Circulating blowing cooling device for electrolytic aluminum electrolytic bath

By designing an electrolytic aluminum electrolytic cell circulating blowing cooling device with intelligent air supply components including infrared thermometer, blowing duct and solenoid valve, the problem of inconvenience of intelligent control and poor energy saving effect of existing devices is solved, efficient and intelligent cooling control is achieved and the practicality and durability of the device is improved.

CN222613492UActive Publication Date: 2025-03-14邹平县汇盛新材料科技有限公司
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202420888525.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-04-26
Publication Date
2025-03-14
Estimated Expiration
2034-04-26

AI Technical Summary

Technical Problem

The existing electrolytic aluminum electrolytic cell blowing and cooling device is not convenient for intelligent control, the energy saving effect is average, and the practicality and durability need to be improved.

Method used

An electrolytic aluminum electrolytic cell circulating blowing and cooling device is designed, including a blower, a base and an intelligent air supply assembly. The intelligent air supply assembly consists of an infrared thermometer, a blower duct and a solenoid valve. The infrared thermometer monitors the temperature of the groove shell, controls the solenoid valve to open the blower duct for cooling, and sets a cooler on the blower duct to improve the cooling effect.

Benefits of technology

Intelligent cooling control of the electrolytic tank shell is realized, energy saving effect is improved, the practicality and durability of the device is enhanced, and safety and reliability are further improved through the installation of pressure early warning components, insulation layer and protective reinforcement plate.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222613492U_ABST
    Figure CN222613492U_ABST
Patent Text Reader

Abstract

The utility model discloses a circulating blowing cooling device for an electrolytic aluminum electrolytic bath, which belongs to the technical field of blowing cooling and comprises a blowing box, a base and an intelligent air supply component, the blowing box is mounted on the base, the intelligent air supply component is mounted in the blowing box, and the intelligent air supply component comprises an infrared thermometer, a blowing pipe and an electromagnetic valve. An electromagnetic valve is installed in the middle of the air blowing pipe, and a refrigerator is arranged on one side of the electromagnetic valve. The device has the beneficial effects that the device is moved to the position near the electrolytic aluminum electrolytic tank shell, the surface temperature of the tank shell can be monitored through the infrared thermometer, the electromagnetic valve can be controlled to open the blowpipe and blow and cool the surface of the tank shell when the temperature is too high, and the blowpipe is supplied with air through an external high-pressure air source of an air supply pipe; the intelligent air supply effect of the whole device is greatly improved, the device is easy to control and operate, meanwhile, the refrigerator is further arranged on the air blowing pipe, blown air can be changed into cold air, and therefore the cooling effect is improved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of air blowing and cooling, in particular to a circulating air blowing and cooling device for an electrolytic aluminum reduction cell. Background Art

[0002] The electrolytic cell consists of a cell body, an anode and a cathode. Most of them use a diaphragm to separate the anode chamber and the cathode chamber. According to the different electrolytes, they are divided into three categories: aqueous solution electrolytic cell, molten salt electrolytic cell and non-aqueous solution electrolytic cell. When direct current passes through the electrolytic cell, an oxidation reaction occurs at the interface between the anode and the solution, and a reduction reaction occurs at the interface between the cathode and the solution to produce the desired product. When the electrolytic cell runs for a long time, its cell shell will heat up, which will affect the use of the electrolytic cell, so it needs to be cooled.

[0003] The aluminum electrolysis workshop handles the over-high temperature of the electrolytic cell shell by continuously sweeping the shell with ground wind to cool it down. However, opening the ground wind for a long time will waste the gas source, wear the ball valve and the pipeline. The air blowing and cooling device of the aluminum electrolytic cell in the prior art is not easy to be intelligently controlled, and its energy-saving effect is general. The practicality and durability of the device itself also need to be improved. At the same time, the utility model patent with announcement number CN218710922U discloses an intelligent air blowing and cooling device for the bottom of the electrolytic cell; it includes a temperature measuring device fixed on the bottom frame of the electrolytic cell. Thermal imaging also includes a control power box arranged on the side wall of the bottom frame of the electrolytic cell, wherein a power switch, a time-space switch, and a time relay are arranged in the control power box, and a pilot diaphragm solenoid valve is arranged on the side wall of the control power box, the air inlet end of the pilot diaphragm solenoid valve is connected to the compressed air inlet pipe, and the air outlet end is connected to the compressed air outlet pipe, the power switch, the time-space switch, the time relay and the pilot diaphragm solenoid valve are all connected to the controller, which is not convenient for cooling effect and flexible movement, and its practicality and durability need to be improved. Utility Model Content

