Test device and test method for vertical compressive static load of foundation pile

By designing the pier components and anchor components of the rotary support frame and telescopic rod, the problem of excessive volume of the secondary beam pier is solved, and the stability and transportation convenience of the vertical compression and static load test device of the foundation pile are realized, improving the Test efficiency.

CN119041498APending Publication Date: 2024-11-29ANHUI YUANZHENG ENG TESTING TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411307548.0
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-09-19
Publication Date
2024-11-29

AI Technical Summary

Technical Problem

In the existing foundation pile static load test device, the secondary beam pier is too large, which is inconvenient to use and takes up a lot of space, which affects transportation and operation efficiency.

Method used

A vertical compression-resistant static load test device for foundation piles including a support module and an anchor assembly is designed. The support module forms a pier assembly through a rotating support frame and a telescopic rod, and the anchor assembly and fixture are used to stabilize the support of the secondary beam. The fixture between the support frame and the auxiliary frame increases resistance strength, and the pier assembly can shrink to reduce space occupancy.

Benefits of technology

The stability of the support structure and uniform load transmission are achieved, the inclination phenomenon is avoided, the handling and transportation are facilitated, and the use efficiency of the test device is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119041498A_ABST
    Figure CN119041498A_ABST
Patent Text Reader

Abstract

The invention discloses a foundation pile vertical compression resistance static load test device and method, the device comprises a bearing module and a supporting module, the supporting module comprises two buttress tables used for supporting a main beam and two buttress assemblies used for supporting a plurality of secondary beams, each buttress assembly comprises a supporting plate parallel to the main beam, and the supporting plates are connected with the bearing module. Two supporting frames which deflect in the opposite direction are rotationally connected to the bottom of the supporting plate in an inserted mode, an auxiliary frame which reciprocates in the direction of the supporting frames is arranged on one side of each supporting frame, and a plurality of telescopic rods are arranged between the supporting frames and the auxiliary frames. The supporting frame and the auxiliary frame can be rotationally opened, the pulled-out auxiliary frame and the supporting frame telescopic rod form a buttress assembly which is in an opening state for a supporting column body of the supporting plate, the buttress assembly and the anchoring assembly are used in cooperation to form a buttress to support the secondary beam, the buttress assembly can be contracted when not used, and therefore occupied space is reduced, and use is convenient. And carrying and transportation are facilitated.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of pile foundation static load testing, and in particular relates to a pile foundation vertical compressive static load testing device and a pile foundation vertical compressive static load testing method. Background Art

[0002] The pile static load test is an experiment used in civil engineering to evaluate and verify the bearing capacity of pile foundations. This experiment applies a static load to the pile foundation and observes the deformation and bearing performance of the pile foundation to determine its actual bearing capacity and deformation characteristics. The bearing platform that carries the load block in the experiment consists of a main beam and multiple secondary beams overlapped on the main beam. Before the load block is stacked, the main beam pier and secondary beam pier need to be used to support the main beam and secondary beam to prevent the bearing platform from tipping over.

[0003] In order to facilitate users to operate the jack at the bottom of the bearing platform, the entire bearing platform is set at a higher position, which results in the secondary beam pier supporting the secondary beam being too large. The secondary beam pier is not convenient to carry and occupies more transportation space, which is very inconvenient to use. Summary of the invention

[0004] The present invention aims to solve the problem that the secondary beam pier in the prior art is too large and inconvenient to use, and proposes the following technical solution:

[0005] The pile vertical compressive static load test device includes:

[0006] A load-bearing module, the load-bearing module is used to bear the load block, the load-bearing module comprises a main beam and a plurality of secondary beams overlapped on the main beam;

[0007] A support module, the support module includes two piers for supporting the main beam and two pier assemblies for supporting multiple secondary beams, the pier assemblies are used in conjunction with the anchor assembly, the pier assembly includes a support plate arranged in parallel with the main beam, two support frames deflected towards each other are rotatably plugged at the bottom of the support plate, an auxiliary frame that reciprocates in the direction of the support frame is arranged on one side of the support frame, the top of the auxiliary frame is fitted with the bottom of the support plate, and multiple telescopic rods are arranged between the support frame and the auxiliary frame;

[0008] After the main beam is placed, the external lifting equipment continues to lift the two support plates. After the support plates are parallel to the main beam, the two support frames are deflected to make them perpendicular to the support plates, and the two auxiliary frames are pulled out in the opposite direction to form a support column for the support plate together with the support frames and the telescopic rods. The pier assembly in the open state is used in conjunction with the anchor assembly to form a pier supporting the secondary beam.

