Energy-saving hot shear furnace

By setting up heat recovery components and circulating fans in the circulation chamber in the heat shear furnace, the problem that existing heat shear furnaces cannot recover heat energy is solved, efficient heat recovery and stable heating effect are achieved, and energy consumption is reduced.

CN222617614UActive Publication Date: 2025-03-14HUBEI XINLIN ENERGY SAVING EQUIPMENT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421372157.2
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-06-17
Publication Date
2025-03-14
Estimated Expiration
2034-06-17

AI Technical Summary

Technical Problem

The existing heat shear furnace cannot effectively recover heat energy during use, resulting in high energy consumption of the heating furnace and affecting energy conservation and environmental protection.

Method used

An energy-saving heat shear furnace is designed, which can connect heat energy to the heating chamber and the discharge chamber by setting up a heat recovery component to realize heat recovery, and the internal circulation of air in the heating chamber is realized through the circulation fan in the circulation chamber to stabilize the heating temperature.

Benefits of technology

It effectively realizes heat energy recovery, reduces heating time and energy loss, ensures the stability of heating effect, and reduces energy consumption.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222617614U_ABST
    Figure CN222617614U_ABST
Patent Text Reader

Abstract

The utility model relates to an energy-saving hot shearing furnace which comprises a supporting frame, a plurality of heating bins are arranged on the supporting frame, heating rollers are arranged in the heating bins and used for heating metal, a circulating bin is arranged on the left side of each heating bin, and a discharging bin is arranged on the right side of each heating bin. According to the energy-saving hot shear furnace, the heat recovery assembly is arranged and keeps communicating with the discharging bin and the preheating bin, so that the effect of recovering heat energy can be effectively achieved in the using process of the energy-saving hot shear furnace, and therefore it is guaranteed that when metal needing to be heated enters the heating bin, the metal has a certain temperature; therefore, when the metal is heated by the heating roller, the metal can be quickly heated to the required temperature, the heating time is shortened, and the energy loss is reduced. And by arranging the circulating bin, the internal circulation effect of air in the heating bin can be achieved in the using process, and it is effectively guaranteed that the internal temperature of the heating bin can be more stable.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of hot shear furnaces, in particular to an energy-saving hot shear furnace. Background Art

[0002] Hot shear furnaces mainly include heating furnaces and hot shears. The heating furnaces are mainly used to heat long rod-shaped metals, and the hot shears shear the heated metals into specific lengths. Hot shear furnaces are usually divided into two types: single-rod hot shear furnaces and multi-rod hot shear furnaces. They may differ slightly in structure and function, but their basic working principles are similar.

[0003] The existing hot shear furnace usually does not have the effect of heat recovery during use. When the flue gas is discharged from the heating furnace, it will carry a lot of heat, causing heat loss in the heating furnace, thereby increasing the energy consumption of the heating furnace, which is not conducive to the energy saving and environmental protection of the heating furnace. Therefore, an energy-saving hot shear furnace is proposed to solve the above problems. Utility Model Content

[0004] In view of the deficiencies in the prior art, the utility model provides an energy-saving hot shear furnace, which has the advantages of being able to recover heat energy, etc., and solves the problem of high energy consumption of traditional devices.

[0005] To achieve the above object, the utility model provides the following technical solutions: an energy-saving hot shear furnace, comprising a support frame, a plurality of heating chambers are arranged on the support frame, a heating roller is arranged in the heating chamber, the heating roller is used to heat the metal, a circulation chamber is arranged on the left side of the heating chamber, and a discharge chamber is arranged on the right side of the heating chamber;

[0006] The top of the circulation bin is connected with a connecting pipe, the other end of the connecting pipe is fixedly connected with a heat recovery component, the heat recovery component is connected with the connecting pipe, a preheating bin is provided at the bottom of the heat recovery component, the preheating bin is connected with the heat recovery component, the right side of the preheating bin is connected with a feeding port, and a sealing door is provided on the feeding port.

[0007] Furthermore, a circulation fan is arranged on the top of the circulation bin, and a plurality of air outlets are arranged on the circulation bin.

[0008] Furthermore, a feed port is provided on the discharge bin, a transmission belt is provided in the feed port, and the other end of the transmission belt extends into the feed port.

