An integrated structure and installation method for platform canopies

Through the integrated structure of the prefabricated platform canopy, the connection of drilled piles, frame beams and grouting sleeves, combined with the U-shaped drainage channel, the non-integration and maintenance problems of the existing platform canopy structure are solved, achieving high efficiency The platform structure stability and deformation resistance reduce maintenance costs and difficulty.

CN114908998BActive Publication Date: 2024-11-08LANZHOU JIAOTONG UNIV +1
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202210437158.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-04-27
Publication Date
2024-11-08
Estimated Expiration
2042-04-27

AI Technical Summary

Technical Problem

The existing platform canopy structure is a non-integrated structure, which is prone to partial protrusion of the platform wall cap and wall waist plate expansion mold protruding under the influence of uneven foundation settlement, post-refill geodeposition, operating load vibration, temperature expansion and long-term deformation, etc. The invasion problems of canopy and other invasion limits, and the water saturation of the soil at the bottom of the platform wall in the trapped loess area leads to a reduction in the bearing capacity and is difficult to repair. The rectification cycle after operation is long and the cost is high.

Method used

Adopt the integrated structure of the prefabricated platform canopy, including concrete foundation, cast-in-place canopy column, prefabricated π-shaped beam canopy column, drainage facilities and pipe corridor space optimization, through drilling, cast-in piles, frame beams, shear wall structure, The grouting sleeve connection and U-shaped drainage channel have strong integrity and high deformation resistance, which facilitates later maintenance and replacement, and reduces the platform invasion and uneven settlement of loess wet.

Benefits of technology

It realizes the integrity and deformation resistance of the platform canopy structure, shortens construction period, reduces maintenance costs, improves the stability and sustainability of the platform, effectively solves the problems of platform wall tilt and loess wet, and reduces the difficulty and cost of maintenance. .

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN114908998B_ABST
    Figure CN114908998B_ABST
Patent Text Reader

Abstract

The present invention provides a platform canopy integrated structure and installation method, including a concrete foundation, a cast-in-place canopy column, a prefabricated π-beam canopy column integral structure, a cast-in-place canopy column and a prefabricated π-beam canopy column connection node, a prefabricated canopy beam slab, and a prefabricated π-beam and prefabricated canopy beam slab connection node. The canopy concrete foundation includes bored cast-in-place piles, platform frame beams, platform walls, platform columns, platform surfaces, caps and drainage ditches. The platform interior includes pipe galleries such as water supply and drainage pipes, reserved pipes, power cable pipelines, communication pipelines, and fire-fighting pipelines. The assembled platform canopy integrated structure has good integrity, strong deformation resistance, and convenient assembly construction, which is convenient for later maintenance and replacement, and can effectively reduce platform encroachment, loess collapse and uneven settlement and other diseases; the internal pipe gallery system of the platform not only solves the problem of cross congestion of various pipelines and lines, maintains integrity and beauty, but also greatly facilitates later maintenance and inspection, reduces maintenance costs, and effectively utilizes the internal space of the platform.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an integrated platform canopy structure and an installation method, in particular to an assembled integrated platform canopy structure, and belongs to the technical field of concrete structures in structural engineering. Background Art

[0002] Cast-in-place reinforced concrete structures need to be constructed on site, with a poor working environment, long labor and formwork cycles, complicated processes, and are greatly affected by seasons and bad weather, and are difficult to reinforce and repair. Prefabricated structures, on the other hand, are semi-automatically produced in factories, and the main task of the construction site is assembly rather than construction. They are less affected by objective factors such as climate, have controllable quality, shorten construction periods, are highly efficient, and comply with energy conservation, environmental protection, and sustainable development.

