External wall temporary enclosure handrail for building construction

By designing an adjustable vertical pole and a flexible connecting cross bar and oblique rod, the existing enclosure railings are solved, the problems of shaping, structural damage and difficulty in adjusting are achieved, and low-cost, safe and efficient construction use is achieved Enclosing railings.

CN222456897UActive Publication Date: 2025-02-11HANGZHOU TONGDA GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420517844.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-18
Publication Date
2025-02-11
Estimated Expiration
2034-03-18

AI Technical Summary

Technical Problem

The existing building enclosure railings need to be shaped and will cause damage to the structure during installation, and will not be easily disassembled and adjusted, and will not be able to adapt to irregular site edges.

Method used

A temporary enclosure railing for exterior walls for construction consisting of vertical poles, cross bars and adjustable roof support is designed. The vertical poles can be spliced ​​with different sizes according to needs, and the cross bars and oblique rods can be flexibly adjusted to adapt to irregular sites. And no drilling installation is required.

Benefits of technology

It realizes flexible adjustment and low-cost use of the enclosure rail, avoids damage to the structure, and improves the safety protection effect at the construction site.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222456897U_ABST
    Figure CN222456897U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of handrails for constructional engineering, and discloses an outer wall temporary enclosure handrail for building construction, which comprises a vertical rod, a transverse rod and an adjustable top support, the multiple vertical rods are vertically arranged on a lower floor, the adjustable jacking is arranged at the tops of the vertical rods, the vertical rods and the adjustable jacking are arranged between the upper floor and the lower floor in an opposite jacking mode, and the opposite jacking strength is controlled by adjusting the relative distance between the adjustable jacking and the vertical rods. The multiple transverse rods are arranged between the adjacent vertical rods in the vertical direction, the two ends of each transverse rod are fixedly connected with the corresponding vertical rod, and the vertical rods and the transverse rods jointly form an enclosure face used for temporary enclosure of an outer wall; the enclosure handrail consists of small components, and is simple in structure and convenient to use; meanwhile, the handrail is convenient to locally disassemble, adjust and recover after being installed, and the overall protection effect of the fence rod is not affected; and the device is a green construction facility, is beneficial to civilized construction, and is suitable for modern building construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of railings for construction projects, in particular to a temporary external wall enclosure railing for construction projects. Background Art

[0002] During the construction of a building project, it is usually necessary to set up temporary guardrails on the outer wall of the construction floor, referred to as fences.

[0003] Edges and openings are the focus of safety protection at construction sites. Setting up fences can prevent construction workers on site from falling from edges and openings, avoiding casualties.

[0004] There are many types and quantities of building guardrails on the market, but the commonly used building guardrails have some disadvantages: 1) They need to be produced in a standardized manner; 2) When installing the railing columns, expansion bolts are generally required to fix them. The installation of expansion bolts requires drilling holes in the structural surface, which will cause certain damage and damage to the structure; 3) After the guardrails are installed, they are not easy to disassemble or move; 4) Standardized fences cannot adapt to the edges of irregular sites.

[0005] Based on the actual safety needs on construction sites, we propose a temporary exterior wall guardrail for building construction. Utility Model Content

[0006] The purpose of the present invention is to solve the deficiencies of the above-mentioned background technology and to provide a temporary guardrail for exterior walls for construction, which solves the drawbacks that exterior wall fences need to be manufactured in a standardized manner, damage the structure during installation and use, are difficult to adjust after installation, and cannot adapt to irregular edges. Compared with existing temporary guardrails for exterior walls, the cost of use is lower, the installation is more convenient, and the angle of the railing can be flexibly adjusted according to the shape of the construction site, thereby eliminating security blind spots and improving the protection effect.

[0007] The technical solution of the utility model is as follows:

[0008] A temporary guardrail for exterior walls used in construction, comprising vertical poles, horizontal poles and adjustable top supports; a plurality of the vertical poles are vertically arranged on a lower floor slab, the adjustable top supports are arranged on top of the vertical poles, and the vertical poles and the adjustable top supports are arranged facing each other between the upper and lower floor slabs, and the strength of the facing each other is controlled by adjusting the relative distance between the adjustable top supports and the vertical poles; a plurality of horizontal poles are arranged in a vertical direction between adjacent vertical poles, and both ends of the horizontal poles are fixedly connected to the vertical poles, and the vertical poles and the horizontal poles together constitute a guardrail surface used for temporary enclosure of exterior walls.

