Operating platform suitable for pier body steel bar installation
By designing an operating platform suitable for installation of pier body steel bars, the traditional method of setting up scaffolding is solved, and the effects of simplifying operation, improving safety, saving labor and reducing costs are achieved.
Patent Information
- Application Number
- CN202420511213.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-17
- Publication Date
- 2025-02-11
- Estimated Expiration
- 2034-03-17
AI Technical Summary
During the process of tying the steel bars on the pier body, the traditional method of setting up scaffolding is time-consuming and labor-intensive, posing safety hazards and the construction progress is slow.
An operating platform suitable for installation of pier body steel bars is designed, including pier columns, columns, support rods, walkway plates, poles, protective nets, connecting square grooves, ladders and cross bars, forming a wrap-around protection system, and construction personnel can Climb up the walkway board to install the steel bars in the connecting square groove.
By simplifying operations and improving safety, this operating platform can save labor, reduce construction costs, speed up construction progress, and is suitable for the promotion and application of municipal bridge projects.
Smart Images

Figure CN222455824U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of building construction devices, in particular to an operating platform suitable for installing pier body steel bars. Background Art
[0002] Construction refers to the production activities in the implementation stage of engineering construction. It is the construction process of various buildings. It can also be said to be the process of turning various lines on the design drawings into physical objects at designated locations. It includes foundation engineering construction, main structure construction, roof engineering construction, decoration engineering construction, etc. The place where the construction work is done is called "construction site" or "construction site", also called construction site.
[0003] Construction is a production activity that people use various building materials, mechanical equipment and equipment to build various building products in a certain space and time according to a specific design blueprint. It includes the entire production process from construction preparation, groundbreaking to project completion acceptance. In this process, construction preparation, construction organization design and management, earthwork engineering, blasting engineering, foundation engineering, steel engineering, formwork engineering, scaffolding engineering, concrete engineering, prestressed concrete engineering, masonry engineering, steel structure engineering, wood structure engineering, structural installation engineering and other work will be carried out.
[0004] In the process of tying the steel bars of the pier body, the traditional method is to erect scaffolding, which is time-consuming and labor-intensive, and is prone to potential safety hazards, resulting in slow construction progress.
[0005] Therefore, it is necessary to provide an operating platform suitable for pier body reinforcement installation to solve the above technical problems. Utility Model Content
[0006] The utility model provides an operating platform suitable for installing pier body reinforcement bars, which solves the problem that in the process of tying pier body reinforcement bars, a traditional method is to erect scaffolding, which is time-consuming and labor-intensive, and is prone to potential safety hazards and slow construction progress.
[0007] In order to solve the above technical problems, the utility model provides an operating platform suitable for installing pier body reinforcement, comprising: a pier column;
[0008] The four columns are respectively arranged around the outer surface of the pier, the surface of the column is fixedly installed with a support rod, the top of the support rod is fixedly installed with a walkway board, the top of the walkway board is fixedly installed with a vertical pole, the top of the vertical pole is fixedly installed with a cross bar, and the outer surface of the vertical pole is provided with a protective net.
[0009] Preferably, a connecting square groove is opened in the middle of the top of the walkway plate.
[0010] Preferably, a ladder is fixedly mounted on one side of the surface of the walkway plate.
[0011] Preferably, a standing hole is provided on the surface of the walkway plate, a protective device is installed inside the standing hole, and slots are provided on both sides of the inner cavity wall of the standing hole.
[0012] Preferably, the protective device includes a fixed column, a connecting groove is opened in the middle of one side of the fixed column, a fixing plate is fixedly installed in the middle of the inner cavity of the connecting groove, fixing rods are fixedly installed on both sides of the fixing plate, a limiting block is fixedly installed at one end of the fixing rod, and a spring is sleeved on one side of the outer surface of the fixing rod.
[0013] Preferably, moving blocks are sleeved on both sides inside the protective device, a setting hole is opened in the middle of one side of the moving block, one side of the setting hole is connected to the limiting cavity, and a clamping block is fixedly installed on the other side of the moving block.
[0014] Preferably, the card block and the card slot are matched, and the card block is hemispherical.
[0015] Compared with the related art, the operating platform suitable for installing pier reinforcement provided by the utility model has the following beneficial effects:
[0016] The utility model provides an operating platform suitable for the installation of pier body steel bars. Through the cooperation of pier columns, columns, support rods, walkway boards, poles, protective nets, connecting square grooves, ladders and cross bars, a safety net is hung outside the poles to form a wrapped protection system. Construction workers can climb up the walkway boards to install steel bars in the connecting square grooves, fully utilizing existing materials, being simple and easy to operate, effectively ensuring the construction safety of workers, being reusable, saving labor, reducing construction costs and accelerating construction progress; having a wide range of uses, the utility model can be further promoted and applied in municipal bridge projects. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic structural diagram of a first embodiment of an operating platform suitable for installing pier shaft reinforcement provided by the utility model;
[0018] Figure 2 for Figure 1 The schematic diagram of the pier structure shown;
[0019] Figure 3 A schematic structural diagram of a second embodiment of an operating platform suitable for installing pier shaft reinforcement provided by the utility model;
[0020] Figure 4 for Figure 3 The walkway slab is shown in a front cross-sectional schematic view;
[0021] Figure 5 for Figure 4An enlarged schematic diagram of point A is shown.
