Integrated decision-making optimization method and system for prefabricated building design and construction based on BIM
By establishing the objective function library, constraint function library and algorithm library on the BIM platform, multiple sets of component procurement plans are generated, which solves the problems of structural design splitting and component selection decision-making in the existing technology, and realizes the intelligent design and construction of prefabricated buildings. Integration reduces cost and construction period.
Patent Information
- Application Number
- CN202110711220.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-06-25
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2041-06-25
AI Technical Summary
The existing technology cannot scientifically and rationally complete structural design splitting and component selection decisions in the component library. Especially when the types and quantities of components increase, it is difficult to ensure the smooth progress of subsequent stages of work and the realization of the goals expected by decision-makers.
An integrated decision-making optimization method for the design and construction of prefabricated buildings based on BIM. By establishing an objective function library, a constraint function library and an algorithm library, the objective function and constraint function are automatically selected based on the demand information input by the decision-maker, and multiple sets of components are generated by combining optimization algorithms. Procurement plan assists decision-makers in completing structural design splitting and component selection decisions.
It has achieved scientific and reasonable completion of structural design splitting and component selection decisions on the basis of ensuring the smooth progress of subsequent stages of work and the smooth realization of the goals expected by decision-makers, reducing costs and construction periods, and improving the intelligent integration of prefabricated building design and construction. level.
Smart Images

Figure CN113569382B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to a BIM-based prefabricated building design and construction integrated decision-making optimization method and system, belonging to the technical field of building design. Background Art
[0002] In recent years, the entire construction industry in my country is accelerating its transformation. With the continuous development of energy conservation, environmental protection and green building concepts, prefabricated buildings will surely follow the historical trend and gradually replace traditional cast-in-place buildings to become the "main force" in the development of the construction industry. Prefabricated buildings have received strong support from the Chinese government and are increasingly favored by enterprises for their advantages such as high-quality components, less construction pollution, short construction period and high resource utilization.
[0003] However, due to various reasons such as an imperfect standard system, immature technology, and an imbalance in market supply and demand, my country's prefabricated building projects generally face many problems such as increased costs, extended construction periods, and increased difficulty in implementing green construction. In the prior art, there are methods that use BIM databases to solve the standardized and unified management of prefabricated components in prefabricated building projects. For example, the invention patent with the publication number "CN107563089A" proposes a method and computing device for generating a task list of PC components based on BIM. The prefabricated building is decomposed through the BIM database to obtain the information of each PC component, and then the task list for the production and procurement of each PC component is generated and published based on the information of each PC component;
[0004] However, the problem that this type of existing technology cannot solve is that when the types and number of components in the component library increase, it is impossible to achieve scientific and reasonable structural design splitting and component optimization decision-making on the basis of ensuring the smooth progress of subsequent stages of work and the smooth realization of decision makers' expected goals. This is a difficult problem that urgently needs to be solved. Summary of the invention
[0005] In order to solve the problems existing in the above-mentioned prior art, the present invention proposes an integrated decision-making optimization method and system for prefabricated building design and construction based on BIM, establishes an objective function library, a constraint function library and an algorithm library with multiple optimization algorithms for different characteristic mathematical models for various types of decision-making demand information, and can solve multiple sets of optimized component procurement plans for decision makers to choose from according to the needs of decision makers and all required known information, so as to achieve the scientific and reasonable completion of structural design splitting and component optimization decision-making on the basis of ensuring the smooth progress of subsequent stages of work and the smooth realization of decision makers' expected goals.
[0006] The technical solution of the present invention is as follows:
[0007] Technical solution 1:
[0008] The integrated decision-making optimization method for design and construction of prefabricated buildings based on BIM includes the following steps:
[0009] Structural design and splitting: Complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library;
[0010] Determine decision optimization information; decision makers input decision requirement information according to needs, and automatically import objective related information, and save decision requirement information and objective related information to the information database;
[0011] Providing an optimization plan; establishing an objective function library, a constraint function library and an algorithm library; the objective function library includes a number of objective functions for different types of decision demand information, the constraint function library includes a number of constraint functions for different types of decision demand information, and the algorithm library includes a number of optimization algorithms for mathematical models with different characteristics; automatically selecting at least one objective function and at least one constraint function to form a mathematical model according to the type of decision demand information input by the decision maker, the algorithm library matches the most relevant optimization algorithm according to the characteristics of the mathematical model, and uses the most relevant optimization algorithm and all required known information to solve the mathematical model to obtain multiple sets of optimized component procurement plans;
[0012] Determine the optimization plan; decision makers determine the final optimization plan from multiple sets of optimized component procurement plans based on objective relevant information, and update, revise and deliver the BIM building model based on the final optimization plan.
