Portable concrete structure casing pre-embedding tool and method

Through the portable concrete structure casing pre-embedded tool, the combination of fixed steel plates and support components is used to solve the problem of inaccurate positioning of the embedded casing in the concrete structure, precise positioning and efficient fixing during construction, and reduced structural leakage Risk and material costs.

CN113187228BActive Publication Date: 2024-12-03CHINA MCC5 GROUP CORP LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202110629964.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2021-06-07
Publication Date
2024-12-03
Estimated Expiration
2041-06-07

AI Technical Summary

Technical Problem

During construction, the embedded casing in the concrete structure is prone to move and incline in position, resulting in inaccurate positioning, complex and inconvenient fixing methods, resulting in hidden dangers of structural leakage and low construction efficiency.

Method used

Using portable concrete structural casing pre-embedded tools, including fixed steel plates and fixed support components, they are fixed on the concrete pouring formwork by welding, and fixed steel plates and support components are installed at both ends of the embedded casing to ensure accurate positioning and fixed strength. Steel belt, steel plate, steel bar and other materials simplify the production and installation process.

Benefits of technology

The precise positioning and stable fixation of concrete structural casings is achieved, which reduces the hidden danger of structural leakage, improves construction efficiency and operation convenience, and reduces material losses and costs.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN113187228B_ABST
    Figure CN113187228B_ABST
Patent Text Reader

Abstract

The invention discloses a portable concrete structure casing pre-embedding tool and method, comprising a fixed steel plate and a fixed support assembly, wherein the fixed steel plate is fixed on a concrete casting template, the fixed support assembly is vertically welded and fixed on a side of the fixed steel plate away from the concrete casting template, and the fixed support assembly is used to insert the pre-embedded casing and fix the pre-embedded casing; the number of the fixed steel plates and the fixed support assembly is two, and a fixed steel plate and a fixed support assembly are respectively provided at both ends of the pre-embedded casing, so as to fix the two ends of the pre-embedded casing; a convenient concrete structure casing pre-embedding construction method is adopted, and before the construction of the building structure beams, walls and columns, the convenient concrete structure casing pre-embedding construction method is used, which has the advantages of convenient installation, accurate positioning, not easy to move, good fixing strength, reduced structural leakage risks, convenient operation, convenient installation and disassembly, and efficient construction.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of construction, and in particular to a portable concrete structure casing pre-embedding tool and method. Background Art

[0002] During the construction process, it is necessary to set embedded sleeves in the concrete structure. However, during the concrete pouring process, the position of the embedded sleeves is easily moved, resulting in the tilt of the embedded sleeves in the poured concrete. Therefore, the precise positioning of the embedded parts is very demanding. Deviations in the manufacturing process may cause mismatches in on-site installation and may even cause them to be scrapped. The embedded parts are usually fixed by welding or binding of steel structure, resulting in inaccurate positioning of the embedded parts or embedded holes, and the process is complicated and inconvenient to operate. Therefore, there is an urgent need for a portable concrete structure sleeve embedding tool and method that is easy to use and has precise positioning. Summary of the invention

[0003] The present invention aims to provide a portable concrete structure casing pre-embedding tool and method, which adopts a convenient concrete structure casing pre-embedding construction method. Before the construction of building structure beams, walls and columns, the convenient concrete structure casing pre-embedding construction method is used, which is convenient to install, accurate in positioning, not easy to move, good in fixing strength, reduces the hidden danger of structural leakage, is easy to operate, easy to install and disassemble, and has efficient construction.

