Secondary lining and trench integrated lining trolley for tunnel

By designing an integrated lining trolley with secondary lining and trench lining for tunnels, the problems of long construction period, low efficiency and high equipment cost of tunnel lining and trench lining are solved, achieving the effects of shortening the construction period, improving efficiency and reducing costs.

CN222391406UActive Publication Date: 2025-01-24PINGDINGSHAN ZHIDE COAL MASCH EQUIP CO LTD
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202420910796.3
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-29
Publication Date
2025-01-24
Estimated Expiration
2034-04-29

AI Technical Summary

Technical Problem

The existing tunnel lining and trench lining construction have problems such as long construction cycle, low efficiency and high equipment costs.

Method used

Design an integrated lining trolley with secondary lining and trench lining for tunnels. By integrating the tunnel secondary lining trolley with the trench formwork structure, an integrated lining trolley is formed to realize tunnel lining and trench lining at the same time.

Benefits of technology

The tunnel construction cycle was shortened, the construction efficiency was improved, and two tasks were completed through one equipment, reducing equipment investment and construction costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222391406U_ABST
    Figure CN222391406U_ABST
Patent Text Reader

Abstract

The utility model relates to a tunnel secondary lining and trench integrated lining trolley which comprises a trolley body and a trench lining system, the trench lining system comprises a trench template body, a trench template supporting system and a trench template control system, and the trench template body comprises an outer side small template, an inner side large template and a through beam. A closed concrete pouring cavity is formed among the outer side small formwork, the excavation primary lining face below the outer side small formwork and the inner side large formworks, and the left end and the right end of the through beam abut against the inner walls of the left inner side large formwork and the right inner side large formwork so as to reinforce and support the inner side large formworks. The device is ingenious in conception, convenient to operate and simple to use, shortens the tunnel construction period, improves the construction efficiency, reduces the construction cost, and solves the technical problems that the construction period is long, the efficiency is low, the tunnel lining and the trench lining are constructed separately, the cost is high when a lining trolley and a trench trolley are configured separately, and the like when the tunnel lining and the trench lining are used in the prior art. Compared with the prior art, the device has good market prospect and development space.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of tunnel lining trolleys, in particular to a secondary lining and trench integrated lining trolley for tunnels. Background Art

[0002] The tunnel lining trolley is a construction equipment used for tunnel lining. In the construction of some tunnel linings, there is trench construction in the tunnel. The current common practice is to carry out tunnel lining and trench lining separately. This practice has clear processes and the tunnel lining and trench lining do not interfere with each other. However, there are two disadvantages. One is that the construction period is long and the efficiency is low. The tunnel lining and trench lining are constructed separately. The trench lining can only be carried out after the tunnel lining is completed, or the tunnel lining can be carried out after the trench lining. The construction period is long and the efficiency is relatively low. The second is that the equipment cost is high. The tunnel lining and trench lining are constructed separately, which requires two sets of equipment, the lining trolley and the trench trolley, which is costly.

[0003] How to design a tunnel secondary lining and trench integrated lining trolley that is ingenious in conception, easy to operate, simple to use, shortens the tunnel construction period, improves construction efficiency, and reduces construction costs is a problem that needs to be solved at present. Utility Model Content

[0004] In order to solve the technical problems existing in the existing tunnel lining and trench lining, such as long construction period, low efficiency, separate construction of tunnel lining and trench lining, and high cost of separately configuring lining trolleys and trench trolleys, the utility model provides a tunnel secondary lining and trench integrated lining trolley, which realizes the purpose of ingenious design, convenient operation, simple use, shortening the tunnel construction period, improving construction efficiency, and reducing construction costs.

[0005] The utility model adopts the following technical solution to solve the above technical problems: a tunnel secondary lining and trench integrated lining trolley, comprising a trolley body and a trench lining system, wherein the trench lining system comprises a trench formwork body, a trench formwork support system and a trench formwork control system, wherein the trench formwork body comprises an outer small formwork, an inner large formwork and a through beam, wherein a closed concrete pouring cavity is formed between the outer small formwork and the primary lining surface excavated thereunder and the inner large formwork, and the left and right ends of the through beam are pressed against the inner walls of the left and right inner large formworks to reinforce and support the inner large formworks.