[0009] Furthermore, a heat recovery bin is provided on the heat recovery component, and the heat recovery bin is connected to the connecting pipe.

[0010] Furthermore, a connecting cover is provided at the bottom of the heat recovery bin, and the connecting cover is connected with the preheating bin.

[0011] Furthermore, an exhaust fan is provided in the heat recovery bin.

[0012] Compared with the prior art, the technical solution of this application has the following beneficial effects:

[0013] 1. The energy-saving hot shear furnace is provided with a heat recovery component and connected with the discharge bin and the preheating bin, so that the heat energy can be effectively recovered during use, thereby ensuring that the metal to be heated has a certain temperature when it enters the heating bin, so that when the heating roller heats it, the metal can be quickly heated to the required temperature, reducing the heating time and reducing the energy loss.

[0014] 2. This energy-saving hot shear furnace is equipped with a circulation chamber so that the air in the heating chamber can achieve the effect of internal circulation during use, effectively ensuring that the temperature inside the heating chamber can be more stable, avoiding the situation where the temperature of each area inside the heating chamber is inconsistent and the metal is heated unevenly, and effectively ensuring its heating effect. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a schematic diagram of the structure of the utility model;

[0016] Figure 2 This is a schematic diagram of the discharge bin structure of the utility model;

[0017] Figure 3 This is a schematic diagram of the structure of the circulation bin of the utility model;

[0018] Figure 4 This is a schematic diagram of the structure of the heat recovery component of the utility model.

[0019] In the figure: 1. support frame; 11. heating chamber; 111. heating roller; 12. circulation chamber; 121. circulation fan; 122. air outlet; 13. discharge chamber; 131. feed port; 132. conveyor belt; 133. negative pressure fan; 15. connecting pipe; 16. preheating chamber; 17. feeding port; 18. sealing door; 2. heat recovery component; 21. heat recovery chamber; 22. exhaust fan; 23. connecting hood. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] Embodiment 1:

[0022] See also Figure 1 An energy-saving hot shear furnace in this embodiment includes a support frame 1, on which a plurality of heating chambers 11 are arranged, and a heating roller 111 is arranged in the heating chamber 11, and the heating roller 111 is used to heat the metal. A circulation chamber 12 is arranged on the left side of the heating chamber 11, and a circulation chamber 12 is arranged on the right side of the heating chamber 11; by arranging the heating roller 111 in the heating chamber 11, the heating effect of the inside of the heating chamber 11 can be effectively achieved during the use, so that the metal inside the heating chamber 11 can be heated to ensure its use effect.

[0023] The top of the circulation bin 12 is connected with a connecting pipe 15, the other end of the connecting pipe 15 is fixedly connected with the heat recovery component 2, the heat recovery component 2 is connected with the connecting pipe 15, the bottom of the heat recovery component 2 is provided with a preheating bin 16, the preheating bin 16 is connected with the heat recovery component 2, the right side of the preheating bin 16 is connected with a feeding port 17, and the feeding port 17 is provided with a sealing door 18. This connection method can effectively achieve the effect of heat recovery during use.

[0024] As a preferred technical solution in this embodiment, in actual use, the staff can first control the exhaust bin 13 to discharge the flue gas required to be discharged in the heating bin 11 into the heat recovery component 2 through the connecting pipe 15, and then enter the preheating bin 16 under the action of the heat recovery component 2. Since the preheating bin 16 and the feeding port 17 remain connected, the exhausted flue gas can effectively increase the temperature in the feeding port 17 and the preheating bin 16. When a batch of metals is being heated, the staff can put another batch of metals into the feeding port 17 and the preheating bin 16 to preheat them. This arrangement can effectively achieve the effect of recovering heat energy during use, thereby ensuring that the metal to be heated has a certain stability when it enters the heating bin 11, so that when the heating roller 111 heats it, the metal can be heated to the required temperature quickly, reducing the heating time and reducing energy loss.

