A bridge cast-in-place concrete anti-collision guardrail formwork construction device and construction method

A technology of anti-collision guardrail and construction device, which is applied in the direction of bridges, bridge construction, erection/assembly of bridges, etc., can solve problems such as low safety, and achieve the effect of eliminating the process of transporting formwork, convenient adjustment of radian, and fast construction.
CN110318339BActive Publication Date: 2021-01-19CHINA FIRST METALLURGICAL GROUP

Patent Information

Authority / Receiving Office
CN Β· China
Patent Type
Patents(China)
Current Assignee / Owner
CHINA FIRST METALLURGICAL GROUP
Publication Date
2021-01-19

Smart Images

  • Figure 1
    Figure 1
  • Figure 2
    Figure 2
  • Figure 3
    Figure 3
Patent Text Reader

Abstract

The invention discloses a bridge cast-in-place concrete anti-collision guardrail formwork construction device and a construction method. The bridge cast-in-place concrete anti-collision guardrail formwork construction device comprises an outer form, an inner form, outer form jacking supports and inner form jacking supports, wherein the outer form is fixed on the outer form jacking supports and canmove up and down along with the outer form jacking supports, the inner form is fixed on the inner form jacking supports and can move up and down along with the inner form jacking supports, the bottomof the inner form and the bottom of the outer form are fixed through opposite-pulling screw rods, the upper end of the inner form and the upper end of the outer form are fixed through pull rods, longitudinal beams are fixed above the inner form jacking supports, transverse beams are fixed to the top ends of the longitudinal beams and extend above the outer form, holes are formed in the transversebeams so as to install limiting pins, the lower ends of the limiting pins are connected with the upper end of the outer form through bolts, and no relative displacement exists in the moving processesof the inner form and the outer form through the limiting pins. According to the bridge cast-in-place concrete anti-collision guardrail formwork construction device and the construction method, the operation is simple and convenient, cooperation of other machinery is not needed, pin shafts between all sections of forms are pulled out, and the jacking supports are used for jacking the forms, the forms can be manually pushed on the inner side of a guardrail, the forms can be moved to the next span of construction, safety and reliability are achieved, and the construction efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

technical field

[0001] The invention relates to the technical field of construction of anti-collision guardrails, in particular to a formwork construction device and construction method for cast-in-place concrete anti-collision guardrails of bridges. Background technique

[0002] In the traditional construction of bridge anti-collision guardrails, the installation and removal of the guardrail formwork requires the use of cranes, but the working radius of the crane is limited, and it needs to be constantly shifted to meet the construction requirements, which greatly reduces the construction efficiency. The connection between the formwork is generally connected by bolts. When installing the connecting bolts of the outer formwork and the tie rods, the operator needs to work in the air outside the guardrail, and the safety is low. Contents of the invention

[0003] Aiming at the deficiencies of the prior art, the purpose of the present invention is to provide an easy-to-operat...

Claims

the structure of the environmentally friendly knitted fabric provided by the present invention; figure 2 Flow chart of the yarn wrapping machine for environmentally friendly knitted fabrics and storage devices; image 3 Is the parameter map of the yarn covering machine