Isolation support structure and construction method of foundation pit of highway tunnel with pipeline under it

By arranging underground continuous walls and dividing walls on both sides of the foundation pit, and setting up structures such as concrete supports and MJS gravity retaining walls, the problem of protecting pipelines and ensuring the safety of the foundation pit when the foundation pit passes through existing pipelines is solved, and the soil mass is reduced. Deformation and construction disturbance, reducing resource waste and construction cycle effects.

CN111576445BActive Publication Date: 2024-10-01CHINA TIESIJU CIVIL ENGINEERING GROUP CO LTD +4
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202010525842.4
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-06-10
Publication Date
2024-10-01
Estimated Expiration
2040-06-10

AI Technical Summary

Technical Problem

In the process of urbanization, when foundation pit construction passes through existing pipelines, it is difficult for existing technologies to effectively protect the existing pipelines and ensure the structural safety of the foundation pit. Moreover, pipeline relocation measures will lead to a waste of resources and prolong the construction period, affecting residents' lives.

Method used

The isolation support structure and construction method of the highway tunnel foundation pit using the pipeline, including laying underground continuous walls and partition walls along both sides of the foundation pit, setting up concrete supports and MJS gravity retaining walls, cast-in-place pile walls and rotary grouting in the interruption area The reinforced wall at the bottom of the pit, the concrete diagonal bracing and horizontal bracing between the dividing wall and the continuous wall use these structures and methods to separate the foundation pit into multiple working areas, reduce the scope of construction disturbance and disperse the soil load.

Benefits of technology

Effectively protect existing pipelines, reduce soil deformation, reduce the impact of foundation pit excavation and unloading on subway tunnels, shorten the construction period, control costs, and improve the strength and construction safety of the soil around the foundation pit.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111576445B_ABST
    Figure CN111576445B_ABST
Patent Text Reader

Abstract

The present invention relates to the technical field of foundation pit support in engineering construction, and specifically to an isolation support structure and a construction method for a highway tunnel foundation pit with a pipeline underpassed, wherein the foundation pit area corresponding to the pipeline is an interruption area, and the isolation support structure includes a pair of underground continuous walls, and the pair of underground continuous walls are respectively disconnected in the interruption area; a concrete support is provided corresponding to each pipeline in the foundation pit of the interruption area, and the concrete support is arranged parallel to the pipeline; a pair of partition walls are arranged between the pair of underground continuous walls, and the foundation pit is divided into an isolation operation area and an external operation area, and an MJS gravity retaining wall is arranged on the side wall of the foundation pit in the interruption area, and a cast-in-place pile wall is arranged along the outer side wall of the pair of continuous walls corresponding to the isolation operation area; an MJS pit bottom reinforcement wall is arranged horizontally at the bottom of the foundation pit in the isolation operation area; and a rotary grouting pit bottom reinforcement wall is arranged at the bottom of the foundation pit in the external operation area. The present invention solves the isolation support problem of the highway tunnel foundation pit with a pipeline underpassed and a subway tunnel overpassed, and ensures the smooth progress of the foundation pit excavation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of foundation pit support in engineering construction, and in particular to an isolation support structure and a construction method for a foundation pit of a highway tunnel with a pipeline passing underneath. Background Art

[0002] With the advancement of urbanization, urban space resources are becoming increasingly scarce. In order to cope with the traffic congestion caused by the rapid population density and improve urban functional construction, more and more traffic arteries are transferred underground. Since traffic arteries are often located in densely built urban areas, the excavation of road foundation pits will inevitably have an adverse impact on the surrounding environment. In view of the current complex urban pipeline settings, the later-built foundation pit will inevitably cross the pipeline construction, which brings many inconveniences to the foundation pit structure support and pipeline protection.

[0003] At present, for projects where the foundation pit crosses the existing pipeline, most of the measures adopted are pipeline relocation. Pipeline relocation can not only avoid the problem of selecting the foundation pit support structure during the foundation pit excavation process and ensure the safety of the foundation pit, but also avoid the impact of excavation unloading on the existing pipeline. Therefore, it is widely used in such projects. However, in the case of the foundation pit crossing the pipeline, the length of the pipeline exposed in the foundation pit is relatively long. The relocation measures will inevitably occupy other land space resources, extend the construction period of the project, increase the project economy, and be unfavorable to cost control. The original pipeline buried in the underground soil layer will also cause a waste of resources; at the same time, for important pipelines required for urban life, relocation will inevitably affect the lives of residents and cause inconvenience to their lives.

