A steel column automatic rapid installation and correction device

Through the combination of clamps, limit pins, electro-hydraulic rods, electronic leveling instruments, and laser line projectors, automatic rapid installation and calibration of steel columns is achieved, solving the problems of low efficiency of steel column correction and waste of resources in the existing technology, and improving Correction accuracy and reduce costs.

CN115788083BActive Publication Date: 2024-11-15NO 2 CONSTR GRP CO LTD OF SHANGHAI CONSTR GRP
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211492002.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-11-25
Publication Date
2024-11-15
Estimated Expiration
2042-11-25

AI Technical Summary

Technical Problem

In the construction of existing steel structures, the installation correction efficiency of steel columns is low, the accuracy requirements are high, and resource waste is involved. The use of temporary connecting ear plates and cable wind ropes leads to increased construction costs and safety risks.

Method used

The combination of clamps, limit pins, electric hydraulic rods, electronic leveling instruments and laser projectors is used to form an automated quick installation correction device, replacing temporary connection ear plates and cable wind ropes, and realize automated docking and calibration of upper and lower columns.

Benefits of technology

It improves the efficiency and accuracy of steel column correction, reduces labor allocation and resource waste, reduces construction costs, and avoids safety hazards of cable and air ropes.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115788083B_ABST
    Figure CN115788083B_ABST
Patent Text Reader

Abstract

The present invention provides an automatic rapid installation and correction device for steel columns. The device adopts a clamp, a limit pin, an electric hydraulic rod, a level, a laser line projector and a plurality of wedge-shaped pins. A temporary fixed support is formed by the clamp, the limit pin and the electric hydraulic rod. A level for leveling and a laser line projector are arranged on the clamp. The steel column is lifted and lowered and swung sideways within a space by lifting and lowering the hydraulic rod. The center line of the column surface is projected to the ground by the line projector. By observing whether the level of the level and the center lines of the upper and lower sections of the steel columns projected to the ground coincide, the level, verticality and centering of the upper section column are judged, and then the installation and adjustment are completed. The device can replace the temporary connecting ear plates and temporary fixing bolts used in the welding and docking of steel columns, and replace the wind ropes used in the correction of steel columns, so as to reduce the input of manpower and mechanical equipment during installation and correction, thereby achieving the effect of optimizing the operation during the installation and correction of steel columns, improving construction efficiency and reducing processing and construction costs.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the field of assembled steel structure construction, and in particular relates to an automatic rapid installation and correction device for steel columns. Background Art

[0002] In recent years, with the increasing popularity of the concept of green engineering and the vigorous promotion and application of prefabricated buildings across the country, steel structures, as a typical form of prefabricated structures, have also been increasingly used and promoted.

[0003] Compared with precast concrete components, steel structural components have considerable advantages in terms of self-weight, strength, and especially processing and manufacturing conditions and technology. Steel structural components are flexible to process, have high precision requirements, and are formed in a variety of ways. Components can be processed in the factory or on site. Component disassembly is relatively flexible, and assembly can be done by welding and bolting.

[0004] At present, in the installation and correction of steel columns of prefabricated steel structures, temporary connecting ear plates are used in combination with temporary fixing bolts and the installation of cables and wind ropes. This method will use a large amount of existing site space in the construction of group columns because the installation of cables and wind ropes in multiple directions will cause difficulties in the layout and transportation of the construction site. The multiple personnel deployment during the correction process also increases the labor cost of the correction, while making the correction efficiency of steel columns low. The installation of cables and wind ropes everywhere will also cause certain safety hazards and increase the cost of accessories and materials. In addition, the method of temporarily fixing the upper and lower section columns using temporary connecting ear plates and temporary fixing bolts will add temporary connecting ear plates and other similar connection structures during the component processing process. After the upper and lower section columns are welded and connected, the temporary connecting ear plates will be cut off, which increases the cost of component production and causes a waste of resources. Summary of the invention

[0005] The present invention aims to invent an automated rapid installation and correction device for steel columns, which replaces temporary connection ear plates and temporary fixing bolts used in welding connections of upper and lower column sections, reduces the use time of lifting machinery during steel column installation and correction, replaces the wind ropes used in steel column correction, solves the impact of wind rope installation on on-site construction environment and correction speed during steel column correction, improves steel column correction efficiency and accuracy, reduces labor allocation during installation and correction, reduces processing and construction costs, and reduces waste of resources.

