Steel chute for guiding brine of salt pan sandwich clay dam and construction method of steel chute
By designing steel chutes for Yantian, including water-stop, wave-proof, vortex-proof and water-stop, the problems of existing chutes prone to leakage and dam collapse in Yantian environment, and improve the safety and use of chutes and dams Lifespan reduces the risk of erosion and leakage.
Patent Information
- Application Number
- CN202310929721.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2023-07-27
- Publication Date
- 2024-11-15
AI Technical Summary
Existing steel chutes are prone to leakage, dam collapse and dam collapse in salt fields, with short service life and insufficient protection function for dams.
A steel chute for brine guided by brine in the sandwich clay dam in Yantian is designed, including the chute main body, water-stop, wave-proof vortex plate at the import end, water-stop, wave-proof vortex plate at the outlet end and water-stop vortex plate at the water-stop vortex plate at the outlet end, and water-stop vortex plate at the water-stop vortex plate at the water-stop vort The space body, trumpet-shaped water inlet and diffused water outlet, and the water-stop and anti-slip plate are embedded in the clay sandwich of the dam to enhance the stability of the chute and the protection of the dam.
It effectively improves the safety of chutes and dams, reduces the risk of leakage and slippage, reduces the erosion of eddy currents and waves, extends the service life, and simplifies the cleaning of salt knots.
Smart Images

Figure CN118954540A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a liquid material conveying chute, in particular to a steel chute for guiding brine in a salt field sandwich clay dam and a construction method thereof. Background Art
[0002] At present, in the production process of potassium chloride in salt lakes, the supersaturated brine produced enters the next level of salt pans according to the requirements of different components. In the past, the brine was transported between salt pans using reinforced concrete chutes. Due to the long-term corrosion environment of brine, the brine is very easy to crystallize in the concrete cracks of the reinforced concrete chute, resulting in salt expansion. In addition, the compaction degree of the salt pan dam is low, and settlement is common, which makes the reinforced concrete easy to loosen and crack, making the service life of the reinforced concrete chute short. At present, it has been basically eliminated in the production of potassium chloride in salt lakes and replaced by steel chutes.
[0003] The existing steel chute is usually made of steel plate, and is a straight box-shaped body with an open top surface. A buffer tank is set at the outlet end to reduce the impact force of the water flow. Its main disadvantages are: the salt field dam is generally a sandwich dam with salt water filling the periphery and clay filling the dam core. Under the disturbance of the chute water flow, the clay below the chute bottom plate is prone to leakage. The dam with serious leakage will cause salt field pipe burst; the chute is anchored to the dam by its own weight. When the impact force of the water flow is too large and the compaction of the dam is not enough, it is easy to cause the chute to slip; eddy currents are easy to form on both sides of the chute water inlet and outlet, causing scouring of the dam, which is easy to cause dam collapse and collapse; salt field waves on windy days are easy to cause scouring of non-continuous dams on both sides of the chute.
[0004] In recent years, several new steel chutes have appeared one after another, such as the buffer trough for guiding brine in salt pans and its use method disclosed in CN 201810589761.3 on January 4, 2019, which is composed of a bottom plate, a wall plate, a high baffle, a low baffle, a steel ring and a reinforced I-beam welded together. This buffer trough for guiding brine in salt pans is a removable structure, and the amount of brine guided is small. It is a temporary device for short-term use, and the buffer trough itself has a weak protective function for the embankment. Summary of the invention
[0005] The technical problem to be solved by the present invention is to overcome the defects of the prior art that leakage and salt field pipe bursts are prone to occur, which are prone to dam collapse and collapse, and to provide a steel chute for guiding brine in salt field sandwich clay dams, which can improve the safety of the chute and the dam and reduce the safety risks of ore escape, ore leakage and dam collapse.
[0006] A further technical problem to be solved by the present invention is to provide a construction method for the steel chute used for conducting brine in the salt field sandwich clay dam.
[0007] The technical solution adopted by the present invention to solve its technical problems is a steel chute for guiding brine in a salt field sandwich clay dam, comprising a chute body, a water-stopping, wave-proof and vortex-proof plate at the inlet end, a water-stopping, wave-proof and vortex-proof plate at the outlet end, and a water-stopping and anti-slide plate. The chute body is a box-shaped space body with open top surfaces at both ends and hollowed out, and the chute body is divided into a chute inlet section, a chute middle section and a chute outlet section. The chute inlet section is the brine inlet, the chute middle section is a straight-through rectangular box-shaped body, and the chute outlet section is a diffused brine outlet; one end of the water-stopping, wave-proof and vortex-proof plate at the inlet end is connected to the chute inlet section, one end of the water-stopping, wave-proof and vortex-proof plate at the outlet end is connected to the chute outlet section, and the water-stopping and anti-slide plate is connected to the chute middle section.