[0004] In order to overcome the problems that the temperature of the electrolytic cell shell of the aluminum electrolytic workshop is too high in the prior art, the surface wind is used to continuously sweep the surface wind to cool the cell shell. However, opening the surface wind for a long time will waste gas source, wear the ball valve and pipeline, and the corresponding electrolytic aluminum electrolytic cell air blowing and cooling device is not convenient for intelligent control, its energy-saving effect is general, and its practicality and durability need to be improved. The utility model provides an electrolytic aluminum electrolytic cell circulating air blowing and cooling device, including a blowing box, a base and an intelligent air supply component, a blowing box is installed on the base, and an intelligent air supply component is installed in the blowing box. The intelligent air supply component includes an infrared thermometer, a blowing pipe and a solenoid valve. The blowing pipe is arranged in the middle of the inner side of the blowing box, and the two ends of the blowing pipe are connected to the middle of the two sides of the blowing box. The blowing hood and the air supply pipe are respectively connected, and the solenoid valve is installed in the middle of the blowing pipe, and a refrigerator is arranged at the side of the solenoid valve. The infrared thermometer is installed on the side wall of the blowing box and is located directly above the blowing box.

[0005] The device is moved to the vicinity of the shell of the electrolytic aluminum reduction cell, and the surface temperature of the shell can be monitored by an infrared thermometer. When the temperature is too high, the solenoid valve can be controlled to open the blowing pipe and blow air to cool the surface of the shell. The blowing pipe is supplied with air by a high-pressure air source connected to an air supply pipe. The outer surface of the electrolytic cell shell can be blown centrally through a blowing hood, which greatly improves the intelligent air supply effect of the entire device and makes it easy to control and operate. At the same time, a refrigerator is also arranged on the blowing pipe to convert the blown air into cold air, thereby improving the cooling effect.

[0006] Preferably, the infrared thermometer is installed on the blowing box through a support plate, and the emission port of the infrared thermometer is parallel to the blowing direction of the blowing pipe, and the infrared thermometer is electrically connected to the solenoid valve.

[0007] Preferably, a connecting flange is provided on the air supply pipe, and the air supply pipe is externally connected to a high-pressure air source.

[0008] Preferably, a plurality of flow reduction holes are formed inside the air hood near the position of the air blowing pipe, and a dustproof filter is installed on the outside of the air hood.

[0009] Preferably, a pressure warning component is arranged on the blow pipe and the blow box, and the pressure warning component includes an alarm and a pressure sensor. The alarm is installed on the front side of the blow box, and the pressure sensor is installed on the blow pipe and is electrically connected to the alarm.

[0010] By setting up a pressure warning component on the blow pipe, the pipeline air pressure can be monitored through the pressure sensor. When the pressure is abnormal, the alarm can be sounded, which is convenient for the staff to deal with it in time and avoid high pressure damaging the pipeline.

[0011] Preferably, a blowing flow meter is installed on the outer circumference of the blowing pipe close to one end of the blowing hood.

[0012] Preferably, a pressure-bearing sleeve is provided on the outside of the blowing pipe, and an inner wall of the blowing pipe is provided on a wear-resistant inner tube.

[0013] Preferably, a protective reinforcement plate is installed on the outer surface of the blow box, and an insulating layer is provided on the inner wall of the blow box.

[0014] By providing an insulating layer inside the blow box, leakage and electric shock can be avoided. By providing a protective reinforcement plate outside the blow box, its pressure and collision resistance can be improved, and the protection of internal devices can be strengthened.

[0015] Preferably, the front of the blow box is arranged on a control panel, a display is mounted on the control panel, and the display is connected to the infrared thermometer.

[0016] Preferably, an inspection plate is installed on the back of the blow box by bolts, a plurality of heat dissipation grids are formed on the inspection plate, and wheels are respectively provided at the four corners of the bottom of the base.

[0017] The inspection panel allows for easy disassembly and maintenance of the interior of the device. The heat dissipation grid improves the heat dissipation effect inside the device. The wheel brakes are provided on the wheels to stop the device, facilitate flexible movement of the device, and maintain stability.