[0022] Numbers in the figure: 1. pier, 2. column, 3. support rod, 4. walkway board, 5. pole, 6. protection net, 7. connecting square groove, 8. ladder, 9. cross bar, 10. erection hole, 11. protective device, 111. fixed column, 112. connecting groove, 113. fixed plate, 114. fixed rod, 115. limit block, 116. spring, 12. moving block, 13. setting hole, 14. limit cavity, 15. card block, 16. card slot. DETAILED DESCRIPTION
[0023] The utility model is further described below in conjunction with the accompanying drawings and implementation modes.
[0024] First embodiment
[0025] Please refer to Figure 1 and Figure 2 ,in, Figure 1 A schematic structural diagram of a first embodiment of an operating platform suitable for installing pier shaft reinforcement provided by the utility model; Figure 2 for Figure 1 Schematic diagram of the pier structure shown.
[0026] An operating platform suitable for installing steel bars of a pier body comprises: a pier column 1;
[0027] The four columns 2 are respectively arranged around the outer surface of the pier 1, and the surface of the column 2 is fixedly installed with a support rod 3, the top of the support rod 3 is fixedly installed with a walkway board 4, the top of the walkway board 4 is fixedly installed with a vertical pole 5, the top of the vertical pole 5 is fixedly installed with a cross bar 9, and the outer surface of the vertical pole 5 is provided with a protective net 6.
[0028] A connecting square groove 7 is provided in the middle of the top of the walkway plate 4 .
[0029] A ladder 8 is fixedly mounted on one side of the surface of the walkway plate 4 .
[0030] The support rods 3 are arranged in three layers and are fixed on the surface of the pillars 2 in sequence from top to bottom. A walkway plate 4 is arranged on the top of each layer of the support rods 3, so that the operating platform can be built in multiple layers to accommodate the installation of steel bars of different heights.
[0031] The working principle of an operating platform suitable for pier body reinforcement installation provided by the utility model is as follows:
[0032] During operation, first, four columns 2 are fixed around the surface of the pier 1 by anchor bolts, and a walkway board 4 is installed on the top of the column 2 through a cross connection. Vertical poles 5 and horizontal poles 9 are arranged around the surface of the walkway board 4, and a safety net is hung on the surface between the horizontal poles 9 and the vertical poles 5 to form a wrap-around protection system.
[0033] A multi-layer walkway board 4 is installed on the surface of the column 2, and the multi-layer walkway boards 4 are connected by ladders 8 to facilitate climbing by operators.
[0034] Compared with the related art, the operating platform suitable for installing pier reinforcement provided by the utility model has the following beneficial effects:
[0035] The utility model provides an operating platform suitable for installing steel bars in a pier body. Through the cooperation of the pier column 1, the column 2, the support rod 3, the walkway plate 4, the pole 5, the protection net 6, the connecting square groove 7, the ladder 8 and the cross bar 9, a safety protection net is hung outside the pole 5 to form a wrapped protection system. Construction workers can climb onto the walkway plate 4 to install steel bars in the connecting square groove 7, fully utilize existing materials, and the operation is simple and easy, effectively ensuring the construction safety of workers. The platform can be reused, can save labor, reduce construction costs, and speed up construction progress. The platform has a wide range of uses and can be further promoted and applied in municipal bridge projects.
[0036] Second embodiment
[0037] Please refer to Figure 3 , Figure 4 and Figure 5 Based on the operating platform suitable for installing pier shaft reinforcement provided by the first embodiment of the present application, the second embodiment of the present application proposes another operating platform suitable for installing pier shaft reinforcement. The second embodiment is only a preferred embodiment of the first embodiment, and the implementation of the second embodiment will not affect the independent implementation of the first embodiment.
[0038] Specifically, the second embodiment of the present application provides an operating platform suitable for installing pier body steel bars. The difference is that, in an operating platform suitable for installing pier body steel bars, the surface of the walkway plate 4 is provided with an erection hole 10, a protective device 11 is installed inside the erection hole 10, and card grooves 16 are provided on both sides of the inner wall of the erection hole 10.
[0039] The protective device 11 includes a fixed column 111, a connecting groove 112 is opened in the middle of one side of the fixed column 111, a fixed plate 113 is fixedly installed in the middle of the inner cavity of the connecting groove 112, fixed rods 114 are fixedly installed on both sides of the fixed plate 113, a limiting block 115 is fixedly installed at one end of the fixed rod 114, and a spring 116 is sleeved on one side of the outer surface of the fixed rod 114.
[0040] Moving blocks 12 are sleeved on both sides of the protective device 11 , a setting hole 13 is opened in the middle of one side of the moving block 12 , one side of the setting hole 13 is connected to a limiting cavity 14 , and a clamping block 15 is fixedly installed on the other side of the moving block 12 .
[0041] The clamping block 15 is matched with the clamping slot 16 , and the clamping block 15 is hemispherical.
[0042] The restoring elastic force of the spring 116 pushes the moving block 12 , and the moving block 12 drives the clamping block 15 to be embedded into the inside of the clamping slot 16 .
[0043] The above description is only an embodiment of the present invention, and does not limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made by using the contents of the specification and drawings of the present invention, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. An operating platform suitable for installing pier reinforcement, characterized in that: include: pier column; The four columns are respectively arranged around the outer surface of the pier, the surface of the column is fixedly installed with a support rod, the top of the support rod is fixedly installed with a walkway board, the top of the walkway board is fixedly installed with a vertical pole, the top of the vertical pole is fixedly installed with a cross bar, and the outer surface of the vertical pole is provided with a protective net.
2. The operating platform suitable for installing pier reinforcement bars according to claim 1, characterized in that: A communicating square groove is provided in the middle of the top of the walkway plate.
3. The operating platform suitable for installing pier reinforcement bars according to claim 1, characterized in that: A ladder is fixedly installed on one side of the surface of the walkway plate.