Trash blocking device for bridge and culvert

By designing floating mechanisms and traction equipment in the bridge and culvert sewage barrier device, the existing equipment has solved the problem of decreasing interception capacity and low collection efficiency when the water surface height changes, and achieved stable and efficient interception effect and convenient maintenance and cleaning.

CN222594782UActive Publication Date: 2025-03-11武国上

Patent Information

Application Number
CN202421110699.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-20
Publication Date
2025-03-11
Estimated Expiration
2034-05-20

AI Technical Summary

Technical Problem

The existing contamination devices for bridges and culverts need to adjust the intercept network regularly when the water surface height changes, resulting in a decrease in interception capacity. The interception network plane setting is likely to cause some garbage not to be collected, the collection efficiency is not high, and maintenance is inconvenient.

Method used

A floating body mechanism is designed, consisting of two floating barrels and an F-shaped guide rail fixedly connected. One end of the intercepting net is always above the water surface, forming a J-shaped mesh structure to ensure that the intercepting effect is not affected by changes in the water surface height. The traction rope is synchronized by the traction equipment, so that the intercepting net is moved to the water surface to concentrate dirt, which is convenient for cleaning and maintenance.

Benefits of technology

It realizes the maintenance of the pollution barrier capacity when the water surface height changes, improves the efficiency of garbage collection, and facilitates the maintenance and cleaning of the interception network.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222594782U_ABST
    Figure CN222594782U_ABST
Patent Text Reader

Abstract

The utility model discloses a trash holding device for bridges and culverts, and belongs to the technical field of trash holding devices. Comprising two floating body mechanisms, the two floating body mechanisms are arranged at bridge piers on the two sides of a bridge and culvert respectively, each floating body mechanism comprises two floating barrels, an F-shaped guide rail is fixedly connected between the floating barrels, and a first sliding groove and a second sliding groove are formed in each F-shaped guide rail; a floating body mechanism formed by fixedly connecting two floating buckets and an F-shaped guide rail is installed on each of the two sides of the bridge culvert, under the action of the floating buckets and the F-shaped guide rails, the initial end of the intercepting net is located above the water surface all the time, a J-shaped net body structure is formed, the good trash intercepting effect is achieved, and due to the fact that the floating buckets float on the water surface, the trash intercepting capacity cannot be reduced; the two pull ropes are synchronously pulled through the traction equipment, so that the end, located below the water surface, of the intercepting net slowly moves upwards to the water surface, dirt is concentrated to the water surface, the dirt is conveniently and intensively cleaned, and the intercepting net can also be conveniently maintained and cleaned.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of trash-blocking devices, and more specifically, to a trash-blocking device for bridges and culverts. Background Art

[0002] With the rapid development of urban life, urban garbage and waste are randomly discarded in the river water, which will seriously pollute the water quality and have a serious impact on the water conservancy facilities along the river. In order to prevent garbage and waste from drifting with the river, affecting more far-reaching waters, and reducing damage to the water ecosystem, it is necessary to add pollution interception equipment in the river. In order to facilitate the cleaning and collection of garbage and waste, it is usually chosen to set up pollution interception equipment at the bridge culvert of the bridge, which can then be convenient for installation and maintenance of the pollution interception equipment. The existing public technology number CN213836595U proposes a pollution interception device for water conservancy bridges and culverts. The device has a simple structure and a reasonable design. It can intercept pollution from bridges and culverts, and at the same time it can centrally process garbage to avoid blockage in rivers. In view of the above-mentioned related technologies, the utility model inventor believes that the following defects still exist: when the pollution intercepting device in the comparative literature is used, if the water level changes, the intercepting net needs to be adjusted regularly, otherwise the intercepting capacity of the intercepting net will gradually decrease when the water level decreases. In addition, the intercepting net is arranged in a flat surface, and the lifting mechanism drives the collection trough to rise, which may easily cause some garbage to not be collected, and it is necessary to collect it repeatedly, and the collection efficiency is not high. In addition, the intercepting net is below the water surface, and the later maintenance is relatively inconvenient. In view of this, we propose a pollution intercepting device for bridges and culverts. Utility Model Content