[0009] As a preferred embodiment of the above technical solution, it also includes an anchoring assembly, wherein the anchoring module includes two anchor piles located at both ends of the support plate, an anchor plate fixedly connected to the top of the anchor piles, an anchor shoulder fitted with the top of the support plate is arranged on the top of the anchor plate, and a plurality of pull rods are arranged between the anchor shoulder and the anchor piles.

[0010] As a preferred embodiment of the above technical solution, the bottom of the support frame and the auxiliary frame are both provided with fixing parts fixedly connected to the anchor plate, and the fixing parts include two fixing bolts, one end of the fixing bolts is rotatably inserted into the support frame or the auxiliary frame, and a fixing nut is threadedly sleeved on the surface of the fixing bolt, and the fixing nut is rotated to fix the fixing bolt on the anchor pile.

[0011] As a preferred embodiment of the above technical solution, the pier assembly also includes a plurality of fixing hoops for fixing the ends of the secondary beams, and a plurality of installation grooves corresponding to the fixing hoops are provided on the surface of the support plate. One end of the fixing hoop passes through the installation groove and extends to the outside, and an auxiliary nut is sleeved on the end surface of the fixing hoop.

[0012] As a preferred embodiment of the above technical solution, a protrusion is provided at the other end of one of the fixing bolts, and a groove is provided at the other end of the other fixing bolt, and the fixing parts between the support frames and the fixing parts between the auxiliary frames match each other.

[0013] As a preferred embodiment of the above technical solution, an auxiliary bolt is provided at the bottom of the auxiliary frame, one end of the auxiliary bolt rotates through the auxiliary frame and the support frame to extend into the support plate, and the end of the auxiliary bolt is threadedly sleeved with the support plate at the insertion point.

[0014] As a preferred embodiment of the above technical solution, a test module is also included, which includes a jack and a displacement sensor connected to a control center, the jack is located between the main beam and the pile to be tested, and the force axis of the jack is coaxially arranged with the pile to be tested.

[0015] The test method of the pile vertical compressive static load test device comprises the following steps:

[0016] S1, hoisting main beam;

[0017] After placing the jack on the pile to be tested, use external lifting equipment to place two piers on both sides of the jack, and then lift the main beam to place it on the platform formed by the two piers;

[0018] S2. Install the buttress assembly;

[0019] The support plate is hoisted on one side of the main beam and is parallel to the main beam. Then the support frame is rotated and the auxiliary frame is pulled out. The auxiliary frame and the support frame form a supporting column for the support plate. The pier assembly and the anchor assembly are used together to form a pier supporting the secondary beam.

[0020] S3, hoisting secondary beam and load block;

[0021] Multiple secondary beams are overlapped on the main beam in sequence, and both ends of the secondary beams are supported by corresponding pier assemblies, and then multiple load blocks can be stacked;

[0022] S4, static load test;

[0023] The jack is started to move the bearing module and the load block upwards, and the static load test data of the pile to be tested is obtained through the data obtained by the control center.

[0024] The beneficial effects of the present invention are:

[0025] 1. The support frame and auxiliary frame can be rotated and opened. The pulled-out auxiliary frame and the telescopic rod of the support frame form a pier assembly for the support column of the support plate. The pier assembly is in an open state and is used in conjunction with the anchor assembly to form a pier to support the secondary beam. The pier assembly can be retracted when not in use, thereby reducing space occupation and facilitating handling and transportation;

[0026] 2. The fixed hoop can connect and fix the secondary beam to the support plate. The anchor assembly can limit the moving path of the support plate, making the support structure of the support module more stable and the load transfer more uniform, effectively avoiding the overall tilt during the test;