[0009] Furthermore, an oblique rod is obliquely arranged between two adjacent vertical poles, one end of the oblique rod is fixedly connected to the lower part of the vertical pole, and the other end is fixedly connected to the upper part of the vertical pole; according to the floor height, multiple oblique rods can also be arranged between two adjacent vertical poles to further strengthen the guardrail.

[0010] Furthermore, an outer sleeve connection portion is provided at the bottom of the vertical pole, which is used for the upper and lower connection of two vertical poles to achieve a connection combination of vertical poles of the same or different specifications. The vertical poles can be processed into different sizes according to requirements and can be spliced ​​according to different sizes during on-site construction to meet different floor height requirements.

[0011] Furthermore, a plurality of discs are arranged on the vertical rod along its axial direction, a through hole is provided in the center of the disc, cross bar connecting holes and oblique bar connecting holes are arranged in the circumferential direction of the disc, and the cross bar connecting holes and oblique bar connecting holes are arranged alternately in the circumferential direction of the disc.

[0012] Furthermore, pin joints A are fixedly provided at both ends of the crossbar for connecting with the crossbar connecting holes of the disc on the vertical pole to form a protective surface.

[0013] Furthermore, pin joints B are movably provided at both ends of the diagonal rod for connecting with the diagonal rod connecting holes of the upper disc of the vertical rod to reinforce the guardrail.

[0014] Furthermore, a temporary guardrail for an exterior wall used in construction also includes a dense mesh, which is arranged between the cross bars. When the dense mesh is installed, it can be set on the cross bars through hooks. The dense mesh can improve the protective effect of the railing.

[0015] Furthermore, a footboard is provided at the rear bottom of the vertical pole to prevent building materials from falling from the bottom. The footboard can be detachably mounted on the vertical pole by fixing with bolts or the like.

[0016] The beneficial effects of the utility model are as follows:

[0017] 1) The utility model forms the guardrail by splicing small components, which has a simple structure and is easy to use. At the same time, the guardrail can be easily disassembled, adjusted and restored after installation without affecting the overall protective effect of the fence.

[0018] 2) The utility model does not require standardized production, has low turnover and cost, and does not require drilling operations, so it will not cause damage to the structure.

[0019] 3) The utility model can quickly offset the position of the vertical poles through cross bars of different specifications, thereby meeting the irregular exterior wall plane of the construction site, eliminating security blind spots, and improving the protection effect.

[0020] 4) The utility model is a green construction facility, which is conducive to civilized construction and is suitable for modern building construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] Figure 1 It is a schematic diagram of the overall structure of the utility model;

[0022] Figure 2 This is a schematic diagram of the installation of vertical poles and diagonal poles of the utility model;

[0023] Figure 3 This is a schematic diagram of the installation of a dense mesh of the present utility model;

[0024] Figure 4 This is a schematic diagram of the pole structure of the utility model;

[0025] Figure 5 This is a schematic diagram of the adjustable jacking structure of the utility model;

[0026] Figure 6 This is a schematic diagram of the disc structure of the utility model;

[0027] Figure 7 This is a schematic diagram of the crossbar structure of the present utility model;

[0028] Figure 8 This is a schematic diagram of the oblique rod structure of the utility model;

[0029] In the figure: 1. Vertical pole; 101. Outer sleeve connection; 2. Adjustable top support; 201. Adjusting nut; 3. Cross bar; 301. Pin joint A; 4. Disc; 401. Through hole; 402. Cross bar connection hole; 403. Diagonal rod connection hole; 5. Diagonal rod; 501. Pin joint B; 6. Fine mesh; 7. Toe board. DETAILED DESCRIPTION

[0030] The present invention will be further described below with reference to the accompanying drawings.