[0003] 1. Technical issues to be solved

[0004] The purpose of the present application is to provide a pollution intercepting device for bridges and culverts, which solves the problem that when the pollution intercepting device in the comparative literature in the above-mentioned background technology is used, if there is a change in the water level, the intercepting net needs to be adjusted regularly, otherwise when the water level decreases, the intercepting ability of the intercepting net gradually decreases. In addition, the intercepting net is arranged in a plane, and the lifting mechanism drives the collection trough to rise, which easily causes some garbage to not be collected, and it is necessary to collect repeatedly, the collection efficiency is not high, and the intercepting net is located below the water surface, and the technical problem of inconvenient later maintenance is realized. A floating body mechanism composed of two floating barrels and an F-shaped guide rail fixedly connected is installed on both sides of the bridge and culvert respectively. Under the action of the floating barrel and the F-shaped guide rail, one end of the intercepting net is always above the water surface, and a J-shaped net structure is formed, so as to achieve a good pollution intercepting effect. Moreover, because the floating barrel floats on the water surface, the pollution intercepting ability will not be reduced. The two pull ropes are synchronously pulled by the traction equipment, so that the end of the intercepting net below the water surface is slowly moved up to the water surface, so that the garbage is concentrated on the water surface, which is convenient for centralized cleaning of the garbage, and the intercepting net can also be convenient for maintenance and cleaning.

[0005] 2. Technical solution

[0006] The technical solution of the present application provides a pollution intercepting device for a bridge culvert, comprising: a floating body mechanism, wherein the number of the floating body mechanisms is two and they are respectively arranged at the piers on both sides of the bridge culvert, the floating body mechanism comprises two float barrels, an F-shaped guide rail is fixedly connected between the float barrels, a first slide groove and a second slide groove are provided on the F-shaped guide rail, an interception net is slidably installed on the F-shaped guide rail through the first slide groove and the second slide groove, and one end of the interception net is threadedly installed in the first slide groove through a threaded structure, a pulling mechanism is installed on the F-shaped guide rail, the pulling mechanism comprises a pull rope, the pull rope is wound around and connected to a guide wheel, and the pull rope is transmission-connected to the other end of the interception net, the guide wheel is rotatably connected to a rotating block through a rotating shaft, and the rotating block is fixedly connected to the F-shaped guide rail.

[0007] By adopting the above technical scheme, a floating body mechanism is respectively installed at the piers on both sides of the bridge culvert, and each floating body mechanism is composed of two floating barrels and an F-shaped guide rail fixedly connected. Under the action of the floating barrel, one end of the interception net is installed in the first slide groove through a thread, so that one end of the interception net can always be above the water surface, and the other end of the interception net is arranged in the second slide groove and arranged at a deeper position below the water surface, so that the interception net at the bridge culvert forms a J-shaped structure, thereby achieving the pollution interception effect, and the pollution interception capacity will not be reduced due to changes in the water surface height. When it is necessary to clean the dirt blocked by the interception net, the two pull ropes are synchronously pulled by the traction equipment, so that the end of the interception net below the water surface is slowly moved up to the water surface, and then the interception net can concentrate the dirt on the water surface, which is convenient for centralized cleaning, and the interception net can also be convenient for maintenance and cleaning.

[0008] Optionally, two annular grooves are provided on the floating barrel, and the floating barrel is tied and installed with a binding rope at the annular grooves. A connecting ring is fixed on the binding rope, and a suspension rod is detachably installed between the connecting rings.

[0009] By adopting the above technical solution, the binding rope is installed along the annular groove, and then the suspension rod is detachably installed through the connecting ring. The suspension rod can be conveniently used for lifting and transportation using mechanical lifting equipment.

[0010] Optionally, a limit block is fixedly provided on the upper surface of the F-shaped guide rail, and a through hole is opened on the limit block, and a pull rope is movably passed through the through hole.

