An automated production line for steel frames
By introducing automated production lines and logistics systems on the steel frame production line, and using robots and automation equipment to complete cutting, welding and other operations, the problems of manual welding dependence and low efficiency are solved, and a more efficient and stable production process is achieved.
Patent Information
- Application Number
- CN201811650705.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-12-31
- Publication Date
- 2024-12-06
- Estimated Expiration
- 2038-12-31
AI Technical Summary
During the production process of existing steel frames, manual welding results in welding accuracy dependent on the operator's proficiency, low efficiency, unable to ensure product quality stability, and not conducive to improving production capacity.
An automated production line was designed, including tracks and six workstations, which were equipped with cutting, spot welding, full welding, attachment welding, flip and material temporary storage equipment. The material turnover between each workstation is achieved through the logistics system, and the use of Robots and automation equipment replace manual processing operations.
It improves production efficiency and product quality stability, reduces manual errors, and enhances the competitiveness of the enterprise.
Smart Images

Figure CN109551128B_ABST
Abstract
Description
[Technical field]
[0002] The invention relates to the field of steel frame processing, and in particular to an automatic production line for steel frames. [Background technology]
[0004] In current industrial production, there are a large number of products that require assembly and welding of steel frames. At present, the production process of steel frames is as follows: after the manual welding of fixtures, the workpieces to be welded are manually transported, laid, and clamped, and the welding of the products is done manually. During the manual assembly and welding of steel frames, the welding accuracy of the products is completely determined by the proficiency and responsibility of the operators, and the quality stability of the products cannot be ensured. At the same time, the manual welding method is inefficient, which is not conducive to the improvement of production capacity and the competitiveness of enterprises. [Summary of the invention]
[0006] In order to solve the above technical problems, an embodiment of the present invention provides an automated production line for steel frames with high production efficiency.
[0007] The embodiment of the present invention solves the technical problem by adopting the following technical solution: providing an automated production line with a steel frame, including a track, six workstations arranged along the track, and a logistics system. The first workstation is provided with cutting equipment for cutting and cutting raw materials, the second workstation is provided with spot welding equipment for laying materials and spot welding, the third workstation is provided with full welding equipment for overall welding, the fourth workstation is provided with accessory welding equipment for welding accessories, the fifth workstation is provided with turning equipment for turning over materials, and the sixth workstation is provided with material temporary storage equipment for temporarily storing materials. The logistics system is used for material turnover between the six workstations.
[0008] Optionally, the cutting equipment is arranged at one end of the track, and the cutting equipment includes a first support frame, a material-retrieving robot and a laser cutting device;
[0009] The material picking robot and the laser cutting equipment are both arranged on the first support frame, and the material picking robot can move relative to the first support frame;
[0010] The material picking robot is used to grab materials and place them on the first support frame, and the laser cutting equipment is used to cut materials.
[0011] Optionally, the spot welding equipment includes a second support frame, a laying robot and a spot welding robot;
[0012] The laying robot and the spot welding robot are both arranged on the second supporting frame, and the laying robot and the spot welding robot can move respectively relative to the second supporting frame;
[0013] The laying robot is used to lay the material on the second support frame, and the spot welding robot is used to spot weld the material.
[0014] Optionally, the all-welding equipment includes a third support frame, an all-welding robot and a welding platform;
[0015] The full welding robot and the welding platform are both arranged on the third support frame, the full welding robot can move relative to the third support frame, and the welding platform can rotate relative to the third support frame;
[0016] The full-welding robot is used to fully weld materials, and the welding platform is used to place and flip materials.
[0017] Optionally, a workbench is provided on the accessory welding equipment, and the workbench is used for welding materials and accessories.
[0018] Optionally, the flipping equipment includes a flip seat, a cover plate and a flip body;
[0019] The cover plate is rotatably connected to the flip seat, the flip body is arranged on the cover plate, and the flip body and the cover plate can rotate together relative to the flip seat;
[0020] The turning body is used to turn horizontally placed materials into a vertical state.
[0021] Optionally, the material temporary storage equipment includes a storage shelf, and rollers are provided at the bottom of the storage shelf; the storage shelf is used to store materials, and the rollers are used to drive the storage shelf to move.
[0022] Optionally, the logistics system includes an AGV transfer trolley and a turnover trolley;
[0023] The turnover trolley can move along the track;
[0024] The AGV transfer trolley and the turnover trolley are used for material turnover of the entire production line.