[0027] 3. The support frame and the auxiliary frame can be fixed on the anchor assembly by using the fixing parts, so as to restrict the pier assembly and prevent the support frame and the auxiliary frame from moving during support, making the anchor assembly more stable. At the same time, with the cooperation of the protrusion and the groove, the set fixing parts can connect the support frames and the auxiliary frames, thereby increasing the resistance strength of the support plate and preventing the support plate from being squeezed and deformed. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] Figure 1 What is shown is a schematic diagram of the overall structure of the embodiment;

[0029] Figure 2 Shown is a diagram of the installation position of the buttress assembly in the embodiment;

[0030] Figure 3 What is shown is a diagram of the contracted state of the buttress assembly in the embodiment;

[0031] Figure 4 What is shown is a diagram of the deflection state of the buttress assembly in the embodiment;

[0032] Figure 5 Shown is a diagram of the installation position of the fixing member in the embodiment.

[0033] In the figure: 11, main beam; 12, secondary beam; 20, jack; 31, anchor pile; 32, anchor plate; 33, anchor support; 34, pull rod; 40, pier platform; 50, pier assembly; 51, support plate; 52, support frame; 53, auxiliary frame; 54, telescopic rod; 55, fixing part; 551, fixing bolt; 552, fixing nut; 561, fixing clamp; 562, mounting groove; 563, auxiliary nut; 571, bump; 572, groove; 58, auxiliary bolt; 60, pile to be tested. DETAILED DESCRIPTION

[0034] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clear, the technical solution of the present invention will be clearly and completely described below in conjunction with the embodiments and the accompanying drawings of the specification.

[0035] Example

[0036] Figure 1-Figure 4 The pile vertical compressive static load test device is characterized by comprising:

[0037] A load-bearing module, the load-bearing module is used to bear the load block, the load-bearing module comprises a main beam 11 and a plurality of secondary beams 12 overlapped on the main beam 11;

[0038] A support module, the support module includes two piers 40 for supporting the main beam 11 and two pier assemblies 50 for supporting multiple secondary beams 12, the pier assemblies 50 are used in conjunction with the anchor assembly, the pier assembly 50 includes a support plate 51 arranged parallel to the main beam 11, two support frames 52 deflected towards each other are rotatably plugged at the bottom of the support plate 51, an auxiliary frame 53 is arranged on one side of the support frame 52 and moves back and forth in the direction of the support frame 52, the top of the auxiliary frame 53 is arranged in contact with the bottom of the support plate 51, and multiple telescopic rods 54 are arranged between the support frame 52 and the auxiliary frame 53;

[0039] After the main beam 11 is placed, the external lifting equipment continues to lift the two support plates 51. After the support plates 51 are parallel to the main beam 11, the two support frames 52 are deflected to make them perpendicular to the support plates 51, and the two auxiliary frames 53 are pulled out in the opposite direction to form a support column for the support plate 51 together with the support frames 52 and the telescopic rods 54. The pier assembly 50 in the open state is used in conjunction with the anchor assembly to form a pier supporting the secondary beam 12.

[0040] It also includes a test module, which includes a jack 20 and a displacement sensor connected to the control center. The jack 20 is located between the main beam 11 and the pile 60 to be tested, and the force axis of the jack 20 is coaxially arranged with the pile 60 to be tested. A bearing plate is arranged at the contact point between the top of the jack 20 and the main beam 11 and the contact point between the bottom of the jack 20 and the pile 60 to be tested.

[0041] When testing the pile 60 to be tested, the top of the pile 60 to be tested is first arranged to make it flat, and then the jack 20 is placed on the top of the pile 60 to be tested. After the jack 20 and the displacement sensor are connected to the remote control center using a line, the piers 40 are placed on both sides of the jack 20 to be tested, and the main beam 11 is hoisted by external hoisting equipment to be placed on the platform formed by the two piers 40. After the support plate 51 is hoisted on one side of the main beam 11 and parallel to the main beam 11, the support frame 52 is rotated to make it parallel to the support plate 51. The auxiliary frame 53 is then pulled out to form a supporting column with the supporting frame 52 to support the supporting plate 51. The pier assembly 50 in the open state is used in conjunction with the anchor assembly to form a pier supporting the secondary beam 12. Subsequently, multiple secondary beams 12 are overlapped on the main beam 11 in turn. Both ends of the secondary beam 12 are supported by the corresponding pier assemblies 50. After multiple load blocks are stacked, the jack 20 is started to move the bearing module and the load block upwards. The static load test data of the pile foundation 60 to be tested is obtained through the data obtained by the control center.

