Battery replacement control method, system, electronic device and storage medium

By introducing liftable platforms and mechanisms into the battery swap equipment and battery transfer devices of electric vehicles, adjusting the height to match the battery swap position, the problem of long battery replacement time is solved and the battery swap efficiency and smoothness is improved.

CN115092007BActive Publication Date: 2024-11-08AULTON NEW ENERGY AUTOMOBILE TECHNOLOGY CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210605538.X
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-01-23
Publication Date
2024-11-08
Estimated Expiration
2040-01-23

AI Technical Summary

Technical Problem

During the battery replacement process of existing electric vehicles, the battery replacement time is long and the efficiency is low, and there is a problem of long disassembly and installation of the battery.

Method used

By introducing liftable battery swap platform and battery transfer mechanism into the battery swap device and the battery transfer device, combined with the liftable load platform in the lane, the height of each device is adjusted to match the battery swap position, and the rapid disassembly and assembly of the battery and Transfer.

Benefits of technology

Save battery transfer time, improve battery swap efficiency, simplify the battery disassembly and assembly process, and shorten the overall battery swap time.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115092007B_ABST
    Figure CN115092007B_ABST
Patent Text Reader

Abstract

The present invention discloses a battery replacement control method, system, electronic device and storage medium. The battery replacement control method includes: adjusting the height of the battery replacement platform and the height of the battery transfer mechanism; controlling the battery transfer mechanism to take the battery from the battery replacement platform or place the battery on the battery replacement platform. The present invention realizes the battery transfer from the battery transfer device to the battery replacement device and from the battery replacement device to the battery transfer device by controlling the battery transfer device and the battery replacement device, saving the battery transfer time and making the entire battery replacement process smoother; it also controls the battery replacement equipment and the vehicle-carrying platform to change the height of the battery replacement equipment and the vehicle-carrying plane in accordance with the battery replacement progress, thereby changing the height of the bottom of the vehicle, realizing the overall process of removing and installing the battery, saving the battery replacement time of the vehicle and improving the battery replacement efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] This application is a divisional application of the invention patent with application date of January 23, 2020, application number 2020100769211, and invention name "Battery replacement control method, system, electronic device and storage medium". Technical Field

[0002] The present invention relates to the field of battery replacement control, and in particular to a battery replacement control method, system, electronic device and storage medium. Background Art

[0003] There are two main charging methods for existing electric vehicles, one is direct charging and the other is quick-change. Among them, direct charging requires the installation of charging piles to charge electric vehicles, but the charging time is long and the efficiency is low. The battery swapping method requires the installation of a battery swapping station to achieve quick battery swapping by replacing the battery of the electric vehicle, which shortens the time compared to direct charging, but the battery swapping process includes battery removal and installation, and there are still problems such as long battery replacement time and low battery swapping efficiency. Summary of the invention

[0004] The technical problem to be solved by the present invention is to overcome the defects of the prior art in that the battery replacement time is long and the battery replacement efficiency is low, and to provide a battery replacement control method, system, electronic device and storage medium.

[0005] The present invention solves the above technical problems through the following technical solutions:

[0006] A battery replacement control method is implemented by the cooperation of a battery replacement device and a battery transfer device, wherein the battery replacement device includes a liftable battery replacement platform, and the battery transfer device has a liftable battery transfer mechanism. The battery replacement control method includes:

[0007] Adjusting the height of the battery swap platform and the height of the battery transfer mechanism;

[0008] Control the battery transfer mechanism to take the battery from the battery exchange platform or place the battery on the battery exchange platform.

[0009] Preferably, the battery exchange control method also includes controlling the battery exchange equipment and the battery transfer device to move to a battery exchange position before adjusting the height of the battery exchange platform and the height of the battery transfer mechanism.

[0010] Preferably, adjusting the height of the battery exchange platform and the height of the battery transfer mechanism specifically includes:

[0011] Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the first matching height, so that the battery swap platform matches the battery transfer mechanism in height:

[0012] Controlling the battery transfer mechanism to take the battery from the battery swap platform specifically includes:

[0013] Moving the battery transfer mechanism horizontally until the battery transfer mechanism extends to the bottom of the battery on the battery exchange platform to carry the battery;

[0014] The battery transfer mechanism is retracted horizontally.

[0015] Preferably, controlling the battery transfer mechanism to take the battery from the battery exchange platform specifically also includes: after horizontally moving the battery transfer mechanism and before horizontally retracting the battery transfer mechanism, lifting the battery transfer mechanism to detach the battery originally located on the battery exchange platform from the battery exchange platform and transfer it to the battery transfer mechanism.

[0016] Preferably, the battery exchange platform and the battery transfer mechanism match in height, specifically including: when the battery exchange platform is located at the battery exchange height and the battery transfer mechanism is located at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery exchange platform, and the battery exchange platform does not interfere with the movement of the battery transfer mechanism.

[0017] Preferably, adjusting the height of the battery exchange platform and the height of the battery transfer mechanism specifically includes:

[0018] Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the second matching height, so that the height of the battery transfer mechanism is higher than the height of the battery swap platform:

[0019] Controlling the battery transfer mechanism to place the battery on the battery exchange platform specifically includes:

[0020] Controlling the battery transfer mechanism to reach a third height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform;

[0021] Moving the battery transfer mechanism horizontally until the battery transfer mechanism reaches above the battery exchange platform;

[0022] Lowering the battery transfer mechanism to place the battery on the battery exchange platform;

[0023] The battery transfer mechanism is retracted horizontally.

[0024] Preferably, the battery exchange control method is also implemented by the cooperation of a track and a battery exchange device, wherein the track has a liftable vehicle loading platform, and the battery exchange control method includes:

[0025] The height of the vehicle loading platform and the height of the battery replacement platform are adjusted to disassemble and install the battery on the electric vehicle.

[0026] Preferably, adjusting the height of the vehicle carrying platform and the height of the battery swapping platform specifically includes:

[0027] The height of the vehicle carrying platform and the height of the battery swapping platform are controlled according to the battery swapping signal.

[0028] Preferably, the sandwiched lane is provided with a battery swapping equipment walking plane for the battery swapping equipment to walk on;

[0029] Controlling the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal specifically includes:

[0030] When the battery replacement signal is a battery removal preparation signal, the vehicle-carrying platform is controlled to reach the first battery replacement equipment entry height and / or the battery replacement platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment;

[0031] And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach a battery removal operation height and / or the vehicle carrier platform is controlled to reach a battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition;

[0032] And / or, when the battery replacement signal is a battery removal completion signal, the vehicle-carrying platform is controlled to reach the exit height of the first battery replacement equipment and / or the battery replacement platform is controlled to reach the initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment after the battery is loaded;

[0033] And / or, when the battery exchange signal is a battery loading preparation signal, the vehicle-carrying platform is controlled to reach the second battery exchange equipment entry height and / or the battery exchange platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery exchange equipment exceeds the height of the battery exchange equipment after the battery is loaded;

[0034] And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach a battery installation operation height and / or the vehicle loading platform is controlled to reach a battery installation matching height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition;

[0035] And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment.

