Coal Mine High Pressure Filling Pipeline Current Limiting Device
A technology for filling pipelines and flow restricting devices, applied in the directions of fillings, safety devices, pipe components, etc., can solve the problems of reduced resistance of filling slurry, damage to risers, hidden safety hazards, etc., to reduce wear, save costs, and improve safety. Guaranteed effect
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment 1
[0017] After the length of the filling main line is shortened to 400m, it is detected that the flow velocity of the filling slurry reaches 1.5m / s; a flow limiter 1 is added on the horizontal pipe between the standpipe 5 and the valve 2, the total length is 1980mm, and the surfacing welding resistance The thickness of the abrasive layer is 4mm, the inner diameter of the restrictor 6 is gradually reduced from 179mm to 95mm, and the inner diameter of the opening 9 is 179mm. The filling slurry initially sets after 240 minutes after entering the filling area. The height of the filling slurry 8 in the standpipe 5 remained constant after 180m, and the pipeline was transported stably within 30 days, without shut-off vibration and pipeline blockage.
Embodiment 2
[0019] After the length of the filling main line is shortened to 350m, it is detected that the flow velocity of the filling slurry reaches 1.6m / s; a flow restrictor 1 is added on the horizontal pipe between the standpipe 5 and the valve 2, the total length is 2200mm, and the flow restrictor The thickness of the surfacing wear-resistant layer on the inner wall is 5mm, the length of the restrictor is 2000mm, the inner diameter of the restrictor is gradually reduced from 195mm to 100mm, the length of the opening is 200mm, and the inner diameter is 195mm. The filling slurry initially sets after 240 minutes after entering the filling area. The height of the filling slurry 8 in the standpipe 5 remained constant after 200m, and the pipeline was transported stably within 30 days, without shut-off vibration and pipeline blockage.
Embodiment 3
[0021] After the length of the filling main line is shortened to 250m, it is detected that the flow velocity of the filling slurry reaches 1.8m / s; a flow limiter 1 is added on the horizontal pipe between the standpipe 5 and the valve 2, the total length is 2750mm, and the surfacing welding resistance The thickness of the abrasive layer is 7 mm, the inner diameter of the restrictor 6 is gradually reduced from 195 mm to 100 mm, and the inner diameter of the opening 9 is 195 mm. The filling slurry initially sets after 240 minutes after entering the filling area. The height of the filling slurry 8 in the standpipe 5 remained constant after 200m, and the pipeline was transported stably within 30 days, without shut-off vibration and pipeline blockage.