[0162] Existing cement-soil pile composite foundation, pile body diameter 0.5m, pile spacing 1.5m, square piles, pile length 12m, pile tip enters rock formation 2m, bulk density of soil between piles γ=18kN / m 3 , soil deformation modulus, specific gravity G s =2.7, the water content of soft soil is 40%, the initial void ratio e 1 =0.9, permeability coefficient k=8.6×10 -8 cm / s, compression factor α v =2.5×10 -4 kpa -1 , The embankment load is 120kpa, the soft soil layer is 10m thick, and the information of the plate load test predicts the settlement of the composite foundation after 20 years of operation.
[0163] Table 3 Test data of cement-soil mixing pile plate load test
[0164] load rating
Load / kPa
Time for each level / min
Average settlement / mm
Pile-soil stress ratio / n
Level 1, 2
48
60
1.66
4.5
level 3
72
60
2.74
5.2
Level 4
96
60
3.79
6.3
level 5
120
60
4.37
6.5
...
PUM
Abstract
Description
Claims
Application Information
- R&D Engineer
- R&D Manager
- IP Professional
- Industry Leading Data Capabilities
- Powerful AI technology
- Patent DNA Extraction
Browse by: Latest US Patents, China's latest patents, Technical Efficacy Thesaurus, Application Domain, Technology Topic, Popular Technical Reports.
© 2024 PatSnap. All rights reserved.Legal|Privacy policy|Modern Slavery Act Transparency Statement|Sitemap|About US| Contact US: help@patsnap.com