A construction method and a large-section technology, applied to artificial islands, water conservancy projects, underwater structures, etc., can solve the problems of increasing construction costs, difficulty in ensuring construction quality, and increasing difficulty in pipe jacking construction, so as to reduce project cost and benefit Reasonable force and simple structure
- Summary
- Abstract
- Description
- Claims
- Application Information
AI Technical Summary
Problems solved by technology
Method used
Image
Examples
Embodiment Construction
[0042] The present invention will be further described below in conjunction with accompanying drawing, and the principle of this method is very clear to those skilled in the art. It should be understood that the specific embodiments described here are only used to explain the present invention, not to limit the present invention.
[0043] Such as figure 1 As shown, in the large-section pipe-jacking river-crossing construction method suitable for shallow-covered soil conditions designed by the present invention, the shallow-covered soil thickness is the minimum thickness from the top of the proposed pipe-jacking tunnel to the bottom of the river bed. Described construction method comprises the following steps:
[0044] 1. Construct one working well on the pipe jacking axis on both sides of the river to be crossed, one of which is the originating well and the other is the receiving well.
[0045] 2. If figure 2 As shown in Fig. 1, the temporary cofferdam of stage I is constr...