[0008] Furthermore, the upper end of the water-stopping, wave-proof and vortex-proof plate at the inlet end is flush with the salt pan embankment and is provided with an opening for brine to enter, and the lower end of the water-stopping, wave-proof and vortex-proof plate at the inlet end is inserted into the salt pan embankment; the upper end of the water-stopping, wave-proof and vortex-proof plate at the outlet end is flush with the chute outlet section and is provided with a brine outlet; the lower end of the water-stopping, wave-proof and vortex-proof plate at the outlet end is inserted into the salt pan embankment; the upper end of the water-stopping and anti-slip plate is welded to the bottom plate of the middle section of the chute, and the lower end of the water-stopping and anti-slip plate is inserted into the salt pan embankment until the clay sandwich of the embankment.
[0009] Furthermore, the chute body, the inlet end water-stopping, wave-proof and vortex-proof plate, the outlet end water-stopping, wave-proof and vortex-proof plate and the water-stopping and anti-slip plate are all assembled by welding steel plates.
[0010] The technical solution adopted by the present invention to further solve the technical problem is a construction method for a steel chute for guiding brine in a salt field sandwich clay dam, comprising the following steps: 1) Construction of the chute outlet section: It consists of the bell mouth of the descending section and the horizontally arranged buffer section, both of which are shaped as a space body with openings at both ends and a hollow top surface. The bell mouth and the buffer section are fixed by continuous welding, and the hollow edge of the top surface is reinforced with steel. The bottom plates of the two are made of one or more steel plates welded together continuously, and the wall plates are also made of one or more steel plates welded together continuously, standing symmetrically on both sides of the bottom plate. The chute outlet section and the middle section of the chute are fixed by continuous welding; 2) Construction of the middle section of the chute: It is welded and spliced by multiple steel plates. It is a box-shaped space with two open ends and a hollow top surface. The hollow edges are reinforced with steel sections. The bottom plate is welded and spliced by one or more steel plates. The wall plate is also welded and spliced by one or more steel plates. They are symmetrically placed on both sides of the bottom plate. The middle section of the chute is fixed to the chute outlet section and the chute inlet section by continuous welding. 3) Construction of the chute inlet section: It is welded and spliced by multiple steel plates, in a horizontal trumpet shape, and is a space body with open top surfaces at both ends. The hollow edges are reinforced with steel sections. The bottom plate is welded and spliced by one or more steel plates, and the wall plate is also welded and spliced by one or more steel plates, standing symmetrically on both sides of the bottom plate. The chute inlet section and the middle section of the chute are fixed by continuous welding; 4) Construction of water-stopping, wave-proof and vortex-proof plates at the inlet end: A rectangular flat plate is formed by welding and splicing multiple steel plates. The water-stopping, wave-proof and vortex-proof plates at the inlet end are fixed to the inlet section of the chute by continuous welding; 5) Water-stop anti-slip plate construction: It is made of multiple steel plates welded together to form a rectangular flat plate. The water-stop anti-slip plate is fixed to the middle section of the chute by continuous welding; 6) Construction of water-stopping, wave-proof and vortex-proof plate at the outlet: It is welded and spliced by multiple steel plates into a rectangular flat plate. The water-stopping, wave-proof and vortex-proof plate at the outlet is fixed to the outlet section of the chute by continuous welding.
[0011] The present invention has the following beneficial technical effects: According to the production conditions of potassium chloride in salt lakes, meteorological environment and other factors, as well as the characteristics of the clay core dam in salt fields, the chute of the present invention can be set up without special treatment of the dam, thereby effectively improving the inherent safety of the chute operation and the dam. The chute flow channel is simple and the flow state is smooth, which reduces the phenomenon of brine salting and is also easy to clean after salting. The trumpet-shaped water inlet and the water-stopping wave-proof and vortex-proof plates can effectively reduce the vortex phenomenon, reduce the scouring of the dam on both sides of the water inlet and the part below the bottom plate of the chute, and effectively reduce the scouring of the discontinuous structure of the dam by waves on windy and sea days; it can preliminarily suppress the leakage of the dam; the setting of the water-stopping and anti-slip plates can improve the stability of the chute and reduce the slippage caused by the action of water flow and the settlement of the dam; the diffused water outlet can effectively reduce the erosion of the brine flow on the dam on both sides and the bottom plate of the salt field; the preferred solution is that the water-stopping and anti-slip plates are embedded in the clay core of the dam, which can effectively reduce the leakage of the dam caused by the water level difference. BRIEF DESCRIPTION OF THE DRAWINGS
[0012] Figure 1 It is a structural schematic diagram of an embodiment of a steel chute for guiding brine in a salt field sandwich clay dam according to the present invention; Figure 2 yes Figure 1 Middle AA section view; Figure 3 yes Figure 2 Middle BB section view.