[0004] The embodiment of the present invention is achieved as follows:

[0005] A portable concrete structure casing pre-embedded tool comprises a fixed steel plate and a fixed support assembly, wherein the fixed steel plate is fixed on a concrete casting template, the fixed support assembly is vertically welded and fixed on a side of the fixed steel plate away from the concrete casting template, and the fixed support assembly is used to insert and fix the pre-embedded casing; the number of the fixed steel plate and the fixed support assembly is two, and a fixed steel plate and a fixed support assembly are respectively provided at both ends of the pre-embedded casing, thereby fixing the two ends of the pre-embedded casing. A convenient concrete structure casing pre-embedded construction method is adopted. Before the construction of the structural beams, walls and columns of the building, the convenient concrete structure casing pre-embedded construction method is used, which is convenient to install, accurate in positioning, not easy to run out of position, good in fixing strength, reduces the hidden danger of structural leakage, is convenient to operate, convenient to install and disassemble, and has high construction efficiency. According to the structural position and construction progress of the pre-embedded casing, the fixed parts are standardized and batch-produced in advance to improve the construction efficiency. Steel strips, steel plates, steel bars and other material components are adopted, and the materials are simple and convenient to make. The mold is flexible and convenient to install and disassemble, with a high turnover rate, reduced material loss and low material cost.

[0006] Preferably, the fixed support assembly includes two support rods, both of which are abutted against the inner hole of the embedded sleeve, and the support rods are symmetrically arranged with the center of the embedded sleeve as the center of symmetry, and the distance between the outer sides of the two support rods is equal to the inner diameter of the embedded sleeve.

[0007] Preferably, the fixed support assembly includes at least three support rods, and the support rods are all abutted against the inner hole of the embedded sleeve.

[0008] Preferably, the support rods are symmetrically arranged with the center of the embedded sleeve as the center of symmetry.

[0009] Preferably, the support rod is a steel bar or a round steel bar.

[0010] Preferably, the length of the support rod is not greater than 100 mm.

[0011] Preferably, the fixed steel plate is an L-shaped structure, and the fixed steel plate includes a first fixed plate for abutting against the wall column formwork and a second fixed plate for abutting against the panel formwork, and the second fixed plate is fixed to the panel formwork by carpentry nails.

[0012] Preferably, the panel template is placed horizontally, and the second fixing plate is supported on the panel template.

[0013] Preferably, the first fixing plate and the second fixing plate are a fixed integral structure.

[0014] A portable concrete structure casing pre-embedding method is also provided, comprising the above-mentioned pre-embedding tool, and further comprising the following steps:

[0015] S1: A steel plate with a thickness of 1 mm is processed to form a fixed steel plate with an L-shaped structure;

[0016] S2: Select the quantity, length and position of the steel bars or round steel bars in the fixed support assembly according to the diameter of the fixed sleeve;

[0017] S3: inserting the fixed support assembly into the fixed sleeve, thereby fixing the fixed sleeve;

[0018] S4: Place the fixed steel plate in the pre-embedded position of the beam, wall and column. After correcting the position, use carpentry nails to fix the entire kit to the board template through the milling holes of the fixing parts.

[0019] S5: After pouring is completed, the slab formwork, wall column formwork, fixed steel plate and fixed support components are disassembled at the same time.

[0020] Due to the adoption of the above technical scheme, the beneficial effects of the present invention include: a portable concrete structure sleeve pre-embedded tool and method of the present invention, including a fixed steel plate and a fixed support assembly, the fixed steel plate is fixed on the concrete casting template, the fixed support assembly is vertically welded and fixed on the side of the fixed steel plate away from the concrete casting template, and the fixed support assembly is used to insert the embedded sleeve and fix the embedded sleeve; the number of the fixed steel plate and the fixed support assembly is two, and a fixed steel plate and a fixed support assembly are respectively provided at both ends of the embedded sleeve, thereby fixing the two ends of the embedded sleeve. The convenient concrete structure sleeve pre-embedded construction method is adopted. Before the construction of the building structure beams, walls, and columns, the convenient concrete structure sleeve pre-embedded construction method is used, which is convenient to install, accurate in positioning, not easy to move, good in fixing strength, reduces the hidden dangers of structural leakage, is convenient to operate, convenient to install and disassemble, and efficient in construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0021] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the drawings in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present invention and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0022] Figure 1 It is a schematic diagram of a first installation structure of the present invention;

[0023] Figure 2 is a schematic diagram of a second installation structure of the present invention;

[0024] Figure 3 It is a schematic diagram of the structure of the embedded tool of the present invention.

