightening the bolts 7 and nuts, and the connecting steel plate 5 is fixed to the steel plate wall body 3.1 by tightening the long bolts 6 and nuts, and then the assembly is completed, the operation is simple, and time is saved.
[0026] The above description of the utility model and its implementation methods is not restrictive. The drawings show only one implementation method of the utility model, and the actual structure is not limited thereto. In short, if ordinary technicians in this field are inspired by it and design structural methods and embodiments similar to the technical solution without creativity without departing from the purpose of the invention of the utility model, they should all fall within the protection scope of the utility model.
Claims
1. A steel plate composite shear wall splicing node, comprising two I-beam cross beams (1) and two I-beam foundation piles (2), wherein the two I-beam cross beams (1) are welded and fixed between the two I-beam foundation piles (2), characterized in that: A steel plate shear wall structure (3) is provided between the two I-steel cross beams (1) and the two I-steel foundation piles (2); a splicing gusset plate (4) is provided between the edge of the steel plate shear wall structure (3) and the I-steel cross beams (1) and the I-steel foundation piles (2); and a plurality of connecting steel plates (5) are fixed to one side of the splicing gusset plate (4).
2. The steel plate composite shear wall splicing node according to claim 1, characterized in that: The steel plate shear wall structure (3) comprises a steel plate wall body (3.1), a circular connecting plate (3.2) is welded on the outside of the steel plate wall body (3.1), and a plurality of reinforcing ribs (3.3) are vertically staggered and fixed on both sides of the steel plate wall body (3.1).
3. The steel plate composite shear wall splicing node according to claim 2 is characterized in that: The connecting steel plate (5) is located between the two reinforcing ribs (3.3).
4. The steel plate composite shear wall splicing node according to claim 2, characterized in that: The side surface of the splicing buckle plate (4) is provided with a plurality of through connection holes (4.1), and the side surface of the connecting steel plate (5) is provided with a connection through hole (5.1).
5. The steel plate composite shear wall splicing node according to claim 4, characterized in that: The I-beam cross beam (1), the I-beam foundation pile (2), and the circular connecting plate (3.2) are all provided with circular holes at the through connecting holes (4.1) on their sides, and the steel plate wall body (3.1) is also provided with connecting circular holes at the connecting through holes (5.1) on its sides.
6. The steel plate composite shear wall splicing node according to claim 5, characterized in that: The through connection hole (4.1) and the circular hole are connected and fixed by means of a fastening bolt (7) and a nut, and the connecting through hole (5.1) and the connecting circular hole are connected and fixed by means of a fastening long bolt (6) and a nut.
7. The steel plate composite shear wall splicing node according to claim 4, characterized in that: The through-connecting hole (4.1) is in the shape of a long slot.
Citation Information
Cited By
Splicing joint of steel plate composite shear wall
CN223838360U