[0004] Although there are engineering cases and support technologies for in-situ protection of pipelines crossing foundation pits, they still focus on in-situ protection of pipelines and ignore the safety of foundation pit support itself.

[0005] In view that the foundation pit and the surrounding environment are a complex community, and the foundation pit and the existing pipelines are an inseparable whole, it is particularly important to design a support system for coordinated control of the foundation pit and the pipelines. Summary of the invention

[0006] The present invention solves the problems in the background technology and provides an isolation protection support system and a construction method for a highway tunnel foundation pit under an existing pipeline. The method can not only meet the foundation pit support requirements, but also play a role in protecting the existing pipeline. The specific technical solution of the present invention is:

[0007] The invention discloses an isolation support structure and construction method for a highway tunnel foundation pit with a pipeline under it, wherein the foundation pit 1 is a highway tunnel construction foundation pit, the foundation pit 1 passes under an existing pipeline 2, and the distance between the top plate of the highway tunnel 5 and the pipeline 2 is ≥0.5m, the area of ​​the foundation pit 1 corresponding to the pipeline 2 is an interruption area 7, and a subway tunnel 6 crosses the soil below the foundation pit 1.

[0008] The isolation support structure includes a pair of underground continuous walls 3 arranged along the two side walls of the foundation pit 1, and the pair of underground continuous walls 3 are respectively disconnected at the interruption area 7; a concrete support 11 is provided in the foundation pit 1 in the interruption area 7 corresponding to each pipeline 2, and the concrete support 11 is arranged parallel to the pipeline 2;

[0009] A pair of partition walls 4 are arranged between the pair of underground continuous walls 3. The pair of partition walls 4 are arranged vertically and at intervals in the foundation pit 1, dividing the foundation pit 1 into an isolated working area 9 and an external working area 10. The area of ​​the foundation pit 1 corresponding to the pair of partition walls 4 is the isolated working area 9, and the interruption area 7 is located in the middle of the isolated working area 9;

[0010] The side wall of the foundation pit 1 of the interruption zone 7 is provided with an MJS gravity retaining wall 14, and a cast-in-place pile wall 13 is evenly distributed along the outer side walls of a pair of continuous walls corresponding to the isolation operation zone 9;

[0011] An MJS pit bottom reinforcement wall 12 is horizontally arranged at the bottom of the foundation pit 1 of the isolation working area 9, and the thickness of the MJS pit bottom reinforcement wall 12 is ≥5m; a pair of partition walls 4 corresponding to the bottom of the foundation pit 1 of the external working area 10 are horizontally arranged with a rotary jet pit bottom reinforcement wall 17, and the thickness of the rotary jet pit bottom reinforcement wall 17 is ≥4m.

[0012] Furthermore, the disconnected parts of the pair of underground continuous walls 3 are provided with folded walls 8, the folded walls 8 and the ends of the continuous walls are vertically connected correspondingly, and the lateral extension length of the folded walls 8 is 1.0 to 1.5 m; the depth of the cast-in-place pile wall 13 is greater than the depth of the MJS gravity retaining wall 14, and the pile bodies of the cast-in-place pile wall 13 are connected by bite.

[0013] Furthermore, the lateral extension length of the MJS gravity retaining wall 14 is greater than twice the longitudinal extension length of the interruption zone 7 , and the thickness of the MJS gravity retaining wall 14 is greater than the longitudinal extension length of the interruption zone 7 .

[0014] Furthermore, the concrete support 11 is flush with the upper end of the fold wall 8, a concrete diagonal brace 15 is provided between the side wall of the partition wall and the corresponding inner wall of the continuous wall, and a concrete transverse brace 16 is provided between a pair of continuous walls adjacent to the diagonal brace.