[0003] At present, most railway platforms adopt traditional high earth-fill retaining wall platforms, in which the earth-fill platform wall and canopy structure are independent of each other. This structure has the following shortcomings: (1) Since the platform wall, platform earth-fill and canopy structure are not integrated structures, they are prone to intrusion problems such as local protrusion of platform wall cap, protrusion of wall waist plate bulge formwork, and canopy tilt due to uneven foundation settlement, post-backfill settlement, operational load vibration, temperature expansion and long-term deformation. These problems not only pose a risk of vehicle intrusion, but also affect passengers' use. (2) In the loess area prone to collapse, the platform wall is filled with plain fill. The platform wall adopts a concrete cantilever retaining wall structure. The bottom is paved with 37 fill, and the retaining wall structure is poured in stages. Finally, the interior is filled with plain concrete, and a concrete structure with a steel mesh structure is laid on the top surface to form the platform surface. The platform surface and the retaining wall structure do not form an effective connection with each other, but are only a lapped structure. When there is heavy rainfall on the platform line, the ballast will not be able to withstand the impact of the ballast due to insufficient drainage slope of the lower surface layer or changes caused by vehicle load. The lower soil cannot absorb all the water in a short time. Part of it flows toward the drainage ditch and is eventually discharged by the drainage ditch. The other part flows toward the platform wall and flows along the edge of the platform wall to the bottom of the platform wall, making the bottom soil saturated with water and causing the bearing capacity to decrease. Rainwater will flow toward the platform wall area and flow along the platform wall surface to the bottom soil of the platform wall, causing uneven changes in the bearing layer at the bottom of the platform wall, and eventually causing the platform wall to tilt or local uneven settlement along the length direction, and eventually causing the platform wall to infringe. (3) Based on the maintenance and repair experience of other operating lines, it is found that the surface drainage is not smooth, and water is easy to accumulate near the platform wall, causing the platform wall and platform surface to sink. Once the platform wall is constructed, its settlement is difficult to deal with. Once the platform infringes the limit, it is necessary to break the platform surface and fill it, replace the filler and foundation on a large scale. In particular, the remediation cycle after operation is long and the cost is high, and maintenance and repair are difficult. Summary of the invention

[0004] In order to overcome the shortcomings of the existing platform canopy structure, this paper provides a new type of prefabricated platform canopy integrated structure and its installation method, which has good integrity, strong deformation resistance, and convenient assembly construction. The line drainage ditch, power cable, water supply and drainage, fire protection, communication and other pipelines can be placed inside the platform, which is convenient for later maintenance and replacement, and can effectively reduce platform encroachment, loess collapse and uneven settlement and other diseases.

[0005] The technical solution of the present invention is as follows: an integrated structure of an assembled platform canopy, including a concrete foundation, cast-in-place canopy columns, a prefabricated π-beam canopy column overall structure, cast-in-place canopy columns and prefabricated π-beam canopy column connection nodes, prefabricated canopy beams and slabs, and prefabricated π-beams and prefabricated canopy beam-slab connection nodes. The canopy concrete foundation includes bored cast-in-place piles, platform frame beams, platform walls, platform columns, platform surfaces, pedestals and drainage ditches. The interior of the platform includes water supply and drainage pipes, reserved pipes, power cable pipelines, communication pipelines, fire-fighting pipelines and other pipeline corridors.

[0006] The upper part of the assembled platform canopy integrated structure is an assembled canopy, and the lower part adopts a frame beam + shear wall structure, using four rows of bored cast-in-place piles, and the platform wall is a shear wall; the bottom of the platform column is connected and fixed to the top of the bored cast-in-place pile through a cap, and the platform frame beam is connected and fixed to the cap and platform column. The cast-in-place canopy column adopts a variable cross-section, wherein the lower part is cast-in-place with the platform structure as a whole, and the upper canopy column and the π-shaped beam are prefabricated as a whole, and the ratio of the upper and lower canopy columns is 0.5:4.08. The top of the cast-in-place canopy column is connected and fixed to the prefabricated canopy column under the prefabricated π-shaped beam by a grout sleeve. The canopy board includes 2 side canopies and 1 middle canopy. The canopy board and the side beam are prefabricated as a whole and hoisted and installed. The canopy side beam and the π-shaped beam are connected by a support. The canopy roof panel adopts a cast-in-place concrete slab. The drainage ditch is arranged on the platform wall in the direction of the track. The platform beam and slab joints are disconnected according to the corresponding size and filled with corresponding fillers.