[0036] Preferably, the battery swapping device further comprises: a chassis, a lifting mechanism, a lifting drive device and a transmission shaft connected to the lifting drive device, the lifting mechanism connects the chassis and the battery swapping platform and lifts the battery swapping platform relative to the chassis, the lifting mechanism comprises a connecting rod, the first end of the connecting rod is rotatably connected to the battery swapping platform, the second end of the connecting rod is rotatably connected to the chassis, and the transmission shaft is connected to the connecting rod and drives the connecting rod to rotate;

[0037] Controlling the battery swap platform to reach any of the heights described above specifically includes:

[0038] The lifting drive device is started, and the lifted lifting drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate.

[0039] Preferably, the transmission shaft is provided with positioning points along the circumference, and the chassis is provided with sensors for sensing the positioning points, and the positioning points are used to locate the rotation angle of the connecting rod to lift the battery exchange platform;

[0040] Controlling the battery swap platform to reach the height as described above, specifically also includes: sensing, by the sensor, whether the positioning point has rotated through a first preset angle, the first preset angle being the angle that the positioning point needs to rotate correspondingly when the battery swap platform reaches the height as described above;

[0041] If yes, the lifting drive device is stopped; if no, the lifting drive device continues to operate until the positioning point rotates by the first preset angle.

[0042] Preferably, when the battery exchange control method includes the step of controlling the battery transfer mechanism to take the battery from the battery exchange platform, it also includes, after controlling the battery transfer mechanism to take the battery from the battery exchange platform, controlling the battery transport device to drive to the battery rack and placing the battery into the battery rack;

[0043] Alternatively, when the battery exchange control method includes the step of controlling the battery transfer mechanism to place the battery on the battery exchange platform, it also includes controlling the battery transfer device to move toward the battery rack and taking the battery from the battery rack and placing it on the battery transfer mechanism before controlling the battery transfer device to move to the battery exchange position.

[0044] A battery exchange control system controls a battery exchange device and a battery transport device, wherein the battery exchange device includes a liftable battery exchange platform, and the battery transport device includes a liftable battery transfer mechanism. The battery exchange control system includes:

[0045] The exchange control module is used to adjust the height of the battery exchange platform and the height of the battery transfer mechanism, and to control the battery transfer mechanism to take the battery from the battery exchange platform or place the battery on the battery exchange platform.

[0046] Preferably, the exchange control module is also used to control the battery exchange equipment and the battery transport device to move to the battery exchange position before adjusting the height of the battery exchange platform and the height of the battery transfer mechanism.

[0047] Preferably, adjusting the height of the battery exchange platform and the height of the battery transfer mechanism specifically includes:

[0048] Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the first matching height, so that the battery swap platform matches the battery transfer mechanism in height:

[0049] Controlling the battery transfer mechanism to take the battery from the battery swap platform specifically includes:

[0050] Moving the battery transfer mechanism horizontally until the battery transfer mechanism extends to the bottom of the battery on the battery exchange platform to carry the battery;

[0051] The battery transfer mechanism is retracted horizontally.

[0052] Preferably, controlling the battery transfer mechanism to take the battery from the battery exchange platform specifically also includes: after horizontally moving the battery transfer mechanism and before horizontally retracting the battery transfer mechanism, lifting the battery transfer mechanism to detach the battery originally located on the battery exchange platform from the battery exchange platform and transfer it to the battery transfer mechanism.

[0053] Preferably, the battery exchange platform and the battery transfer mechanism match in height, specifically including: when the battery exchange platform is located at the battery exchange height and the battery transfer mechanism is located at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery exchange platform, and the battery exchange platform does not interfere with the movement of the battery transfer mechanism.

[0054] Preferably, adjusting the height of the battery exchange platform and the height of the battery transfer mechanism specifically includes:

[0055] Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the second matching height, so that the height of the battery transfer mechanism is higher than the height of the battery swap platform:

[0056] Controlling the battery transfer mechanism to place the battery on the battery exchange platform specifically includes:

[0057] Controlling the battery transfer mechanism to reach a third height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform;

[0058] Moving the battery transfer mechanism horizontally until the battery transfer mechanism reaches above the battery exchange platform;

[0059] Lowering the battery transfer mechanism to place the battery on the battery exchange platform;

[0060] The battery transfer mechanism is retracted horizontally.

[0061] Preferably, the battery exchange control method further controls the sandwiched lane and the battery exchange equipment, the sandwiched lane has a liftable vehicle loading platform, and the battery exchange control system includes:

[0062] The disassembly and assembly control module is used to adjust the height of the vehicle loading platform and the height of the battery exchange platform to disassemble and assemble the battery on the electric vehicle.

[0063] Preferably, adjusting the height of the vehicle carrying platform and the height of the battery swapping platform specifically includes:

[0064] The height of the vehicle carrying platform and the height of the battery swapping platform are controlled according to the battery swapping signal.

[0065] Preferably, the sandwiched lane is provided with a battery swapping equipment walking plane for the battery swapping equipment to walk on;

[0066] Controlling the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal specifically includes:

[0067] When the battery replacement signal is a battery removal preparation signal, the vehicle-carrying platform is controlled to reach the first battery replacement equipment entry height and / or the battery replacement platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment;

[0068] And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach a battery removal operation height and / or the vehicle carrier platform is controlled to reach a battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition;

[0069] And / or, when the battery replacement signal is a battery removal completion signal, the vehicle-carrying platform is controlled to reach the exit height of the first battery replacement equipment and / or the battery replacement platform is controlled to reach the initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment after the battery is loaded;

[0070] And / or, when the battery exchange signal is a battery loading preparation signal, the vehicle-carrying platform is controlled to reach the second battery exchange equipment entry height and / or the battery exchange platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery exchange equipment exceeds the height of the battery exchange equipment after the battery is loaded;

[0071] And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach a battery installation operation height and / or the vehicle loading platform is controlled to reach a battery installation matching height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition;

[0072] And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment.

[0073] Preferably, the battery swapping device further comprises: a chassis, a lifting mechanism, a lifting drive device and a transmission shaft connected to the lifting drive device, the lifting mechanism connects the chassis and the battery swapping platform and lifts the battery swapping platform relative to the chassis, the lifting mechanism comprises a connecting rod, the first end of the connecting rod is rotatably connected to the battery swapping platform, the second end of the connecting rod is rotatably connected to the chassis, and the transmission shaft is connected to the connecting rod and drives the connecting rod to rotate;

[0074] Controlling the battery swap platform to reach the height as described above specifically includes:

[0075] The lifting drive device is started, and the lifted lifting drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate.

[0076] Preferably, the transmission shaft is provided with positioning points along the circumference, and the chassis is provided with sensors for sensing the positioning points, and the positioning points are used to locate the rotation angle of the connecting rod to lift the battery exchange platform;

[0077] Controlling the battery swap platform to reach the height as described above, specifically also includes: sensing by the sensor whether the positioning point has rotated over a first preset angle, the first preset angle being the angle that the positioning point needs to rotate correspondingly when the battery swap platform reaches the height as described above;

[0078] If yes, the lifting drive device is stopped; if no, the lifting drive device continues to operate until the positioning point rotates by the first preset angle.