[0042] The support frame 52 and the auxiliary frame 53 are rotatably opened, and the pulled-out auxiliary frame 53 and the telescopic rod 54 of the support frame 52 form a support column of the support plate 51. The pier assembly 50 is in an open state and is used in conjunction with the anchor assembly to form a pier to support the secondary beam 12. The pier assembly 50 can be retracted when not in use, thereby reducing space occupancy and facilitating handling and transportation.

[0043] The test method of the pile vertical compressive static load test device comprises the following steps:

[0044] S1, hoisting main beam 11;

[0045] After the jack 20 is placed on the pile 60 to be tested, two supporting piers 40 are placed on both sides of the jack 20 using external lifting equipment, and then the main beam 11 is lifted and placed on the platform formed by the two supporting piers 40;

[0046] S2, installing the buttress assembly 50;

[0047] The support plate 51 is hoisted on one side of the main beam 11 and is parallel to the main beam 11, and then the support frame 52 is rotated and the auxiliary frame 53 is pulled out, and the auxiliary frame 53 and the support frame 52 form a supporting column for the support plate 51, and the pier assembly 50 and the anchor assembly cooperate to form a pier supporting the secondary beam 12;

[0048] S3, hoisting the secondary beam 12 and the load block;

[0049] Multiple secondary beams 12 are overlapped on the main beam 11 in sequence, and both ends of the secondary beams 12 are supported by corresponding pier assemblies 50, and then multiple load blocks can be stacked;

[0050] S4, static load test;

[0051] The jack 20 is started to move the bearing module and the load block upward, and the static load test data of the pile 60 to be tested is obtained through the data obtained by the control center.

[0052] Figure 1-Figure 5 The anchoring module also includes two anchor piles 31 located at both ends of the support plate 51, an anchor plate 32 fixedly connected to the top of the anchor pile 31, an anchor shoulder 33 fitted with the top of the support plate 51 is arranged on the top of the anchor plate 32, and a plurality of pull rods 34 are arranged between the anchor shoulder 33 and the anchor pile 31.

[0053] The bottom of the support frame 52 and the auxiliary frame 53 are both provided with a fixing part 55 fixedly connected to the anchor plate 32, and the fixing part 55 includes two fixing bolts 551, one end of the fixing bolt 551 is rotatably inserted into the support frame 52 or the auxiliary frame 53, and a fixing nut 552 is threadedly sleeved on the surface of the fixing bolt 551. The fixing nut 552 is rotated to fix the fixing bolt 551 on the anchor pile 31.

[0054] The anchor pile 31 is cast in advance before the inspection, and its top is leveled before the inspection to facilitate the installation of the anchor plate 32. The anchor plate 32 is fixed on the anchor pile 31 through the corresponding fixing piece 55 after the main beam 11 is hoisted. Then the tie rod 34 can be fixed above the anchor plate 32. After the tie rod 34 is installed, the pier assembly 50 can be installed. After the support frame 52 is deflected, the corresponding fixing bolt 551 is rotated to make it fit with the bottom of the anchor plate 32, and then the fixing nut 552 is rotated to fit with the top of the anchor plate 32. The installation piece corresponding to the support frame 52 fixes the support frame 52 with the anchor plate 3 2 is fixedly connected, and when pulling out the auxiliary frame 53, the auxiliary frame 53 needs to be pushed beyond the position of the anchor plate 32, and then the fixing bolts 551 can be screwed out. The fixing bolts 551 in the retracted state can avoid being unable to be opened due to the obstruction of the anchor plate 32. After adjusting the position of the fixing bolts 551 corresponding to the auxiliary frame 53, the auxiliary frame 53 is partially pushed back to make the fixing bolts 551 inserted into the anchor plate 32, and then the corresponding fixing parts 55 are operated in the same way to fix the auxiliary frame 53. After the support frame 52 is fixed, the anchor support 33 is installed on the pull rod 34, and the support frame 52 is restricted by the anchor assembly.