[0006] As a further optimization scheme of the above-mentioned tunnel secondary lining and trench integrated lining trolley, the trolley body includes a template system, a trolley gantry, an arch frame system, a screw system, a walking mechanism, a jacking and transverse movement mechanism, ancillary structures, a hydraulic system and an electrical system, and the trench lining system is integrally fixed and suspended under the trolley gantry through a fixing assembly.

[0007] As a further optimization scheme of the above-mentioned tunnel secondary lining and trench integrated lining trolley, the trench formwork support system includes a trench formwork support frame and a trench formwork support screw, wherein the trench formwork support frame is fixed on the trolley door frame, and the inner large formwork is hung under the trench formwork support frame through a cylinder, and the trench formwork support frame is used to bear the weight of the inner large formwork.

[0008] As a further optimization scheme for the above-mentioned tunnel secondary lining and trench integrated lining trolley, the trench formwork control system includes a trench formwork horizontal displacement cylinder group and a trench formwork vertical displacement cylinder group. One end of the trench formwork horizontal displacement cylinder group is connected to the trolley gantry through a cylinder pin, and the other end is connected to the top of the inner large formwork through a cylinder pin. The position of the inner large formwork in the horizontal direction is adjusted by adjusting the extension length of the piston rod of the trench formwork horizontal displacement cylinder group.

[0009] As a further optimization scheme for the above-mentioned tunnel secondary lining and trench integrated lining trolley, the upper end of the trench formwork vertical displacement cylinder group is connected to the trench formwork support frame through a cylinder pin shaft, and the lower end of the trench formwork vertical displacement cylinder group is connected to the top of the inner large formwork through a cylinder pin shaft. By adjusting the extension length of the piston rod of the trench formwork vertical displacement cylinder group, the height of the inner large formwork in the vertical direction can be adjusted.

[0010] Compared with the prior art, the beneficial effects of the utility model are:

[0011] The utility model includes a trolley body and a trench lining system, wherein the trench lining system includes a trench formwork body, a trench formwork support system and a trench formwork control system. The utility model integrates the tunnel secondary lining trolley with the trench formwork structure through ingenious design, and derives a secondary lining and trench integrated lining trolley, which can carry out tunnel lining and trench lining at the same time, complete the construction of tunnel lining and trench lining at one time, shorten the tunnel construction period, improve construction efficiency, and complete two tasks with one device at the same time, reducing equipment investment and construction costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the main structure of the utility model;

[0013] Figure 2 This is a schematic diagram of the main structure of the trolley body;

[0014] Figure 3 It is a schematic diagram of the side view structure of the trolley body;

[0015] Figure 4 It is a schematic diagram of the installation location of the trench lining system;

[0016] Figure 5 It is a schematic diagram of the main structure of the trench template;

[0017] Figure 6 It is a schematic diagram of the structure of the trench formwork support system;

[0018] Figure 7 It is a schematic diagram of the structure of the trench template control system;

[0019] Figure 8 This is a schematic diagram of the working state of the secondary lining and the integrated primary lining of the trench of the utility model;

[0020] Markings in the figure: 1. Trolley body; 101. Formwork system; 102. Trolley gantry; 103. Arch frame system; 104. Screw system; 105. Traveling mechanism; 106. Lifting and transverse movement mechanism; 107. Auxiliary structure; 108. Hydraulic system; 109. Electrical system; 2. Trench lining system; 201. Trench formwork body; 20101. Outer small formwork; 20102. Inner large formwork; 20103. Through beam; 202. Trench formwork support system; 20201. Trench formwork support frame; 20202. Trench formwork support screw; 203. Trench formwork control system; 20301. Trench formwork horizontal displacement cylinder group; 20302. Trench formwork vertical displacement cylinder group. DETAILED DESCRIPTION

[0021] The specific implementation of the utility model is further described in detail below with reference to the accompanying drawings.

[0022] like Figure 1 As shown, Figure 1 It is a schematic diagram of the main structure of the utility model; a secondary lining and trench integrated lining trolley for tunnels, comprising a trolley body 1 and a trench lining system 2.

[0023] like Figure 2 , 3 As shown, Figure 2 This is a schematic diagram of the main structure of the trolley body; Figure 3 It is a schematic diagram of the side view of the trolley body structure; the trolley body 1 includes a template system 101, a trolley gantry 102, an arch system 103, a screw system 104, a walking mechanism 105, a lifting and traversing mechanism 106, an auxiliary structure 107, a hydraulic system 108 and an electrical system 109, and the trench lining system 2 is integrally fixed and suspended under the trolley gantry 102 through a fixing assembly. The trench lining system 2 includes a trench template body 201, a trench template support system 202 and a trench template control system 203.