[0007] The top of the cast-in-place canopy column is provided with reserved steel bars, the bottom of the prefabricated canopy column is provided with embedded grouting sleeves, the reserved steel bars extend into the grouting sleeves and the two are connected and fixed by grouting material.

[0008] The integrated structural drainage facilities of the assembled platform canopy are equipped with drainage channels through U-shaped grooves at the joints of the side and middle canopy panels, and drainage pipes are installed in the grooves on the surfaces of the canopy columns. The bottom of the drainage pipes is connected to the drainage pipes, and the water on the top of the canopy flows through the drainage holes and the drainage pipes to the drainage ditch. The platform wall is provided with drainage holes with a diameter of 10 cm and an interval of 1 m, which can effectively drain rainwater from the railway line to the drainage ditch through the drainage holes.

[0009] The space of the prefabricated integrated platform canopy corridor is optimized, and the space inside the platform is divided into multiple corridor spaces, which include water supply and drainage, fire protection, power cables, communications and other pipelines from the outside to the departure line. A lighting system is installed in the passage, which not only solves the problem of cross-congestion of various pipelines and maintains their integrity and beauty, but also greatly facilitates subsequent maintenance and inspection, reduces maintenance costs, and effectively utilizes the internal space of the platform.

[0010] A method for installing an integrated structure of an assembled platform canopy comprises the following steps.

[0011] Bored piles, platform frame beams, caps, platform walls, platform columns, platform surfaces and lower 4.08m high canopy columns are cast in situ. Before installing the pre-beams, the cast-in-situ column top concrete is roughened. To protect the column edges from damage, no roughening is performed within 20mm from the column edge. Use an instrument to measure whether the column top range and the adjacent column tops are level. Use an angle grinder to grind the uneven parts to ensure the column top is flat. Adjust the position and verticality of the steel bars to ensure that the embedded steel bars are in the correct position after adjustment, the upper steel bars are vertically upward, and the positioning steel plates can be smoothly inserted and removed.

[0012] The upper 0.5m high canopy column and π-shaped beam are prefabricated as a whole, and a total of 2 lifting points are set just above the canopy column. The π-shaped beam is transported to the site, and a truck crane (200t) is deployed. The lock buckle is buckled on the lifting ring and the bolts are tightened to start lifting. It is lifted above the cast-in-place canopy column, and the verticality of the reserved steel bar and the sleeve and the position of the shear key are adjusted. The debris on the surface of the reserved part is cleaned and the beam is dropped. The height is adjusted with pads to support the position of all π-shaped beams at the same height.

[0013] Use the seat slurry sealing mold to plug the joints, fill the seat slurry for continuous sealing, pull it out after applying, and grouting after the seat slurry strength reaches the requirement. After filling, seal the grouting hole. Subsequent construction can be carried out when the grouting strength reaches more than 75%. The removal of temporary fixing measures should be carried out after the compressive strength of the grouting material can ensure that the structure can meet the subsequent construction bearing capacity.

[0014] Four lifting rings are symmetrically set 1.5m away from the end of the prefabricated middle canopy. When the middle canopy is transported to the site, the height of the connection between the floor slab and the adjacent π beam is measured before installation. The higher part is polished with an angle grinder, and the lower part is adjusted with a pad. Buckle the lock on the lifting ring and tighten the bolt to start lifting. Lift it above the π-shaped beam, adjust the verticality, clean the surface debris and drop the beam. Before installing the prefabricated board, a support frame should be erected as a temporary fixing measure, and at the same time as an operating surface when lifting it into place. When lifting the prefabricated board, all the supports should be installed and the lifting points can be loosened only after they have passed the inspection.