[0013] Description of reference numerals: 1. Chute outlet section; 2. Chute middle section; 3. Chute inlet section; 4. Water-stopping, wave-proof and vortex-proof plate at the inlet end; 5. Water-stopping and anti-slip plate; 6. Water-stopping, wave-proof and vortex-proof plate at the outlet end. DETAILED DESCRIPTION
[0014] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.
[0015] Reference Figure 1 , Figure 2 and Figure 3 This embodiment includes a chute body, a water-stopping wave and vortex-proof plate 4 at the inlet end, a water-stopping wave and vortex-proof plate 6 at the outlet end, and a water-stopping and anti-slide plate 5. The chute body is welded and spliced with multiple steel plates, and the overall shape is a box-like space body with two open ends and a hollow top surface. The hollow edges are reinforced with steel sections. The chute body is divided into three parts: a chute inlet section 3, a chute middle section 2, and a chute outlet section 1. The chute inlet section 3 is trumpet-shaped and is the brine inlet; the chute middle section 2 is a straight-through rectangular box-shaped body; the chute outlet section 1 is diffused and is the brine buffer outlet. The sections are connected by welding.
[0016] The water-stopping, wave-proof and vortex-proof plate 4 at the inlet end is a rectangular plate welded and spliced by multiple steel plates. The upper end is flush with the salt pan dam and is provided with an opening at the brine inlet end. The lower end of the rectangular plate is inserted into the salt pan dam, and the rectangular plate is connected to the chute inlet section 3 by welding.
[0017] The outlet water-stopping, wave-proof and vortex-proof plate 6 is a rectangular plate formed by welding and splicing multiple steel plates. The upper end is flush with the outlet end of the chute and is provided with an opening for the brine outlet end. The lower end of the rectangular plate is inserted into the salt field dam, and the rectangular plate is connected to the chute outlet section 1 by welding.
[0018] The water-stopping and anti-slip plate 5 is a rectangular plate formed by welding and splicing multiple steel plates. The upper end is welded to the bottom plate of the middle section 2 of the chute, and the lower end of the rectangular plate is inserted into the salt pan dam until the clay sandwich of the dam.
[0019] The main construction methods of the chute are as follows: 1) Construction of chute outlet section 1: It consists of the bell mouth of the descending section and the horizontally arranged buffer section, both of which are shaped as a space body with both ends open and the top surface leaking. The bell mouth and the buffer section are fixed by continuous welding, and the edge of the top surface leaking is reinforced with steel. The bottom plates of the two are made of one or more steel plates welded together, and the wall plates are also made of one or more steel plates welded together, standing symmetrically on both sides of the bottom plate. The chute outlet section 1 and the chute middle section 2 are fixed by continuous welding.
[0020] 2) Construction of the middle section 2 of the chute: It is welded and spliced with multiple steel plates. It is in the shape of a box-shaped space with open ends and a hollow top. The hollow edges are reinforced with steel sections. The bottom plate is welded and spliced with one or more steel plates. The wall plate is also welded and spliced with one or more steel plates. They stand symmetrically on both sides of the bottom plate. The middle section 2 of the chute is fixed to the chute outlet section 1 and the chute inlet section 3 by continuous welding.
[0021] 3) Construction of the chute inlet section 3: It is a horizontally arranged trumpet-shaped structure formed by welding and splicing multiple steel plates. It is in the shape of a space body with open ends and a hollow top surface. The hollow edges are reinforced with steel sections. The bottom plate is formed by continuously welding and splicing one or more steel plates, and the wall plate is also formed by continuously welding and splicing one or more steel plates, standing symmetrically on both sides of the bottom plate. The chute inlet section 3 and the chute middle section 2 are fixed by continuous welding.
[0022] 4) Construction of the water-stopping, wave-proof and vortex-proof plate 4 at the inlet end: It is welded and spliced by multiple steel plates to form a rectangular flat plate. The water-stopping, wave-proof and vortex-proof plate 4 at the inlet end is fixed to the inlet section 3 of the chute by continuous welding.
[0023] 5) Construction of water-stop anti-skid plate 5: It is a rectangular flat plate formed by welding and splicing multiple steel plates. The water-stop anti-skid plate 5 is fixed to the middle section 2 of the chute by continuous welding.
[0024] 6) Construction of the outlet end water-stopping, wave-proof and vortex-proof plate 6: It is welded and spliced by multiple steel plates to form a rectangular flat plate. The outlet end water-stopping, wave-proof and vortex-proof plate 6 is fixed to the chute outlet section 1 by continuous welding.