[0006] In order to solve the above technical problems, the present invention provides the following technical solutions:

[0007] A steel column automatic rapid installation and correction device is used to install an upper section column on the upper part of the already installed lower section column to form a steel column, comprising two clamps, a limit pin, an electric hydraulic rod, an electronic level, a laser line projector and a plurality of wedge-shaped pins. The two clamps are respectively arranged on the outer sides of the butt ends of the upper and lower section columns to be butted, each clamp comprises two L-shaped clamp parts, each L-shaped clamp part comprises two strip-shaped members, the two strip-shaped members are both arranged horizontally, one end of the two strip-shaped members is vertically connected and a pin hole perpendicular to the strip-shaped members is arranged at the connection, and the other end of the two strip-shaped members is provided with comb teeth along their own axis The comb-shaped slot of one L-shaped clamp component is set upward, and the comb-shaped slot of the other L-shaped clamp component is set downward. The two L-shaped clamp components are connected by the corresponding comb-shaped slots to form a rectangular structure with adjustable size. The vertical geometric center lines are marked on the surfaces of a pair of adjacent columns on the lower section column, and the vertical geometric center lines are marked on the surfaces of a pair of adjacent columns on the upper section column. A slide groove is provided along its own axial direction on the strip-shaped component corresponding to the column surface with the vertical geometric center line in each L-shaped clamp component located in the upper section column. Each slide groove is provided with an electronic level and a laser projection instrument. The electronic The level is fixedly connected to the corresponding laser line projector. The electronic level and the corresponding laser line projector can move along the corresponding slide groove. Four electric hydraulic rods are arranged between the two clamps. The four electric hydraulic rods are respectively arranged around the rectangular structure. A number of wedge-shaped pins are arranged between the strip-shaped member and the corresponding section column. By arranging limit pins in the upper and lower corresponding pin holes in the two clamps, the initial positioning and temporary fixation of the upper and lower section columns are realized. The clamps, wedge-shaped pins, limit pins and electric hydraulic rods are combined to form a temporary fixed support structure when the upper and lower section columns are connected. The laser line projector can project laser lines. When the electronic level is horizontal, the laser line projector can have a projection angle of 180° in the vertical elevation perpendicular to the surface of the upper section column; mark two orthogonal control lines on the ground, each control line intersects with the corresponding vertical geometric center line on the lower section column and is perpendicular to each other; by moving the position of the electronic level and the corresponding laser line projector, the laser line projected by the laser line projector to the surface of the upper section column coincides with the corresponding vertical geometric center line on the upper section column, and according to the projection situation of the laser line projector on the ground after centering and the situation shown by the electronic level, the electric hydraulic rod is used to correct and adjust the horizontal, vertical and centering conditions of the upper section column.

[0008] Preferably, in the above-mentioned automatic rapid correction device for steel columns, the horizontality and verticality of the upper section column are corrected and adjusted using an electric hydraulic rod according to the projection of the laser line projector and the situation shown by the electronic level. When the two electronic levels located on the upper section column display horizontality and the laser line projected by the laser line projector toward the upper section column coincides with the geometric center line of the upper section column, and the laser lines in two directions projected outward by the laser line projector coincide with the corresponding control lines on the ground, the upper section column is horizontal, vertical and centered.

[0009] Preferably, in the above-mentioned automatic rapid correction device for steel columns, a slide groove is provided along its own axial direction on the strip-shaped component corresponding to the column surface with the vertical geometric center line in each L-shaped clamp component located in the lower section column, and each slide groove is provided with an electronic level and a laser line projector. The electronic level and the corresponding laser line projector are fixedly connected, and the electronic level and the corresponding laser line projector can move along the corresponding slide groove. The laser line projector projects light outward. When the electronic level is horizontal, the laser line projector can have a projection angle of 180° in the vertical plane perpendicular to the surface of the lower section column. By moving the position of the electronic level and the corresponding laser line projector, the laser line projected by the laser line projector to the surface of the lower section column coincides with the corresponding vertical geometric center line on the lower section column.

[0010] Preferably, in the above-mentioned automatic rapid correction device for steel columns, when the control line on the ground is not long enough, the light projected by the laser line projector located on the lower section column when the corresponding electronic level is horizontal serves as the extension line of the corresponding control line; when the two electronic levels located on the upper section column display horizontality and the laser line projected by the laser line projector toward the upper section column coincides with the geometric center line of the upper section column, when the laser lines in two directions projected outward by the laser line projector coincide with the corresponding control line or the corresponding extension line on the ground, the upper section column is horizontal, vertical and centered.

