Laminated flow channel miniature assembling mechanism

By designing a stacked runner micro assembly mechanism, the superposition space between the lower runner and the upper runner is used to realize multi-process superposition that is difficult to achieve in the traditional assembly method, solving the problem of large space occupation and improving assembly efficiency.

CN222608621UActive Publication Date: 2025-03-14SU ZHOU ZHONG XING LIAN JING MI GONG YE YOU XIAN GONG SI
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202423147724.7
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-12-19
Publication Date
2025-03-14
Estimated Expiration
2034-12-19

AI Technical Summary

Technical Problem

During the assembly process, the traditional planar assembly method takes up a large space and it is difficult to implement multiple processes in a small space at the same time.

Method used

A stacked runner micro assembly mechanism is designed to achieve superposition of processes between the lower runner and the upper runner, and to complete the assembly, testing and sorting processes such as pre-installation mechanism, installation mechanism, testing mechanism, sorting mechanism and vehicle reset mechanism.

Benefits of technology

The area of ​​assembly space is effectively reduced, and the assembly task of multiple processes is completed in a small space, while improving production efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222608621U_ABST
    Figure CN222608621U_ABST
Patent Text Reader

Abstract

The embodiment of the utility model relates to the technical field of automation equipment, and discloses a laminated flow channel miniature assembling mechanism, which comprises a lower layer flow channel and an upper layer flow channel positioned above the lower layer flow channel, and the upper layer flow channel is provided with an assembling station, a testing station and a sorting station which are arranged front and back. The laminated flow channel miniature assembling mechanism comprises a preassembling mechanism, a mounting mechanism, a testing mechanism, a sorting mechanism and a carrier resetting mechanism, the preassembling mechanism comprises a preassembling platform and an assembling carrier located on the preassembling platform. The preassembling platform drives the assembling carrier to be lifted from the front end of the lower-layer flow channel to the front end of the upper-layer flow channel, the assembling carrier is sequentially pushed to the assembling station, the testing station and the sorting station, the mounting mechanism completes assembling of the connector assembly, and the testing mechanism detects the assembling state of the connector assembly. The sorting mechanism sorts the connector assemblies according to a detection result of the testing mechanism; and the carrier resetting mechanism descends the assembled carrier from the test station and pushes the assembled carrier back to the front end of the lower-layer runner, so that a complete assembly cycle is completed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The embodiment of the utility model relates to the technical field of automation equipment, and in particular to a laminated flow channel micro-assembly mechanism. Background Art

[0002] In the process of assembling parts, many processes are usually required, which are usually carried out on a plane. The corresponding site space and area are very large, and the requirements for the factory building will be very large. In order to reduce the site, it is necessary to reduce the assembly space. To achieve this requirement, multiple processes must be completed in the same process or in the same small space, otherwise it cannot be achieved in a very small space.

[0003] Therefore, it is necessary to provide a new laminated flow channel micro-assembly mechanism to overcome the above-mentioned defects. Utility Model Content

[0004] The purpose of the embodiment of the utility model is to provide a laminated flow channel micro-assembly mechanism, which reduces the occupied space while completing the assembly process.

[0005] In order to solve the above technical problems, the embodiment of the utility model provides a stacked flow channel micro-assembly mechanism, comprising a lower flow channel extending in the longitudinal direction and an upper flow channel located above the lower flow channel, wherein the upper flow channel is provided with an assembly station, a test station and a sorting station arranged from front to back in the longitudinal direction. The stacked flow channel micro-assembly mechanism comprises a pre-installation mechanism located at the longitudinal front end of the lower flow channel, a mounting mechanism corresponding to the assembly station, a testing mechanism corresponding to the testing station, a sorting mechanism corresponding to the sorting station and a carrier reset mechanism. The pre-installation mechanism includes a pre-installation platform and an assembly tool arranged on the pre-installation platform, the assembly tool carries the semi-finished connector component, the pre-installation platform drives the assembly tool to be lifted from the longitudinal front end of the lower flow channel to the longitudinal front end of the upper flow channel, and the assembly tool is pushed to the assembly station, the testing station and the sorting station in sequence, the installation mechanism completes the assembly of the connector component on the assembly tool, the testing mechanism detects whether the corresponding assembly state of the connector component is qualified, and the sorting mechanism picks up and sorts the connector component on the assembly tool according to the detection result of the testing mechanism; then, the carrier reset mechanism lowers the assembly tool from the sorting station to the longitudinal rear end of the lower flow channel and pushes it back to the pre-installation platform at the longitudinal front end of the lower flow channel, thereby completing a complete assembly cycle.

