Prefabricated concrete component inverted cone steel frame and steel cage structure and construction method
Through the design of the inverted tapered steel frame and wedge-shaped locking rod, the problem of complicated installation and high cost of prefabricated concrete components is solved, high strength, fast installation and low-cost production are achieved, which is suitable for industrialized production of construction.
Patent Information
- Application Number
- CN201911193362.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-11-28
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2039-11-28
AI Technical Summary
The on-site installation of existing prefabricated concrete components is cumbersome and costly, making it difficult to achieve efficient production in construction industrialization.
A prefabricated concrete component inverted tapered steel frame and steel cage structure is designed. It adopts the design of inverted tapered ends and wedge-shaped locking rods. Through the cooperation of sleeves and outer steps, the steel bars can be quickly locked and screwed to install. , and propose corresponding construction methods.
It achieves high strength, rapid installation and low-cost production of concrete components, simplifies structural design, and is suitable for specialized production and wide market applications.
Smart Images

Figure CN110805207B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to an inverted cone steel bar frame and a steel bar cage structure of a prefabricated concrete component and a construction method. Background Art
[0002] In order to realize the construction industrialization, longevity, quality, green and low-carbon new industrial integrated technology, innovate the construction market, and achieve the great goal of my country's century-old residential projects. In order to effectively improve the level of construction industrialization development, the state has issued relevant support policies for the development of assembly in the construction industry. However, the on-site installation of prefabricated concrete components currently used in industrial production is cumbersome and the installation cost is high. Summary of the invention
[0003] The invention provides an inverted cone steel frame and steel cage structure of a prefabricated concrete member and a construction method.
[0004] The solution adopted by the present invention to solve the technical problem is to provide an inverted tapered steel bar frame for assembled concrete components: it includes a first connecting steel bar and a second connecting steel bar that are arranged relatively to each other, and the two end heads of the first connecting steel bar and the second connecting steel bar are respectively thickened to form inverted tapered ends, and the inverted tapered ends are thickened to form steps. The first connecting steel bar and the second connecting steel bar with inverted tapered ends are respectively sleeved with a first wedge-shaped locking rod and a second wedge-shaped locking rod. The inner peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod are also inverted tapered and are respectively wedged with the inverted tapered outer peripheral wall surfaces of the ends of the first connecting steel bar and the second connecting steel bar. The step diameters of the two end heads of the first connecting steel bar and the second connecting steel bar are larger than the diameter of the inverted tapered ends. The inner end faces of the first wedge-shaped locking rod and the second wedge-shaped locking rod are respectively against the outer end faces of the steps of the corresponding first connecting steel bar and the second connecting steel bar. The outer peripheries of the first wedge-shaped locking rod and the second wedge-shaped locking rod are sleeved with a sleeve, and the outer peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod have external threads that are screwed with the internal threads of the inner walls of the sleeves.
[0005] Furthermore, an outer step is provided on one end of the sleeve.
[0006] Furthermore, the first wedge-shaped locking rod and the second wedge-shaped locking rod have platform steps at the positions where they extend to facilitate twisting.
[0007] Furthermore, the ends of the first wedge-shaped locking rod and the second wedge-shaped locking rod opposite to each other extend out of the sleeve, and the taper of the ends of the first connecting steel bar and the second connecting steel bar is 2-6 degrees to the taper of the inner circumferential wall of the first wedge-shaped locking rod and the second wedge-shaped locking rod.
[0008] A steel cage structure: it also includes a fixed plate A and a template B, wherein the template B is provided with a plurality of through holes in a circular array that match the outer step of the sleeve, the outer step of the sleeve is fixed in the through hole, and the non-step end of the sleeve is downward, and the fixed plate A is provided with a steel bar fixing groove corresponding to the through hole, and the first connecting steel bar is respectively sleeved with a first wedge-shaped locking rod A and a first wedge-shaped locking rod B at both ends, one end of the first connecting steel bar is screwed into the non-step end of the sleeve through the first wedge-shaped locking rod, and the other end is welded to the steel bar fixing groove on the fixed plate A, and the first wedge-shaped locking rod B is located at the lower part of the fixed plate A.
