A construction method, the technology of ground connection wall, which is applied in the direction of construction, sheet pile wall, foundation structure engineering, etc., can solve the problems of wall mud overflow, increase the total amount of mud, and enter the guide wall, so as to avoid mud overflow and reduce the overall The effect of reducing the amount and reducing the overall cost
Patent Information
- Authority / Receiving Office
- CN · China
- Current Assignee / Owner
- Publication Date
- 2022-08-05
Smart Images

Figure 1 
Figure 2 
Figure 3
Abstract
Description
technical field
[0001] The invention relates to the technical field of bridge construction, in particular to a mud overflow prevention construction method used in the pouring construction of ground connecting walls. Background technique
[0002] The underground diaphragm wall is a kind of grooving machine used on the ground in the foundation project. Along the peripheral axis of the deep excavation project, under the condition of mud wall protection, a narrow and long deep groove is excavated. After the groove is cleared, it is suspended in the groove. Place the steel cage, and then use the conduit method to pour the underwater concrete into a unit groove section. This is done section by section, and a continuous reinforced concrete wall is built underground as a water interception, anti-seepage, load-bearing and water-retaining structure.
[0003] In the construction process of pouring the concrete into the groove of the ground connecting wall, in order to avoid the inclusi...
Examples
Embodiment Construction
[0033] like Figure 1-6 Among them, a mud spill-proof construction method used in the construction of ground connecting wall is characterized by comprising the following steps:
[0034] 1) Before excavation of the first-phase groove 1 of the ground-connecting wall, excavate the area between the first-phase groove 1 of the ground-connecting wall and the guide wall 3 at the top of the adjacent unexcavated area 6, and the excavation scope is the design bottom elevation of the guide wall 8 to the design bottom elevation of the crown beam 9, the mud buffer zone 2 will be formed after the excavation is completed;
[0035] 2) Lay a slurry discharge pipe 4 in the mud buffer zone 2, and the slurry discharge pipe 4 is connected to the mud pump 5;
[0036] 3) Carry out the excavation of the first-phase groove 1 of the ground connecting wall;
[0037] 4) Carry out the first sealing operation of groove 1 of the first phase of the ground connection wall;
[0038] 4.1) A pouring frame is ...