[0079] Preferably, when the exchange control module is used to control the battery transfer mechanism to take the battery from the battery exchange platform, it is also used to control the battery transport device to drive to the battery rack and put the battery into the battery rack after controlling the battery transfer mechanism to take the battery from the battery exchange platform;

[0080] Alternatively, when the exchange control module is used to control the battery transfer mechanism to place the battery on the battery exchange platform, it is also used to control the battery transfer device to move to the battery rack and take the battery from the battery rack and place it on the battery transfer mechanism before controlling the battery transfer device to move to the battery exchange position.

[0081] An electronic device comprises a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the above-mentioned method when executing the program.

[0082] A computer-readable storage medium stores a computer program, which implements the steps of the method described above when the program is executed by a processor.

[0083] On the basis of being in accordance with the common sense in the art, the above-mentioned preferred conditions can be arbitrarily combined to obtain the preferred embodiments of the present invention.

[0084] The positive progressive effect of the present invention is that: the present invention realizes the battery transfer from the battery transfer device to the battery exchange device and the battery transfer from the battery exchange equipment to the battery transfer device by controlling the battery transfer device and the battery exchange equipment, thereby saving the battery transfer time and making the entire battery exchange process smoother; it also controls the battery exchange equipment and the vehicle carrier platform, changes the height of the battery exchange equipment and the vehicle carrier plane in accordance with the battery exchange progress, thereby changing the height of the bottom of the vehicle, realizing the overall process of removing and installing batteries, saving the vehicle's battery exchange time, and improving the battery exchange efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0085] Figure 1 This is a schematic diagram of the layout of the lanes, battery swapping equipment and battery transfer devices in the battery swap station.

[0086] Figure 2 This is a schematic diagram of the vehicle loading platform at its initial height.

[0087] Figure 3 This is a flow chart of the battery replacement control method according to embodiment 1 of the present invention.

[0088] Figure 4 This is a flow chart of transferring the battery on the battery swap platform to the battery transfer mechanism in Example 1 of the present invention.

[0089] Figure 5This is a flow chart of transferring the battery on the battery transfer mechanism to the battery exchange platform in Example 1 of the present invention.

[0090] Figure 6 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is located at the entry height of the first battery exchange equipment.

[0091] Figure 7 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is at a height suitable for removing the battery.

[0092] Figure 8 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is located at the exit height of the first battery exchange device.

[0093] Fig. 9 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is located at the entry height of the second battery exchange equipment.

[0094] Fig.10 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is located at a height suitable for installing batteries.

[0095] Fig.11 This is a schematic diagram of the vehicle-carrying platform in Embodiment 1 of the present invention when it is located at the second battery exchange equipment's exit height.

[0096] Fig.12 This is a schematic diagram of the top view of the structure of the battery exchange device of Example 1 of the present invention.

[0097] Fig.13 Schematic diagram of the matching structure of the connecting rod and the lifting frame of Example 1 of the present invention.

[0098] Fig.14 It is a partially enlarged schematic diagram of the battery exchange equipment of Example 1 of the present invention.

[0099] Fig.15 This is a flow chart of controlling the battery swap platform to reach any height in Example 1 of the present invention.

[0100] Fig.16 This is a schematic block diagram of a battery replacement control system according to embodiment 2 of the present invention.

[0101] Fig.17 This is a schematic diagram of the structure of an electronic device according to Embodiment 3 of the present invention. DETAILED DESCRIPTION

[0102] The present invention is further described below by way of examples, but the present invention is not limited to the scope of the examples.

[0103] Example 1

[0104] Before describing the various embodiments of the present invention in detail, a brief description of the lane, the battery replacement equipment and the battery transport device is first given.

[0105] like Figure 1 As shown, the clamping lane 1 is a device used in removing and installing battery packs, usually used in battery swap stations. Its main function is to adjust the height of the vehicle for the bottom battery swapping method, thereby providing sufficient space at the bottom of the vehicle for battery swapping.

[0106] The lane 1 has a vehicle-carrying platform 11, which is used to carry the electric car 9 and can be raised and lowered in height. The lifting and lowering can be achieved by a related lifting mechanism. Since the mechanical structure of the lifting mechanism is not the focus of the present invention, it will not be described in detail here. The vehicle-carrying platform 11 is not a continuous and complete plane, but a segmented type, that is, there are two sections of vehicle-carrying platforms 11 on both sides that can carry wheels 91. The hollow area between the two sections of the vehicle-carrying platforms 11 can be called a battery replacement station, which is used for replacing the battery of the electric car 9. When the vehicle is parked on the vehicle-carrying platform 11, the battery at the bottom of the vehicle is aligned with the battery replacement station. In the following embodiment, the two sections of the vehicle-carrying platform 11 are synchronously controlled, that is, they rise or fall at the same time and the height is always the same.

[0107] The battery swapping device 2 is a bottom battery swapping device, which is used to remove the battery pack and install the battery from the bottom of the vehicle. It has a liftable battery swapping platform, a walking mechanism for controlling the overall movement of the battery swapping device and other components. A battery swapping device walking plane 12 is provided on the track 1 for the battery swapping device 2 to walk on. A battery swapping position is provided in the battery swapping device walking plane 12. The battery swapping position corresponds to the battery swapping station up and down, that is, when the battery swapping device 2 is located at the battery swapping position, the battery swapping device 2 only needs to adjust the height of the battery swapping platform up and down, with a small horizontal movement or no horizontal movement, so that the battery swapping platform can pass through the battery swapping station and reach the bottom of the vehicle, thereby completing the removal or installation of the battery pack. Figure 2 The vehicle loading platform 11 is shown as not being raised or lowered. At this time, the vehicle loading platform 11 is at an initial height h0. The plane where the lane 1 is located, the vehicle loading platform 11 that is not being raised or lowered, and the battery swapping equipment walking plane 12 can be located in the same plane. The arrows in the figure show the feasible walking routes of the battery swapping equipment 2.

[0108] The battery transfer device 3 is a movable battery carrying device that can be docked with the battery exchange equipment 2 and the battery rack. It has a battery transfer mechanism that can be raised and lowered and moved horizontally, a lifting mechanism that controls the raising and lowering of the battery transfer mechanism, an extending mechanism that controls the horizontal movement of the battery transfer mechanism, and a walking mechanism that controls the overall movement of the battery transfer device.

[0109] It should be noted that the above content and drawings only schematically show a type of lane clamping, battery exchange equipment and battery transfer device that can be applicable to the following embodiments, but it does not mean that the following embodiments can only be used for lane clamping, battery exchange equipment and battery transfer devices of the above structure or style. Lane clamping, battery exchange equipment and battery transfer devices with the same or similar functions and battery exchange principles are also applicable to the following embodiments.

[0110] Example 1

[0111] This embodiment provides a battery replacement control method, which is implemented by the cooperation of a battery replacement device and a battery transfer device. The battery replacement control method includes: Figure 3 As shown:

[0112] Step S001: Adjust the height of the battery swap platform and the height of the battery transfer mechanism;

[0113] Step S002: Control the battery transfer mechanism to take the battery from the battery exchange platform, or place the battery on the battery exchange platform.

[0114] In this embodiment, the battery exchange control method further includes, before step S001, controlling the battery exchange device and the battery transport device to move to a battery exchange position. The battery exchange position may be a position on the walking plane 12 of the battery exchange device, for example, a position close to the battery rack.