[0009] Furthermore, the steel bar fixing groove is also provided with an insert for preventing cement from leaking out.
[0010] A construction method of a steel cage structure:
[0011] Step 1) First, select several steel bars of appropriate length according to the needs, put wedge-shaped locking rods on both ends of the steel bars, and then thicken the two ends respectively;
[0012] Step 2) spot welding a plurality of sleeve outer steps to each through hole on the lower side of a plurality of templates B to form a plurality of standard templates;
[0013] Step 3) Screw the upper ends of several steel bars to the non-stepped ends of the sleeves on the lower side of the standard template through wedge-shaped locking rods, screw the lower ends of the steel bars to the outer step ends of the sleeves on the upper side of another standard template through wedge-shaped locking rods, and weld the lower ends of each steel bar to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower standard template;
[0014] Step 4) screwing the lower ends of the other several steel bars into the outer step ends of the sleeves located on the upper side of the upper standard template in the previous step through wedge-shaped locking rods;
[0015] Step 5) Screw the upper end of the steel bar in the previous step to each sleeve without step on the lower side of another standard template through a wedge-shaped locking rod;
[0016] Step 6) Weld the lower end of each steel bar in the previous step to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower end of the standard template;
[0017] Step 7) Repeat steps 4) to 6) until a steel cage assembly of appropriate length is produced, insert the steel bar welding groove of the fixing plate A on each steel cage, and pour cement between the standard template on each steel cage and the fixing plate A to form a concrete component assembly;
[0018] Step 8) unscrewing the steel bars on the non-stepped ends of each sleeve on the upper side of the standard template to obtain multiple concrete components;
[0019] Step 9) After transporting to the construction site, assemble and use.
[0020] Compared with the prior art, the present invention has the following beneficial effects: high strength, convenient and quick installation, low price, broad market prospects, simple structure, reasonable design, and convenient specialized production. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The present invention is further described below in conjunction with the accompanying drawings.
[0022] Figure 1 A schematic diagram of the structure of the inverted tapered steel reinforcement frame of the present invention;
[0023] Figure 2 A schematic diagram of the steel cage structure of the present invention;
[0024] Figure 3 Schematic diagram of the structure of template B;
[0025] Figure 4 Schematic diagram of the structure of fixed plate A.
[0026] In the figure: 1-first connecting steel bar; 2-second connecting steel bar; 3-sleeve; 4-second wedge-shaped locking rod; 5-first wedge-shaped locking rod; 6-inner step; 7-outer step; 8-template B; 9-fixing plate A; 10-through hole; 11-insert. DETAILED DESCRIPTION
[0027] The present invention is further described below in conjunction with the accompanying drawings and specific embodiments.
[0028] like Figure 1-4 As shown, an inverted tapered steel bar frame of an assembled concrete component comprises a first connecting steel bar 1 and a second connecting steel bar 2 which are arranged opposite to each other, wherein both end heads of the first connecting steel bar and the second connecting steel bar are respectively thickened to form inverted tapered end heads, and the inverted tapered end heads are thickened to form steps, and the peripheries of the first connecting steel bar and the second connecting steel bar with inverted tapered end heads are respectively sleeved with a first wedge-shaped locking rod 5 and a second wedge-shaped locking rod 4, and the inner peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod are also inverted tapered and respectively wedged with the inverted tapered outer peripheral wall surfaces of the end heads of the first connecting steel bar and the second connecting steel bar, and the step diameters of the two end heads of the first connecting steel bar and the second connecting steel bar are larger than the diameter of the inverted tapered end heads, and the inner end faces of the first wedge-shaped locking rod and the second wedge-shaped locking rod respectively abut against the outer end faces of the steps of the corresponding first connecting steel bar and the second connecting steel bar, and the peripheries of the first wedge-shaped locking rod and the second wedge-shaped locking rod are sleeved with a sleeve 3, and the outer peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod have external threads screwed with the internal threads of the inner walls of the sleeves.