[0013] Preferably, the specific steps of designing and splitting the building model are:
[0014] Complete the structural design and splitting based on the BIM building model, and obtain the basic information of each split component;
[0015] According to the basic information of each split component, confirm whether there is a corresponding component in the BIM component library. If there is a corresponding component, directly obtain the complete information of the corresponding component from the BIM component library, wherein the complete information includes production information of different manufacturers;
[0016] If there is no corresponding component, the basic information of the corresponding component including geometry and reinforcement will be added to the BIM component library; for the newly added components in the BIM component library, each manufacturer will import their own production information and integrate it with the basic information to form the complete information of the newly added corresponding component.
[0017] Preferably, the step of determining the decision optimization information is specifically:
[0018] The decision maker inputs decision requirement information, wherein the decision requirement information includes at least one type of optimization objective and at least one type of constraint condition;
[0019] The objective relevant information includes project information and market price information; the project information and market price information are automatically imported and updated in real time according to the construction project, the project information includes project overview and construction organization plan, and the market price information includes labor costs, material costs and machinery rental fees;
[0020] The decision requirement information, project information and market price information are saved in the information database.
[0021] Preferably, in the step of providing an optimization solution:
[0022] The objective function library includes a number of objective functions for different types of decision-making demand information, and the constraint function library includes a number of constraint functions for different types of decision-making demand information;
[0023] The algorithm library selects corresponding objective functions and constraint functions according to the type of optimization objective and constraint conditions input by the decision maker, and combines them to obtain an optimization mathematical model based on the optimization objective and constraint conditions;
[0024] The algorithm library matches the most relevant optimization algorithm for solving the problem according to the characteristic partial matching of the optimization mathematical model;
[0025] The most relevant optimization algorithm is used to solve the optimization mathematical model, and all required known information is used as solution conditions to generate multiple sets of optimized component procurement plans.
[0026] Preferably, the step of determining the optimization solution is specifically as follows:
[0027] In the step of generating multiple sets of optimized component procurement plans, a number of optimization times i is set, the initial value of i is set to 0, each time a round of optimized component procurement plans is generated, i+1 is set, and an upper limit value of i is set;
[0028] Whenever a round of optimized component procurement plans is generated, it is determined whether they meet the needs of the decision maker; if the currently generated optimized component procurement plans have met the needs of the decision maker, the decision maker determines the final optimization plan;
[0029] If the currently generated optimized multiple sets of component procurement plans do not meet the needs of the decision maker, determine whether the current number of optimization times i reaches the upper limit value. If it does not reach the upper limit value, return to continue to generate the next round of optimized multiple sets of component procurement plans;
[0030] If the upper limit value has been reached, the decision maker will determine whether it is necessary to re-design the structure and split it based on objective relevant information; if it is necessary, the structural design and splitting steps will be re-executed; if it is not necessary, the decision maker will determine the final optimization plan from the existing multiple optimized procurement plans.
[0031] Technical solution 2:
[0032] The integrated decision-making and optimization system for prefabricated building design and construction based on BIM includes:
[0033] The front-end display layer is used to provide user interaction operations and optimize result output functions;
[0034] The business logic layer is used to complete the structural design and splitting based on the BIM building model, provide multiple sets of optimized component procurement plans based on the split component information and decision information, assist decision makers in completing the optimization decision-making work, and provide a data information transmission interface;
[0035] Data persistence layer, used to implement data transmission and caching functions;
[0036] The data storage layer provides the required data storage services for all activities and work within the system.
[0037] Preferably, the front-end display layer includes a user interaction module and a result output display module;
[0038] The user interaction module is used to process business requests including user information registration, login and logout, and known parameter information input;
[0039] The result output display module is used to output the final optimization solution in an output mode specified by the user.