[0115] The specific process of transferring the battery on the battery swap platform to the battery transfer mechanism is given below: Figure 4 As shown:

[0116] Step S101: Control the battery exchange equipment and the battery transport device to move to the battery exchange position;

[0117] Step S102: Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the first matching height, so that the battery swap platform and the battery transfer mechanism match in height:

[0118] Step S103: Move the battery transfer mechanism horizontally until the battery transfer mechanism extends into the bottom of the battery on the battery swap platform to carry the battery;

[0119] Step S104: Horizontally retract the battery transfer mechanism.

[0120] A step of lifting the battery transfer mechanism may be added between step S103 and step S104 to detach the battery originally located on the battery exchange platform from the battery exchange platform and transfer it to the battery transfer mechanism. At the same time, the battery transfer mechanism may be restored to its original height after the transfer.

[0121] Among them, the battery swap platform and the battery transfer mechanism are matched in height, specifically including: when the battery swap platform is at the battery exchange height and the battery transfer mechanism is at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery swap platform, and the battery swap platform does not interfere with the movement of the battery transfer mechanism.

[0122] After the battery transfer mechanism is horizontally retracted, the battery transfer from the battery swap platform to the battery transport device is completed. Thereafter, the battery swap control method can further control the battery transport device to drive to the battery rack and place the battery into the battery rack.

[0123] The following is a specific process of transferring the battery on the battery transfer mechanism to the battery swap platform by adjusting the battery swap equipment and the battery transfer device, such as Figure 5 As shown:

[0124] Step S201: Control the battery exchange equipment and the battery transfer device to move to the battery exchange position;

[0125] Step S202: Control the battery swap platform to reach the battery swap height and control the battery transfer mechanism to reach the second matching height, so that the height of the battery transfer mechanism is higher than the height of the battery swap platform:

[0126] Step S203: horizontally moving the battery transfer mechanism until the battery transfer mechanism reaches above the battery swap platform;

[0127] Step S204: lowering the battery transfer mechanism to place the battery on the battery replacement platform;

[0128] Step S205: Restore the battery transfer mechanism to its initial height and / or retract the battery transfer mechanism horizontally.

[0129] After the battery transfer mechanism is horizontally retracted, the battery transfer from the battery transport device to the battery exchange device is completed. The battery exchange control method can further control the battery transport device to drive to the battery rack before adjusting the battery exchange device and the battery transport device, and take the battery from the battery rack and place it on the battery transfer mechanism. After the battery transport device takes the battery, it can be in a waiting state, and perform the above control process after receiving the instruction.

[0130] In this embodiment, the battery swap control method is also implemented by cooperating with the lane clamping and the battery swap equipment. The battery swap control method also includes:

[0131] The height of the vehicle loading platform and the height of the battery swapping platform are adjusted to disassemble and install the batteries on the electric vehicle.

[0132] Among them, adjusting the height of the vehicle loading platform and the height of the battery swapping platform specifically includes:

[0133] The height of the vehicle loading platform and the height of the battery swapping platform are controlled according to the battery swapping signal. The battery swapping signal can be sent by the control center of the battery swapping station or by different monitoring devices in the battery swapping station. The battery swapping signal can include multiple types, such as battery removal preparation signal, battery removal signal, battery removal completion signal, battery installation preparation signal, battery installation signal and battery installation completion signal.

[0134] The height of the vehicle loading platform and the height of the battery swapping platform are controlled according to the battery swapping signal, specifically including:

[0135] When the battery replacement signal is a battery removal preparation signal, the vehicle loading platform is controlled to reach the entry height of the first battery replacement equipment and / or the battery replacement platform is maintained at the initial height before being raised or lowered, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment. Figure 6 The schematic diagram shows the vehicle-carrying platform 11 at the first battery-swapping device entry height h1. In the actual battery-swapping process, the battery removal preparation signal is usually generated after the electric vehicle enters the vehicle-carrying platform; the first battery-swapping device entry height can be higher than the initial height of the vehicle-carrying platform before it is raised or lowered; the above control can ensure that the subsequent battery-swapping devices will not be blocked by the vehicle-carrying platform when entering the battery-swapping position.

[0136] And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach the battery removal operation height and / or the vehicle carrier platform is controlled to reach the battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric car on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition. Figure 7 The schematic diagram shows the case where the vehicle-carrying platform 11 is located at the battery removal matching height h2. In the actual battery replacement process, the battery removal signal is usually generated after the battery replacement equipment enters the battery replacement position; the battery removal height condition needs to be determined according to the operation process of the battery replacement equipment when removing the battery, and usually needs to meet the requirements that the battery removal structure on the battery replacement platform (such as the battery unlocking mechanism that unlocks the battery pack from the battery pack outer box) is sufficient to contact the battery pack outer box under the vehicle in the height direction; the battery removal operation height can be higher than the initial height of the battery replacement platform before it is raised or lowered; the battery removal matching height can be lower than the first battery replacement equipment entry height, or even lower than the initial height of the vehicle-carrying platform before it is raised or lowered; the above control allows the battery replacement platform to enter the bottom of the vehicle, thereby ensuring that the subsequent battery removal operation of the battery replacement equipment is completed smoothly.

[0137] And / or, when the battery replacement signal is a battery removal completion signal, the vehicle loading platform is controlled to reach the exit height of the first battery replacement device and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement device exceeds the height of the battery replacement device after the battery is loaded. Figure 8The schematic diagram shows the case where the vehicle-carrying platform 11 is located at the first battery-swapping device exit height h3. In the actual battery-swapping process, the battery removal completion signal is usually generated after the battery-swapping device removes the battery from the electric vehicle; the exit height of the first battery-swapping device can be higher than the initial height before the vehicle-carrying platform is raised or lowered, preferably higher than the entry height of the first battery-swapping device; the above control can ensure that the subsequent battery-swapping device that removes the battery will not be blocked by the vehicle-carrying platform when it exits the battery-swapping position.

[0138] And / or, when the battery swap signal is a battery loading preparation signal, the vehicle loading platform is controlled to reach the second battery swap equipment entry height and / or the battery swap platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle loading platform and the walking plane of the battery swap equipment exceeds the height of the battery swap equipment after the battery is loaded. Fig. 9 The schematic diagram shows the vehicle-carrying platform 11 at the second battery-swapping device entry height h4. In the actual battery-swapping process, the battery loading preparation signal is usually generated after the battery-swapping device removes the battery, leaves the battery-swapping position, and reloads a new battery compatible with the electric vehicle; the second battery-swapping device entry height can be higher than the initial height of the vehicle-carrying platform before it is raised or lowered, preferably equal to the exit height of the first battery-swapping device; the above control can ensure that the battery-swapping device loaded with new batteries will not be blocked by the vehicle-carrying platform when it re-enters the battery-swapping position.

[0139] And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach the battery installation operation height and / or the vehicle loading platform is controlled to reach the battery installation coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition. Fig.10 The schematic diagram shows the case where the vehicle-carrying platform 11 is located at the battery installation matching height h5. In the actual battery replacement process, the battery installation signal is usually generated after the battery replacement equipment re-enters the battery replacement position; the battery installation height condition needs to be determined according to the operation process of the battery replacement equipment during battery installation, and usually needs to meet the requirements that the battery installation structure can sufficiently place the battery pack on the battery replacement platform into the battery pack outer box at the bottom of the vehicle in the height direction; the battery installation height can be higher than the initial height of the battery replacement platform before it is raised or lowered, preferably equal to the battery removal operation height; the battery installation matching height can be lower than the second battery replacement equipment entry height, or even lower than the initial height of the vehicle-carrying platform before it is raised or lowered, preferably equal to the battery removal matching height; the above control allows the battery replacement platform to enter the bottom of the vehicle, thereby ensuring that the subsequent battery installation operation of the battery replacement equipment is completed smoothly.