[0015] Two lifting rings are symmetrically set at 1.5m from the ends on both sides of the prefabricated side canopy. When the side canopy is transported to the site, the lock buckle is buckled on the lifting ring and the bolts are tightened to start lifting. It is lifted above the π-shaped beam, the verticality is adjusted, and the surface debris is cleaned to drop the beam. The prefabricated panels and prefabricated beams are connected by an anti-drop beam device. When prefabricating concrete components, embedded bolts are pre-buried in advance. After the prefabricated panels are installed, the anti-drop beam device is installed.

[0016] A U-shaped groove with a certain slope is set at the joints of the side and middle canopy boards, and the flexible waterproof material SBC120 polyethylene polypropylene composite waterproof membrane is used for waterproofing. The rainwater flows along the U-shaped groove to the canopy column position and then flows to the drainage ditch along the drainage pipe at the groove of the canopy column. A 30mm installation width is reserved at the junction of the board and the π beam, and 100*150 concrete water retaining platforms are made on both sides. The water retaining platforms are made simultaneously during prefabrication, and then the waterproof membrane is constructed on the water retaining platform, and a 2mm thick aluminum plate cover is added on the top for protection.

[0017] The beneficial effects of the present invention are as follows:

[0018] The overall structure of the π-beam canopy column and the canopy beams and slabs are all prefabricated in the factory, with controllable quality, shortened construction period, efficient construction, and compliance with energy conservation, environmental protection and sustainable development.

[0019] The cast-in-place canopy column and the prefabricated π-beam canopy column overall structure are connected and fixed with grouting sleeves, and its seismic performance is equivalent to that of cast-in-place.

[0020] The integrated structure of the platform canopy is an integral structure, with an assembled canopy on the upper part and four rows of bored cast-in-place piles + frame beams on the lower part. The platform wall is a shear wall. This design scheme can place water supply and drainage, fire protection, power cables, communications and other pipelines inside the platform, which is convenient for later maintenance and replacement, and effectively reduces platform intrusion diseases.

[0021] The structural drainage facilities set up drainage channels through U-shaped grooves at the joints of the side and middle canopy panels, install drain pipes in the grooves on the surfaces of the canopy columns, connect the drain pipes to the bottom of the drain pipes, and the water on the top of the canopy flows through the drain pipes and the drain pipes and is discharged to the drainage ditch. Furthermore, the platform wall is provided with drainage holes with a diameter of 10 cm and an interval of 1 m, which can effectively drain rainwater from the railway line to the drainage ditch through the drainage holes, effectively reducing diseases such as loess collapse and uneven settlement. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the embodiments of the present invention are further described in detail below in combination with the embodiments and drawings. Here, the illustrative embodiments of the present invention and their description are used to explain the present invention, but are not intended to limit the present invention.

[0023] Figure 1 It is a side elevation structural cross-sectional view of the present invention.

[0024] Figure 2 It is a schematic diagram of the top structure of the present invention.

[0025] Figure 3 It is a side elevation view of the side and middle beam plates of the present invention.

[0026] Figure 4 This is a large-scale drawing of the beam and column connection of the present invention.

[0027] Figure 5 for Figure 3 bb view.

[0028] Figure 6 It is a schematic diagram of the column top and column bottom of the grouting sleeve of the present invention.

[0029] Figure 7 It is a cross-sectional view of the bottom of the grouting sleeve column of the present invention.

[0030] Figure 8 This is a cross-sectional view of the integrated pipe gallery structure within the platform of the present invention.

[0031] Fig. 9 It is a cross-sectional view of the anti-fall beam of the present invention.