[0024] like Figure 5 As shown, Figure 5It is a schematic diagram of the trench formwork body structure; the trench formwork body 201 includes an outer small formwork 20101, an inner large formwork 20102, and a through beam 20103, wherein a closed concrete pouring cavity is formed between the outer small formwork 20101 and the initial lining excavated thereunder and the inner large formwork 20102, and the left and right ends of the through beam 20103 are against the inner walls of the left and right inner large formworks 20102 to reinforce and support the inner large formworks 20102.

[0025] like Figure 6 As shown, Figure 6 It is a structural schematic diagram of the trench formwork support system; the trench formwork support system 202 includes a trench formwork support frame 20201 and a trench formwork support screw 20202, wherein the trench formwork support frame 20201 is fixed on the trolley door frame 102, and the inner large formwork 20102 is suspended under the trench formwork support frame 20201 through a cylinder, and the trench formwork support frame 20201 is used to bear the weight of the inner large formwork 20102.

[0026] like Figure 7 As shown, Figure 7 It is a schematic diagram of the structure of the trench template control system; the trench template control system 203 includes a trench template horizontal displacement cylinder group 20301 and a trench template vertical displacement cylinder group 20302. One end of the trench template horizontal displacement cylinder group 20301 is connected to the trolley gantry 102 through a cylinder pin, and the other end is connected to the top of the inner large template 20102 through a cylinder pin. The position of the inner large template 20102 in the horizontal direction is adjusted by adjusting the extension length of the piston rod of the trench template horizontal displacement cylinder group 20301. The upper end of the trench template vertical displacement cylinder group 20302 is connected to the trench template support frame 2201 through a cylinder pin, and the lower end of the trench template vertical displacement cylinder group 20302 is connected to the top of the inner large template 20102 through a cylinder pin. The height of the inner large template 20102 in the vertical direction can be adjusted by adjusting the extension length of the piston rod of the trench template vertical displacement cylinder group 20302.

[0027] The working process of this utility model is as follows:

[0028] The primary lining pouring of the tunnel secondary lining and trench integrated lining trolley can be divided into three steps, as follows:

[0029] 1. Set up the mold

[0030] (1) Trolley template stand

[0031] ① Control the trolley travel mechanism 105 to adjust the trolley's front and rear positions so that the trolley template overlaps the inner side of the lined tunnel.

[0032] ② Adjust the trolley lifting and transverse movement mechanism 106 to align the trolley center with the tunnel design center, and to make the center of the trolley top template flush with the tunnel design height.

[0033] ③ Adjust the side mold cylinder of the trolley template so that the trolley side mold reaches the designed position to complete the positioning of the trolley template.

[0034] ④ Install the trolley screw system 104 to form a rigid support between the trolley template system 101 and the trolley gantry 102. The trolley body mold is now completed.

[0035] (2) Trench formwork

[0036] ① Adjust the trench template horizontal displacement cylinder group 20301 so that the horizontal position of the large template 20102 inside the trench meets the design requirements.

[0037] ② Adjust the vertical displacement cylinder group 20302 of the trench template to compact the bottom of the large template 20102 inside the trench with the trench ground to prevent the concrete from falling from the bottom of the trench template and complete the positioning of the trench template.

[0038] ③Install the trench template support screw 20202 to support and fix the two large trench inner templates 20102 to each other.

[0039] ④Install the small template 20101 on the outside of the trench and complete the trench template erection.

[0040] 2. Pouring

[0041] (1) When pouring trench concrete, the trench concrete should be poured first. The two sides should be poured symmetrically, and the height difference of the concrete liquid level on both sides should not be too large.

[0042] (2) Secondary lining concrete pouring: After the trench concrete pouring is completed, the secondary lining concrete pouring can be carried out. There is no pause between the trench concrete pouring and the secondary lining concrete pouring.

[0043] When pouring the secondary lining concrete, it is also necessary to pour it symmetrically on both sides, and the height difference of the concrete liquid level on both sides must not be too large until the pouring of the trolley arch is completed.