[0029] In this embodiment, in order to relatively lock the first connecting steel bar and the second connecting steel bar, the middle section of the internal thread of the sleeve is provided with an inner step 6 or may not be provided with an inner step, and an outer step 7 is provided on one end of the sleeve.
[0030] In this embodiment, in order to design reasonably and make the locking smooth, the taper of the first connecting steel bar and the second connecting steel bar end and the taper of the inner peripheral wall of the first wedge-shaped locking rod and the second wedge-shaped locking rod are 2-6 degrees, and the preferred slope is 3 degrees. The taper of the outer peripheral wall of the first connecting steel bar and the second connecting steel bar end and the taper of the inner peripheral wall of the first wedge-shaped locking rod and the second wedge-shaped locking rod can be the same or different.
[0031] In this embodiment, the ends of the first wedge-shaped locking rod and the second wedge-shaped locking rod opposite to each other extend out of the sleeve, and the positions where the first wedge-shaped locking rod and the second wedge-shaped locking rod extend have platform steps for easy twisting. Other structures may also be used to facilitate the twisting of the wedge-shaped locking rod.
[0032] In this embodiment, a steel cage structure is also provided: it also includes a fixed plate A and a template B, and the template B is provided with a plurality of through holes in a circular array that match the outer step of the sleeve. The outer step of the sleeve is fixed in the through hole, and the non-step end of the sleeve is downward. The fixed plate A is provided with a steel bar fixing groove corresponding to the through hole, and the first connecting steel bar is respectively sleeved with a first wedge-shaped locking rod A and a first wedge-shaped locking rod B at both ends. One end of the first connecting steel bar is screwed into the non-step end of the sleeve through the first wedge-shaped locking rod, and the other end is welded to the steel bar fixing groove on the fixed plate A, and the first wedge-shaped locking rod B is located at the lower part of the fixed plate A.
[0033] In this embodiment, an insert 11 for preventing cement from leaking out is also provided on the steel bar fixing groove.
[0034] In this embodiment, a construction method of a steel cage structure is also provided:
[0035] Step 1) First, select several steel bars of appropriate length according to the needs, put wedge-shaped locking rods on both ends of the steel bars, and then thicken the two ends respectively, and make the inner wall surface of the wedge-shaped locking rod and the end of the steel bar wedge-fit;
[0036] Step 2) spot welding a plurality of sleeve outer steps to each through hole on the lower side of a plurality of templates B to form a plurality of standard templates;
[0037] Step 3) Screw the upper ends of several steel bars to the non-stepped ends of the sleeves on the lower side of the standard template through wedge-shaped locking rods, screw the lower ends of the steel bars to the outer step ends of the sleeves on the upper side of another standard template through wedge-shaped locking rods, and weld the lower ends of each steel bar to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower standard template;
[0038] Step 4) screwing the lower ends of the other several steel bars into the outer step ends of the sleeves located on the upper side of the upper standard template in the previous step through wedge-shaped locking rods;
[0039] Step 5) Screw the upper end of the steel bar in the previous step to each sleeve without step on the lower side of another standard template through a wedge-shaped locking rod;
[0040] Step 6) Weld the lower end of each steel bar in the previous step to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower end of the standard template;
[0041] Step 7) Repeat steps 4) to 6) until a steel cage assembly of appropriate length is produced, insert the steel bar welding groove of the fixing plate A on each steel cage, and pour cement between the standard template on each steel cage and the fixing plate A to form a concrete component assembly;
[0042] Step 8) unscrewing the steel bars on the non-stepped ends of each sleeve on the upper side of the standard template to obtain multiple concrete components;
[0043] Step 9) After transporting to the construction site, the reinforcement bar on the lower fixing plate of the concrete component is connected to the sleeve on the standard template on the other concrete component, and the wedge-shaped locking rod is screwed into the sleeve to achieve the connection between the two concrete components. Repeat the above steps to complete the assembly.
[0044] The invention has high strength, convenient and quick installation, low price, broad market prospects, simple structure, reasonable design and convenient specialized production.