[0040] Preferably, the business logic layer includes a structure design and splitting module, a component optimization module, an auxiliary decision-making module and a data information interface module;
[0041] The structural design and splitting module is used to complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library;
[0042] The component optimization module is used to call the objective function library, the constraint function library and the algorithm library; the objective function library includes several objective functions for different types of decision demand information, the constraint function library includes several constraint functions for different types of decision demand information, and the algorithm library includes several optimization algorithms for mathematical models with different characteristics; the component optimization module calls the type of decision demand information input by the decision maker and automatically selects at least one objective function and at least one constraint function to form a mathematical model, and matches the most relevant optimization algorithm from the algorithm library according to the characteristics of the mathematical model, and finally uses the most relevant optimization algorithm and all the required known information to solve the mathematical model to obtain multiple sets of optimized component procurement plans;
[0043] The auxiliary decision module is used to assist the decision maker in determining the final optimization plan from multiple sets of optimized component procurement plans;
[0044] The data information interface module is used to provide an interface for data information transmission and processing between the system and third-party software.
[0045] Preferably, the data persistence layer includes a data connection configuration module, a database connection module and a data information cache module;
[0046] The data connection configuration module is used to provide parameters and environment configuration for data connection and data call to ensure the reliability and stability of data transmission;
[0047] The database connection module is used to solve the data transfer and call problems between the business logic layer and the data storage layer;
[0048] The data information cache module is used to temporarily cache various types of data and calculation processing results.
[0049] Preferably, the data storage layer is used to be divided into different sub-databases according to storage type differences, including but not limited to a BIM component library, an objective function library, a constraint function library, an algorithm library and an information library.
[0050] The present invention has the following beneficial effects:
[0051] 1. The BIM-based prefabricated building design and construction integrated decision-making optimization method and system of the present invention can comprehensively and systematically plan the entire design and construction process in the structural design stage, which is of great significance and value in solving the current problems of prefabricated buildings. At the same time, the present invention is based on multidisciplinary theories such as civil engineering, computer and management, combined with the characteristics of building information model sharing, inheritance, and intelligent optimization algorithms, aiming to provide scientific and reasonable structural design splitting solutions and component procurement solutions. Optimization recommendation, ultimately assisting decision makers to comprehensively consider multiple objectives such as cost, construction period and low-carbon environmental protection, and realize intelligent integration of the entire process of prefabricated building design and construction.
[0052] 2. The BIM-based integrated decision-making optimization method and system for prefabricated building design and construction of the present invention establishes an objective function library and a constraint function library for various types of decision-making demand information, automatically selects a combination of objective functions and constraint functions according to the decision-making demand information input by the decision maker, and generates a corresponding mathematical model based on the combination; an optimization algorithm for solving mathematical models with different characteristics is also provided, and each optimization algorithm solves multiple sets of optimized component procurement schemes based on all required known information for decision makers to choose from, and assists decision makers in making decisions efficiently, thereby achieving scientific and reasonable completion of structural design splitting and component optimization decisions on the basis of ensuring the smooth progress of subsequent stages of work and the smooth realization of decision makers' expected goals. BRIEF DESCRIPTION OF THE DRAWINGS
[0053] Figure 1 is a flow chart of a method according to an embodiment of the present invention;
[0054] Figure 2 4 is a system framework diagram of an embodiment of the present invention. DETAILED DESCRIPTION
[0055] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0056] It should be understood that the step numbers used in this document are only for convenience of description and are not intended to limit the order in which the steps are executed.
[0057] It should be understood that the terms used in the present specification are only for the purpose of describing specific embodiments and are not intended to limit the present invention. As used in the present specification and the appended claims, unless the context clearly indicates otherwise, the singular forms "a", "an" and "the" are intended to include plural forms.
[0058] The terms “include” and “comprising” indicate the presence of described features, integers, steps, operations, elements and / or components, but do not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or combinations thereof.
[0059] The term "and / or" means and includes any and all possible combinations of one or more of the associated listed items.