[0140] And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment. Fig.11The schematic diagram shows the vehicle-carrying platform 11 at the second battery-swapping device exit height h6. In the actual battery-swapping process, the battery installation completion signal is usually generated after the battery-swapping device installs the battery on the electric vehicle; the second battery-swapping device exit height can be higher than the initial height before the vehicle-carrying platform is raised or lowered, preferably lower than the second battery-swapping device entry height, and can be equal to the first battery-swapping device entry height; the above control can ensure that the subsequent battery-swapping device that has completed the battery installation will not be blocked by the vehicle-carrying platform when it exits the battery-swapping position.

[0141] The following is a specific structure of a battery swap device and a control process for the battery swap device, so that the battery swap platform can reach different heights:

[0142] like Figure 12-14 As shown, the battery swapping device includes: the above-mentioned battery swapping platform 202, as well as a chassis 201 and a lifting mechanism. The lifting mechanism connects the chassis 201 and the battery swapping platform 202 and lifts the battery swapping platform 202 relative to the chassis 201. The lifting mechanism includes a connecting rod, the first end of the connecting rod is rotatably connected to the battery swapping platform 202, and the second end of the connecting rod is rotatably connected to the chassis 201.

[0143] Fig.13 The diagram illustrates the matching structure of the connecting rod and the battery exchange platform 202. In this embodiment, the connecting rod is a cam 203, but the present invention is not limited thereto, and the connecting rod can be in other forms.

[0144] The battery swap platform 202 is provided with a horizontally extending guide groove 204, and the tip of the cam 203 is provided with a roller 205, which is arranged in the guide groove 204 and can roll in the guide groove 204, and the thick end of the cam 203 is rotatably connected to the chassis 201. When the cam 203 rotates, it can drive the battery swap platform 202 to move in the up and down directions, and the cooperation between the guide groove 204 and the roller 205 prevents the battery swap platform 202 from moving in the horizontal direction as the cam 203 rotates.

[0145] The shuttle-type power exchange device 2 also includes: a lifting drive device 206 and a transmission shaft 207 connected to the lifting drive device 206, and the transmission shaft 207 is connected to the connecting rod and drives the connecting rod to rotate. The transmission shaft 207 is provided with positioning points along the circumference, and a sensor for sensing the positioning points is provided on the chassis 201, and the positioning points are used to locate the rotation angle of the connecting rod lifting the power exchange platform 202. In the figure, only two positioning points are schematically set to accurately locate the maximum height that the power exchange platform 202 can rise and the lowest height that it can fall. However, the present invention is not limited to this, and technicians in this field can also set more than two positioning points to locate multiple heights as needed. The positioning points include a first positioning point 211 and a second positioning point 212, and the sensor includes a first sensor 221 for sensing the first positioning point 211 and a second sensor 222 for sensing the second positioning point 212. The first positioning point 211 is used to locate the rotation angle of the connecting rod lifting the power exchange platform 202 to the highest point, and the second positioning point 212 is used to locate the rotation angle of the connecting rod from the bottom of the power exchange platform 202 to the lowest point.

[0146] Fig.14 The structure around the first positioning point 211 and the second positioning point 212 is illustrated. The transmission shaft 207 is provided with a first positioning ring 231 and a second positioning ring 232 in parallel, the protrusion of the first positioning ring 231 is the first positioning point 211, and the protrusion on the second positioning ring 232 is the second positioning point 212. Although the present embodiment is provided in the form of a positioning ring, the present invention is not limited thereto, and those skilled in the art may also use other forms to set the positioning points as needed, such as directly setting an identifiable mark such as a color point on the transmission shaft 207.

[0147] Optionally, the first positioning point 211 and the second positioning point 212 can also be arranged on the same circumference, and the sensor determines the height of the power exchange platform 202 by identifying different positioning points. The first sensor 221 and the second sensor 222 are arranged on the same side of the transmission shaft 207 and arranged side by side. The first positioning point 211 and the second positioning point 212 are 180 degrees apart in the circumferential direction. Since the connecting rod generally rotates 180 degrees in the process of lifting the power exchange platform 202 to the highest point and lowering it to the lowest point, it is preferred that the first positioning point 211 and the second positioning point 212 are 180 degrees apart in the circumferential direction.

[0148] Control the battery swap platform to reach any of the above heights, including: Fig.15 As shown:

[0149] Step S301: starting the lifting drive device, the lifted drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate;

[0150] And the detection steps to check whether it is lifted into place after starting:

[0151] Step S302: using a sensor to sense whether the positioning point has rotated past a preset angle, where the preset angle is the corresponding rotation angle of the positioning point when the battery swap platform reaches the required height;

[0152] If yes, then execute step S303: stop the lifting drive device;

[0153] If not, execute step S304: continue to operate the lifting drive device until the positioning point rotates through a preset angle.

[0154] For example, preset angles corresponding to the battery removal operation height, battery installation operation height, and battery swap height are set respectively. If the battery swap platform is required to reach the battery removal operation height, whether the battery swap platform has reached the battery removal operation height is determined by whether the positioning point has rotated through the preset angle corresponding to the battery removal operation height.

[0155] The battery replacement control method of this embodiment realizes the coordinated control of the sandwich lane and the battery replacement equipment, saves the vehicle's battery replacement time and improves the battery replacement efficiency; it also realizes the coordinated control of the battery replacement equipment and the battery transfer device, saves the transfer of batteries from the battery replacement equipment to the battery transfer device and the transfer of batteries from the battery transfer device to the battery replacement equipment, and improves the battery transfer efficiency.

[0156] Example 2

[0157] This embodiment provides a battery replacement control system to control the battery replacement equipment and the battery transport device. Fig.16 As shown, the battery swap control system includes:

[0158] The exchange control module 401 is used to adjust the height of the battery exchange platform and the height of the battery transfer mechanism, and to control the battery transfer mechanism to take the battery from the battery exchange platform or place the battery on the battery exchange platform.

[0159] In this embodiment, the exchange control module 401 is also used to control the battery exchange equipment and the battery transfer device to move to the battery exchange position before adjusting the height of the battery exchange platform and the height of the battery transfer mechanism. The battery exchange position can be a position on the walking plane 12 of the battery exchange equipment, for example, set at a position close to the battery rack.

[0160] In order to transfer the battery on the battery swap platform to the battery transfer mechanism, the height of the battery swap platform and the height of the battery transfer mechanism are adjusted, specifically including: controlling the battery swap platform to reach the battery swap height and controlling the battery transfer mechanism to reach the first matching height, so that the battery swap platform and the battery transfer mechanism match in height. Controlling the battery transfer mechanism to take the battery from the battery swap platform specifically includes: horizontally moving the battery transfer mechanism until the battery transfer mechanism extends into the bottom of the battery on the battery swap platform to carry the battery; horizontally retracting the battery transfer mechanism.