[0015] The present invention also includes a construction method for the isolation support structure of the highway tunnel foundation pit, which specifically includes the following construction steps:

[0016] Step (1): simultaneously pouring a pair of underground continuous walls 3, a folded wall 8 and a partition wall in the foundation pit 1, wherein the thickness and depth of the folded wall 8, the partition wall and the pair of underground continuous walls 3 are the same;

[0017] The area of ​​the foundation pit 1 corresponding to the pipeline 2 is the interruption area 7, and a pair of continuous walls are disconnected in the interruption area 7. A folding wall 8 is provided at the end of the pair of continuous walls corresponding to the interruption area 7, and the folding wall 8 is vertically connected to the end of the corresponding continuous wall, and the lateral extension length of the folding wall 8 is 1.0 to 1.5 m;

[0018] Step (2): The soil is reinforced on the side wall of the foundation pit 1 corresponding to the interruption zone 7 by using the MJS method to form an MJS gravity retaining wall 14, wherein the lateral extension length of the MJS gravity retaining wall 14 is greater than twice the longitudinal extension length of the interruption zone 7, the thickness of the MJS gravity retaining wall 14 is greater than the longitudinal extension length of the interruption zone 7, and the depth of the MJS gravity retaining wall 14 is greater than the depth of a pair of underground continuous walls 3; wherein the construction cement slurry pressure of the MJS method is ≥40MPa, the water-cement ratio is 1:1, and the air pressure is 1.05MPa;

[0019] Step (3): constructing bored cast-in-place piles along the outer side walls of a pair of continuous walls corresponding to the isolation operation area 9 to form a bored pile wall 13. To ensure the quality of the bored pile wall 13, the bored cast-in-place piles adopt an interlocking construction technology so that the pile bodies of the bored pile wall 13 are interlocked and connected, and the depth of each pile body is 1 to 1.5 times the depth of the pair of underground continuous walls 3;

[0020] Step (4): using the MJS method to reinforce the soil layer at the bottom of the foundation pit 1 of the isolation operation area 9, forming a horizontal MJS pit bottom reinforcement wall 12, and the thickness of the MJS pit bottom reinforcement wall 12 is ≥5m; wherein the cement slurry pressure of the MJS method is ≥30MPa, the water-cement ratio is 1:1, and the air pressure is 0.8MPa;

[0021] The soil layer at the bottom of the foundation pit 1 in the external operation area 10 is reinforced by using a high-pressure jet grouting pile reinforcement method to form a horizontal jet grouting pit bottom reinforcement wall 17 with a thickness of ≥4m and a length of 4~5m; the water-cement ratio of the high-pressure jet grouting pile reinforcement method is 1.0, the air pressure is 0.6~0.8Mpa, and the water pressure is 30~35Mpa;

[0022] Step (5): construct a concrete support 11 corresponding to each pipe 2, the height of the concrete support 11 is flush with the upper end of the folding wall 8, and each concrete support 11 is arranged parallel to the corresponding pipe 2.

[0023] A concrete diagonal brace 15 is constructed between the outer side wall of the partition wall and the inner side wall of the corresponding continuous wall, and a concrete transverse brace 16 is constructed between a pair of continuous walls adjacent to the diagonal brace;

[0024] Step (6): After the isolation support structure is constructed and its strength meets the design strength requirements, the isolation operation area 9 is dewatered by dewatering in the pit. After dewatering, the water level is at least 0.5 m lower than the bottom excavation surface of the foundation pit 1 of the isolation operation area 9;

[0025] Adopting the layered and block excavation method, excavate the earthwork from the middle of the isolated working area 9 to both sides in sequence until the excavation of the foundation pit 1 of the isolated working area 9 is completed;

[0026] Step (7): Dewatering the external working areas 10 on both sides, so that the water level after dewatering is at least 0.5 m lower than the bottom excavation surface of the foundation pit 1 of the external working areas 10;

[0027] The external working area 10 is excavated by adopting a layered and block-by-block excavation method until the excavation of the foundation pit 1 of the external working area 10 is completed;

[0028] Step (8): Remove a pair of partition walls 4 and concrete diagonal braces 15 to make the entire foundation pit 1 connected. After the construction of the highway tunnel 5 in the foundation pit 1 is completed, backfill the soil.