[0025] Optionally, the turnover trolley includes a base and a telescopic platform;
[0026] The base is arranged on the track, and the base can move along the track;
[0027] The telescopic platform is arranged on the base, and the telescopic platform can be telescoped to both sides of the base, and the telescopic direction of the telescopic platform is perpendicular to the track;
[0028] The telescopic platform is used to fork materials onto the base.
[0029] Optionally, materials are transferred between the cutting equipment and the spot welding equipment via the AGV transfer trolley;
[0030] The AGV transfer trolley is used to transfer the cut materials to the spot welding equipment.
[0031] Compared with the prior art, the track in this embodiment is arranged between the first workstation and the sixth workstation, and is used for material transportation of the entire production line. Material turnover between each workstation is realized through a logistics system. The equipment on the above six workstations replaces manual labor to complete product processing operations, thereby improving production efficiency and the stability of product quality.
Brief Description of the Drawings
[0033] One or more embodiments are exemplarily described by corresponding drawings, which do not constitute limitations on the embodiments. Elements with the same reference numerals in the drawings represent similar elements, and the figures in the drawings do not constitute proportional limitations unless otherwise stated.
[0034] Figure 1 A schematic structural diagram of an automated production line for a steel frame provided by one embodiment of the present invention;
[0035] Figure 2 for Figure 1 The structural schematic diagram of the track of the automated production line with a steel frame and the turnover trolley in the first state is shown;
[0036] Figure 3 for Figure 2 A schematic diagram of the structure of the track and the turnover trolley in the second state shown;
[0037] Figure 4 for Figure 1 A schematic diagram of the structure of the cutting equipment of the automated production line of the steel frame shown;
[0038] Figure 5 for Figure 1 A schematic diagram of the structure of the spot welding equipment of the automated production line of the steel frame shown;
[0039] Figure 6 for Figure 1 The schematic diagram of the structure of the fully welded equipment of the automated production line of the steel frame shown;
[0040] Figure 7 for Figure 1 The schematic diagram of the structure of the accessory welding equipment of the automated production line of the steel frame shown;
[0041] Figure 8 for Figure 1 A schematic diagram of the structure of the turning equipment of the automated production line of the steel frame shown;
[0042] Fig. 9 for Figure 1 The schematic diagram of the structure of the material temporary storage equipment of the automated production line with a steel frame is shown. [Specific implementation method]
[0044] For ease of understanding of the present invention, the present invention is described in more detail below in conjunction with the accompanying drawings and specific embodiments. It should be noted that when an element is described as "fixed to" another element, it can be directly on another element, or there can be one or more centered elements therebetween. When an element is described as "connected to" another element, it can be directly connected to another element, or there can be one or more centered elements therebetween. The terms "vertical", "horizontal", "left", "right", "inside", "outside" and similar expressions used in this specification are for illustrative purposes only.
[0045] Unless otherwise defined, all technical and scientific terms used in this specification have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used in this specification includes any and all combinations of one or more of the related listed items.
[0046] In addition, the technical features involved in different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.
[0047] See also Figure 1 , Figure 1 A structural schematic diagram of an automated production line 100 for a steel frame provided in one embodiment of the present invention. The automated production line 100 for a steel frame includes: a work area 10, a logistics system 20 for realizing product turnover on the entire production line, six workstations are arranged on the work area 10, the first workstation is located at the head end of the work area 10, the first workstation is provided with a cutting device 30 for cutting and blanking, the second workstation is provided with a spot welding device 40 for spot welding, the third workstation is provided with a full welding device 50 for overall welding, the fourth workstation is provided with an accessory welding device 60 for welding accessories, the fifth workstation is provided with a flipping device 70 for flipping the welded product, and the sixth workstation is provided with a material temporary storage device 80 for temporarily storing the product. It can be understood that the number of the workstations can be increased or decreased in actual production, and the processes in the post-processing process are not exactly the same according to the different requirements of the processed finished products. For example, seven workstations can be set, as long as the processing requirements are met.
[0048] A track 11 is provided on the work area 10, one end of the track 11 is provided at the head end of the work area 10, and the other end of the track 11 is provided at the tail end of the work area 10. The above six workstations are all arranged along the track 11, and the track 11 is used for product transportation of the entire production line.