[0161] Among them, controlling the battery transfer mechanism to take the battery from the battery swap platform specifically also includes: after horizontally moving the battery transfer mechanism and before horizontally retracting the battery transfer mechanism, lifting the battery transfer mechanism to detach the battery originally located on the battery swap platform from the battery swap platform and transfer it to the battery transfer mechanism.

[0162] After the battery transfer mechanism is horizontally retracted, the battery transfer from the battery exchange platform to the battery transfer device is completed. Thereafter, the exchange control module 401 can further control the battery transfer device to move toward the battery rack and place the battery into the battery rack.

[0163] Among them, the battery swap platform and the battery transfer mechanism are matched in height, specifically including: when the battery swap platform is at the battery exchange height and the battery transfer mechanism is at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery swap platform, and the battery swap platform does not interfere with the movement of the battery transfer mechanism.

[0164] In order to transfer the battery on the battery transfer mechanism to the battery swap platform, the height of the battery swap platform and the height of the battery transfer mechanism are adjusted, specifically including: controlling the battery swap platform to reach the battery swap height and controlling the battery transfer mechanism to reach the second matching height, so that the height of the battery transfer mechanism is higher than the height of the battery swap platform. Controlling the battery transfer mechanism to place the battery on the battery swap platform specifically includes: controlling the battery transfer mechanism to reach the third height, so that the height of the battery transfer mechanism is higher than the height of the battery swap platform; horizontally moving the battery transfer mechanism until the battery transfer mechanism reaches above the battery swap platform; lowering the battery transfer mechanism to place the battery on the battery swap platform; and horizontally retracting the battery transfer mechanism.

[0165] In this embodiment, the battery swap control system also controls the sandwich lane and the battery swap equipment. The battery swap control system includes:

[0166] The disassembly and assembly control module 402 is used to adjust the height of the vehicle loading platform and the height of the battery replacement platform to disassemble and assemble the battery on the electric vehicle.

[0167] Among them, adjusting the height of the vehicle loading platform and the height of the battery swapping platform specifically includes:

[0168] The height of the vehicle carrying platform and the height of the battery swapping platform are controlled according to the battery swapping signal.

[0169] The height of the vehicle loading platform and the height of the battery swapping platform are controlled according to the battery swapping signal, specifically including:

[0170] When the battery swap signal is a battery removal preparation signal, the vehicle-carrying platform is controlled to reach the first battery swap equipment entry height and / or the battery swap platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery swap equipment exceeds the height of the battery swap equipment;

[0171] And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach the battery removal operation height and / or the vehicle carrier platform is controlled to reach the battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition;

[0172] And / or, when the battery swap signal is a battery removal completion signal, the vehicle-carrying platform is controlled to reach the exit height of the first battery swapping device and / or the battery swapping platform is controlled to reach the initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery swapping device exceeds the height of the battery swapping device after the battery is loaded;

[0173] And / or, when the battery swap signal is a battery loading preparation signal, the vehicle-carrying platform is controlled to reach the second battery swap equipment entry height and / or the battery swap platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery swap equipment exceeds the height of the battery swap equipment after the battery is loaded;

[0174] And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach the battery installation operation height and / or the vehicle loading platform is controlled to reach the battery installation matching height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition;

[0175] And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment.

[0176] In reference example 1 Figure 12-14 A specific structure of a battery swapping device is given. The exchange control module 401 and the disassembly control module 402 of this embodiment control the battery swapping platform to reach any of the above heights, specifically including:

[0177] The lifting drive device is started, and the lifted lifting drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate.

[0178] Specifically, it also includes: using a sensor to sense whether the positioning point has rotated past a preset angle, where the preset angle is the corresponding rotation angle of the positioning point when the battery swap platform reaches the required height;

[0179] If yes, the lifting drive device is stopped; if no, the lifting drive device is continued to operate until the positioning point rotates through a preset angle.

[0180] The battery exchange control system of this embodiment realizes the coordinated control of the battery exchange equipment and the battery transfer device, saves the transfer of batteries from the battery exchange equipment to the battery transfer device and the transfer of batteries from the battery transfer device to the battery exchange equipment, and improves the battery transfer efficiency; it also realizes the coordinated control of the sandwich lanes and the battery exchange equipment, saves the vehicle's battery exchange time and improves the battery exchange efficiency.

[0181] Example 3

[0182] Fig.17 This is a schematic diagram of the structure of an electronic device provided in Embodiment 3 of the present invention. The electronic device includes a memory, a processor, and a computer program stored in the memory and executable on the processor. When the processor executes the program, a method in Embodiment 1 is implemented. Fig.17 The electronic device 50 shown is only an example and should not bring any limitation to the functions and scope of use of the embodiments of the present invention.

[0183] like Fig.17 As shown, the electronic device 50 may be in the form of a general-purpose computing device, for example, it may be a server device. The components of the electronic device 50 may include, but are not limited to: at least one processor 51, at least one memory 52, and a bus 53 connecting different system components (including the memory 52 and the processor 51).

[0184] The bus 53 includes a data bus, an address bus, and a control bus.

[0185] The memory 52 may include a volatile memory, such as a random access memory (RAM) 521 and / or a cache memory 522 , and may further include a read-only memory (ROM) 523 .

[0186] The memory 52 may also include a program / utility 525 having a set (at least one) of program modules 524, such program modules 524 including but not limited to: an operating system, one or more application programs, other program modules, and program data, each of which or some combination may include an implementation of a network environment.

[0187] The processor 51 executes various functional applications and data processing by running the computer program stored in the memory 52, such as the method provided in Embodiment 1 of the present invention.

[0188] The electronic device 50 may also communicate with one or more external devices 54 (e.g., keyboards, pointing devices, etc.). Such communication may be performed via an input / output (I / O) interface 55. Furthermore, the model generating device 50 may also communicate with one or more networks (e.g., a local area network (LAN), a wide area network (WAN), and / or a public network, such as the Internet) via a network adapter 56. Fig.17 As shown, the network adapter 56 communicates with other modules of the model-generated device 50 via the bus 53. It should be understood that, although not shown in the figure, other hardware and / or software modules can be used in conjunction with the model-generated device 50, including but not limited to: microcode, device drivers, redundant processors, external disk drive arrays, RAID (disk array) systems, tape drives, and data backup storage systems, etc.

[0189] It should be noted that although several units / modules or sub-units / modules of the electronic device are mentioned in the above detailed description, this division is merely exemplary and not mandatory. In fact, according to an embodiment of the present invention, the features and functions of two or more units / modules described above can be embodied in one unit / module. Conversely, the features and functions of one unit / module described above can be further divided into multiple units / modules to be embodied.

[0190] Example 4

[0191] This embodiment provides a computer-readable storage medium on which a computer program is stored. When the program is executed by a processor, the steps of a method provided in Embodiment 1 are implemented.

[0192] The readable storage medium may include but is not limited to: a portable disk, a hard disk, a random access memory, a read-only memory, an erasable programmable read-only memory, an optical storage device, a magnetic storage device or any suitable combination of the above.

[0193] In a possible implementation manner, the present invention may also be implemented in the form of a program product, which includes program code. When the program product is run on a terminal device, the program code is used to enable the terminal device to execute the steps in any one of the methods of implementing Embodiment 1.