[0018] Beneficial effects:

[0019] The beneficial effects of the technical solution of the utility model are as follows:

[0020] (1) The device is moved to the vicinity of the shell of the electrolytic aluminum cell. The surface temperature of the shell can be monitored by an infrared thermometer. When the temperature is too high, the solenoid valve can be controlled to open the blow pipe and blow air to cool the shell surface. The blow pipe is supplied with air by a high-pressure air source connected to the air supply pipe. The outer surface of the electrolytic cell shell can be blown centrally through the blow hood, which greatly improves the intelligent air supply effect of the entire device and makes it easy to control and operate. At the same time, a refrigerator is also arranged on the blow pipe to convert the blown air into cold air, thereby improving the cooling effect.

[0021] (2) By installing a pressure warning component on the blowpipe, the pipeline air pressure can be monitored through a pressure sensor. When the pressure is abnormal, the alarm can be sounded, which is convenient for the staff to deal with it in time and avoid high pressure damage to the pipeline.

[0022] (3) By setting up an insulating layer inside the blow box, the phenomenon of leakage and electric shock can be avoided. By setting up a protective reinforcement plate outside the blow box, its pressure resistance and anti-collision ability can be improved, and the protection of internal devices can be strengthened. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solution of the implementation mode of the utility model, the drawings required for use in the implementation mode will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the utility model and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other relevant drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 It is a schematic diagram of the overall three-dimensional structure of the circulating air blowing and cooling device for the electrolytic aluminum electrolytic cell of the utility model;

[0025] Figure 2 It is a schematic diagram of the connection structure of the front side of the circulating air blowing and cooling device for electrolytic aluminum electrolytic cell of the utility model;

[0026] Figure 3 This is a schematic diagram of the internal structure of the circulating air blowing and cooling device for the electrolytic aluminum cell of the utility model;

[0027] Figure 4 It is a schematic diagram of the internal structure of the upper air blowing pipe of the circulating air blowing and cooling device for the electrolytic aluminum electrolytic cell of the utility model;

[0028] Figure 5 It is a structural schematic diagram of the back side of the circulating air blowing and cooling device for the electrolytic aluminum electrolytic cell of the utility model.

[0029] In the figure: 1. Blowing box; 2. Base; 3. Blowing hood; 4. Air supply pipe; 5. Control panel; 6. Display; 7. Alarm; 8. Wheel; 9. Infrared thermometer; 10. Blowing pipe; 11. Dust filter; 12. Flow reduction hole; 13. Pressure sensor; 14. Blowing flow meter; 15. Solenoid valve; 16. Refrigerator; 17. Insulation layer; 18. Protection reinforcement plate; 19. Pressure casing; 20. Wear-resistant inner tube; 21. Inspection plate; 22. Heat dissipation grid. DETAILED DESCRIPTION

[0030] In order to make the purpose, technical solutions and advantages of the embodiments of the utility model clearer, the technical solutions in the embodiments of the utility model will be clearly and completely described below in conjunction with the drawings in the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Therefore, the following detailed description of the embodiments of the utility model provided in the drawings is not intended to limit the scope of the utility model for which protection is sought, but merely represents the selected embodiments of the utility model. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without making creative work are within the scope of protection of the utility model.

[0031] This embodiment moves the device to the vicinity of the shell of the electrolytic aluminum cell, and can monitor the shell surface temperature through an infrared thermometer. When the temperature is too high, the solenoid valve can be controlled to open the blowing pipe and blow air to cool the shell surface. The blowing pipe is supplied with air by a high-pressure air source connected to the air supply pipe, and the outer surface of the electrolytic cell shell can be blown centrally through the blowing hood, which greatly improves the intelligent air supply effect of the entire device and makes it easy to control and operate. At the same time, a refrigerator is also provided on the blowing pipe to convert the blown air into cold air, thereby improving the cooling effect. The specific implementation is as follows:

[0032] like Figures 1 to 5 As shown, a circulating air blowing and cooling device for an electrolytic aluminum reduction cell comprises a blowing box 1, a base 2 and an intelligent air supply component. The blowing box 1 is installed on the base 2, and the intelligent air supply component is installed in the blowing box 1. The intelligent air supply component comprises an infrared thermometer 9, a blowing pipe 10 and a solenoid valve 15. The blowing pipe 10 is arranged in the middle of the inner side of the blowing box 1, and the two ends of the blowing pipe 10 are connected to the middle of the two sides of the blowing box 1 respectively, and the blowing hood 3 and the air supply pipe 4 are connected. The middle of the blowing pipe 10 is installed with a solenoid valve 15, and a refrigerator 16 is arranged next to the solenoid valve 15. The infrared thermometer 9 is installed on the side wall of the blowing box 1 at a position directly above the blowing box 1. The device is moved to the vicinity of the shell of the electrolytic aluminum reduction cell. The surface temperature of the shell can be monitored by the infrared thermometer 9. When the temperature is too high, the solenoid valve 15 can be controlled to open the blowing pipe 10 and blow air to cool the surface of the shell. The blowing pipe 10 is supplied with air by an external high-pressure air source connected to the air supply pipe 4. The outer surface of the electrolytic cell shell can be blown centrally through the blowing hood 3, which greatly improves the intelligent air supply effect of the entire device and makes it easy to control and operate. At the same time, a refrigerator 16 is also arranged on the blowing pipe 10, which can convert the blown air into cold air, thereby improving the cooling effect. The refrigerator 16 is a common semiconductor refrigerator in the prior art, which can cool the wind to form cold air.