[0032] In the figure: 1. bored cast-in-place piles, 2. platform frame beams, 3. platform walls, 4. platform columns, 5. pedestals, 6. platform surfaces, 7. cast-in-place canopy columns, 8. prefabricated canopy columns, 9. prefabricated π-shaped beams, 10. drainage ditches, 11. drainage holes, 12. drainage pipes, 13. middle canopy boards, 14. side canopy boards, 15. grouting sleeves, 16. shear members, 17. water supply and drainage pipes, 18. reserved pipes, 19. power cable pipelines, 20. communication pipelines, 21. fire-fighting pipes, 22. canopy board side beams, 23. supports, 24. reserved steel bars, 25. reserved bolts. DETAILED DESCRIPTION

[0033] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0034] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0035] In the present invention, the terms "include / comprise", "consist of..." or any other variations are intended to cover non-exclusive inclusion, so that a product, device, process or method including a series of elements includes not only those elements, but also other elements not explicitly listed when necessary, or also includes elements inherent to such product, device, process or method. In the absence of more restrictions, the elements defined by the sentence "include / comprise...", "consist of..." do not exclude the presence of other identical elements in the product, device, process or method including the elements.

[0036] In the present invention, terms such as "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside" and "outside" indicating directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device, component or structure must have a specific direction, be constructed or operate in a specific direction, and should not be understood as a limitation on the present invention.

[0037] like Figure 1-4 As shown, this embodiment provides an integrated structure of a prefabricated platform canopy, including bored piles 1, platform frame beams 2, platform walls 3, platform columns 4, caps 5, platform surfaces 6, cast-in-place canopy columns 7, prefabricated canopy columns 8, prefabricated π-shaped beams 9, drainage ditches 10, drainage holes 11, drainage pipes 12, middle canopy panels 13, side canopy panels 14, grouting sleeves 15, and shear members 16. The present invention provides an integrated structure of a prefabricated platform canopy, which reasonably divides the cast-in-place and prefabricated components, controls quality, shortens construction period, and realizes efficient construction; it plans the drainage system, and effectively reduces the risk of platform tilt and loess collapsibility.

[0038] Furthermore, the upper part of the assembled platform canopy integrated structure is an assembled canopy, and the main components include cast-in-place canopy columns 7, prefabricated canopy column π-shaped beam integral structure 8.9, and prefabricated canopy beam slabs 13.14. The lower part adopts a frame beam 2+shear wall 3 structure, and four rows of bored piles 1 are used. The platform wall 3 is a shear wall. The bottom of the platform column 4 is connected and fixed to the top of the bored pile 1 through a cap 5. The platform frame beam 2 is connected and fixed to the cap 5 and the platform column 4. The cast-in-place canopy column 7 adopts a variable cross-section, wherein the lower part is cast-in-place with the platform structure as a whole, and the upper canopy column 8 is connected to the π The π-shaped beam 9 is prefabricated as a whole, the ratio of the upper and lower canopy columns is 0.5:4.08, the top of the cast-in-place canopy column 7 is connected and fixed to the prefabricated π-shaped beam canopy column 8.9 by a tank grout sleeve 15, the canopy board includes a middle canopy 13 and two side canopy boards 14, the canopy boards 13.14 and the side beams 22 are prefabricated as a whole and hoisted and installed, the canopy side beams 22 and the π-shaped beams are connected by supports 23, the canopy roof panel is a cast-in-place concrete slab, the drainage ditch 10 is arranged on the platform wall 3 in the direction of the track, the platform beam and slab joints are disconnected according to corresponding sizes and filled with corresponding fillers.

[0039] The top of the cast-in-place canopy column 7 has reserved steel bars 24, and the bottom of the prefabricated canopy column 8 has embedded grouting sleeves 15. The reserved steel bars 24 extend into the grouting sleeves 15 and the two are connected and fixed by grouting material, and the seismic performance is equivalent to that of cast-in-place.