[0055] The support frame 52 and the auxiliary frame 53 can be fixed to the anchor assembly by using the fixing member 55, so as to restrict the pier assembly 50, prevent the support frame 52 and the auxiliary frame 53 from moving during support, and make the anchor assembly more stable.

[0056] Figure 1-Figure 4In the figure, the pier assembly 50 also includes a plurality of fixing hoops 561 for fixing the ends of the secondary beams 12, and a plurality of mounting grooves 562 corresponding to the fixing hoops 561 are provided on the surface of the support plate 51. One end of the fixing hoop 561 extends through the mounting groove 562 to the outside, and an auxiliary nut 563 is sleeved on the end surface of the fixing hoop 561.

[0057] After the secondary beam 12 is placed, the fixing hoop 561 is inserted into the support plate 51 from the installation groove 562, and then the fixing hoop 561 is fixed using the auxiliary nut 563 so that the secondary beam 12 and the support plate 51 are fixed together. When the jack 20 lifts the supporting module, the support plate 51 limits the moving path through the pull rod 34 to prevent the supporting module from tilting due to unstable center of gravity.

[0058] The fixed clamp 561 can connect and fix the secondary beam 12 and the support plate 51. The anchor assembly restricts the moving path of the support plate 51, making the support structure of the support module more stable and transferring load more evenly, effectively avoiding the overall tilting during the test.

[0059] Figure 4-Figure 5 In the embodiment, a protrusion 571 is provided at the other end of one of the fixing bolts 551, and a groove 572 is provided at the other end of the other fixing bolt 551. The fixing members 55 between the supporting frames 52 and the fixing members 55 between the auxiliary frames 53 and the auxiliary frames 53 match each other.

[0060] After the support frame 52 has been deflected, the two fixing bolts 551 at opposite positions are rotated to bring them closer together, and the protrusions 571 are then inserted into the corresponding grooves 572 , so that the two support frames 52 are connected through the two fixing members 55 , thereby increasing the resistance strength of the support plate 51 .

[0061] With the cooperation of the protrusion 571 and the groove 572 , the provided fixing member 55 can connect the support frames 52 and the auxiliary frames 53 , thereby increasing the resistance strength of the support plate 51 and preventing the support plate 51 from being squeezed and deformed.

[0062] Figure 5 In the figure, an auxiliary bolt 58 is provided at the bottom of the auxiliary frame 53, one end of the auxiliary bolt 58 rotates through the auxiliary frame 53 and the support frame 52 to extend to the inside of the support plate 51, and the end of the auxiliary bolt 58 is threadedly sleeved with the insertion part of the support plate 51.

[0063] The auxiliary bolts 58 can be used to fit and fix the auxiliary frame 53 and the support frame 52, so that the auxiliary frame 53 can be deflected together with the support frame 52. After the auxiliary bolts 58 are fixed to the support plate 51, the fixing parts 55 between the auxiliary frames 53 can increase the resistance strength of the support plate 51 again to prevent the support plate 51 from being squeezed and deformed.

[0064] The above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them.

Claims

1. The pile vertical compressive static load test device is characterized by: include: A load-bearing module, the load-bearing module is used to bear the load block, the load-bearing module comprises a main beam (11) and a plurality of secondary beams (12) overlapped on the main beam (11); A support module, the support module comprising two pier platforms (40) for supporting a main beam (11) and two pier assemblies (50) for supporting a plurality of secondary beams (12), the pier assemblies (50) being used in conjunction with an anchor assembly, the pier assembly (50) comprising a support plate (51) arranged parallel to the main beam (11), two support frames (52) deflected towards each other being rotatably plugged into the bottom of the support plate (51), an auxiliary frame (53) reciprocating in the direction of the support frame (52) being arranged on one side of the support frame (52), the top of the auxiliary frame (53) being arranged in close contact with the bottom of the support plate (51), and a plurality of telescopic rods (54) being arranged between the support frame (52) and the auxiliary frame (53); After the main beam (11) is placed, the external lifting equipment continues to lift the two support plates (51). After the support plates (51) are parallel to the main beam (11), the two support frames (52) are deflected to be perpendicular to the support plates (51), and the two auxiliary frames (53) are pulled out in the opposite direction to form a support column for the support plate (51) together with the support frames (52) and the telescopic rods (54). The pier assembly (50) in the open state is used in conjunction with the anchor assembly to form a pier supporting the secondary beam (12).