[0033] The infrared thermometer 9 is installed on the blowing box 1 through a supporting plate, and the emission port of the infrared thermometer 9 is parallel to the blowing direction of the blowing pipe 10. The infrared thermometer 9 is electrically connected to the solenoid valve 15. The infrared thermometer 9 is a common structure and can identify the surface temperature of the electrolytic cell shell through the principle of infrared temperature measurement. When the temperature is too high, the solenoid valve 15 can be controlled to start, and the solenoid valve 15 will not be started when the temperature is normal.

[0034] A connecting flange is arranged on the air supply pipe 4, and the air supply pipe 4 is externally connected to a high-pressure air source. Through the air supply pipe 4, the external air source pipeline can be connected through the connecting flange, and the tightness of the connection is enhanced.

[0035] A plurality of flow reducing holes 12 are formed inside the blowing hood 3 near the blowing pipe 10, and a dustproof filter 11 is installed on the outside of the blowing hood 3. The flow reducing holes 12 can reduce the blowing intensity to avoid a large impact on the tank shell and affect the electrolytic cell. The dustproof filter 11 can improve the dustproof effect of the outside of the blowing hood 3 to avoid impurities from entering the blowing pipe 10.

[0036] The blow pipe 10 and the blow box 1 are provided with a pressure warning assembly, which includes an alarm 7 and a pressure sensor 13. The alarm 7 is installed on the front of the blow box 1, and the pressure sensor 13 is installed on the blow pipe 10 and is electrically connected to the alarm 7. By providing the pressure warning assembly on the blow pipe 10, the pipeline air pressure can be monitored through the pressure sensor 13. When the pressure is abnormal, the alarm 7 can sound an alarm, which is convenient for the staff to handle in time and avoid high pressure damaging the pipeline. The detection end of the pressure sensor 13 is provided on the inner wall of the blow pipe 10.

[0037] A blowing flow meter 14 is installed on the outer circumference of the blowing pipe 10 near one end of the blowing cover 3. The blowing flow meter 14 can detect and record the blowing air volume, which is convenient for staff to check and manage.

[0038] A pressure-bearing sleeve 19 is arranged outside the blowing pipe 10, and the inner wall of the blowing pipe 10 is arranged on a wear-resistant inner tube 20. The pressure-bearing sleeve 19 can improve the rolling pressure-bearing capacity, and the wear-resistant inner tube 20 can improve the wear resistance of the inner wall of the pipeline.

[0039] The outer surface of the blow box 1 is provided with a protective reinforcement plate 18, and the inner wall of the blow box 1 is provided with an insulating layer 17. The insulating layer 17 provided inside the blow box 1 can avoid the phenomenon of electric shock caused by leakage, and the protective reinforcement plate 18 provided outside the blow box 1 can improve its pressure resistance and collision resistance, and strengthen the protection of internal devices. The insulating layer 17 is made of epoxy resin insulating material.

[0040] The front of the blow box 1 is provided with a control panel 5, on which a display 6 is mounted, which is connected to an infrared thermometer 9. The control panel 5 can be connected to the internal electronic components of the device for manual control, and the display 6 can also be connected to a pressure sensor 13 and a blow flow meter 14, so as to display data such as temperature, air pressure, and flow, thereby greatly improving the convenience of using the device.

[0041] An access panel 21 is bolted to the back of the blow box 1, and a plurality of heat dissipation grids 22 are formed on the access panel 21. Wheels 8 are respectively provided at the four corners of the bottom of the base 2. The access panel 21 facilitates the maintenance of the inside of the device after disassembly, and the heat dissipation grids 22 improve the heat dissipation effect inside the device. Wheel brakes are provided on the wheels 8 to stop the device, facilitate flexible movement of the device, and maintain stability.