[0011] Preferably, in the above-mentioned automatic rapid correction device for steel columns, a support plate for supporting the electric hydraulic rod is provided on the strip-shaped component.

[0012] Preferably, in the above-mentioned automatic rapid correction device for steel columns, the support plate located at the upper clamp is arranged below the corresponding slide groove, and the support plate located at the lower clamp is arranged above the corresponding slide groove.

[0013] It can be seen from the technical solutions disclosed above that, compared with the prior art, the beneficial effects of the present invention are as follows:

[0014] In summary, the present invention provides an automatic rapid correction device for steel columns, which is used to install an upper section column above an already installed lower section column to form a steel column. It uses two clamps, a limit pin, an electric hydraulic rod, an electronic level, a laser line projector and a plurality of wedge-shaped pins. The two clamps are respectively arranged on the outer sides of the butt ends of the upper and lower section columns to be butted, and each clamp includes two L-shaped clamp components. A slide groove is provided along its own axial direction on a strip-shaped component corresponding to the column surface with a vertical geometric center line in each L-shaped clamp component of the upper section column. An electronic level and a laser line projector are provided in each slide groove. The electronic level and the corresponding The corresponding laser line projector is fixedly connected, the electronic level and the corresponding laser line projector can move along the corresponding slide groove, four electric hydraulic rods are arranged between the two clamps, and the four electric hydraulic rods are respectively arranged around the rectangular structure, and a number of wedge-shaped pins are arranged between the strip-shaped member and the corresponding section column, and the initial positioning and temporary fixation of the upper and lower section columns are realized by arranging limit pins in the upper and lower corresponding pin holes in the two clamps. The clamps, wedge-shaped pins, limit pins and electric hydraulic rods are combined to form a temporary fixed support structure when the upper and lower section columns are connected. The laser line projector projects light outward, and when the electronic level is level, The laser line projector can have a projection angle of 180° in a vertical plane perpendicular to the surface of the upper section column, and mark two control lines on the ground. Each control line intersects with the corresponding vertical geometric center line on the lower section column and is perpendicular to each other. By moving the position of the electronic level and the corresponding laser line projector, the laser line projected by the laser line projector to the surface of the upper section column coincides with the corresponding vertical geometric center line on the upper section column; the electric hydraulic rod is used to lift, drop and swing the clamp on the outer periphery of the upper section column to correct and adjust the horizontal, vertical and centering conditions of the upper section column. By observing that the laser lines projected outward in two directions by the laser line projector are aligned with the ground, the laser line projector can be adjusted to the horizontal, vertical and centering conditions of the upper section column. The corresponding control lines on the upper part are overlapped to judge whether the horizontal, vertical and centering conditions of the upper section column meet the requirements; a temporary fixed support structure is formed by a combination of clamps, limit pins and electric hydraulic rods to fix and support the upper and lower sections of the steel columns, thereby replacing the temporary connection ear plates and temporary fixing bolts used in the welding connection of the upper and lower sections of the steel columns, reducing the use time of the lifting machinery in the installation and correction of the steel columns, replacing the cable wind rope used in the correction of the steel columns, solving the impact of the cable wind rope setting on the on-site construction environment and correction speed during the correction of the steel columns, improving the correction efficiency and accuracy of the steel columns, reducing the labor allocation during installation and correction, reducing construction costs, and reducing resource waste. BRIEF DESCRIPTION OF THE DRAWINGS

[0015] Figure 1 It is a structural schematic diagram of the automatic rapid correction device for steel columns.

[0016] Figure 2 This is a schematic diagram of the installation of the automatic rapid correction device for steel columns.

[0017] Figure 3 It is a structural diagram of the clamp.

[0018] Figure 4 It is a schematic diagram of the structure of the L-shaped clamp component located at the upper section column.

[0019] Figure 5 It is a top view schematic diagram of the L-shaped clamp component located at the upper section column.

[0020] Figure 6 It is a side view schematic diagram of the L-shaped clamp component located at the upper section column.

[0021] Figure 7 This is one of the assembly diagrams of the electronic level and the laser line projector.

[0022] Figure 8 This is one of the assembly diagrams of the electronic level and the laser line projector.

[0023] Fig. 9 It is a structural diagram of the electric hydraulic rod.

[0024] Fig.10 It is a schematic diagram of the structure of the limit pin.