[0194] Among them, the program code for executing the present invention can be written in any combination of one or more programming languages, and the program code can be executed completely on the user device, partially on the user device, as an independent software package, partially on the user device and partially on a remote device, or completely on the remote device.

[0195] Although the specific embodiments of the present invention are described above, it should be understood by those skilled in the art that this is only for illustration and the protection scope of the present invention is defined by the appended claims. Those skilled in the art may make various changes or modifications to these embodiments without departing from the principles and essence of the present invention, but these changes and modifications all fall within the protection scope of the present invention.

Claims

1. A battery replacement control method, characterized in that: The battery replacement device and the battery transfer device are used to achieve the battery replacement control method. The battery replacement device includes a liftable battery replacement platform, and the battery transfer device has a liftable battery transfer mechanism. The battery replacement control method includes: Adjusting the height of the battery swap platform and the height of the battery transfer mechanism; Control the battery transfer mechanism to take the battery from the battery exchange platform or place the battery on the battery exchange platform; The adjusting the height of the battery swap platform and the height of the battery transfer mechanism includes: Controlling the battery exchange platform to reach the battery exchange height and controlling the battery transfer mechanism to reach the matching height; The battery replacement control method is also implemented by the cooperation of a track and a battery replacement device, wherein the track has a liftable vehicle loading platform, and the battery replacement control method includes: Adjusting the height of the vehicle loading platform and the height of the battery swapping platform to disassemble and install the battery on the electric vehicle; Adjusting the height of the vehicle carrying platform and the height of the battery swapping platform specifically includes: Control the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal; When the battery replacement signal is a battery removal signal, the battery replacement platform is controlled to reach a battery removal operation height and the vehicle carrier platform is controlled to reach a battery removal coordination height; the battery removal operation height is higher than an initial height of the battery replacement platform before it is raised or lowered; the battery removal coordination height is lower than an initial height of the vehicle carrier platform before it is raised or lowered.

2. The battery replacement control method according to claim 1, characterized in that: The battery exchange control method also includes controlling the battery exchange equipment and the battery transport device to move to a battery exchange position before adjusting the height of the battery exchange platform and the height of the battery transfer mechanism.

3. The battery replacement control method according to claim 1, characterized in that: The controlling the battery transfer mechanism to reach the matching height specifically includes: Control the battery transfer mechanism to reach a first matching height so that the battery swap platform matches the battery transfer mechanism in height: Controlling the battery transfer mechanism to take the battery from the battery swap platform specifically includes: Moving the battery transfer mechanism horizontally until the battery transfer mechanism extends to the bottom of the battery on the battery exchange platform to carry the battery; The battery transfer mechanism is retracted horizontally.

4. The battery replacement control method according to claim 3, characterized in that: Controlling the battery transfer mechanism to take the battery from the battery exchange platform specifically also includes: after horizontally moving the battery transfer mechanism and before horizontally retracting the battery transfer mechanism, lifting the battery transfer mechanism to detach the battery originally located on the battery exchange platform from the battery exchange platform and transfer it to the battery transfer mechanism.

5. The battery replacement control method according to claim 3, characterized in that: The battery exchange platform and the battery transfer mechanism are matched in height, specifically including: when the battery exchange platform is located at the battery exchange height and the battery transfer mechanism is located at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery exchange platform, and the battery exchange platform does not interfere with the movement of the battery transfer mechanism.

6. The battery replacement control method according to claim 1, characterized in that: The controlling the battery transfer mechanism to reach the matching height specifically includes: Control the battery transfer mechanism to reach a second mating height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform: Controlling the battery transfer mechanism to place the battery on the battery exchange platform specifically includes: Controlling the battery transfer mechanism to reach a third height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform; Moving the battery transfer mechanism horizontally until the battery transfer mechanism reaches above the battery exchange platform; Lowering the battery transfer mechanism to place the battery on the battery exchange platform; The battery transfer mechanism is retracted horizontally.

7. The battery replacement control method according to any one of claims 1 to 6, characterized in that: The battery swapping device further includes: a chassis, a lifting mechanism, a lifting drive device, and a transmission shaft connected to the lifting drive device, wherein the lifting mechanism connects the chassis and the battery swapping platform and lifts the battery swapping platform relative to the chassis, and the lifting mechanism includes a connecting rod, wherein a first end of the connecting rod is rotatably connected to the battery swapping platform, a second end of the connecting rod is rotatably connected to the chassis, and the transmission shaft is connected to the connecting rod and drives the connecting rod to rotate; Controlling the battery swap platform to reach the height of the battery swap platform specifically includes: The lifting drive device is started, and the lifted lifting drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate.

8. The battery replacement control method according to claim 7, characterized in that: The transmission shaft is provided with positioning points along the circumference, and the chassis is provided with sensors for sensing the positioning points, and the positioning points are used to locate the rotation angle of the connecting rod to lift the battery exchange platform; Controlling the battery swap platform to reach the height of the battery swap platform, specifically also includes: sensing, by the sensor, whether the positioning point has rotated over a first preset angle, the first preset angle being the angle at which the positioning point needs to rotate correspondingly when the battery swap platform reaches the height of the battery swap platform; If yes, the lifting drive device is stopped; if no, the lifting drive device continues to operate until the positioning point rotates by the first preset angle.

9. The battery replacement control method according to claim 1, characterized in that: When the battery exchange control method includes the step of controlling the battery transfer mechanism to take the battery from the battery exchange platform, it also includes, after controlling the battery transfer mechanism to take the battery from the battery exchange platform, controlling the battery transport device to drive to the battery rack and placing the battery into the battery rack; Alternatively, when the battery exchange control method includes the step of controlling the battery transfer mechanism to place the battery on the battery exchange platform, it also includes controlling the battery transfer device to move toward the battery rack and taking the battery from the battery rack and placing it on the battery transfer mechanism before controlling the battery transfer device to move to the battery exchange position.

10. The battery replacement control method according to claim 1, characterized in that: The clamping lane is provided with a battery swapping equipment walking plane for the battery swapping equipment to walk on; Controlling the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal specifically includes: When the battery replacement signal is a battery removal preparation signal, the vehicle-carrying platform is controlled to reach the first battery replacement equipment entry height and / or the battery replacement platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment; And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach a battery removal operation height and / or the vehicle carrier platform is controlled to reach a battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition; And / or, when the battery replacement signal is a battery removal completion signal, the vehicle-carrying platform is controlled to reach the exit height of the first battery replacement equipment and / or the battery replacement platform is controlled to reach the initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment after the battery is loaded; And / or, when the battery exchange signal is a battery loading preparation signal, the vehicle-carrying platform is controlled to reach the second battery exchange equipment entry height and / or the battery exchange platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery exchange equipment exceeds the height of the battery exchange equipment after the battery is loaded; And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach a battery installation operation height and / or the vehicle loading platform is controlled to reach a battery installation matching height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition; And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment.