[0042] Working principle: Move the device to the vicinity of the shell of the electrolytic aluminum electrolytic cell, and the electrolytic cell can be cooled by blowing air through the intelligent air supply component. First, the surface temperature of the shell is monitored by an infrared thermometer. When the temperature is too high, the solenoid valve can be controlled to open the blowing pipe and blow air to cool the surface of the shell. The blowing pipe is supplied with air by a high-pressure air source connected to the air supply pipe. The outer surface of the electrolytic cell shell can be blown centrally through the blowing hood, which greatly improves the intelligent air supply effect of the entire device and makes it easy to control and operate. At the same time, a refrigerator is also provided on the blowing pipe, which can convert the blown air into cold air, thereby improving the cooling effect. By providing a pressure warning component on the blowing pipe, the pipeline air pressure can be monitored by a pressure sensor. When the pressure is abnormal, the alarm can be sounded by the alarm, which is convenient for the staff to deal with it in time and avoid high pressure damage to the pipeline. By providing an insulating layer inside the blowing box, leakage and electric shock can be avoided. By providing a protective reinforcement plate outside the blowing box, its pressure resistance and anti-collision ability can be improved, and the protection of internal devices can be strengthened.

[0043] The above description is only the preferred implementation of the utility model, and is not intended to limit the utility model. For those skilled in the art, the utility model can have various modifications and changes. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A circulating air blowing and cooling device for an electrolytic aluminum reduction cell, characterized in that: The invention comprises a blowing box (1), a base (2) and an intelligent air supply component, wherein the blowing box (1) is installed on the base (2), the intelligent air supply component is installed in the blowing box (1), the intelligent air supply component comprises an infrared thermometer (9), a blowing pipe (10) and a solenoid valve (15), the blowing pipe (10) is arranged in the middle of the inner side of the blowing box (1), the two ends of the blowing pipe (10) are connected to the middle of the two sides of the blowing box (1) and are respectively connected to a blowing cover (3) and an air supply pipe (4), the middle of the blowing pipe (10) is installed with a solenoid valve (15), a refrigerator (16) is arranged at a position beside the solenoid valve (15), the infrared thermometer (9) is installed on the side wall of the blowing box (1) and is located at the side of the blowing box (1). 1) directly above the blow box (1); a pressure warning component is arranged on the blow pipe (10) and the blow box (1), and the pressure warning component includes an alarm (7) and a pressure sensor (13), the alarm (7) is installed on the front of the blow box (1), and the pressure sensor (13) is installed on the blow pipe (10) and is electrically connected to the alarm (7); a protective reinforcement plate (18) is installed on the outer surface of the blow box (1), an insulating layer (17) is provided on the inner wall of the blow box (1), an inspection plate (21) is installed on the back of the blow box (1) by bolts, and a plurality of heat dissipation grilles (22) are formed on the inspection plate (21), and wheels (8) are respectively provided at the four corners of the bottom of the base (2).

2. The circulating air blowing and cooling device for an electrolytic aluminum cell according to claim 1, characterized in that: The infrared thermometer (9) is installed on the blowing box (1) through a support plate, and the emission port of the infrared thermometer (9) is parallel to the blowing direction of the blowing pipe (10), and the infrared thermometer (9) is electrically connected to the solenoid valve (15).

3. The circulating air blowing and cooling device for an electrolytic aluminum cell according to claim 1, characterized in that: The air supply pipe (4) is provided with a connecting flange, and the air supply pipe (4) is externally connected to a high-pressure air source.

4. The circulating air blowing and cooling device for an electrolytic aluminum cell according to claim 1, characterized in that: A plurality of flow reduction holes (12) are formed inside the blowing hood (3) near the blowing pipe (10), and a dustproof filter (11) is installed on the outside of the blowing hood (3).

5. The circulating air blowing and cooling device for an electrolytic aluminum reduction cell according to claim 1, characterized in that: A blowing flow meter (14) is installed on the outer circumference of the blowing pipe (10) at one end close to the blowing cover (3).

6. The circulating air blowing and cooling device for an electrolytic aluminum reduction cell according to claim 1, characterized in that: The outside of the blowing pipe (10) is provided with a pressure-bearing sleeve (19), and the inner wall of the blowing pipe (10) is provided with a wear-resistant inner pipe (20).

7. The circulating air blowing and cooling device for an electrolytic aluminum cell according to claim 1, characterized in that: The front of the blowing box (1) is provided with a control panel (5), a display (6) is installed on the control panel (5), and the display (6) is connected to the infrared thermometer (9).