[0049] Please see also Figure 2 and Figure 3 , Figure 2 is a schematic structural diagram of the track 11 and the turnover trolley 22 in an extended state, Figure 3 Schematic diagram of the structure of the track 11 and the turnover trolley 22 in the retracted state. The logistics system 20 includes an AGV transfer trolley 21 and a turnover trolley 22. The AGV transfer trolley 21 is used for material transfer between the first station and the second station. The turnover trolley 22 can move along the track 11, and the turnover trolley 22 realizes product turnover of the entire production line.
[0050] The turnover trolley 22 includes a base 220, which is arranged on the track 11. The base 220 can be driven to move along the track 11 by a power device such as a motor. The base 220 is provided with a base rail 222, and the number of the base rails 222 is two. The two base rails 222 are arranged parallel to each other and are perpendicular to the track 11. The base rail 222 is provided with a telescopic platform 224, and the number of the telescopic platforms 224 is two, and each of the telescopic platforms 224 corresponds to one of the base rails 222. The telescopic platform 224 is installed on the base rail 222, and the telescopic platform 224 can slide along the base rail 222 to the two sides of the base 220. The two telescopic platforms 224 respectively extend to the outside of the base 220 to fork the square steel 200, and then retract to the inside of the base 220 to move the square steel 200 onto the base 220. The power device drives the retracted turnover trolley 22 to move to the next workstation. After arriving at the next workstation, the two telescopic platforms 224 respectively extend to the outside to place the square steel 200 at the designated position.
[0051] See also Figure 4 , Figure 4 Schematic diagram of the structure of the cutting equipment 30. The cutting equipment 30 is arranged at the head end of the working area 10. There are two cutting equipments 30, both of which are arranged at the head end of the working area 10 and are located on opposite sides of the track 11.
[0052] The cutting equipment 30 includes a first support frame 31, a material picking robot 32 and a laser cutting device 33. Two support rails 310 are provided on the first support frame 31. The two support rails 310 are arranged on the same horizontal plane and are parallel to each other. A material picking robot 32 is arranged between the two support rails 310. The two ends of the material picking robot 32 are respectively connected to the two support rails 310. The material picking robot 32 can move longitudinally along the support rails 310. The material picking robot 32 includes a material picking rail 320 and a material picking manipulator 322. The material picking manipulator 322 is arranged on the material picking rail 320. The material picking manipulator 322 can move laterally along the material picking rail 320. A square steel laying frame 312 and a cutting equipment rail 314 are also arranged between the two support rails 310. The square steel laying frame 312 and the cutting equipment rail 314 are both arranged below the material picking rail 320. The laser cutting device 33 is disposed on the cutting device guide rail 314 , and the laser cutting device 33 can move laterally along the cutting device guide rail 314 .
[0053] Unprocessed square steel 200 is placed at one end of the first support frame 31, the material picking robot 322 moves to the designated position to grab the square steel 200, and places the square steel 200 on the square steel laying frame 312, the laser cutting equipment 33 performs laser cutting on the square steel 200, and then the material picking robot 322 grabs the cut square steel 200 and places it in order on the AGV transfer cart 21, and the AGV transfer cart 21 transports the cut square steel 200 to the next workstation.
[0054] See also Figure 5 , Figure 5 : is a schematic diagram of the structure of the spot welding equipment 40. The spot welding equipment 40 is arranged at one end of the cutting equipment 30 away from the head end of the working area 10. The number of the spot welding equipment 40 is six, three of which are arranged on one side of the track 11, and the other three are arranged on the other side opposite to the track.