[0029] The beneficial technical effects of the present invention are as follows:

[0030] (1) For the existing pipelines in the foundation pit, the present invention uses partition walls to divide the foundation pit into multiple operation areas, wherein the foundation pit corresponding to the pipeline is further divided into interruption areas in the isolation operation area. By adjusting the position of the partition wall to avoid the easily damaged parts of the foundation pit, the protection work of the existing pipeline becomes an independent construction operation area, which greatly reduces the scope of construction disturbance, weakens the mutual influence of construction in other operation areas, and effectively controls the deformation of the foundation pit, the existing pipeline and the soil around the foundation pit;

[0031] Concrete supports are arranged corresponding to each pipeline in the interruption area, cast-in-place pile walls are arranged outside the continuous wall of the isolation working area, MJS gravity retaining walls are arranged on the side walls of the foundation pit in the interruption area, and folding walls are arranged at the ends of the continuous walls. The above-mentioned isolation support structure is continuous and complete, which can disperse the soil load and reduce the stress and deformation of the existing pipelines. Among them, the MJS gravity retaining wall formed by the MJS method reinforces the soil outside the isolation working area, which is beneficial to enhance the retaining and water-stopping effects of the support structure, increase the strength of the soil outside the pit, and reduce the displacement of the soil, thereby achieving the purpose of controlling deformation.

[0032] (2) In order to solve the problem of the subway tunnel crossing under the highway tunnel foundation pit, the present invention uses the MJS method to reinforce the soil layer at the bottom of the foundation pit in the isolation operation area to form a horizontal MJS pit bottom reinforcement wall, and the thickness of the MJS pit bottom reinforcement wall is ≥5m, which is conducive to reducing the unloading effect of the excavation of the earthwork in the pit and weakening the impact of the subsequent subway tunnel construction on the upper underground passage and existing pipelines;

[0033] The high-pressure rotary jet pile reinforcement method is used to reinforce the soil layer at the bottom of the foundation pit in the external working area, forming a horizontal rotary jet pit bottom reinforcement wall with a thickness of ≥4m. This is beneficial to ensure the continuity of the pit bottom reinforcement and avoid uneven force on the foundation pit. At the same time, the use of rotary jet reinforcement technology is also beneficial to reduce costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0034] Figure 1 A top view of the isolation protection support structure of the present invention;

[0035] Figure 2 It is a three-dimensional schematic diagram of the isolation protection support structure of the present invention;

[0036] Figure 3 A schematic diagram of the pit bottom of the isolation protection support structure of the present invention;

[0037] Figure 4 1-1 is a cross-sectional view of the isolation protection support structure of the present invention;

[0038] Figure 5 It is a schematic diagram of the three-dimensional structure of the isolation working area of ​​the isolation protection support structure of the present invention;

[0039] Figure 6 A side view of the isolation working area of ​​the isolation protection support structure of the present invention;

[0040] In the figure: 1-foundation pit; 2-pipeline; 3-a pair of underground continuous walls; 4-a pair of partition walls; 5-highway tunnel; 6-subway tunnel; 7-interruption area; 8-fold wall; 9-isolation work area; 10-external work area; 11-concrete support; 12-MJS pit bottom reinforcement wall; 13-cast-in-place pile wall; 14-MJS gravity retaining wall; 15-concrete diagonal brace; 16-concrete horizontal brace; 17-jet-cast pit bottom reinforcement wall. DETAILED DESCRIPTION

[0041] To make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific implementation methods described herein are only used to explain the present invention and are not intended to limit the present invention.

[0042] Example 1

[0043] See Figure 1 to Figure 6 The isolation support structure of the highway tunnel foundation pit under the pipeline of the present invention, the foundation pit 1 is the construction foundation pit 1 of the highway tunnel 5, the foundation pit 1 extends horizontally for 30m and the excavation depth is 12m, the foundation pit 1 passes under the existing pipeline 2, and the distance between the top plate of the highway tunnel 5 and the pipeline 2 is 0.7m, the diameter of the pipeline 2 is 1.8m and 1.4m, and the buried depth of the pipeline 2 is 2.3m.

[0044] The area of ​​the foundation pit 1 corresponding to the pipeline 2 is the interruption zone 7, and the longitudinal extension length of the interruption zone 7 is 7.2m. A subway tunnel 6 crosses the soil below the foundation pit 1. The subway tunnel 6 has a diameter of 6.6m and a burial depth of 22.8m.

[0045] The isolation support structure includes a pair of underground continuous walls 3 arranged along the two side walls of the foundation pit 1, and the thickness of the continuous wall is 0.6m and the depth is 18m.