[0025] Specific element symbol description: 1 embedded sleeve; 2 fixed support assembly; 3 fixed steel plate; 4 board surface formwork; 5 wall column formwork; 31 carpentry nails; 32 second fixed plate; 33 first fixed plate; 321 milling hole. DETAILED DESCRIPTION

[0026] In order to make the purpose, technical solutions and advantages of the embodiments of the present invention clearer, the technical solutions in the embodiments of the present invention will be clearly and completely described below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are part of the embodiments of the present invention, not all of the embodiments. Generally, the components of the embodiments of the present invention described and shown in the drawings here can be arranged and designed in various different configurations.

[0027] The following detailed description of the embodiments of the present invention provided in the accompanying drawings is not intended to limit the scope of the invention claimed for protection, but merely represents selected embodiments of the present invention. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0028] It should be noted that similar reference numerals and letters denote similar items in the following drawings, and therefore, once an item is defined in one drawing, further definition and explanation thereof is not required in subsequent drawings.

[0029] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inside", "outside", etc. indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, or the positions or positional relationships in which the product of the invention is usually placed when in use. They are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the device or element referred to must have a specific position, be constructed and operated in a specific position, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", "third", etc. are only used to distinguish the description, and cannot be understood as indicating or implying relative importance.

[0030] In addition, the terms "horizontal", "vertical", "overhanging" and the like do not mean that the components are required to be absolutely horizontal or overhanging, but can be slightly tilted. For example, "horizontal" only means that its direction is more horizontal than "vertical", and does not mean that the structure must be completely horizontal, but can be slightly tilted.

[0031] In the description of the present invention, it is also necessary to explain that, unless otherwise clearly specified and limited, the terms "set", "install", "connect", and "connect" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0032] Example 1: Please refer to Figures 1 to 3A portable concrete structure casing pre-embedded tool of this embodiment includes a fixed steel plate 3 and a fixed support assembly 2. The fixed steel plate 3 is fixed on the concrete casting template. The fixed support assembly 2 is vertically welded and fixed on the side of the fixed steel plate 3 away from the concrete casting template. The fixed support assembly 2 is used to insert the embedded casing 1 and fix the embedded casing 1; the number of the fixed steel plate 3 and the fixed support assembly 2 is two, and a fixed steel plate 3 and a fixed support assembly 2 are respectively provided at both ends of the embedded casing 1, thereby fixing the two ends of the embedded casing 1. The convenient concrete structure casing pre-embedded construction method is adopted. Before the construction of the building structure beams, walls, and columns, the convenient concrete structure casing pre-embedded construction method is used. The installation is convenient, the positioning is accurate, it is not easy to run, the fixing strength is good, the structural leakage risk is reduced, the operation is convenient, the installation and disassembly are convenient, and the construction is efficient. According to the structural position and construction progress of the pre-embedded casing, the fixed parts are standardized and batch-produced in advance to improve the construction efficiency. Steel strips, steel plates, steel bars and other material components are adopted, and the materials are simple and the production is convenient. The mold installation and disassembly are flexible and convenient, the turnover rate is high, the material loss is reduced, and the material cost is low.