[0011] By adopting the above technical solution, the pull rope can be linearly displaced along the perforations of the limit block and the guide wheel, so that the end of the interception net below the water surface can slowly move up to the water surface along the second slide groove.

[0012] Optionally, an anti-slip block is fixedly provided at one end of the pull rope, and the diameter of the anti-slip block is larger than the inner diameter of the perforation.

[0013] By adopting the above technical solution, one end of the pull rope is limited by the anti-drop block to prevent the pull rope from falling into the water body, which would cause the interception net to fail to hold.

[0014] Optionally, a first slider is fixedly provided at a corner of the interception net located at the first slide groove, the first slider is slidably disposed in the first slide groove, and a threaded rod is threadedly connected between the first slider and the F-shaped guide rail, and a second slider is fixedly provided at a corner of the interception net located at the second slide groove, the second slider is slidably disposed in the second slide groove, and the second sliders are respectively fixedly connected to a pull rope.

[0015] By adopting the above technical solution, a first slider is provided at the corner position of the interception net located in the first slide groove, the first slider can be slidably installed along the first slide groove, and is limited by a threaded rod so that one end of the interception net can be installed above the water surface, and a second slider is fixedly provided at the corner position of the other end of the interception net located in the second slide groove, and the second sliders are respectively fixedly connected to a pull rope, and then the end of the interception net located below the water surface can be slowly moved up to the water surface along the second slide groove through the synchronous displacement of the pull rope.

[0016] 3. Beneficial effects

[0017] One or more technical solutions provided in the technical solution of the present application have at least the following technical effects or advantages: a floating body mechanism consisting of two floats and an F-shaped guide rail fixedly connected is installed on both sides of the bridge culvert respectively. Under the action of the floats and the F-shaped guide rail, one end of the interception net is always above the water surface and forms a J-shaped net structure, achieving a good pollution interception effect. Moreover, since the floats float on the water surface, the pollution interception capacity will not be reduced. By synchronously pulling the two pull ropes through the traction equipment, the end of the interception net below the water surface is slowly moved up to the water surface, so that the dirt is concentrated on the water surface, which is convenient for centralized cleaning of the dirt, and the interception net can also be conveniently maintained and cleaned. BRIEF DESCRIPTION OF THE DRAWINGS

[0018] Figure 1 This is a schematic diagram of the overall structure of a trash intercepting device for a bridge or culvert disclosed in a preferred embodiment of the present application;

[0019] Figure 2 A schematic diagram of a floating body mechanism and an F-shaped guide rail structure of a pollution-blocking device for a bridge or culvert disclosed in a preferred embodiment of the present application;

[0020] Figure 3 A preferred embodiment of the present application discloses a bridge and culvert trash intercepting device Figure 2 The enlarged structural diagram at A in the middle;

[0021] Figure 4 A schematic diagram of the structure of an intercepting net and a lifting mechanism of a pollution intercepting device for a bridge or culvert disclosed in a preferred embodiment of the present application;

[0022] Figure 5 A preferred embodiment of the present application discloses a bridge and culvert trash intercepting device Figure 4 The enlarged structural diagram at B in the middle;

[0023] Explanation of the numbers in the figure: 1. Floating body mechanism; 11. Floating barrel; 111. Annular groove; 12. Binding rope; 13. Connecting ring; 14. Hanging rod; 2. F-shaped guide rail; 21. First slide groove; 22. Second slide groove; 24. Limit block; 241. Perforation; 3. Intercepting net; 31. First slider; 311. Threaded rod; 32. Second slider; 4. Lifting mechanism; 41. Anti-slip block; 42. Pull rope; 43. Guide wheel; 44. Rotating block. DETAILED DESCRIPTION

[0024] The present application is further described in detail below in conjunction with the accompanying drawings.