[0046] A pair of underground continuous walls 3 are respectively disconnected at the interruption area 7 , and a concrete support 11 is provided in the foundation pit 1 of the interruption area 7 corresponding to each pipeline 2 , and the concrete support 11 is arranged parallel to the pipeline 2 .

[0047] A pair of partition walls 4 is arranged between the pair of underground continuous walls 3. The pair of partition walls 4 are arranged vertically and at intervals in the foundation pit 1. The thickness of the partition walls is 0.6 m and the depth is 18 m.

[0048] A pair of partition walls 4 divides the foundation pit 1 into an isolated working area 9 and an external working area 10. The area of ​​the foundation pit 1 corresponding to the pair of partition walls 4 is the isolated working area 9, and the interruption area 7 is located in the middle of the isolated working area 9. The longitudinal extension length of the isolated working area 9 is 38m, and the water level is reduced to 1m from the bottom of the pit.

[0049] The side wall of the foundation pit 1 of the interruption zone 7 is provided with an MJS gravity retaining wall 14, which has a thickness of 8.5m, a longitudinal extension length of 15m and a depth of 25m. Cast-in-place pile walls 13 are evenly distributed along the outer side walls of a pair of continuous walls corresponding to the isolation working area 9. The diameter of each cast-in-place pile of the cast-in-place pile wall 13 is 850mm and the pile body depth is 25m.

[0050] An MJS pit bottom reinforcement wall 12 is horizontally arranged at the bottom of the foundation pit 1 of the isolation working area 9, and the thickness of the MJS pit bottom reinforcement wall 12 is 5m; a pair of partition walls 4 corresponding to the bottom of the foundation pit 1 of the external working area 10 are horizontally arranged with a rotary jet pit bottom reinforcement wall 17, and the thickness of the rotary jet pit bottom reinforcement wall 17 is 4m.

[0051] The disconnected parts of the pair of underground continuous walls 3 are both provided with folded walls 8, which are 0.6m thick and 18m deep. The folded walls 8 are vertically connected to the ends of the continuous walls, and the longitudinal extension length of the folded walls 8 is 1.5m. The vertical depth of the cast-in-place pile wall 13 is 1.2 times the depth of the MJS gravity retaining wall 14, and the pile bodies of the cast-in-place pile wall 13 are connected by bite.

[0052] The longitudinal extension length of the MJS gravity retaining wall 14 is greater than twice the longitudinal extension length of the interruption zone 7 , and the thickness of the MJS gravity retaining wall 14 is greater than the longitudinal extension length of the interruption zone 7 .

[0053] The concrete support 11 is flush with the upper end of the fold wall 8, a concrete diagonal brace 15 is provided between the side wall of the partition wall and the corresponding inner wall of the continuous wall, and a concrete transverse brace 16 is provided between a pair of continuous walls adjacent to the diagonal brace.

[0054] Example 2

[0055] The construction method of the isolation support structure of the foundation pit 1 of the highway tunnel 5 under the pipeline 2 based on Example 1 specifically includes the following steps:

[0056] Step (1): simultaneously pouring a pair of underground continuous walls 3, a folded wall 8 and a partition wall in the foundation pit 1, wherein the thickness and depth of the folded wall 8, the partition wall and the pair of underground continuous walls 3 are the same, and the thickness is 0.6 m and the depth is 18 m;

[0057] The area of ​​the foundation pit 1 corresponding to the pipeline 2 is the interruption zone 7, the longitudinal extension length of the interruption zone 7 is 7.2m, and a pair of continuous walls are disconnected in the interruption zone 7. A folding wall 8 is provided at the end of a pair of continuous walls corresponding to the interruption zone 7, and the folding wall 8 is vertically connected to the end of the corresponding continuous wall, and the lateral extension length of the folding wall 8 is 1.5m.

[0058] Step (2): The soil is reinforced on the side wall of the foundation pit 1 corresponding to the interruption zone 7 by the MJS method to form an MJS gravity retaining wall 14, and the lateral extension length of the MJS gravity retaining wall 14 is greater than twice the longitudinal extension length of the interruption zone 7, the thickness of the MJS gravity retaining wall 14 is greater than the longitudinal extension length of the interruption zone 7, and the depth of the MJS gravity retaining wall 14 is greater than the depth of a pair of underground continuous walls 3; the construction cement slurry pressure of the MJS method is ≥40MPa, the water-cement ratio is 1:1, the air pressure is 1.05MPa, and the thickness of the formed MJS gravity retaining wall 14 is 8.5m, the length is 15m, and the depth is 25m.