[0025] Embodiment 2:

[0026] See also Figure 2-4In order to achieve the effect of preheating the metal, a circulating fan 121 is provided on the top of the circulation bin 12 in this embodiment, and a plurality of air outlets 122 are provided on the circulation bin 12. A feed port 131 is provided on the discharge bin 13, and a transmission belt 132 is provided in the feed port 131, and the other end of the transmission belt 132 extends into the feeding port 17. A heat recovery bin 21 is provided on the heat recovery component 2, and the heat recovery bin 21 is connected to the connecting pipe 15. A connecting cover 23 is provided at the bottom of the heat recovery bin 21, and the connecting cover 23 is connected to the preheating bin 16. An exhaust fan 22 is provided in the heat recovery bin 21. By providing the exhaust fan 22, it can effectively realize the effect of preheating the metal to be heated by sending the flue gas into the preheating bin 16 and the feeding port 17 during use. Further, in the actual use process, the staff can set an activated carbon filter in the heat recovery bin 21 to achieve the effect of absorbing particulate matter and harmful gases in the flue gas.

[0027] It is worth noting that the exhaust fan 22 in this embodiment should be made of high temperature resistant materials, such as metal, to avoid damage due to high temperature during use.

[0028] As a preferred technical solution in this embodiment, in actual use, the staff can control the negative pressure fan 133 to generate negative pressure, so that the smoke required to be discharged from the heating chamber 11 can be drawn into the discharge chamber 13, and then the staff can control the exhaust fan 22 to drive the smoke in the circulation chamber 12 to flow into the heat recovery chamber 21, and then enter the preheating chamber 16 and the feeding port 17 through the connecting hood 23 to achieve the effect of preheating the metal.

[0029] The working principle of the above embodiment is:

[0030] 1. The staff can first control the negative pressure fan 133 to generate negative pressure, so that it can draw the smoke required to be discharged from the heating chamber 11 into the discharge chamber 13, and then the staff can control the exhaust fan 22 to drive the smoke in the circulation chamber 12 to circulate in the heat recovery chamber 21, and then enter the preheating chamber 16 through the connecting cover 23. Because the preheating chamber 16 and the feeding port 17 are connected, the discharged smoke can effectively increase the temperature in the feeding port 17 and the preheating chamber 16. When a batch of metals is being heated, the staff can put another batch of metals into the feeding port 17 and the preheating chamber 16 to preheat them. This arrangement can effectively achieve the effect of recovering heat energy during use, thereby ensuring that when the metal to be heated enters the heating chamber 11, it has a certain stability, so that when the heating roller 111 heats it, it can quickly heat the metal to the required temperature, reducing the heating time and reducing the energy loss.

[0031] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. An energy-saving hot shear furnace, comprising a support frame (1), characterized in that: A plurality of heating chambers (11) are arranged on the support frame (1), a heating roller (111) is arranged in the heating chamber (11), and the heating roller (111) is used to heat the metal, a circulation chamber (12) is arranged on the left side of the heating chamber (11), and a discharge chamber (13) is arranged on the right side of the heating chamber (11); The top of the circulation bin (12) is connected to a connecting pipe (15), the other end of the connecting pipe (15) is fixedly connected to a heat recovery component (2), the heat recovery component (2) and the connecting pipe (15) are kept in communication, a preheating bin (16) is arranged at the bottom of the heat recovery component (2), the preheating bin (16) and the heat recovery component (2) are kept in communication, the right side of the preheating bin (16) is connected to a feeding port (17), and a sealing door (18) is arranged on the feeding port (17).

2. The energy-saving hot shear furnace according to claim 1, characterized in that: A circulation fan (121) is arranged on the top of the circulation bin (12), and a plurality of air outlets (122) are arranged on the circulation bin (12).

3. The energy-saving hot shear furnace according to claim 1, characterized in that: The discharge bin (13) is provided with a feed port (131), a transmission belt (132) is arranged in the feed port (131), and the other end of the transmission belt (132) extends into the feed port (17).

4. The energy-saving hot shear furnace according to claim 1, characterized in that: The heat recovery component (2) is provided with a heat recovery bin (21), and the heat recovery bin (21) is connected to the connecting pipe (15).

5. The energy-saving hot shear furnace according to claim 4, characterized in that: A connecting cover (23) is provided at the bottom of the heat recovery bin (21), and the connecting cover (23) is connected to the preheating bin (16).

6. The energy-saving hot shear furnace according to claim 5, characterized in that: An exhaust fan (22) is arranged in the heat recovery bin (21).