[0031] like Figure 1 As shown, a temporary external wall guardrail for construction is arranged between the upper and lower floor slabs, including a vertical pole 1, a horizontal pole 3 and an adjustable top support 2; the adjustable top support 2 is arranged on the upper part of the vertical pole 1, and the two are arranged top to top between the upper and lower floor slabs. By adjusting the relative distance between the adjustable top support 2 and the vertical pole 1, the strength of the top is controlled to prevent the vertical pole 1 from tipping over between the upper and lower floor slabs.

[0032] A plurality of discs 4 are sleeved on the vertical pole 1, and the spacing between the discs 4 is 500 mm. A through hole 401 is provided in the center of the disc 4, and the inner diameter of the through hole 401 matches the outer diameter of the vertical pole 1. Cross bar connecting holes 402 and diagonal bar connecting holes 403 are arranged at intervals in the circumferential direction of the disc 4, that is, the cross bar connecting holes 402 and the diagonal bar connecting holes 403 are arranged alternately.

[0033] Both ends of the cross bar 3 are fixed with latch joints A301, and the cross bar 3 is connected to the cross bar connecting hole 402 of the disc 4 on the vertical pole 1 through the latch joints A301 at both ends.

[0034] like Figure 2 As shown, an outer sleeve connecting portion 101 is provided at the bottom of the vertical pole 1, which is used for the upper and lower connection of two vertical poles 1; for houses with different storeys, vertical poles 1 of different specifications can be connected and used in combination to meet the enclosure requirements; the vertical poles are available in a variety of lengths, and the commonly used specifications are 500mm, 1000mm, 1500mm, 2000mm, 2500mm, and 3000mm.

[0035] Note: The adjustable top support 2 needs to be used in conjunction with the vertical pole 1. The height of the vertical pole 1 needs to be lower than the height of the floor and controlled within 500mm.

[0036] When the building floor height is too high, the combined connection of the vertical pole 1 is not stable enough, and an inclined rod 5 can be installed on the side of the vertical pole 1; pin joints B501 are movably provided at both ends of the inclined rod 5 for connection with the inclined rod connection hole 403 of the disc 4 on the vertical pole 1.

[0037] For super high storey height, a guardrail composed of multiple vertical poles needs to be used with multiple diagonal rods to tighten and prevent it from falling apart and overturning. Multiple diagonal rods 5 can be set between the vertical poles 1 to improve the stability of the railing.

[0038] like Figure 3 As shown, in this embodiment, the crossbar 3 only needs to be connected to the three discs 4 at the lower part of the vertical pole 1 to meet the protection requirements; at the same time, a dense mesh 6 is matched between the three layers of crossbars 3 to improve the protection effect.

[0039] In another embodiment, the discs 4 within the entire height range of the vertical pole 1 can be installed with the crossbar 3 to achieve a fully enclosed protective effect.

[0040] In another embodiment, a footboard 7 may be provided at the bottom of the upright pole 1 after installation to prevent building materials from falling from the bottom.

[0041] In another embodiment, if a locally protruding structure is encountered, the vertical pole 1 can partially offset the position of the vertical pole through cross bars 3 of different specifications, thereby avoiding the locally protruding structure. For this purpose, the cross bars have models of various lengths, and commonly used specifications are 300mm, 600mm, 900mm, 1200mm, 1500mm, 1800mm, 2400mm, and 3000mm.

[0042] Construction process:

[0043] 1) Material preparation: According to the height of the floor, select the corresponding specifications of vertical poles, horizontal poles and adjustable top supports, and use diagonal poles depending on the height of the floor.

[0044] 2) Positioning and laying out: Set up guardrails on the exterior wall as needed, arrange the positions of the vertical poles on the floor plan, and lay out the positions.

[0045] 3) Installation of vertical pole 1: Connect the adjustable top support to the top of vertical pole 1, and manually adjust the adjusting nut so that the combined length of vertical pole 1 and the adjustable top support is slightly shorter than the floor height; according to the positioning of the layout, install vertical pole 1 to the designated position, first tighten the adjusting nut to temporarily align vertical pole 1 and the adjustable top support in the current position, and after the verticality is adjusted, use a tool to tighten the adjusting nut again to increase the force of the top.