[0040] The drainage facility is configured to set a drainage channel through the U-shaped groove at the joint of the side and middle canopy boards 13.14, and a drain pipe 12 is installed in the groove on the surface of the canopy column. The bottom of the drain pipe is connected to the drain pipe 12, and the water on the top of the canopy flows through the drain pipe to the drain ditch 10. Furthermore, the platform wall 3 is provided with drainage holes 11 with a diameter of 10 cm and an interval of 1 m, which can effectively drain rainwater from the railway line to the drainage ditch 10 through the drainage holes 11, effectively reducing the problem of the platform wall tilting under long-term rain erosion.

[0041] The pipeline gallery space is optimized, and the space inside the platform is divided into multiple pipeline gallery spaces, including water supply and drainage pipes 17, reserved pipes 18, power cable pipelines 19, communication pipelines 20 and fire protection pipes 21, etc., and a lighting system is installed in the passage, which not only solves the problem of cross-congestion of various pipelines and maintains their integrity and beauty, but also greatly facilitates subsequent maintenance and inspection, reduces maintenance costs, and effectively utilizes the internal space of the platform.

[0042] A method for installing an integrated structure of an assembled platform canopy, the method comprising the following steps:

[0043] Bored piles 1, platform frame beams 2, platform walls 3, platform columns 4, caps 5, platform surfaces 6 and lower 4.08m high canopy columns 7 are cast in place. Before installing the pre-beams, the top concrete of the cast-in-place columns 7 is roughened. To protect the edges and corners of the columns from damage, roughening is not performed within 20mm from the column edges. Use an instrument to measure whether the top of the column and the tops of adjacent columns are level. Use an angle grinder to grind the uneven parts to ensure that the top of the column is flat. Adjust the position and verticality of the steel bars to ensure that the embedded steel bars 24 are in the correct position after adjustment, the upper steel bars are vertically upward, and the positioning steel plates can be smoothly inserted and removed.

[0044] The upper 0.5m high canopy column 8 and π-shaped beam 9 are prefabricated as a whole, and a total of 2 lifting points are set on the π-shaped beam 9 just above the canopy column 8. The π-shaped beam is transported to the site, and a truck crane (200t) is deployed. The lock buckle is buckled on the lifting ring and the bolts are tightened to start lifting. It is lifted above the cast-in-place canopy column 7, and the verticality of the reserved steel bar 24 and the sleeve 15 and the position of the shear member 16 are adjusted. The debris on the surface of the reserved part is cleaned to drop the beam, and the height is adjusted with pads to support all π-shaped beams at the same height.

[0045] Use the seat slurry sealing mold to plug the joints, fill the seat slurry for continuous sealing, pull it out after applying, and grouting after the seat slurry strength reaches the requirement. After filling, seal the grouting hole. Subsequent construction can be carried out when the grouting strength reaches more than 75%. The removal of temporary fixing measures should be carried out after the compressive strength of the grouting material can ensure that the structure can meet the subsequent construction bearing capacity.

[0046] Four lifting rings are symmetrically set 1.5m away from the end of the prefabricated middle canopy 13. When the middle canopy is transported to the site, the height of the connection between the floor slab and the adjacent π beam is measured before installation. The higher part is polished with an angle grinder, and the lower part is adjusted with a pad. Buckle the lock on the lifting ring and tighten the bolt to start lifting. Lift it above the π-shaped beam, adjust the verticality, clean the surface debris and drop the beam. Before installing the prefabricated panels 13.14, a support frame should be erected as a temporary fixing measure, and at the same time as an operating surface when lifting it into place. When lifting the prefabricated panels, all the supports should be installed and the lifting points should be loosened after passing the inspection.

[0047] Two lifting rings are symmetrically set at 1.5m from the end on both sides of the prefabricated side canopy 14. When the side canopy is transported to the site, the lock buckle is buckled on the lifting ring and the bolts are tightened to start lifting. It is lifted above the π-shaped beam, the verticality is adjusted, and the surface debris is cleaned to drop the beam. The prefabricated panels 13.14 and the prefabricated beams 9 are connected by an anti-drop beam device. When prefabricating concrete components, embedded bolts 25 are pre-buried in advance. After the prefabricated panels are installed, the anti-drop beam device is installed.