[0006] In a preferred embodiment, the preloading mechanism includes a preloading translation cylinder connected to the bottom of the preloading platform, and the preloading translation cylinder drives the preloading platform to translate laterally, so that the preloading platform drives the assembled tool with the connector component to move to the longitudinal front end of the lower layer flow channel, or drives the assembled tool without the connector component to move away from the longitudinal front end of the lower layer flow channel.

[0007] In a preferred embodiment, the preloading mechanism includes a preloading lifting cylinder connected to the bottom of the preloading platform, and the preloading lifting cylinder drives the preloading platform to move vertically so that the preloading platform switches between the longitudinal front end of the lower layer flow channel and the longitudinal front end of the upper layer flow channel.

[0008] In a preferred embodiment, the stacked flow channel micro-assembly mechanism includes a part translation mechanism, which is provided with a translation component located at the longitudinal front end of the upper flow channel and a translation cylinder connected to the translation component; when the pre-installation platform drives the assembly tool to move to the longitudinal front end of the upper flow channel, the translation cylinder drives the translation component to push the assembly tool backward in the longitudinal direction until the assembly tool moves to the assembly station.

[0009] In a preferred embodiment, the testing mechanism includes image testing devices located on both lateral sides of the testing station, and the image testing devices are used to detect whether the assembly state of the connector assembly on the testing station is qualified.

[0010] In a preferred embodiment, the sorting mechanism includes a gripping mechanism and a good product outflow platform and a defective product collection box located on a lateral side of the upper flow channel, and the defective product collection box is located on the lateral outer side of the good product outflow platform.

[0011] In a preferred embodiment, the good product outflow platform has a conveyor belt that moves longitudinally. If the assembly state of the connector component detected by the image testing device is qualified, the grabbing mechanism grabs the connector component and places it on the conveyor belt to flow out of the good product outflow platform.

[0012] In a preferred embodiment, if the assembly state of the connector assembly detected by the image testing device is unqualified, the grabbing mechanism grabs the connector assembly and places it in the defective product collection box.

[0013] In a preferred embodiment, the carrier resetting mechanism includes a carrier lifting platform and a carrier lifting cylinder connected to the carrier lifting platform. When the assembled carrier moves to the sorting station, the carrier lifting platform is located at the sorting station to carry the assembled carrier; and after the connector component on the sorting station is grabbed, the carrier lifting cylinder drives the carrier lifting platform to drive the assembled carrier to descend to the longitudinal rear end of the lower layer flow channel.

[0014] In a preferred embodiment, the carrier resetting mechanism includes a carrier shifting mechanism. When the assembled carrier is located at the longitudinal rear end of the lower flow channel, the carrier shifting mechanism pushes the assembled carrier to move forward in the longitudinal direction and be placed on the pre-installation platform.

[0015] Compared with the prior art, the embodiment of the utility model has the following beneficial effects: the pre-installation platform drives the assembly tool to be lifted from the longitudinal front end of the lower flow channel to the longitudinal front end of the upper flow channel, and the assembly tool is pushed to the assembly station, the test station and the sorting station in sequence, the installation mechanism completes the assembly of the connector components on the assembly tool, the test mechanism detects whether the assembly state of the corresponding connector components is qualified, and the sorting mechanism picks up and sorts the connector components on the assembly tool according to the detection results of the test mechanism; then, the carrier reset mechanism lowers the assembly tool from the sorting station to the longitudinal rear end of the lower flow channel and pushes it back to the pre-installation platform at the longitudinal front end of the lower flow channel, thereby completing a complete assembly cycle. The upper flow channel and the lower flow channel are stacked and assembled without interfering with each other, effectively utilizing the height space and saving floor space. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] One or more embodiments are exemplarily described by pictures in the corresponding drawings, and these exemplified descriptions do not constitute limitations on the embodiments. Elements with the same reference numerals in the drawings represent similar elements, and unless otherwise stated, the figures in the drawings do not constitute proportional limitations.

