Intelligent construction site monitoring and management method

A technology of intelligent monitoring and management methods, applied in the field of electronic information, can solve problems such as dust and noise easily exceeding the standard, replacement of project managers, chaotic management of dump trucks by project managers, etc., and achieve the effect of convenient use and centralized monitoring and management

Inactive Publication Date: 2013-09-18
GUANGDONG NEW VISION INFO TECH
View PDF5 Cites 11 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0002] During construction, in order to ensure the safety of each project, each project is equipped with a special project manager with professional qualifications. During the construction, the dump trucks on the construction site and the sealing of the dump trucks are relatively tight. Strict requirements. In the existing technology, the management of project managers and dump trucks on the construction site is relatively chaotic, and project managers often replace each other. Moreover, the dump trucks are not filled with mud, and the license plates of dump trucks are easily covered. In addition, On the construction site, there are likely to be potential safety hazards during construction, and dust noise is likely to exceed the standard and affect nearby residents.

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • Intelligent construction site monitoring and management method

Examples

Experimental program
Comparison scheme
Effect test

Embodiment Construction

[0014] The present invention will be described in detail below in conjunction with the accompanying drawings and specific embodiments.

[0015] Such as figure 1 As shown, this embodiment provides a method for intelligent monitoring and management of construction sites. The intelligent monitoring and management method for construction sites is applied to the monitoring of building construction sites, and can monitor the construction video of the construction site, the amount of dust and noise during construction, and provide guidance to responsible persons. The project manager of the construction and the dump truck carrying the mud carry out centralized management, timely discover potential safety hazards, and ensure that the construction complies with relevant regulations and proceeds safely.

[0016] The construction site intelligent monitoring and management method includes the following steps: Firstly, the first step A is performed: the project manager identity data and the...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

PUM

No PUM Login to view more

Abstract

The invention discloses an intelligent construction site monitoring and management method. The method includes: setting alarm standard data by pre-storing construction site project manager identity data and plate number data of dump trucks, collecting the plate number data of dump trucks entering a construction site and the identity data of a project manager entering the construction site, collecting video data, noise data, dust data and dump truck mud carrying airtightness data of the construction site, and using preset manners to give out alarm. By the method, construction videos and construction dust and noise can be monitored intelligently, the project manage in charge of construction guidance and the dump trucks for carrying mud can be managed in a centralized manner, abnormality can be discovered and alarmed timely, construction at the construction site can be performed safely and smoothly, and monitoring and management are centralized, intelligent and convenient.

Description

technical field [0001] The invention relates to electronic information technology, in particular to an intelligent monitoring and management method for a construction site. Background technique [0002] During construction, in order to ensure the safety of each project, each project is equipped with a special project manager with professional qualifications. During the construction, the dump trucks on the construction site and the sealing of the dump trucks are relatively tight. Strict requirements. In the existing technology, the management of project managers and dump trucks on the construction site is relatively chaotic, and project managers often replace each other. Moreover, the dump trucks are not filled with mud, and the license plates of dump trucks are easily covered. In addition, On the construction site, there are likely to be potential safety hazards during construction, and dust noise is likely to exceed the standard and affect nearby residents. [0003] Theref...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to view more

Application Information

Patent Timeline
no application Login to view more
Patent Type & Authority Applications(China)
IPC IPC(8): H04N7/18H04L29/08G08B21/18
Inventor 李航杜胜堂
Owner GUANGDONG NEW VISION INFO TECH
Who we serve
  • R&D Engineer
  • R&D Manager
  • IP Professional
Why Eureka
  • Industry Leading Data Capabilities
  • Powerful AI technology
  • Patent DNA Extraction
Social media
Try Eureka
PatSnap group products