[0046] 4) Installation of horizontal bar 1: Securely connect the pin joint at one end of horizontal bar 1 to the disc of vertical bar 1, and leave the other end suspended in the air and parallel to the outer wall.

[0047] 5) Installation of the second vertical pole: Connect the adjustable top support to the top of the second vertical pole, and manually adjust the adjusting nut so that the combined length of the second vertical pole and the adjustable top support is slightly shorter than the floor height; connect the disks of the corresponding heights of the first vertical pole and the suspended horizontal bar, and fine-tune the position of the second vertical pole to coincide with the positioning of the line. First, tighten the adjusting nut initially to temporarily align the second vertical pole and the adjustable top support in the current position. After the verticality adjustment is completed, use a tool to finally tighten the adjusting nut to increase the force of the top.

[0048] 6) Subsequent installation: Follow the above steps to continue installing horizontal bar 2, vertical bar 3, ... horizontal bar n-1, vertical bar n.

[0049] 7) Tightening of railings: After all guardrails are installed, further tighten the pin joints connecting the horizontal bars and vertical discs.

[0050] The above embodiments are only preferred embodiments of the present invention and are not limitations on the technical solutions of the present invention. Any technical solution that can be implemented on the basis of the above embodiments without creative work should be deemed to fall within the scope of protection of the patent of the present invention.

Claims

1. A temporary external wall guardrail for building construction, characterized in that: The invention comprises a vertical pole (1), a horizontal pole (3) and an adjustable top support (2); a plurality of the vertical poles (1) are vertically arranged on a lower floor slab, the adjustable top support (2) is arranged on the top of the vertical poles (1), and the vertical poles (1) and the adjustable top support (2) are arranged between the upper and lower floors in a top-to-top manner, and the strength of the top-to-top arrangement is controlled by adjusting the relative distance between the adjustable top support (2) and the vertical poles (1); a plurality of the horizontal poles (3) are arranged between adjacent vertical poles (1) in a vertical direction, and the two ends of the horizontal poles (3) are respectively fixedly connected to the vertical poles (1).

2. A temporary external wall guardrail for construction according to claim 1, characterized in that: An inclined rod (5) is obliquely arranged between two adjacent vertical rods (1); one end of the inclined rod (5) is connected to the lower part of the vertical rod (1), and the other end is connected to the upper part of the vertical rod (1).

3. The temporary external wall guardrail for construction according to claim 1, characterized in that: An outer sleeve connecting portion (101) is provided at the bottom of the vertical pole (1) for connecting two vertical poles (1) up and down, thereby realizing a connection combination of vertical poles (1) of the same or different specifications.

4. The temporary external wall guardrail for construction according to claim 1, characterized in that: A plurality of disks (4) are arranged on the vertical rod (1) along its axial direction, a through hole (401) is provided at the center of the disk (4), a crossbar connecting hole (402) and an oblique rod connecting hole (403) are arranged in a circumferential direction of the disk (4), and the crossbar connecting hole (402) and the oblique rod connecting hole (403) are arranged alternately in the circumferential direction of the disk (4).

5. A temporary external wall guardrail for construction according to claim 4, characterized in that: Pin joints A (301) are fixedly provided at both ends of the crossbar (3) for connecting with the crossbar connection holes (402) of the upper disk (4) of the vertical pole (1), and together with the vertical pole (1) form a protective surface.

6. A temporary external wall guardrail for construction according to claim 4, characterized in that: Pin joints B (501) are movably provided at both ends of the diagonal rod (5) for connecting with the diagonal rod connecting holes (403) of the upper disc (4) of the vertical rod (1) to reinforce the guardrail.

7. The temporary external wall guardrail for construction according to claim 1, characterized in that: It also comprises a dense mesh net (6), wherein the dense mesh net (6) is arranged between the cross bars (3) to improve the protective effect.

8. The temporary external wall guardrail for construction according to claim 1, characterized in that: A foot plate (7) is provided at the rear bottom of the upright pole (1) to prevent building materials from falling from the bottom.