[0017] Figure 1 It is a three-dimensional schematic diagram of the laminated flow channel micro-assembly mechanism of the utility model;

[0018] Figure 2 yes Figure 1 A top view of the laminated flow channel micro-assembly mechanism shown;

[0019] Figure 3 yes Figure 1 A right side view of the laminated flow channel micro-assembly mechanism shown;

[0020] Figure 4 yes Figure 1 A front view of the laminated flow channel micro-assembly mechanism is shown. DETAILED DESCRIPTION

[0021] In order to make the purpose, technical scheme and advantages of the embodiment of the utility model clearer, the implementation mode of the utility model will be described in detail below with reference to the accompanying drawings. However, it can be understood by those skilled in the art that in the implementation mode of the utility model, many technical details are proposed in order to make the reader better understand the present application. However, even without these technical details and various changes and modifications based on the following implementation modes, the technical scheme claimed in the present application can be implemented.

[0022] See also Figures 1 to 4 The present invention shows a stacked flow channel micro-assembly mechanism 100, which overlaps the assembly space so that different processes can be carried out in a stacked manner to achieve a reduction in space and area. The stacked flow channel micro-assembly mechanism 100 includes a lower flow channel 101 extending in the longitudinal direction and an upper flow channel 102 located above the lower flow channel 101. The upper flow channel 102 is provided with an assembly station, a test station 41 and a sorting station 51 arranged from front to back in the longitudinal direction. In this embodiment, the stacked flow channel micro-assembly mechanism 100 also includes a pre-installation mechanism 10 located at the longitudinal front end of the lower flow channel 101, a part translation mechanism 20, an installation mechanism 30 corresponding to the assembly station, a test mechanism 40 corresponding to the test station 41, a sorting mechanism 50 corresponding to the sorting station 51, and a carrier reset mechanism 60.

[0023] The pre-installation mechanism 10 includes a pre-installation platform 11, a pre-installation translation cylinder 12 and a pre-installation lifting cylinder 13 connected to the bottom of the pre-installation platform 11, and an assembly tool 201 arranged on the pre-installation platform 11, wherein the assembly tool 201 is used to carry the semi-finished connector assembly 200. The pre-installation translation cylinder 12 drives the pre-installation platform 11 to translate horizontally, so that the pre-installation platform 11 drives the assembly tool 201 with the semi-finished connector assembly 200 to move to the longitudinal front end of the lower layer flow channel 101, or drives the assembly tool 201 without the connector assembly 200 to move away from the longitudinal front end of the lower layer flow channel 101. The pre-installation lifting cylinder 13 drives the pre-installation platform 11 to move vertically, so that the pre-installation platform 11 switches between the longitudinal front end of the lower layer flow channel 101 and the longitudinal front end of the upper layer flow channel 102.

[0024] The part translation mechanism 20 is provided with a translation component 21 located at the longitudinal front end of the upper flow channel 102 and a translation cylinder 22 connected to the translation component 21; when the pre-installation platform 11 drives the assembly tool 201 to move to the longitudinal front end of the upper flow channel 102, the translation component 21 is located at the longitudinal front end of the pre-installation platform 11, and the translation cylinder 22 drives the translation component 21 to push the assembly tool 201 backward in the longitudinal direction until the assembly tool 201 drives the semi-finished connector component 200 to move to the assembly station. The installation mechanism 30 is used to complete the assembly of the connector component 200 on the assembly tool 201 located at the assembly station to form a finished connector component 200.

[0025] The testing mechanism 40 includes an image testing device 42 located on both sides of the testing station 41 in the lateral direction, and the image testing device 42 is used to detect whether the assembly state of the connector assembly 200 on the testing station 41 is qualified. The sorting mechanism 50 includes a gripping mechanism 52 and a good product outflow platform 53 and a defective product collection box 54 located on one side of the upper flow channel 102 in the lateral direction, and the defective product collection box 54 is located on the lateral outer side of the good product outflow platform 53. The good product outflow platform 53 has a conveyor belt moving in the longitudinal direction. If the assembly state of the connector assembly 200 detected by the image testing device 42 is qualified, the gripping mechanism 52 grips the connector assembly 200 and places it on the conveyor belt to flow out of the good product outflow platform 53. If the assembly state of the connector assembly 200 detected by the image testing device 42 is unqualified, the gripping mechanism 52 grips the connector assembly 200 and places it in the defective product collection box 54 for subsequent scrapping.