[0033] Embodiment 2: The fixed support assembly 2 of this embodiment includes two support rods, and the support rods are both against the inner hole of the embedded sleeve 1. The support rods are symmetrically arranged with the center of the embedded sleeve 1 as the symmetry center, and the spacing between the outer sides of the two support rods is equal to the inner diameter of the embedded sleeve 1. The fixed support assembly 2 of this embodiment includes at least three support rods, and the support rods are both against the inner hole of the embedded sleeve 1. The support rods of this embodiment are symmetrically arranged with the center of the embedded sleeve 1 as the symmetry center. The support rods of this embodiment are steel bars or round steel. The length of the support rods of this embodiment is not more than 100mm. The fixed steel plate 3 of this embodiment is an L-shaped structure, and the fixed steel plate 3 includes a first fixed plate 33 for abutting against the wall column template 5 and a second fixed plate 32 for abutting against the panel template 4, and the second fixed plate 32 is fixed to the panel template 4 by carpentry nails 31. The panel template 4 of this embodiment is placed horizontally, and the second fixed plate 32 is supported on the panel template 4. The first fixed plate 33 and the second fixed plate 32 of this embodiment are fixed integrated structures.

[0034] Embodiment 3: This embodiment also provides a portable concrete structure sleeve pre-embedding method, including the above-mentioned pre-embedding tool, and also includes the following steps: S1: Use a steel plate with a thickness of 1 mm for processing to make a fixed steel plate 3 with an L-shaped structure; S2: Select the number, length and position of the steel bars or round steel in the fixed support assembly 2 according to the pipe diameter of the fixed sleeve; S3: Insert the fixed support assembly 2 into the fixed sleeve, and then fix the fixed sleeve; S4: Place the fixed steel plate 3 in the pre-embedded position in the beam, wall, or column, and after correcting the position, use a carpenter nail 31 to fix the entire kit to the board template 4 from the milling hole 321 of the fixing part; S5: After the pouring is completed, the board template 4, the wall column template 5, the fixed steel plate 3 and the fixed support assembly 2 are disassembled at the same time.

[0035] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. For those skilled in the art, the present invention may have various modifications and variations. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.

Claims

1. A portable concrete structure casing pre-embedding method, characterized in that: It comprises a portable concrete structure casing pre-embedded tool, which comprises a fixed steel plate and a fixed support assembly, wherein the fixed steel plate is fixed on a concrete casting template, the fixed support assembly is vertically welded and fixed on a side of the fixed steel plate away from the concrete casting template, and the fixed support assembly is used to insert and fix the pre-embedded casing; the number of the fixed steel plate and the fixed support assembly is two, and a fixed steel plate and a fixed support assembly are respectively provided at both ends of the pre-embedded casing, thereby fixing the two ends of the pre-embedded casing; The fixed support assembly includes two support rods, both of which are in contact with the inner hole of the embedded sleeve, and the support rods are symmetrically arranged with the center of the embedded sleeve as the symmetry center, and the distance between the outer sides of the two support rods is equal to the inner diameter of the embedded sleeve; The fixed support assembly includes at least three support rods, and the support rods are all against the inner hole of the embedded sleeve; The support rods are symmetrically arranged with the center of the embedded sleeve as the symmetry center; The support rod is a steel bar or a round steel bar; The length of the support rod is not greater than 100 mm; The fixed steel plate is an L-shaped structure, and includes a first fixed plate for abutting against the wall column template and a second fixed plate for abutting against the panel template, and the second fixed plate is fixed to the panel template by carpentry nails; The panel template is placed horizontally, and the second fixing plate is supported on the panel template; The first fixing plate and the second fixing plate are a fixed integrated structure; The pre-embedding method also includes the following steps: S1: A steel plate with a thickness of 1 mm is processed to form a fixed steel plate with an L-shaped structure; S2: Select the quantity, length and position of the steel bars or round steel bars in the fixed support assembly according to the diameter of the fixed sleeve; S3: inserting the fixed support assembly into the fixed sleeve, thereby fixing the fixed sleeve; S4: Place the fixed steel plate in the pre-embedded position of the beam, wall and column. After correcting the position, use carpentry nails to fix the entire kit to the board template through the milling holes of the fixing parts. S5: After pouring is completed, the slab formwork, wall column formwork, fixed steel plate and fixed support components are disassembled at the same time.