[0059] Step (3): bored cast-in-place piles are constructed along the outer walls of a pair of continuous walls corresponding to the isolation operation area 9 to form a bored pile wall 13. To ensure the quality of the bored pile wall 13, the bored cast-in-place piles are constructed using bite-joint construction technology, so that the pile bodies of the bored pile wall 13 are connected by bite-joint connection, and the depth of each pile body is 1.5 times the depth of the pair of underground continuous walls 3.

[0060] Step (4): Use the MJS method to reinforce the soil layer at the bottom of the foundation pit 1 of the isolation operation area 9 to form a horizontal MJS pit bottom reinforcement wall 12, and the thickness of the MJS pit bottom reinforcement wall 12 is 5m, the cement slurry pressure of the MJS method is ≥30MPa, the water-cement ratio is 1:1, and the air pressure is 0.8MPa;

[0061] The soil layer at the bottom of the foundation pit 1 in the external operation area 10 is reinforced by using a high-pressure jet grouting pile reinforcement method to form a horizontal jet grouting pit bottom reinforcement wall 17 with a thickness of 4m and a length of 4-5m. The high-pressure jet grouting pile reinforcement method uses 42.5 grade silicate cement, a water-cement ratio of 1.0, an air pressure of 0.6-0.8Mpa, and a water pressure of 30-35Mpa;

[0062] Step (5): Construct a concrete support 11 on one side of each pipe 2. The height of the concrete support 11 is consistent with the height of the folding wall 8, and each concrete support 11 is arranged parallel to the corresponding pipe 2.

[0063] A concrete diagonal brace 15 is constructed between the outer side wall of the partition wall and the inner side wall of the corresponding continuous wall, and a concrete transverse brace 16 is constructed between a pair of continuous walls adjacent to the diagonal brace;

[0064] Step (6): After the isolation support structure is constructed and its strength meets the design strength requirements, the isolation operation area 9 is dewatered by dewatering in the pit. After dewatering, the water level is at least 0.5 m lower than the bottom excavation surface of the foundation pit 1 of the isolation operation area 9;

[0065] A layered and block excavation method is adopted to carry out earth excavation from the middle of the isolated working area 9 to both sides in sequence. The excavation thickness of each layer is ≤2m, and the block excavation length is ≤5m, until the excavation of the foundation pit 1 of the isolated working area 9 is completed.

[0066] Step (7): Dewatering the external working areas 10 on both sides, so that the water level after dewatering is at least 0.5 m lower than the bottom excavation surface of the foundation pit 1 of the external working areas 10;

[0067] The external working area 10 is excavated by adopting a layered and block excavation method, with the excavation thickness of each layer ≤2m and the block excavation length ≤5m, until the excavation of the foundation pit 1 of the external working area 10 is completed.

[0068] Step (8): Remove a pair of partition walls 4 and concrete diagonal braces 15 to make the entire foundation pit 1 connected. After the construction of the highway tunnel 5 in the foundation pit 1 is completed, backfill the soil.

[0069] The present invention solves the isolation support problem of a highway tunnel foundation pit with a pipeline passing underneath, and the details are as follows:

[0070] (1) With respect to the existing pipeline 2 in the foundation pit 1, the present invention uses a partition wall to divide the foundation pit 1 into a plurality of operation sections, wherein the foundation pit 1 corresponding to the pipeline 2 is further divided into an interruption section 7 in the isolation operation section 9. By adjusting the position of the partition wall to avoid the easily damaged parts of the foundation pit 1, the protection work of the existing pipeline 2 becomes an independent construction operation section, which greatly reduces the scope of construction disturbance, weakens the mutual influence of construction in other operation sections, and effectively controls the deformation of the foundation pit 1, the existing pipeline 2 and the soil around the foundation pit 1;

[0071] Concrete supports 11 are evenly arranged corresponding to each pipeline 2 in the interruption zone 7, cast-in-place pile walls 13 are arranged outside the continuous wall of the isolation working area 9, MJS gravity retaining walls 14 are arranged on the side walls of the foundation pit 1 of the interruption zone 7, and folding walls 8 are provided at the ends of the continuous wall. The above-mentioned isolation support structure is continuous and complete, which can disperse the soil load and reduce the stress deformation of the existing pipeline 2; the MJS gravity retaining wall 14 formed by the MJS method reinforces the soil outside the isolation working area 9, which is beneficial to enhance the retaining and water-stopping effects of the support structure, increase the strength of the soil outside the pit, and reduce the displacement of the soil, thereby achieving the purpose of controlling deformation.