[0025] Reference Figures 1 to 5 The embodiment of the present application provides a pollution intercepting device for a bridge culvert, comprising: a floating body mechanism 1, the number of the floating body mechanisms 1 is two, and they are respectively arranged at the piers on both sides of the bridge culvert, the floating body mechanism 1 includes two floating barrels 11, an F-shaped guide rail 2 is fixedly connected between the floating barrels 11, a first slide groove 21 and a second slide groove 22 are opened on the F-shaped guide rail 2, an interception net 3 is slidably installed on the F-shaped guide rail 2 through the first slide groove 21 and the second slide groove 22, and one end of the interception net 3 is threadedly installed in the first slide groove 21 through a threaded structure, a pulling mechanism 4 is installed on the F-shaped guide rail 2, the pulling mechanism 4 includes a pull rope 42, the pull rope 42 is wound and connected with a guide wheel 43, and the pull rope 42 is transmission-connected to the other end of the interception net 3, the guide wheel 43 is rotatably connected to a rotating block 44 through a rotating shaft, and the rotating block 44 is fixedly connected to the F-shaped guide rail 2, located on both sides of the bridge culvert. A floating body mechanism 1 is installed at each pier, and each floating body mechanism 1 is composed of two floating barrels 11 and an F-shaped guide rail 2 fixedly connected. Under the action of the floating barrel 11, one end of the interception net 3 is installed in the first slide groove 21 through a thread, so that one end of the interception net 3 can always be above the water surface, and the other end of the interception net 3 is arranged in the second slide groove 22 and is arranged at a deeper position below the water surface, so that the interception net 3 at the culvert forms a J-shaped structure, thereby achieving a pollution interception effect, and the pollution interception capacity will not be reduced due to changes in the water surface height. When it is necessary to clean the dirt blocked by the interception net 3, the two pull ropes 42 are pulled synchronously through the traction equipment, so that the end of the interception net 3 below the water surface is slowly moved up to the water surface, and then the interception net 3 can concentrate the dirt on the water surface, which is convenient for centralized cleaning, and the interception net 3 can also be convenient for maintenance and cleaning.

[0026] Reference Figure 2 and Figure 3Two annular grooves 111 are provided on the buoy 11. A binding rope 12 is installed on the buoy 11 at the annular groove 111. A connecting ring 13 is fixed on the binding rope 12. A suspension rod 14 is detachably installed between the connecting rings 13. The binding rope 12 is bound and installed along the annular groove 111, and then the suspension rod 14 is detachably installed through the connecting ring 13. The suspension rod 14 can be conveniently used for lifting and transportation using mechanical lifting equipment.

[0027] Reference Figure 2 and Figure 3 A limit block 24 is fixedly provided on the upper surface of the F-shaped guide rail 2, and a through hole 241 is opened on the limit block 24. A pull rope 42 movably passes through the through hole 241. The pull rope 42 can move linearly along the through hole 241 of the limit block 24 and the guide wheel 43, so that the end of the interception net 3 located below the water surface can slowly move up to the water surface along the second slide groove 22.

[0028] Reference Figure 4 and Figure 5 One end of the pull rope 42 is fixed with an anti-slip block 41, the diameter of the anti-slip block 41 is larger than the inner diameter of the perforation 241, and one end of the pull rope 42 is limited by the anti-slip block 41 to prevent the pull rope 42 from falling into the water body, which will cause the interception net 3 to fail to hold its purpose.

[0029] Reference Figure 4 and Figure 5 The first slider 31 is fixedly provided at a corner of the first slide groove 21 of the intercepting net 3, and the first slider 31 is slidably arranged in the first slide groove 21, and a threaded rod 311 is threadedly connected between the first slider 31 and the F-shaped guide rail 2, and a second slider 32 is fixedly provided at a corner of the intercepting net 3 located at the second slide groove 22, and the second slider 32 is slidably arranged in the second slide groove 22, and the second slider 32 is respectively fixedly connected to a pull rope 42.