[0060] Embodiment 1:
[0061] See also Figure 1 , the integrated decision-making optimization method for prefabricated building design and construction based on BIM is implemented based on computer equipment and includes the following steps:
[0062] S1. Structural design and splitting: Complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library (such as the model and characteristics of each split component, and the production price of each split component from different manufacturers, etc.);
[0063] S2. Determine decision optimization information; the decision maker inputs various types of decision demand information (such as low carbon, cost, construction period, etc.) according to the needs, and the computer equipment automatically imports objective related information (such as construction process time consumption, relevant equipment rental price, etc.), and saves the decision demand information and objective related information to the information database;
[0064] S3. Provide an optimization plan; establish an objective function library, a constraint function library and an algorithm library; the objective function library includes several objective functions for different types of decision demand information, the constraint function library includes several constraint functions for different types of decision demand information, and the algorithm library includes several optimization algorithms for mathematical models with different characteristics (such as genetic algorithm, particle swarm algorithm, taboo algorithm, hybrid algorithm, etc.); automatically select at least one objective function and at least one constraint function to form a mathematical model according to the type of decision demand information input by the decision maker, the algorithm library matches the most relevant optimization algorithm according to the characteristics of the mathematical model, uses the most relevant optimization algorithm and all the required known information extracted from the decision demand information and objective related information to solve the mathematical model, and obtains multiple sets of optimized component procurement plans;
[0065] S4. Determine the optimization plan. According to the needs and feedback of decision makers, assist decision makers to determine the final optimization plan from multiple sets of optimized component procurement plans based on objective relevant information;
[0066] S5. According to the final preferred solution selected by the decision maker, automatically place an order to purchase the corresponding prefabricated component products; then export the corresponding component model from the BIM component library, and complete the BIM building model update and correction work in the BIM modeling software; finally, deliver the BIM building model in the construction preparation stage.
[0067] The present embodiment establishes an objective function library and a constraint function library for various types of decision-making demand information, automatically selects a combination of objective functions and constraint functions according to the decision-making demand information input by the decision maker, and generates a corresponding mathematical model based on the combination. The present embodiment also provides an optimization algorithm for solving mathematical models with different characteristics. Each optimization algorithm solves multiple sets of optimized component procurement plans based on all required known information for decision makers to choose from, and assists decision makers in making decisions efficiently, thereby achieving scientific and reasonable completion of structural design splitting and component optimization decisions on the basis of ensuring the smooth progress of subsequent stages of work and the smooth realization of decision makers' expected goals.
[0068] As another embodiment of the present invention, the step S1, designing and splitting the building model is specifically as follows:
[0069] S11. Import the BIM building model in the preliminary design phase in the BIM modeling software into the structural design and splitting module (or third-party structural design software), complete the structural design and splitting work, and obtain the basic information of each split component;
[0070] S12, according to the basic information of each split component, query whether there is a corresponding component in the BIM component library, if there is a corresponding component, directly associate the component with the BIM component library to obtain the complete information of the corresponding component, the complete information includes production information; if there is no corresponding component, proceed to step S13;
[0071] S13, adding basic information including geometry and reinforcement of the corresponding component in the BIM component library; then proceeding to step S14;
[0072] S14. For the newly added components in the BIM component library, each manufacturer shall import its own component production unit price, transportation unit price, transportation distance and other information based on the basic information of the newly added components and its own production conditions to complete the component information.
[0073] In another embodiment of the present invention, the step S2, determining the decision optimization information, is specifically as follows:
[0074] S21. The decision maker inputs decision requirement information according to his own needs, where the decision requirement information includes at least one type of optimization objective and at least one type of constraint condition;
[0075] S22, saving decision-making requirement information to the information database;
[0076] S23, automatically importing and updating project information and market price information in real time according to the construction project, wherein the objective relevant information includes project information and market price information, wherein the project information includes project overview and construction organization plan, and the market price information includes labor costs, material costs and machinery rental fees;
[0077] S24. Save the project information and market price information to the information database.