[0045] The preferred embodiments listed above further illustrate the objectives, technical solutions and advantages of the present invention in detail. It should be understood that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. A steel cage structure, using an assembled concrete member inverted cone steel frame, characterized in that: The assembled concrete component inverted tapered steel bar frame includes a first connecting steel bar and a second connecting steel bar that are relatively arranged, and the two end heads of the first connecting steel bar and the second connecting steel bar are respectively thickened to form inverted tapered ends, and the inverted tapered ends are thickened to form steps, and the first connecting steel bar and the second connecting steel bar with inverted tapered ends are respectively sleeved with a first wedge-shaped locking rod and a second wedge-shaped locking rod, and the inner peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod are also inverted tapered and respectively wedged with the inverted tapered outer peripheral wall surfaces of the first connecting steel bar and the second connecting steel bar ends, and the step diameters of the two end heads of the first connecting steel bar and the second connecting steel bar are larger than the diameter of the inverted tapered end, and the inner end faces of the first wedge-shaped locking rod and the second wedge-shaped locking rod respectively abut against the outer end faces of the steps of the corresponding first connecting steel bar and the second connecting steel bar, and the outer peripheries of the first wedge-shaped locking rod and the second wedge-shaped locking rod are sleeved, and the outer peripheral walls of the first wedge-shaped locking rod and the second wedge-shaped locking rod have external threads that are screwed with the internal threads of the inner wall of the sleeve; An outer step is provided on one end of the sleeve; The ends of the first wedge-shaped locking rod and the second wedge-shaped locking rod opposite to each other extend out of the sleeve, and the positions where the first wedge-shaped locking rod and the second wedge-shaped locking rod extend have platform steps for easy twisting; The taper of the first connecting steel bar and the second connecting steel bar end is 2-6 degrees with the taper of the inner peripheral wall of the first wedge-shaped locking rod and the second wedge-shaped locking rod; It also includes a fixing plate A and a template B. The template B is provided with a plurality of through holes in a circular array that match the outer step of the sleeve. The outer step of the sleeve is fixed in the through hole, and the non-step end of the sleeve is downward. The fixing plate A is provided with a steel bar fixing groove corresponding to the through hole. The two ends of the first connecting steel bar are respectively sleeved with a first wedge-shaped locking rod A and a first wedge-shaped locking rod B. One end of the first connecting steel bar is screwed into the non-step end of the sleeve through the first wedge-shaped locking rod, and the other end is welded to the steel bar fixing groove on the fixing plate A. The first wedge-shaped locking rod B is located at the lower part of the fixing plate A. The steel bar fixing groove is also provided with an insert for preventing cement from leaking out.
2. A construction method of a steel cage structure, using the steel cage structure as claimed in claim 1, characterized in that: Step 1) First, select several steel bars of appropriate length according to the needs, put wedge-shaped locking rods on both ends of the steel bars, and then thicken the two ends respectively; Step 2) spot welding a plurality of sleeve outer steps to each through hole on the lower side of a plurality of templates B to form a plurality of standard templates; Step 3) Screw the upper ends of several steel bars to the non-stepped ends of the sleeves on the lower side of the standard template through wedge-shaped locking rods, screw the lower ends of the steel bars to the outer step ends of the sleeves on the upper side of another standard template through wedge-shaped locking rods, and weld the lower ends of each steel bar to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower standard template; Step 4) screwing the lower ends of the other several steel bars into the outer step ends of the sleeves located on the upper side of the upper standard template in the previous step through wedge-shaped locking rods; Step 5) Screw the upper end of the steel bar in the previous step to each sleeve without step on the lower side of another standard template through a wedge-shaped locking rod; Step 6) Weld the lower end of each steel bar in the previous step to the corresponding steel bar welding groove on the fixed plate A 30-50 cm above the lower end of the standard template; Step 7) Repeat steps 4) to 6) until a steel cage assembly of appropriate length is produced, insert the steel bar welding groove of the fixing plate A on each steel cage, and pour cement between the standard template on each steel cage and the fixing plate A to form a concrete component assembly; Step 8) unscrewing the steel bars on the non-stepped ends of each sleeve on the upper side of the standard template to obtain multiple concrete components; Step 9) After transporting to the construction site, assemble and use.