[0055] The spot welding equipment 40 includes a second support frame 41, a laying robot 42 and a spot welding robot 43. The second support frame 41 includes a support base 410 and a platform frame 412. The number of the support bases 410 is two, and the two support bases 410 are respectively arranged on opposite sides of the platform frame 412 and are parallel to each other. The support base 410 includes a first guide rail 4100, a second guide rail 4102 and two columns. Both ends of the first guide rail 4100 and the second guide rail 4102 are respectively connected to the two columns. The first guide rail 4100 is arranged at the upper end of the column, and the second guide rail 4102 is arranged in the middle of the column, that is, the first guide rail 4100 is arranged above the second guide rail 4102. The platform frame 412 is arranged between the two support bases 410, and the platform frame 412 is arranged below the second guide rail 4102. A spot welding platform 414 is provided on the platform frame 412, and the spot welding platform 414 is provided with an electromagnet. When the spot welding platform 414 is powered on, the square steel 200 can be adsorbed and fixed. A laying robot 42 is provided between the two supporting bases 410, and the two ends of the laying robot 42 are respectively connected to the first guide rails 4100 on the two supporting bases 410, and the laying robot 42 can move longitudinally along the first guide rails 4100. The laying robot 42 includes a laying guide rail 420 and a laying manipulator 422, and the laying manipulator 422 is provided on the laying guide rail 420, and the laying manipulator 422 can move laterally along the laying guide rail 420. A spot welding robot 43 is also provided between the two supporting bases 410, and the two ends of the spot welding robot 43 are respectively connected to the second guide rails 4102 on the two supporting bases 410, and the spot welding robot 43 can move longitudinally along the second guide rails 4102. The spot welding robot 43 includes a spot welding rail 430 and a spot welding manipulator 432 . The spot welding manipulator 432 is disposed on the spot welding rail 430 , and the spot welding manipulator 432 can move laterally along the spot welding rail 430 .
[0056] The laying robot 42 identifies the cut square steel 200 on the AGV transfer trolley 21, the laying manipulator 422 grabs the cut square steel 200 and lays it to the specified position on the spot welding platform 414, the spot welding platform 414 is powered on to adsorb and fix the square steel 200, and then the spot welding robot 43 spot welds the square steel 200 to connect the cut square steel 200 to form the square steel 200 of the frame structure, and the spot welded square steel 200 of the frame structure is transported to the next workstation by the turnover trolley 22.
[0057] See also Figure 6 , Figure 6: is a schematic diagram of the structure of the full welding equipment 50. The full welding equipment 50 is arranged at one end of the spot welding equipment 40 away from the cutting equipment 30. The number of the full welding equipment 50 is six, three of which are arranged on one side of the track 11, and the other three are arranged on the other side opposite to the track 11.
[0058] The fully welded equipment 50 includes a third support frame 51, a fully welded robot 52 and a welding platform. The third support frame 51 is provided with a transverse guide rail 510, and the number of the transverse guide rails 510 is three. The three transverse guide rails 510 are arranged in the same horizontal plane and are parallel to each other. The fully welded robot 52 is connected to the three transverse guide rails 510, and the fully welded robot 52 can move along the transverse guide rails 510. The fully welded robot 52 includes a fully welded guide rail 520 and a fully welded manipulator 522, and the fully welded guide rail 520 is connected to the three transverse guide rails 510, and the fully welded guide rail 520 can move laterally along the transverse guide rail 510. The fully welded manipulator 522 is arranged on the fully welded guide rail 520, and the fully welded manipulator 522 can move longitudinally along the fully welded guide rail 520. The welding platform 53 is provided between the three transverse guide rails 510. There are two welding platforms 53. One welding platform 53 is provided between the transverse guide rail 510 on one side and the transverse guide rail 510 in the middle. The other welding platform 53 is provided between the transverse guide rail 510 on the other side and the transverse guide rail 510 in the middle. The two welding platforms 53 are provided at the same height plane, and both welding platforms 53 are provided below the fully welded guide rail 520. A front cover plate 530 and a back cover plate 532 are provided on the welding platform. The front cover plate 530 is connected to the back cover plate 532. The square steel 200 can be laid between the front cover plate 530 and the back cover plate 532. Any one of the front cover plate 530 and the back cover plate 532 can be flipped relative to the other. The front cover plate 530 and the back cover plate 532 are connected to the third support frame 51 via a rotating device, and the front cover plate 530 and the back cover plate 532 can rotate together around a rotation axis relative to the third support frame 51.
[0059] When the all-welding robot 52 welds the square steel 200, the square steel 200 is placed horizontally. The turnover trolley 22 transports the square steel 200 of the frame structure that has been spot-welded to between the front cover plate 530 and the back cover plate 532 of one of the welding platforms 53, the front cover plate 530 is flipped up and opened, and the all-welding manipulator 522 performs front welding on the square steel 200. The square steel 200 that has been welded on the front needs to be placed for cooling. After cooling, the front cover plate 530 is closed, and the front cover plate 530 and the back cover plate 532 drive the square steel 200 that has been welded on the front to flip 180 degrees together, and the back cover plate 532 is flipped open, and the all-welding manipulator 522 performs back welding on the square steel 200. The square steel 200 that has been welded on the front and back is moved to the next station by the turnover trolley 22. The two welding platforms 53 share one full-welding robot 522 for welding. After the front side welding of the square steel 200 on one welding platform 53 is completed, the full-welding robot 522 welds the square steel 200 on the other welding platform 53 during the cooling and flipping time of the square steel 200.