[0030] Working principle: A floating body mechanism 1 is installed at the piers on both sides of the bridge culvert, each of which is composed of two floating barrels 11 and an F-shaped guide rail 2 fixedly connected. The binding rope 12 is tied and installed along the annular groove 111, and then the suspension rod 14 is detachably installed through the connecting ring 13. The suspension rod 14 can be conveniently used to lift it to the water surface using mechanical lifting equipment. Under the action of the floating barrel 11, one end of the interception net 3 located on the first sliding block 31 is threadedly installed in the first sliding groove 21 through the threaded rod 311, so that one end of the interception net 3 can always be above the water surface, and the other end of the interception net 3 is slidably set on the second sliding block through the second sliding block 32. The second slider 32 is installed in a suspended manner by a pull rope 42, and one end of the pull rope 42 is limited at the limit block 24 by the anti-slip block 41, so that the interception net 3 at the culvert forms a J-shaped structure, thereby achieving a good pollution-blocking effect and will not reduce the pollution-blocking ability due to changes in the water surface height. When it is necessary to clean the dirt blocked by the interception net 3, the two pull ropes 42 are pulled synchronously by the traction equipment, so that the end of the interception net 3 below the water surface is slowly moved up to the water surface, and then the interception net 3 can concentrate the dirt on the water surface, which is convenient for centralized cleaning, and the interception net 3 can also be convenient for maintenance and cleaning.

Claims

1. A pollution-blocking device for bridges and culverts, characterized in that: The invention comprises: a floating body mechanism (1), wherein the floating body mechanism (1) is two in number and is respectively arranged at the piers on both sides of the bridge culvert, the floating body mechanism (1) comprises two floating barrels (11), an F-shaped guide rail (2) is fixedly connected between the floating barrels (11), a first slide groove (21) and a second slide groove (22) are provided on the F-shaped guide rail (2), an interception net (3) is slidably installed on the F-shaped guide rail (2) through the first slide groove (21) and the second slide groove (22), and the interception net (3) is One end of the intercepting net (3) is threadedly installed in the first slide groove (21) through a threaded structure. A pulling mechanism (4) is installed on the F-shaped guide rail (2). The pulling mechanism (4) includes a pull rope (42). The pull rope (42) is wound and connected to a guide wheel (43), and the pull rope (42) is transmission-connected to the other end of the intercepting net (3). The guide wheel (43) is rotatably connected to a rotating block (44) through a rotating shaft, and the rotating block (44) is fixedly connected to the F-shaped guide rail (2).

2. A pollution-blocking device for bridges and culverts according to claim 1, characterized in that: The floating barrel (11) is provided with two annular grooves (111), and a binding rope (12) is installed on the floating barrel (11) at the annular groove (111). A connecting ring (13) is fixedly provided on the binding rope (12), and a suspension rod (14) is detachably installed between the connecting rings (13).

3. A pollution-blocking device for bridges and culverts according to claim 1, characterized in that: A limit block (24) is fixedly provided on the upper surface of the F-shaped guide rail (2), a through hole (241) is provided on the limit block (24), and a pull rope (42) is movably passed through the through hole (241).

4. A pollution-blocking device for bridges and culverts according to claim 3, characterized in that: An anti-slip block (41) is fixedly provided at one end of the pull rope (42), and the diameter of the anti-slip block (41) is larger than the inner diameter of the through hole (241).

5. The pollution-blocking device for bridges and culverts according to claim 1, characterized in that: A first slider (31) is fixedly provided at a corner of the intercepting net (3) located at the first slide groove (21), the first slider (31) is slidably arranged in the first slide groove (21), and a threaded rod (311) is threadedly connected between the first slider (31) and the F-shaped guide rail (2), and a second slider (32) is fixedly provided at a corner of the intercepting net (3) located at the second slide groove (22), the second slider (32) is slidably arranged in the second slide groove (22), and the second slider (32) is fixedly connected to a pull rope (42) respectively.

Citation Information

Patent Citations

  • Trash holding device for water conservancy bridge and culvert

    CN213836595U

Cited By

  • Unpowered intercepting net device for water taking open channel of nuclear power plant

    CN121556409A