[0078] In another embodiment of the present invention, the step S3 of providing an optimization solution is specifically as follows:
[0079] S31. Extract all the known information required for optimization decision-making from the BIM component library and information library to the component optimization module, including decision-making demand information (such as cost target, construction period target, etc., as well as construction period constraints, low-carbon constraints and corresponding constraint upper limits, etc.), project information (construction organization plan and project overview, etc.), market price information (such as construction tower crane rental price, etc.) and complete information of each split component (including the model and characteristics of the split component, and the corresponding manufacturer production price information of various split components, etc.);
[0080] S32. In this embodiment, the objective function library includes a number of objective functions for different types of decision-making demand information (such as low-carbon objective function, cost objective function, construction period objective function, etc.), and the constraint function library includes a number of constraint functions for different types of decision-making demand information (such as low-carbon constraint function, cost constraint function, construction period constraint function, etc.);
[0081] The extracted decision requirement information is used as a selection basis. The algorithm library selects corresponding objective functions and constraint functions according to the type of optimization objective and constraint condition input by the decision maker, and combines them to obtain an optimization mathematical model based on the optimization objective and constraint condition. The optimization mathematical model may have different characteristics (such as linear or nonlinear, continuous or discrete variables, etc.);
[0082] S33. Then, the system will automatically select a suitable intelligent optimization algorithm from the algorithm library for model solving according to different characteristics of the optimization mathematical model;
[0083] S34. Finally, with the lowest cost and construction period as the optimization target, the upper limit of construction period and low carbon limit as the constraint conditions, and all the extracted data information as the solution conditions, combined with the optimization mathematical model and intelligent optimization algorithm, multiple sets of component procurement plans after optimization are automatically generated. The above multiple sets of component procurement plans after optimization are produced in a round of providing optimization plan steps. In each round of cycle steps, multiple sets of component procurement plans will be produced. Compared with the original plan, the optimized component procurement plan can significantly reduce the cost, construction period and other goals.
[0084] It should be noted that, in this embodiment, a preferred number value i is set, and the initial value of i is set to 0. Each time a round of optimization is generated, multiple sets of component procurement plans are set to i+1, and an upper limit value of i is set.
[0085] In another embodiment of the present invention, the step S4, determining the optimization scheme is specifically as follows:
[0086] S41, each time a round of optimized component procurement plans is generated, the decision maker determines whether the needs are met; if the currently generated multiple sets of optimized component procurement plans have met the needs of the decision maker, step S45 is performed; if not, step S42 is performed;
[0087] S42, record the current preferred number i, and then proceed to step S43;
[0088] S43: Determine whether the current optimization times i has reached the upper limit. If not, proceed to step S34 again (start a new round of component procurement plan optimization); if it has reached the upper limit, proceed to step S44.
[0089] S44, the decision maker determines whether it is necessary to redesign and split the structure based on objective relevant information such as the consumed funds and time; if it is determined to be necessary, proceed to step S11; if it is determined not to be necessary due to time constraints, etc., proceed to step S45 based on the existing generated and optimized multiple sets of component procurement plans;
[0090] S45. Decision makers determine the final optimization plan based on their own needs.
[0091] Embodiment 2:
[0092] See also Figure 2 , an integrated decision-making optimization system for prefabricated building design and construction based on BIM, including:
[0093] The front-end display layer is used to provide user interaction operations and optimize result output functions;
[0094] The business logic layer is the core of the entire system. It is used to complete the structural design and splitting of the building model, provide multiple sets of optimized component procurement plans based on all the required known information, assist decision makers in completing the optimization decision-making work, and provide the necessary data information transmission interface;
[0095] Data persistence layer, used to implement data transmission and caching functions;
[0096] The data storage layer provides the required data storage services for all activities and work within the system.
[0097] In another embodiment of the present invention, the front-end display layer includes a user interaction module and a result output display module;
[0098] The user interaction module is used to process business requests including user information registration, login and logout, and known parameter information input;
[0099] The result output display module is used to output the final optimization solution in an output mode specified by the user.
[0100] In another embodiment of the present invention, the business logic layer includes a structure design and splitting module, a component optimization module, an auxiliary decision module and a data information interface module;
[0101] The structural design and splitting module is used to complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library;
[0102] The component optimization module is used to call the objective function library, the constraint function library and the algorithm library; the objective function library includes several objective functions for different types of decision demand information, the constraint function library includes several constraint functions for different types of decision demand information, and the algorithm library includes several optimization algorithms for mathematical models with different characteristics; the component optimization module calls the type of decision demand information input by the decision maker and automatically selects at least one objective function and at least one constraint function to form a mathematical model, and matches the most relevant optimization algorithm from the algorithm library according to the characteristics of the mathematical model, and finally uses the most relevant optimization algorithm and all the required known information to solve the mathematical model to obtain multiple sets of optimized component procurement plans;
[0103] The auxiliary decision module is used to assist the decision maker in determining the final optimization plan from multiple sets of optimized component procurement plans;
[0104] The data information interface module is used to provide an interface for data information transmission and processing between the system and third-party software.