[0026] The carrier resetting mechanism 60 includes a carrier lifting platform 61, a carrier lifting cylinder 62 connected to the carrier lifting platform 61, and a carrier shifting mechanism 63. When the assembled vehicle 201 moves to the sorting station 51, the carrier lifting platform 61 is located at the sorting station 51 to carry the assembled vehicle 201. After the connector component 200 on the sorting station 51 is grabbed, the carrier lifting cylinder 62 drives the carrier lifting platform 61 to drive the assembled vehicle 201 without the connector component 200 to descend to the longitudinal rear end of the lower flow channel 101, and when the assembled vehicle 201 is located at the longitudinal rear end of the lower flow channel 101, the carrier shifting mechanism 63 pushes the assembled vehicle 201 to move forward in the longitudinal direction and place it on the pre-installation platform 11.

[0027] In this embodiment, the working steps of the stacked flow channel micro-assembly mechanism 100 are as follows: first, the assembly container 201 with the semi-finished connector component 200 is placed on the pre-installation platform 11, the pre-installation translation cylinder 12 drives the pre-installation platform 11 to move to the longitudinal front end of the lower flow channel 101, and the pre-installation lifting cylinder 13 lifts the pre-installation platform 11 from the longitudinal front end of the lower flow channel 101 to the longitudinal front end of the upper flow channel 102. Then, the translation cylinder 22 of the part translation mechanism 20 drives the translation component 21 to push the assembly tool 201 to the assembly station, the test station 41 and the sorting station 51 in sequence. When the assembly tool 201 is located at the assembly station, the installation mechanism 30 completes the assembly of the connector component 200 on the assembly tool 201. When the assembly tool 201 is located at the test station 41, the image testing device 42 of the testing mechanism 40 detects whether the assembly state of the corresponding connector component 200 is qualified. When the assembly tool 201 is located at the sorting station 51, the grasping mechanism 52 of the sorting mechanism 50 picks up and sorts the connector component 200 on the assembly tool 201 according to the detection result of the image testing device 42. Finally, the carrier lifting cylinder 62 of the carrier resetting mechanism 60 drives the carrier lifting platform 61 to lower the assembled carrier 201 from the sorting station 51 to the longitudinal rear end of the lower flow channel 101, and the carrier shifting mechanism 63 pushes the assembled carrier 201 back to the longitudinal front end of the lower flow channel 101 and places it on the pre-installation platform 11, and the pre-installation platform 11 drives the assembled carrier 201 without the connector component 200 to move away from the longitudinal front end of the lower flow channel 101, thereby completing a complete assembly cycle.

[0028] In the present invention, the pre-installation platform 11 drives the assembly tool 201 to be lifted from the longitudinal front end of the lower flow channel 101 to the longitudinal front end of the upper flow channel 102, and the assembly tool 201 is pushed to the assembly station, the test station 41 and the sorting station 51 in sequence, the installation mechanism 30 completes the assembly of the connector assembly 200 on the assembly tool 201, the test mechanism 40 detects whether the assembly state of the corresponding connector assembly 200 is qualified, and the sorting mechanism 50 picks up and sorts the connector assembly 200 on the assembly tool 201 according to the detection result of the test mechanism 40; then, the carrier reset mechanism 60 lowers the assembly tool 201 from the sorting station 51 to the longitudinal rear end of the lower flow channel 101 and pushes it back to the pre-installation platform 11 at the longitudinal front end of the lower flow channel 101, thereby completing a complete assembly cycle. The upper flow channel 102 and the lower flow channel 101 are stacked and assembled without interfering with each other, effectively utilizing the height space and saving floor space.

[0029] Those skilled in the art will appreciate that the above embodiments are specific examples for implementing the present invention, and in actual applications, various changes may be made to them in form and detail without departing from the spirit and scope of the present invention.