[0048] A U-shaped groove with a certain slope is set at the joints of the side and middle canopy boards 13.14, and the flexible waterproof material SBC120 polyethylene polypropylene composite waterproof membrane is used for waterproofing. After the rainwater flows along the U-shaped groove to the canopy column position, it flows along the drainage pipe 12 at the groove of the canopy column to the drainage ditch 10. A 30mm installation width is reserved at the junction of the board and the π beam, and a 100*150 concrete water retaining platform is made on both sides. The water retaining platform is made simultaneously during prefabrication, and then the waterproof membrane is constructed on the water retaining platform, and a 2mm thick aluminum plate cover is added on the top for protection.

[0049] The above description of the disclosed examples enables those skilled in the art to implement or use the present invention, and many other variations or modifications that conform to the principles of the present invention can still be directly determined or derived based on the content disclosed in the present invention without departing from the spirit and scope of the present invention. Therefore, the scope of the present invention should be understood and recognized as covering all such other variations or modifications.

Claims

1. An integrated structure of an assembled platform canopy, characterized in that: Including bored cast-in-place piles, platform frame beams, platform walls, platform columns, caps, platform surfaces, cast-in-place canopy columns, prefabricated canopy columns, prefabricated π-shaped beams, drainage ditches, drainage holes, drainage pipes, middle canopy panels, side canopy panels, grouting sleeves, shear-resistant parts, water supply and drainage pipes, reserved pipes, power cable pipelines, communication pipelines, fire-fighting pipelines, canopy panel side beams, beam-column connection supports, reserved steel bars, and anti-drop beams; The upper part is a prefabricated canopy, and the lower part is a frame beam + shear wall structure. Four rows of bored cast-in-place piles are used, and the platform wall is a shear wall; the bottom of the platform column is connected and fixed to the top of the bored cast-in-place pile through a cap, and the platform frame beam is connected and fixed to the cap and platform column. The cast-in-place canopy column adopts a variable cross-section, wherein the lower part is cast-in-place with the platform structure as a whole, and the upper canopy column and the π-shaped beam are prefabricated as a whole. The ratio of the upper and lower canopy column heights is 0.5:4.

08. The top of the cast-in-place canopy column is connected and fixed to the prefabricated canopy column under the prefabricated π-shaped beam by a grouting sleeve. The canopy board includes 1 middle canopy and 2 side canopies. The canopy board and the side beam are prefabricated as a whole and hoisted and installed. The canopy board side beam and the π-shaped beam are connected by a support. The canopy board adopts a cast-in-place concrete board. The drainage ditch is set on the platform wall in the direction of the track. The platform beam and slab joints are disconnected according to the corresponding size and filled with corresponding fillers. The top of the cast-in-place canopy column is reserved with steel bars, and the bottom of the prefabricated canopy column is pre-buried with a grouting sleeve, the reserved steel bars extend into the grouting sleeve and the two are connected and fixed by grouting material; A drainage channel is set through the U-shaped groove at the joint of the side and middle canopy panels, and a drainage pipe is installed in the groove on the surface of the canopy column. The bottom of the drainage pipe is connected to the drainage pipe. The water on the top of the canopy flows through the drainage pipe and the drainage pipe and is discharged to the drainage ditch. The platform wall is provided with drainage holes with a diameter of 10 cm and an interval of 1 m, which can effectively drain rainwater from the railway line to the drainage ditch through the drainage holes.

2. The assembled platform canopy integrated structure according to claim 1 is characterized by: The space inside the platform is divided into multiple pipe gallery spaces, which include water supply and drainage pipes, reserved pipes, power cable pipelines, communication pipelines, and fire-fighting pipes from the outside to the departure line, and a lighting system is installed in the passage.