[0025] The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention. Any equivalent changes made based on the structure, shape, and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A steel chute for conducting brine in a salt field sandwich clay dam, characterized in that: The invention comprises a chute body, a water-stopping, wave-proof and vortex-proof plate (4) at the inlet end, a water-stopping, wave-proof and vortex-proof plate (6) at the outlet end, and a water-stopping and anti-slide plate (5). The chute body is a box-shaped space body with two open ends and a hollow top surface, and the chute body is divided into a chute inlet section (3), a chute middle section (2) and a chute outlet section (1). The chute inlet section (3) is the inlet of brine, the chute middle section (2) is a straight-through rectangular box-shaped body, and the chute outlet section (1) is a diffused brine outlet; one end of the water-stopping, wave-proof and vortex-proof plate (4) at the inlet end is connected to the chute inlet section (3), one end of the water-stopping, wave-proof and vortex-proof plate (4) at the inlet end is connected to the chute outlet section (1), and the water-stopping and anti-slide plate (5) is connected to the chute middle section (2).
2. A steel chute for conducting brine in a salt field sandwich clay dam according to claim 1, characterized in that: The upper end of the water-stopping, wave-proof and vortex-proof plate (4) at the inlet end is flush with the salt pan dam and is provided with an opening for brine to enter, and the lower end of the water-stopping, wave-proof and vortex-proof plate (4) at the inlet end is inserted into the salt pan dam; the upper end of the water-stopping, wave-proof and vortex-proof plate (6) at the outlet end is flush with the chute outlet section (1) and is provided with an opening for brine to enter and exit; the lower end of the water-stopping, wave-proof and vortex-proof plate (6) at the outlet end is inserted into the salt pan dam; the upper end of the water-stopping and anti-slip plate (5) is welded to the bottom plate of the middle section (2) of the chute, and the lower end of the water-stopping and anti-slip plate (5) is inserted into the salt pan dam until the clay sandwich of the dam.
3. The steel chute for conducting brine in a salt field sandwich clay dam according to claim 1, characterized in that: The chute body, the inlet end water-stopping wave-proof and vortex-proof plate (4), the outlet end water-stopping wave-proof and vortex-proof plate (6) and the water-stopping and anti-slip plate (5) are all assembled by welding steel plates.
4. A construction method for a steel chute for conducting brine in a salt field sandwich clay dam according to any one of claims 1 to 3, characterized in that: The following steps are involved: 1) Construction of the chute outlet section (1): It consists of a trumpet-shaped outlet of the descending section and a horizontally arranged buffer section, both of which are space bodies with open ends and hollow top surfaces. The trumpet-shaped outlet and the buffer section are fixed by continuous welding, and the hollow edges of the top surface are reinforced with steel sections. The bottom plates of the two are formed by continuous welding and splicing of one or more steel plates, and the wall plates are also formed by continuous welding and splicing of one or more steel plates, standing symmetrically on both sides of the bottom plate. The chute outlet section (1) and the chute middle section (2) are fixed by continuous welding; 2) Construction of the middle section (2) of the chute: It is welded and spliced together with multiple steel plates, and is in the shape of a box-shaped space with two open ends and a hollow top surface. The hollow edges are reinforced with steel sections. The bottom plate is welded and spliced together with one or more steel plates, and the wall plate is also welded and spliced together with one or more steel plates, and is symmetrically placed on both sides of the bottom plate. The middle section (2) of the chute is fixed to the chute outlet section (1) and the chute inlet section (3) by continuous welding. 3) Construction of the chute inlet section (3): It is a horizontally arranged trumpet-shaped structure formed by welding and splicing multiple steel plates. The shape is a space body with two open ends and a hollow top surface. The hollow edges are reinforced with steel sections. The bottom plate is formed by continuous welding and splicing of one or more steel plates. The wall plate is also formed by continuous welding and splicing of one or more steel plates. They are symmetrically placed on both sides of the bottom plate. The chute inlet section (3) and the chute middle section (2) are fixed by continuous welding. 4) Construction of the water-stop wave-proof and vortex-proof plate (4) at the inlet end: a plurality of steel plates are welded and spliced together to form a rectangular flat plate, and the water-stop wave-proof and vortex-proof plate (4) at the inlet end is fixed to the inlet section (3) of the chute by continuous welding; 5) Construction of the water-stop anti-skid plate (5): It is a rectangular flat plate formed by welding and splicing multiple steel plates. The water-stop anti-skid plate (5) is fixed to the middle section of the chute (2) by continuous welding; 6) Construction of the outlet end water-stopping, wave-proof and vortex-proof plate (6): A plurality of steel plates are welded and spliced together to form a rectangular flat plate. The outlet end water-stopping, wave-proof and vortex-proof plate (6) is fixed to the chute outlet section (1) by continuous welding.
Citation Information
Patent Citations
Buffering groove for guiding brine in salt field and use method of buffering groove
CN109133107A