2. The pile vertical compressive static load test device according to claim 1, characterized in that: It also includes an anchoring assembly, wherein the anchoring module includes two anchor piles (31) located at both ends of the support plate (51), an anchor plate (32) fixedly connected to the top of the anchor piles (31), an anchor support (33) in contact with the top of the support plate (51) is arranged on the top of the anchor plate (32), and a plurality of pull rods (34) are arranged between the anchor support (33) and the anchor piles (31).

3. The pile vertical compressive static load test device according to claim 2, characterized in that: The bottom of the support frame (52) and the auxiliary frame (53) are both provided with a fixing member (55) fixedly connected to the anchor plate (32), and the fixing member (55) comprises two fixing bolts (551), one end of each fixing bolt (551) is rotatably inserted into the support frame (52) or the auxiliary frame (53), and a fixing nut (552) is threadedly sleeved on the surface of the fixing bolt (551), and the fixing nut (552) is rotated to fix the fixing bolt (551) on the anchor pile (31).

4. The pile vertical compressive static load test device according to claim 1, characterized in that: The pier assembly (50) further comprises a plurality of fixing hoops (561) for fixing the ends of the secondary beams (12); a plurality of mounting grooves (562) corresponding to the fixing hoops (561) are provided on the surface of the support plate (51); one end of the fixing hoop (561) passes through the mounting groove (562) and extends to the outside; and an auxiliary nut (563) is sleeved on the end surface of the fixing hoop (561).

5. The pile vertical compressive static load test device according to claim 3, characterized in that: A protrusion (571) is provided at the other end of one of the fixing bolts (551), and a groove (572) is provided at the other end of the other fixing bolt (551). The fixing members (55) between the supporting frames (52) and the fixing members (55) between the auxiliary frames (53) and the auxiliary frames (53) are matched.

6. The pile vertical compressive static load test device according to claim 3, characterized in that: An auxiliary bolt (58) is provided at the bottom of the auxiliary frame (53), one end of the auxiliary bolt (58) is rotated to penetrate the auxiliary frame (53) and the support frame (52) and extend to the inside of the support plate (51), and the end of the auxiliary bolt (58) is threadedly sleeved with the support plate (51) at the insertion point.

7. The pile vertical compressive static load test device according to claim 1, characterized in that: Also includes: A test module, the test module comprising a jack (20) and a displacement sensor connected to a control center, the jack (20) being located between a main beam (11) and a foundation pile (60) to be tested, and a force axis of the jack (20) being coaxially arranged with the foundation pile (60) to be tested.

8. The test method of the pile vertical compressive static load test device according to any one of claims 1 to 7, characterized in that: The following steps are included: S1, hoisting the main beam (11); After placing the jack (20) on the foundation pile (60) to be tested, use external lifting equipment to place two supporting piers (40) on both sides of the jack (20), and then lift the main beam (11) to place it on the platform formed by the two supporting piers (40); S2, installing the buttress assembly (50); The support plate (51) is hoisted on one side of the main beam (11) and is parallel to the main beam (11), and then the support frame (52) is rotated and the auxiliary frame (53) is pulled out, the auxiliary frame (53) and the support frame (52) form a supporting column for the support plate (51), and the pier assembly (50) and the anchor assembly are used in conjunction to form a pier supporting the secondary beam (12); S3, hoisting the secondary beam (12) and the load block; Multiple secondary beams (12) are overlapped on the main beam (11) in sequence, and both ends of the secondary beams (12) are supported by corresponding pier assemblies (50), and then multiple load blocks can be stacked; S4, static load test; The jack (20) is started to move the bearing module and the load block upward, and the static load test data of the pile foundation (60) to be tested is obtained through the data obtained by the control center.