[0060] See also Figure 7 , Figure 7 : is a schematic diagram of the structure of the accessory welding equipment 60. The accessory welding equipment 60 is arranged at one end of the full welding equipment 50 away from the spot welding equipment 40. The number of the accessory welding equipment 60 is four, two of which are arranged on one side of the track 11, and the other two of which are arranged on the other side opposite to the track 11.
[0061] The accessory welding equipment 60 is provided with a workbench 61, and the workbench 61 is fixed on the work area 10. The turnover trolley 22 transports the fully welded square steel 200 to the workbench 61, and the square steel 200 is welded with accessories such as the hoisting structure and the auxiliary structure on the workbench 61. Since the welding of the square steel 200 with the above accessories is relatively complex, the cost of automated welding is high and difficult to achieve, so manual welding is used to place, position and weld the above accessories. The square steel 200 with completed accessory welding is transported to the next station by the turnover trolley.
[0062] See also Figure 8 , Figure 8: is a schematic diagram of the structure of the flipping device 70. The flipping device 70 is arranged on the tail end of the working area 10 away from the cutting device 30, and the flipping device 70 is arranged on one side of the track 11. The flipping device 70 includes a flip seat 71, a cover plate 72 and a flip body 73. The flip seat 71 is provided with two vertical frames, and the two vertical frames are respectively arranged on both sides of the flip seat 71 and are parallel to each other. The two sides of the cover plate 72 are rotatably connected to the two vertical frames respectively. The cover plate 72 can rotate relative to the flip seat 71 around the rotation axis, and the cover plate 72 is provided with a receiving groove that can accommodate the square steel 200. The number of the flip bodies 73 is three, and the three flip bodies 73 are parallel to each other and are all arranged vertically relative to the cover plate 72. The flip body 73 is provided with a clamping groove, and the cover plate 72 is accommodated in the clamping groove. The flip body 73 and the cover plate 72 can rotate relative to the flip seat 71 together.
[0063] The square steel 200 after the accessories are welded is placed horizontally, and the turnover trolley 22 transfers the square steel 200 to the receiving groove on the cover plate 72. The horizontally placed square steel 200 is flipped into a vertical state by the flipping equipment 70, and the square steel 200 in the vertical state is transported to the next workstation by the bottom roller.
[0064] See also Fig. 9 , Fig. 9 The schematic diagram is a structural diagram of a material temporary storage device 80 storing the square steel 200. The material temporary storage device 80 includes a storage shelf 81, on which a plurality of placement slots 82 are provided, and the processed square steel 200 are stored in the placement slots 82. The bottom of the storage shelf 81 is provided with rollers, and the rollers can drive the storage shelf 81 to move.
[0065] The material temporary storage equipment 80 is docked with the flipping equipment 70, and the square steel 200 flipped into a vertical state by the flipping equipment 70 is transferred to the material temporary storage equipment 80. After the material temporary storage equipment 80 is full of materials, it is transported to the warehouse in a unified manner.
[0066] It can be understood that in the embodiment of the present invention, the quantity of the AGV transfer trolley 21, the turnover trolley 22 and each equipment on the above-mentioned six workstations can be increased or decreased according to actual needs, and the actual required quantity can be determined according to the material turnover efficiency of the factory.
[0067] It should be noted that the square steel 200 in the embodiment of the present invention is only used to illustrate the technical solution of the present invention, and the actual processing material is not limited to square steel. For example, the processing material can be steel pipes or steel bars.
[0068] Compared with the prior art, the track 11 in this embodiment is arranged between the first workstation and the sixth workstation and is used for material transportation of the entire production line. The AGV transfer trolley and the turnover trolley realize material turnover between the various workstations. The material picking robot 322, the laying robot 422, the spot welding robot 432, the full welding robot 522 and other machines are used to replace manual operations to complete a series of process flows such as cutting and unloading, spot welding, full welding, accessory welding, and flipping and unloading, thereby improving production efficiency and product quality stability.