[0072] (2) To address the problem of the subway tunnel 6 crossing the bottom of the highway tunnel foundation pit, the present invention uses the MJS method to reinforce the bottom soil layer of the foundation pit 1 of the isolation operation area 9 to form a horizontal MJS pit bottom reinforcement wall 12, and the thickness of the MJS pit bottom reinforcement wall 12 is ≥5m, which is conducive to reducing the unloading effect of the excavation of the earthwork in the pit and weakening the impact of the subsequent construction of the subway tunnel 6 on the upper underground passage and the existing pipeline 2;

[0073] The soil layer at the bottom of the foundation pit 1 in the external working area 10 is reinforced by using high-pressure jet grouting pile reinforcement method to form a horizontal jet grouting pit bottom reinforcement wall 17 with a thickness of ≥4m, which is beneficial to ensure the continuity of the pit bottom reinforcement and avoid uneven force on the foundation pit 1. At the same time, the use of jet grouting reinforcement technology is also beneficial to reducing costs.

[0074] (3) The MJS method is used in both the MJS pit bottom reinforcement wall 12 and the MJS gravity retaining wall 14. The MJS method can be constructed in all directions and at any angle, with controllable construction quality, high reliability, and little impact on the surrounding environment during the construction process. The MJS method is used to reinforce the soil outside the isolation operation area 9, which is beneficial to enhancing the retaining and water-stopping effects of the support structure, increasing the strength of the soil outside the pit, and reducing the displacement of the soil, thereby achieving the purpose of controlling deformation; the reinforcement of the pit bottom of the isolation operation area 9 is beneficial to reducing the unloading effect of the excavation of the earthwork in the pit, and reducing the impact of the subsequent construction of the subway tunnel 6 on the upper underground passage and the existing pipeline 2.

[0075] It will be easily understood by those skilled in the art that the above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions and improvements made within the spirit and principles of the present invention should be included in the protection scope of the present invention.