Claims

1. A stacked flow channel micro-assembly mechanism, comprising a lower flow channel extending in the longitudinal direction and an upper flow channel located above the lower flow channel, wherein the upper flow channel is provided with an assembly station, a testing station and a sorting station arranged from front to back in the longitudinal direction; characterized in that: The stacked flow channel micro-assembly mechanism includes a pre-installation mechanism located at the longitudinal front end of the lower flow channel, a mounting mechanism corresponding to the assembly station, a testing mechanism corresponding to the testing station, a sorting mechanism corresponding to the sorting station, and a carrier reset mechanism; the pre-installation mechanism includes a pre-installation platform and an assembly tool arranged on the pre-installation platform, the assembly tool carries a semi-finished connector component, the pre-installation platform drives the assembly tool to be lifted from the longitudinal front end of the lower flow channel to the longitudinal front end of the upper flow channel, and the assembly tool is pushed to the assembly station in sequence. The assembly tool comprises a mounting mechanism, a test station, and a sorting station. The mounting mechanism completes the assembly of the connector components on the assembly tool. The testing mechanism detects whether the assembly status of the corresponding connector components is qualified. The sorting mechanism picks up and sorts the connector components on the assembly tool according to the detection results of the testing mechanism. Then, the carrier resetting mechanism lowers the assembly tool from the sorting station to the longitudinal rear end of the lower flow channel and pushes it back to the pre-installation platform at the longitudinal front end of the lower flow channel, thereby completing a complete assembly cycle.

2. The laminated flow channel micro-assembly mechanism according to claim 1, characterized in that: The preloading mechanism includes a preloading translation cylinder connected to the bottom of the preloading platform, and the preloading translation cylinder drives the preloading platform to translate laterally, so that the preloading platform drives the assembled tool with the connector component to move to the longitudinal front end of the lower layer flow channel, or drives the assembled tool without the connector component to move away from the longitudinal front end of the lower layer flow channel.

3. The laminated flow channel micro-assembly mechanism according to claim 2, characterized in that: The preloading mechanism includes a preloading lifting cylinder connected to the bottom of the preloading platform, and the preloading lifting cylinder drives the preloading platform to move vertically so that the preloading platform switches between the longitudinal front end of the lower layer flow channel and the longitudinal front end of the upper layer flow channel.

4. The laminated flow channel micro-assembly mechanism according to claim 1, characterized in that: The stacked flow channel micro-assembly mechanism includes a part translation mechanism, which is provided with a translation component located at the longitudinal front end of the upper flow channel and a translation cylinder connected to the translation component; when the pre-installation platform drives the assembly tool to move to the longitudinal front end of the upper flow channel, the translation cylinder drives the translation component to push the assembly tool backward in the longitudinal direction until the assembly tool moves to the assembly station.

5. The laminated flow channel micro-assembly mechanism according to claim 1, characterized in that: The testing mechanism includes image testing devices located on both lateral sides of the testing station, and the image testing devices are used to detect whether the assembly state of the connector assembly on the testing station is qualified.

6. The laminated flow channel micro-assembly mechanism according to claim 5, characterized in that: The sorting mechanism includes a grabbing mechanism and a good product outflow platform and a defective product collection box located on one lateral side of the upper flow channel, and the defective product collection box is located on the lateral outer side of the good product outflow platform.

7. The laminated flow channel micro-assembly mechanism according to claim 6, characterized in that: The good product outflow platform has a conveyor belt that moves in the longitudinal direction. If the assembly state of the connector component detected by the image testing device is qualified, the grabbing mechanism grabs the connector component and places it on the conveyor belt to flow out of the good product outflow platform.

8. The laminated flow channel micro-assembly mechanism according to claim 7, characterized in that: If the assembly state of the connector assembly detected by the image testing device is unqualified, the grabbing mechanism grabs the connector assembly and places it in the defective product collection box.

9. The laminated flow channel micro-assembly mechanism according to claim 1, characterized in that: The carrier resetting mechanism includes a carrier lifting platform and a carrier lifting cylinder connected to the carrier lifting platform. When the assembled vehicle moves to the sorting station, the carrier lifting platform is located at the sorting station to carry the assembled vehicle; and after the connector component on the sorting station is grabbed, the carrier lifting cylinder drives the carrier lifting platform to drive the assembled vehicle to descend to the longitudinal rear end of the lower flow channel.

10. The laminated flow channel micro-assembly mechanism according to claim 9, characterized in that: The carrier resetting mechanism comprises a carrier shifting mechanism. When the assembled carrier is located at the longitudinal rear end of the lower flow channel, the carrier shifting mechanism pushes the assembled carrier to move forward in the longitudinal direction and be placed on the pre-installation platform.