11. A battery replacement control system, characterized in that: The battery exchange equipment and the battery transport device are controlled, wherein the battery exchange equipment includes a liftable battery exchange platform, the battery transport device has a liftable battery transfer mechanism, and the battery exchange control system includes: An exchange control module, used to adjust the height of the battery exchange platform and the height of the battery transfer mechanism, and to control the battery transfer mechanism to take the battery from the battery exchange platform or place the battery on the battery exchange platform; Adjusting the height of the battery exchange platform and the height of the battery transfer mechanism includes: Controlling the battery exchange platform to reach the battery exchange height and controlling the battery transfer mechanism to reach the matching height; The battery exchange control method further controls the sandwiched lane and the battery exchange equipment, wherein the sandwiched lane has a liftable vehicle loading platform, and the battery exchange control system includes: A disassembly and assembly control module, used to adjust the height of the vehicle loading platform and the height of the battery exchange platform to disassemble and assemble the battery on the electric vehicle; Adjusting the height of the vehicle carrying platform and the height of the battery swapping platform specifically includes: Control the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal; When the battery replacement signal is a battery removal signal, the battery replacement platform is controlled to reach a battery removal operation height and the vehicle carrier platform is controlled to reach a battery removal coordination height; the battery removal operation height is higher than an initial height of the battery replacement platform before it is raised or lowered; the battery removal coordination height is lower than an initial height of the vehicle carrier platform before it is raised or lowered.

12. The battery replacement control system according to claim 11, characterized in that: The exchange control module is also used to control the battery exchange equipment and the battery transport device to move to the battery exchange position before adjusting the height of the battery exchange platform and the height of the battery transfer mechanism.

13. The battery replacement control system according to claim 11, characterized in that: Adjusting the height of the battery transfer mechanism specifically includes: Control the battery transfer mechanism to reach a first matching height so that the battery swap platform matches the battery transfer mechanism in height: Controlling the battery transfer mechanism to take the battery from the battery swap platform specifically includes: Moving the battery transfer mechanism horizontally until the battery transfer mechanism extends to the bottom of the battery on the battery exchange platform to carry the battery; The battery transfer mechanism is retracted horizontally.

14. The battery replacement control system according to claim 13, characterized in that: Controlling the battery transfer mechanism to take the battery from the battery exchange platform specifically also includes: after horizontally moving the battery transfer mechanism and before horizontally retracting the battery transfer mechanism, lifting the battery transfer mechanism to detach the battery originally located on the battery exchange platform from the battery exchange platform and transfer it to the battery transfer mechanism.

15. The battery replacement control system according to claim 13, characterized in that: The battery exchange platform and the battery transfer mechanism are matched in height, specifically including: when the battery exchange platform is located at the battery exchange height and the battery transfer mechanism is located at the first matching height, if the battery transfer mechanism is moved horizontally, the battery transfer mechanism can extend to the bottom of the battery pack on the battery exchange platform, and the battery exchange platform does not interfere with the movement of the battery transfer mechanism.

16. The battery replacement control system according to claim 11, characterized in that: Adjusting the height of the battery transfer mechanism comprises: Control the battery transfer mechanism to reach a second mating height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform: Controlling the battery transfer mechanism to place the battery on the battery exchange platform specifically includes: Controlling the battery transfer mechanism to reach a third height so that the height of the battery transfer mechanism is higher than the height of the battery exchange platform; Moving the battery transfer mechanism horizontally until the battery transfer mechanism reaches above the battery exchange platform; Lowering the battery transfer mechanism to place the battery on the battery exchange platform; The battery transfer mechanism is retracted horizontally.

17. The battery replacement control system according to any one of claims 11 to 16, characterized in that: The battery swapping device further includes: a chassis, a lifting mechanism, a lifting drive device, and a transmission shaft connected to the lifting drive device, wherein the lifting mechanism connects the chassis and the battery swapping platform and lifts the battery swapping platform relative to the chassis, and the lifting mechanism includes a connecting rod, wherein a first end of the connecting rod is rotatably connected to the battery swapping platform, a second end of the connecting rod is rotatably connected to the chassis, and the transmission shaft is connected to the connecting rod and drives the connecting rod to rotate; Controlling the battery swap platform to reach the height of the battery swap platform specifically includes: The lifting drive device is started, and the lifted lifting drive device drives the transmission shaft to rotate, and the transmission shaft drives the connecting rod to rotate.

18. The battery replacement control system according to claim 17, characterized in that: The transmission shaft is provided with positioning points along the circumference, and the chassis is provided with sensors for sensing the positioning points, and the positioning points are used to locate the rotation angle of the connecting rod to lift the battery exchange platform; Controlling the battery swap platform to reach the height of the battery swap platform, specifically also includes: sensing, by the sensor, whether the positioning point has rotated over a first preset angle, the first preset angle being the angle at which the positioning point needs to rotate correspondingly when the battery swap platform reaches the height of the battery swap platform; If yes, the lifting drive device is stopped; if no, the lifting drive device continues to operate until the positioning point rotates by the first preset angle.

19. The battery replacement control system according to claim 11, characterized in that: When the exchange control module is used to control the battery transfer mechanism to take the battery from the battery exchange platform, it is also used to control the battery transport device to drive to the battery rack and put the battery into the battery rack after controlling the battery transfer mechanism to take the battery from the battery exchange platform; Alternatively, when the exchange control module is used to control the battery transfer mechanism to place the battery on the battery exchange platform, it is also used to control the battery transfer device to move to the battery rack and take the battery from the battery rack and place it on the battery transfer mechanism before controlling the battery transfer device to move to the battery exchange position.

20. The battery replacement control system according to claim 11, characterized in that: The clamping lane is provided with a battery swapping equipment walking plane for the battery swapping equipment to walk on; Controlling the height of the vehicle carrying platform and the height of the battery swapping platform according to the battery swapping signal specifically includes: When the battery replacement signal is a battery removal preparation signal, the vehicle-carrying platform is controlled to reach the first battery replacement equipment entry height and / or the battery replacement platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment; And / or, when the battery swap signal is a battery removal signal, the battery swap platform is controlled to reach a battery removal operation height and / or the vehicle carrier platform is controlled to reach a battery removal coordination height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle carrier platform is a negative distance, satisfying the battery removal height condition; And / or, when the battery replacement signal is a battery removal completion signal, the vehicle-carrying platform is controlled to reach the exit height of the first battery replacement equipment and / or the battery replacement platform is controlled to reach the initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment after the battery is loaded; And / or, when the battery exchange signal is a battery loading preparation signal, the vehicle-carrying platform is controlled to reach the second battery exchange equipment entry height and / or the battery exchange platform is maintained at an initial height before being raised or lowered, so that the height difference between the vehicle-carrying platform and the walking plane of the battery exchange equipment exceeds the height of the battery exchange equipment after the battery is loaded; And / or, when the battery swap signal is a battery installation signal, the battery swap platform is controlled to reach a battery installation operation height and / or the vehicle loading platform is controlled to reach a battery installation matching height, so that the distance between the battery swap platform and the bottom of the electric vehicle on the vehicle loading platform is a negative distance, satisfying the battery installation height condition; And / or, when the battery replacement signal is a battery installation completion signal, the vehicle loading platform is controlled to reach the second battery replacement equipment exit height and / or the battery replacement platform is controlled to reach the initial height before lifting, so that the height difference between the vehicle loading platform and the walking plane of the battery replacement equipment exceeds the height of the battery replacement equipment.

21. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the method according to any one of claims 1 to 10 is implemented.

22. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the program is executed by a processor, the steps of the method according to any one of claims 1 to 10 are implemented.