A construction scheme generation method and device

A construction plan, the technology of the construction party, applied in the direction of instruments, data processing applications, resources, etc., can solve the problem of the operator's life safety not being guaranteed.

Active Publication Date: 2019-06-18
北京拓疆者智能科技有限公司
View PDF12 Cites 2 Cited by
  • Summary
  • Abstract
  • Description
  • Claims
  • Application Information

AI Technical Summary

Problems solved by technology

[0003] This application provides a method and device for generating a construction plan to improve the problem that the life safety of operators of construction machinery equipment cannot be guaranteed

Method used

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
View more

Image

Smart Image Click on the blue labels to locate them in the text.
Viewing Examples
Smart Image
  • A construction scheme generation method and device
  • A construction scheme generation method and device
  • A construction scheme generation method and device

Examples

Experimental program
Comparison scheme
Effect test

no. 1 example

[0038] The following details are based on figure 1 For the generation method of the construction plan of the construction system, please refer to image 3 , image 3 It is a flow chart of a method for generating a construction scheme provided in an embodiment of the present application. The method for generating a construction scheme includes the following steps:

[0039] Step S210: the client of the assignment party sends the construction target to the client of the construction party.

[0040] Exemplarily, the construction target sent by the task assigner client to the construction party client may be determined in advance by the task assigner client based on construction demand information and other content, or may be stored in advance in the task assigner client. Among them, the construction demand information can include the construction completion effect required by the client, the acceptance time required by the client, etc. Correspondingly, the construction target ca...

no. 2 example

[0105] The following details are based on figure 2 The generation method of the construction scheme of the construction system, the generation method of the construction scheme comprises the following steps:

[0106] Step S250: the client of the task allocator sends the construction target to the server.

[0107] Step S260: The server receives the construction target.

[0108] Step S270: the server sends the construction target to the client of the construction party.

[0109] Exemplarily, the client of the task allocator first sends the construction target to the server, and the server can immediately send the construction target to the client of the construction party according to demand, or store the construction target and send it when needed.

[0110] It should be noted that the server may receive and send the construction target in various ways, including wireless transmission and wired transmission. For example, wireless transmission methods such as Wifi and Bluetoo...

no. 3 example

[0146] The embodiment of this application provides a construction scheme generation device 600, please refer to Figure 10 , Figure 10 It is a structural block diagram of a device for generating a construction scheme provided in the embodiment of the present application. The device 600 for generating the construction plan includes: a first receiving module 610, configured to receive the construction target sent by the server 130 and / or the task assigner client 110, the construction target includes the construction site and construction content; the evaluation module 620, used The construction environment is evaluated according to the construction target, and an evaluation result is obtained; the first determination module 630 is used to determine a construction plan according to the construction target and the evaluation result; wherein, the construction plan includes construction equipment and The refitting plan of the construction equipment is described, and the refitting ...

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

PUM

No PUM Login to View More

Abstract

The invention provides a construction scheme generation method and device. The method comprises the steps of receiving a construction target sent by a server and / or a task distributor user side; Assessing the construction environment according to the construction target to obtain an assessment result; Determining a construction scheme according to the construction target and the evaluation result;Wherein the construction scheme comprises construction equipment and a refitting scheme for the construction equipment, and the refitting scheme comprises construction unmanned refitting. Therefore,the construction party user side evaluates the construction environment after receiving the construction target, determines the construction scheme according to the evaluation result, performs construction unmanned modification on the construction equipment according to the modification scheme of the construction equipment in the construction scheme, and constructs by using the modified construction equipment. By means of the method, the technical problem that equipment needs to be operated by an equipment operator during construction in the prior art can be solved, and therefore the safety ofthe equipment operator is guaranteed.

Description

technical field [0001] The present application relates to the technical field of construction management, in particular, to a method and device for generating a construction plan. Background technique [0002] Construction machinery projects are mainly used in mines, urban construction, farms and other scenarios. The current working process of construction machinery projects is roughly that the task assignor gets an implementation task and recruits construction machinery equipment operators in the form of recruitment. The construction machinery equipment operators use leased or self-owned equipment to carry out project implementation. After the implementation is completed, the construction party Accepted, the project is completed. However, in the existing work process, since the operator is required to go to the construction site to operate the construction machinery equipment, the life safety of the construction machinery equipment operator cannot be guaranteed. Contents...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine
Login to View More

Application Information

Patent Timeline
no application Login to View More
Patent Type & Authority Applications(China)
IPC IPC(8): G06Q10/06G06Q10/10G06Q50/08
Inventor 张越殷铭隋少龙
Owner 北京拓疆者智能科技有限公司