[0105] In another embodiment of the present invention, the data persistence layer includes a data connection configuration module, a database connection module and a data information cache module;
[0106] The data connection configuration module is used to provide parameters and environment configuration for data connection and data call to ensure the reliability and stability of data transmission;
[0107] The database connection module is used to solve the data transfer and call problems between the business logic layer and the data storage layer;
[0108] The data information cache module is used to temporarily cache various types of data and calculation processing results.
[0109] In another embodiment of the present invention, the data storage layer is used to be divided into different sub-databases according to storage type differences, including but not limited to a BIM component library, an objective function library, a constraint function library, an algorithm library, and an information library.
[0110] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. Integrated decision-making optimization method for prefabricated building design and construction based on BIM, It is characterized in that The following steps are involved: Structural design and disassembly; Complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library; Determine decision optimization information; decision makers input decision requirement information according to needs, and automatically import objective related information, and save decision requirement information and objective related information to the information database; Providing an optimization plan; establishing an objective function library, a constraint function library and an algorithm library; the objective function library includes a number of objective functions for different types of decision demand information, the constraint function library includes a number of constraint functions for different types of decision demand information, and the algorithm library includes a number of optimization algorithms for mathematical models with different characteristics; automatically selecting at least one objective function and at least one constraint function to form a mathematical model according to the type of decision demand information input by the decision maker, the algorithm library matches the most relevant optimization algorithm according to the characteristics of the mathematical model, and uses the most relevant optimization algorithm and all required known information to solve the mathematical model to obtain multiple sets of optimized component procurement plans; Determine the optimization plan; The decision maker determines the final optimization plan from multiple sets of optimized component procurement plans based on objective relevant information, and updates and amends the BIM building model based on the final optimization plan and delivers it; The step of determining the optimization solution is specifically as follows: In the step of generating multiple sets of optimized component procurement plans, a number of optimization times i is set, the initial value of i is set to 0, each time a round of optimized component procurement plans is generated, i+1 is set, and an upper limit value of i is set; Whenever a round of optimized component procurement plans is generated, it is determined whether they meet the needs of the decision maker; if the currently generated optimized component procurement plans have met the needs of the decision maker, the decision maker determines the final optimization plan; If the currently generated optimized multiple sets of component procurement plans do not meet the needs of the decision maker, determine whether the current number of optimization times i reaches the upper limit value. If it does not reach the upper limit value, return to continue to generate the next round of optimized multiple sets of component procurement plans; If the upper limit value has been reached, the decision maker will determine whether it is necessary to re-design and split the structure based on objective relevant information; if it is necessary, the structural design and splitting steps will be re-executed; if it is not necessary, the decision maker will determine the final optimization plan from the existing optimized multiple sets of component procurement plans.
2. According to the BIM-based integrated decision-making optimization method for prefabricated building design and construction according to claim 1, It is characterized in that The specific steps of designing and splitting the building model are: Complete the structural design and splitting based on the BIM building model, and obtain the basic information of each split component; According to the basic information of each split component, confirm whether there is a corresponding component in the BIM component library. If there is a corresponding component, directly obtain the complete information of the corresponding component from the BIM component library, wherein the complete information includes production information of different manufacturers; If there is no corresponding component, the basic information of the corresponding component including geometry and reinforcement will be added to the BIM component library; for the newly added components in the BIM component library, each manufacturer will import their own production information and integrate it with the basic information to form the complete information of the newly added corresponding component.
3. According to the BIM-based integrated decision-making optimization method for prefabricated building design and construction according to claim 1, It is characterized in that The step of determining the decision optimization information is specifically as follows: The decision maker inputs decision requirement information, wherein the decision requirement information includes at least one type of optimization objective and at least one type of constraint condition; The objective relevant information includes project information and market price information; the project information and market price information are automatically imported and updated in real time according to the construction project, the project information includes project overview and construction organization plan, and the market price information includes labor costs, material costs and machinery rental fees; The decision requirement information, project information and market price information are saved in the information database.