[0069] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit them. Under the concept of the present invention, the technical features in the above embodiments or different embodiments may also be combined, the steps may be implemented in any order, and there are many other changes in different aspects of the present invention as described above, which are not provided in detail for the sake of simplicity. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they may still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not deviate the essence of the corresponding technical solutions from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. An automated production line for steel frames, characterized in that: include: track; There are six workstations arranged along the track, the first workstation is equipped with cutting equipment for cutting and cutting raw materials, the second workstation is equipped with spot welding equipment for laying materials and spot welding, the third workstation is equipped with full welding equipment for overall welding, the fourth workstation is equipped with accessory welding equipment for welding accessories, the fifth workstation is equipped with turning equipment for turning over materials, and the sixth workstation is equipped with material temporary storage equipment for temporarily storing materials; The full-welding equipment includes a third support frame, a full-welding robot and a welding platform, the full-welding robot is used to perform full welding on the material, the full-welding robot is arranged on the third support frame, the full-welding robot can move relative to the third support frame, the number of the welding platforms is two, the welding platform is provided with a front cover plate and a back cover plate, the front cover plate is connected to the back cover plate, the front cover plate and the back cover plate are connected to the third support frame through a rotating device, the front cover plate and the back cover plate can rotate together around the rotation axis relative to the third support frame, the front cover plate and the back cover plate are used for laying materials, any one of the front cover plate and the back cover plate can be flipped open relative to the other so that the full-welding robot can weld the material; A logistics system, which is used for material turnover between six workstations; When the full welding equipment is working, after one side of the material on one welding platform is welded and the material is cooled, the front cover plate and the back cover plate drive the material to flip 180 degrees. During the time when the material is cooling and flipping, the full welding robot welds the material on another welding platform.
2. The automated production line for steel frames according to claim 1, characterized in that: The cutting equipment is arranged at one end of the track, and the cutting equipment comprises a first support frame, a material taking robot and a laser cutting device; The material picking robot and the laser cutting equipment are both arranged on the first support frame, and the material picking robot can move relative to the first support frame; The material picking robot is used to grab materials and place them on the first support frame, and the laser cutting equipment is used to cut materials.
3. The automated production line for steel frames according to claim 1, characterized in that: The spot welding equipment includes a second support frame, a laying robot and a spot welding robot; The laying robot and the spot welding robot are both arranged on the second supporting frame, and the laying robot and the spot welding robot can move respectively relative to the second supporting frame; The laying robot is used to lay the material on the second support frame, and the spot welding robot is used to spot weld the material.
4. The automated production line for steel frames according to claim 1, characterized in that: The accessory welding equipment is provided with a workbench, and the workbench is used for welding materials and accessories.
5. The automated production line for steel frames according to claim 1, characterized in that: The turning equipment comprises a turning seat, a cover plate and a turning body; The cover plate is rotatably connected to the flip seat, the flip body is arranged on the cover plate, and the flip body and the cover plate can rotate together relative to the flip seat; The turning body is used to turn horizontally placed materials to a vertical state.
6. The automated production line for steel frames according to claim 1, characterized in that: The material temporary storage equipment includes a storage shelf, and rollers are provided at the bottom of the storage shelf; the storage shelf is used to store materials, and the rollers are used to drive the storage shelf to move.
7. The automated production line for steel frames according to any one of claims 1 to 6, characterized in that: The logistics system includes an AGV transfer trolley and a turnover trolley; The turnover trolley can move along the track; The AGV transfer trolley and the turnover trolley are used for material turnover of the entire production line.
8. The automated production line for steel frames according to claim 7, characterized in that: The turnover trolley comprises a base and a telescopic platform; The base is arranged on the track, and the base can move along the track; The telescopic platform is arranged on the base, and the telescopic platform can be telescoped to both sides of the base, and the telescopic direction of the telescopic platform is perpendicular to the track; The telescopic platform is used to fork materials onto the base.
9. The automated production line for steel frames according to claim 8, characterized in that: The materials are transferred between the cutting equipment and the spot welding equipment by the AGV transfer trolley; The AGV transfer trolley is used to transfer the cut materials to the spot welding equipment.
Citation Information
Patent Citations
Robot automatic flexible welding production line of box-type substation and production process
CN107953045A
Full-automatic uncoiling laser cutting production line
CN108817698A
Automatic production line of steel frame
CN209491449U