3. A method for installing an assembled platform canopy integrated structure according to claim 1, characterized in that: The installation method includes the following steps: (1) Bored piles, platform frame beams, caps, platform walls, platform columns, platform surfaces and lower 4.08m high canopy columns are cast in situ. Before the pre-beams are installed, the top concrete of the cast-in-situ columns is roughened. To protect the edges and corners of the columns from damage, roughening is not performed within 20mm of the column edge. Use an instrument to measure whether the top of the column and the tops of adjacent columns are level, and use an angle grinder to grind the uneven parts to ensure that the top of the column is flat; Adjust the position and verticality of the steel bars to ensure that the embedded steel bars are in the correct position after adjustment, the upper steel bars are vertically upward, and the positioning steel plates can be smoothly inserted and removed; (2) The upper 0.5m high canopy column and π-shaped beam are prefabricated as a whole, and two lifting points are set up, respectively located directly above the canopy column. The π-shaped beam is transported to the site, and a truck crane is deployed. The lock buckle is buckled on the lifting ring and the bolts are tightened to start lifting. It is lifted above the cast-in-place canopy column, and the verticality of the reserved steel bar and the sleeve and the position of the shear key are adjusted. The surface of the reserved parts is cleaned and the beam is lowered. The height is adjusted with pads to support all π-shaped beams at the same height; (3) Use the seat grout plugging mold to plug the joints, fill the seat grout for continuous plugging, and then pull it out. When the seat grout strength reaches the requirement, grouting is carried out. After filling, the grouting hole is sealed. Subsequent construction can be carried out when the grouting strength reaches more than 75%. The removal of temporary fixing measures should be carried out after the compressive strength of the grouting material can ensure that the structure can meet the subsequent construction load; (4) Four lifting rings are symmetrically set 1.5m away from the end of the prefabricated middle canopy. The middle canopy is transported to the site. Before installation, the height of the connection between the floor slab and the adjacent π beam is measured to see if they are consistent. The higher part is grinded with an angle grinder, and the lower part is adjusted with pads; Put the lock buckle on the lifting ring and tighten the bolt to start lifting. Lift it above the π-shaped beam, adjust the verticality, clean the surface debris and lower the beam. Before installing the prefabricated board, a support frame should be set up as a temporary fixing measure and also as an operating surface when lifting into place; When hoisting prefabricated panels, the hoisting points can only be released after all supports have been installed and inspected. (5) Two lifting rings are symmetrically set at 1.5m from the ends on both sides of the prefabricated side canopy. The side canopy is transported to the site, the lock buckle is buckled on the lifting ring, the bolts are tightened and the canopy is lifted to the top of the π-shaped beam, the verticality is adjusted, and the surface debris is cleaned to lower the beam; The precast panels and precast beams are connected by an anti-falling beam device. When precast concrete components are installed, bolts are embedded in advance, and the anti-falling beam device is installed after the precast panels are installed. (6) A U-shaped groove with a certain slope is set at the joints of the side and middle canopy boards, and the flexible waterproof material SBC120 polyethylene polypropylene composite waterproof membrane is used for waterproofing. Rainwater flows along the U-shaped groove to the canopy column and then flows to the drainage ditch along the drainage pipe at the groove of the canopy column. A 30mm installation width is reserved at the intersection of the board and the π beam. A 100*150mm concrete water retaining platform is made on both sides. The water retaining platform is made simultaneously during prefabrication, and then the waterproof membrane is constructed on the water retaining platform, and a 2mm thick aluminum plate cover is added on the top for protection.

Citation Information

Patent Citations

  • Station platform canopy

    CN111088898A

  • Retaining wall structure of combined type high -speed railway platform

    CN208363127U

  • Wide flat beam type assembled concrete canopy for railway platform

    CN210239246U

  • Prefabricated concrete pi-shaped beam for fabricated concrete canopy of railway passenger station

    CN212583040U

  • High-speed rail station house bare concrete canopy and high-speed rail station

    CN213449635U