4. According to the BIM-based prefabricated building design and construction integrated decision-making optimization method according to claim 3, It is characterized in that In the step of providing an optimization solution: The objective function library includes a number of objective functions for different types of decision-making demand information, and the constraint function library includes a number of constraint functions for different types of decision-making demand information; The algorithm library selects corresponding objective functions and constraint functions according to the type of optimization objective and constraint conditions input by the decision maker, and combines them to obtain an optimization mathematical model based on the optimization objective and constraint conditions; The algorithm library matches the most relevant optimization algorithm for solving the problem according to the characteristic partial matching of the optimization mathematical model; The most relevant optimization algorithm is used to solve the optimization mathematical model, and all required known information is used as solution conditions to generate multiple sets of optimized component procurement plans.
5. Integrated decision-making and optimization system for prefabricated building design and construction based on BIM, It is characterized in that include: The front-end display layer is used to provide user interaction operations and optimize result output functions; The business logic layer is used to complete the structural design and splitting based on the BIM building model, provide multiple sets of optimized component procurement plans based on all known information including split component information and decision information, assist decision makers in completing the optimization decision-making work, and provide a data information transmission interface; Data persistence layer, used to implement data transmission and caching functions; The data storage layer provides the required data storage services for all activities and tasks within the system; The business logic layer includes a structure design and splitting module, a component optimization module, an auxiliary decision-making module and a data information interface module; The structural design and splitting module is used to complete the structural design and splitting work based on the BIM building model, obtain the basic information of each split component, and obtain the complete information of each split component according to the BIM component library; The component optimization module is used to call the objective function library, the constraint function library and the algorithm library; the objective function library includes several objective functions for different types of decision demand information, the constraint function library includes several constraint functions for different types of decision demand information, and the algorithm library includes several optimization algorithms for mathematical models with different characteristics; the component optimization module calls the type of decision demand information input by the decision maker and automatically selects at least one objective function and at least one constraint function to form a mathematical model, and matches the most relevant optimization algorithm from the algorithm library according to the characteristics of the mathematical model, and finally uses the most relevant optimization algorithm and all the required known information to solve the mathematical model to obtain multiple sets of optimized component procurement plans; The auxiliary decision module is used to assist the decision maker in determining the final optimization plan from multiple sets of optimized component procurement plans; The step of determining the optimization solution is specifically as follows: In the step of generating multiple sets of optimized component procurement plans, a number of optimization times i is set, the initial value of i is set to 0, each time a round of optimized component procurement plans is generated, i+1 is set, and an upper limit value of i is set; Whenever a round of optimized component procurement plans is generated, it is determined whether they meet the needs of the decision maker; if the currently generated optimized component procurement plans have met the needs of the decision maker, the decision maker determines the final optimization plan; If the currently generated optimized multiple sets of component procurement plans do not meet the needs of the decision maker, determine whether the current number of optimization times i reaches the upper limit value. If it does not reach the upper limit value, return to continue to generate the next round of optimized multiple sets of component procurement plans; If the upper limit value has been reached, the decision maker shall determine whether it is necessary to re-design and split the structure based on objective relevant information; if it is necessary, the structural design and splitting steps shall be re-executed; if it is not necessary, the decision maker shall determine the final optimization plan from the existing optimized multiple component procurement plans; The data information interface module is used to provide an interface for data information transmission and processing between the system and third-party software.
6. According to the BIM-based prefabricated building design and construction integrated decision-making optimization system of claim 5, Features: The front-end display layer includes a user interaction module and a result output display module; The user interaction module is used to process business requests including user information registration, login and logout, and known parameter information input; The result output display module is used to output the final optimization solution in an output mode specified by the user.
7. According to the BIM-based prefabricated building design and construction integrated decision-making optimization system of claim 5, Features: The data persistence layer includes a data connection configuration module, a database connection module and a data information cache module; The data connection configuration module is used to provide parameters and environment configuration for data connection and data call to ensure the reliability and stability of data transmission; The database connection module is used to solve the data transfer and call problems between the business logic layer and the data storage layer; The data information cache module is used to temporarily cache various types of data and calculation processing results.
8. According to the BIM-based prefabricated building design and construction integrated decision-making optimization system of claim 5, Features: The data storage layer is used to be divided into different sub-databases according to storage type differences, including a BIM component library, an objective function library, a constraint function library, an algorithm library and an information library.
Citation Information
Patent Citations
Task list generating method for PC components based on BIM and computing device
CN107563089A
BIM and big data-based assembly type building deepening design and construction method
CN111561182A