Claims

1. A method for constructing an isolation support structure for a highway tunnel foundation pit with a pipeline passing underneath, wherein the foundation pit (1) is a highway tunnel construction foundation pit, the foundation pit (1) passes underneath an existing pipeline (2), and the distance between the top plate of the highway tunnel (5) and the pipeline (2) is ≥0.5 m, the area of ​​the foundation pit (1) corresponding to the pipeline (2) is an interruption area (7), and a subway tunnel (6) passes through the soil below the foundation pit (1). Features: The isolation support structure comprises a pair of underground continuous walls (3) arranged along the two side walls of the foundation pit (1), and the pair of underground continuous walls (3) are respectively disconnected at the interruption area (7); a concrete support (11) is provided in the foundation pit (1) in the interruption area (7) corresponding to each pipeline (2), and the concrete support (11) is arranged parallel to the pipeline (2); A pair of partition walls (4) are arranged between the pair of underground continuous walls (3); the pair of partition walls (4) are arranged vertically and at intervals in the foundation pit (1), dividing the foundation pit (1) into an isolated working area (9) and an external working area (10); the area of ​​the foundation pit (1) corresponding to the pair of partition walls (4) is the isolated working area (9), and the interruption area (7) is located in the middle of the isolated working area (9); The side walls of the foundation pit (1) of the interruption zone (7) are provided with MJS gravity retaining walls (14), and cast-in-place pile walls (13) are evenly distributed along the outer side walls of a pair of continuous walls corresponding to the isolation operation zone (9); The bottom of the foundation pit (1) of the isolation operation area (9) is horizontally provided with an MJS pit bottom reinforcement wall (12), and the thickness of the MJS pit bottom reinforcement wall (12) is ≥5m; the bottom of the foundation pit (1) of the external operation area (10) is horizontally provided with a jet grouting pit bottom reinforcement wall (17) corresponding to a pair of partition walls (4), and the thickness of the jet grouting pit bottom reinforcement wall (17) is ≥4m; The specific construction steps include the following: Step (1): simultaneously pouring a pair of underground continuous walls (3), a folded wall (8) and a partition wall in the foundation pit (1), wherein the thickness and depth of the folded wall (8), the partition wall and the pair of underground continuous walls (3) are the same; The area of ​​the foundation pit (1) corresponding to the pipeline (2) is an interruption zone (7), and the pair of continuous walls are disconnected in the interruption zone (7). The ends of the pair of continuous walls corresponding to the interruption zone (7) are provided with folded walls (8), and the folded walls (8) are vertically connected to the ends of the corresponding continuous walls. The lateral extension length of the folded walls (8) is 1.0 to 1.5 m. Step (2): The soil is reinforced on the side wall of the foundation pit (1) corresponding to the interruption zone (7) by using the MJS method to form an MJS gravity retaining wall (14), wherein the lateral extension length of the MJS gravity retaining wall (14) is greater than twice the longitudinal extension length of the interruption zone (7), the thickness of the MJS gravity retaining wall (14) is greater than the longitudinal extension length of the interruption zone (7), and the depth of the MJS gravity retaining wall (14) is greater than the depth of a pair of underground continuous walls (3); wherein the construction cement slurry pressure of the MJS method is ≥40MPa, the water-cement ratio is 1:1, and the air pressure is 1.05MPa; Step (3): constructing bored cast-in-place piles along the outer side walls of a pair of continuous walls corresponding to the isolation operation area (9) to form a bored cast-in-place pile wall (13). To ensure the quality of the bored cast-in-place pile wall (13), the bored cast-in-place piles adopt an interlocking construction technology so that the pile bodies of the bored cast-in-place pile wall (13) are interlocked and connected, and the depth of each pile body is 1 to 1.5 times the depth of the pair of underground continuous walls (3); Step (4): using the MJS method to reinforce the soil layer at the bottom of the foundation pit (1) of the isolation operation area (9) to form a horizontal MJS pit bottom reinforcement wall (12), and the thickness of the MJS pit bottom reinforcement wall (12) is ≥5m; wherein the cement slurry pressure of the MJS method is ≥30MPa, the water-cement ratio is 1:1, and the air pressure is 0.8MPa; The soil layer at the bottom of the foundation pit (1) of the external working area (10) is reinforced by using a high-pressure jet grouting pile reinforcement method to form a horizontal jet grouting pit bottom reinforcement wall (17) with a thickness of ≥4m and a length of 4-5m; wherein the water-cement ratio of the high-pressure jet grouting pile reinforcement method is 1.0, the air pressure is 0.6-0.8Mpa, and the water pressure is 30-35Mpa; Step (5): constructing a concrete support (11) corresponding to each pipe (2), wherein the height of the concrete support (11) is flush with the upper end of the folded wall (8), and each concrete support (11) is arranged parallel to the corresponding pipe (2). A concrete diagonal brace (15) is constructed between the outer wall of the partition wall and the inner wall of the corresponding continuous wall, and a concrete transverse brace (16) is constructed between a pair of continuous walls adjacent to the diagonal brace; Step (6): after the construction of the isolation support structure is completed and the strength meets the design strength requirements, the isolation operation area (9) is dewatered by using an in-pit dewatering method, and the water level after dewatering is at least 0.5 m lower than the bottom excavation surface of the foundation pit (1) of the isolation operation area (9); Adopting a layered and block-by-block excavation method, excavating earthwork from the middle of the isolated working area (9) to both sides in sequence until the excavation of the foundation pit (1) of the isolated working area (9) is completed; Step (7): dewatering the external working areas (10) on both sides, so that the water level after dewatering is at least 0.5 m lower than the bottom excavation surface of the foundation pit (1) of the external working areas (10); Excavating the external working area (10) in layers and blocks until the excavation of the foundation pit (1) of the external working area (10) is completed; Step (8): dismantle a pair of partition walls (4) and concrete diagonal braces (15) to allow the entire foundation pit (1) to be connected, and backfill the foundation pit (1) with earth after the highway tunnel (5) is constructed.

Citation Information

Cited By

  • Strong supporting device and method for tunnel underneath passing natural gas pipeline

    CN121322734A