[0044] 3. Demolding

[0045] After the trolley lining is poured, the demoulding can be carried out when the concrete reaches a certain strength. The demoulding sequence is to first demould the trench formwork, and then demould the trolley formwork. The implementation method is as follows:

[0046] (1) Demolding of trench formwork

[0047] ①Remove the small template 20101 on the outside of the trench.

[0048] ②Remove the trench formwork supporting screw 20202.

[0049] ③ Operate the trench template horizontal displacement cylinder group 20301 to make the large template 20102 inside the trench move horizontally toward the center line of the tunnel, so that the trench template is separated from the trench wall.

[0050] ④ Operate the vertical displacement cylinder group 20302 of the trench template to make the large template 20102 inside the trench leave the ground and maintain a certain height above the ground, thereby completing the demoulding work of the trench template.

[0051] (2) Demolding of the trolley template

[0052] ① Remove the trolley screw system 104.

[0053] ② Contract the trolley template side form oil cylinder 101 to separate the trolley side form from the tunnel side wall and keep a certain distance from the side wall.

[0054] ③ Adjust the trolley lifting and transverse movement mechanism lifting cylinder 106 to lower the height of the trolley and complete the demoulding work of the trolley template.

[0055] The utility model has the advantages of ingenious design, convenient operation and simple use, shortens the tunnel construction period, improves construction efficiency and reduces construction costs at the same time, and solves the technical problems existing in the existing tunnel lining and trench lining, such as long construction period, low efficiency, separate construction of tunnel lining and trench lining, and high cost of separately configuring lining trolleys and trench trolleys. Compared with the existing technology, it has good market prospects and development space.

[0056] The preferred specific implementation modes and embodiments of the utility model are described in detail above in conjunction with the accompanying drawings, but the utility model is not limited to the above implementation modes and embodiments, and various changes can be made within the knowledge scope of those skilled in the art without departing from the concept of the utility model.

Claims

1. A tunnel secondary lining and trench integrated lining trolley, comprising a trolley body (1) and a trench lining system (2), characterized in that: The trench lining system (2) comprises a trench formwork body (201), a trench formwork support system (202) and a trench formwork control system (203); the trench formwork body (201) comprises an outer small formwork (20101), an inner large formwork (20102) and a through beam (20103); a closed concrete pouring cavity is formed between the outer small formwork (20101) and the primary lining surface excavated thereunder and the inner large formwork (20102); the left and right ends of the through beam (20103) are pressed against the inner walls of the left and right inner large formworks (20102) to reinforce and support the inner large formworks (20102).

2. A tunnel secondary lining and trench integrated lining trolley as claimed in claim 1, characterized in that: The trolley body (1) comprises a template system (101), a trolley portal frame (102), an arch frame system (103), a screw system (104), a walking mechanism (105), a lifting and lateral movement mechanism (106), an auxiliary structure (107), a hydraulic system (108) and an electrical system (109); the trench lining system (2) is integrally fixed and suspended below the trolley portal frame (102) via a fixing assembly.

3. A tunnel secondary lining and trench integrated lining trolley as claimed in claim 2, characterized in that: The trench formwork support system (202) comprises a trench formwork support frame (20201) and a trench formwork support screw (20202), wherein the trench formwork support frame (20201) is fixed on a trolley door frame (102), the inner large formwork (20102) is suspended below the trench formwork support frame (20201) via an oil cylinder, and the trench formwork support frame (20201) is used to bear the weight of the inner large formwork (20102).

4. The tunnel secondary lining and trench integrated lining trolley according to claim 2, characterized in that: The trench template control system (203) comprises a trench template horizontal displacement cylinder group (20301) and a trench template vertical displacement cylinder group (20302); one end of the trench template horizontal displacement cylinder group (20301) is connected to the trolley gantry (102) via a cylinder pin, and the other end is connected to the top of the inner large template (20102) via a cylinder pin; the position of the inner large template (20102) in the horizontal direction is adjusted by adjusting the extension length of the piston rod of the trench template horizontal displacement cylinder group (20301).

5. The tunnel secondary lining and trench integrated lining trolley according to claim 4, characterized in that: The upper end of the trench template vertical displacement cylinder group (20302) is connected to the trench template support frame (20201) via a cylinder pin, and the lower end of the trench template vertical displacement cylinder group (20302) is connected to the top of the inner large template (20102) via a cylinder pin. The height of the inner large template (20102) in the vertical direction can be adjusted by adjusting the extension length of the piston rod of the trench template vertical displacement cylinder group (20302).