[0025] Fig.11 It is a structural schematic diagram of the steel column automatic rapid correction device for steel columns with rectangular cross-sections.

[0026] Fig.12 It is a structural schematic diagram of the steel column automatic rapid correction device for steel columns with circular cross-sections.

[0027] Fig.13 It is a structural schematic diagram of the steel column automatic rapid correction device for steel columns with special-shaped cross-sections.

[0028] In the figure:

[0029] 1-Wedge Latch

[0030] 2-Laser line projector

[0031] 3-L-type clamp parts

[0032] 4-Chute

[0033] 5-Electronic level

[0034] 6-Comb-shaped card slot

[0035] 7-Pallet

[0036] 8-Electric hydraulic lever

[0037] 9-Limiting pin

[0038] 10- Casting light

[0039] 11-Vertical geometric centerline

[0040] 12-Control line

[0041] 13-Pin hole

[0042] 14- Slider

[0043] 100-upper section column

[0044] 200-lower section column. DETAILED DESCRIPTION

[0045] The present invention is further described in detail below in conjunction with the accompanying drawings and specific embodiments. The technical content and features of the present invention will be described in detail below by combining the enumerated embodiments with the accompanying drawings. It should be noted that the accompanying drawings are all in a very simplified form and are not in precise proportions, and are only used to conveniently and clearly assist in explaining the purpose of the embodiments of the present invention. For the convenience of description, the "upper" and "lower" described below are consistent with the upper and lower directions of the accompanying drawings, but this cannot be a limitation of the technical solution of the present invention.

[0046] See also Figures 1 to 13The present embodiment discloses an automatic rapid correction device for steel columns, which is used to install an upper section column 100 on the upper part of the already installed lower section column 200 to form a steel column. The automatic rapid correction device for steel columns includes two clamps, four electric hydraulic rods 8, an electronic level 5, a laser line projector 2 and a plurality of wedge-shaped pins 1. The two clamps are respectively arranged on the outer sides of the butt ends of the upper and lower section columns to be butted, each clamp includes two L-shaped clamp components 3, each L-shaped clamp component 3 includes two strip-shaped members, the two strip components are arranged horizontally, one end of the two strip components are vertically connected and a pin hole perpendicular to the strip components is provided at the connection, the other end of the two strip components is provided with a comb-shaped slot 6 along its own axial direction, and the comb teeth of an L-shaped clamp component The comb-shaped slot 6 of the other L-shaped clamp component is opened downward, and the two L-shaped clamp components are connected by the corresponding comb-shaped slots to form a rectangular structure with adjustable size. A vertical geometric center line 11 is marked on the surface of a pair of adjacent columns on the lower section column, and a vertical geometric center line 11 is marked on the surface of the upper column of the upper section column. The vertical geometric center lines 11 of the upper and lower section columns are arranged correspondingly up and down. A slide groove 4 is provided along its own axial direction on the strip-shaped component corresponding to the column surface with the vertical geometric center line 11 in each L-shaped clamp component of the upper section column. An electronic level 5 and a laser line projector 2 are provided in each slide groove. The electronic level 5 is fixedly connected to the corresponding laser line projector 2. The electronic level 5 is connected to the corresponding laser line projector 2. The corresponding laser line projector 2 can move along the corresponding slide groove 4. Four electric hydraulic rods 8 are arranged between the two clamps. The four electric hydraulic rods 8 are respectively arranged on the four sides of the rectangular structure. The clamp is driven to lift, fall and swing sideways through the lifting and falling of the electric hydraulic rods 8. A number of wedge-shaped pins 1 are arranged between the strip-shaped member and the corresponding section column. By inserting the wedge-shaped pins 1 into the gap between the section column surface and the clamp, a horizontal hugging clamp for steel columns with different cross-sectional sizes and different shapes can be achieved; by setting limit pins 9 in the upper and lower corresponding pin holes in the two clamps, the initial positioning and temporary fixation of the upper and lower section columns can be achieved. The clamp, wedge-shaped pin, limit pin and electric hydraulic rod combination form a temporary fixing support when the upper and lower section columns are connected. The support structure is a laser line projector 2 that projects light 10 outwards. When the electronic level 5 is horizontal, the laser line projector 2 can have a projection angle of 180° in a vertical plane perpendicular to the surface of the corresponding column segment. Two orthogonal control lines 12 are marked on the ground, and each control line 12 intersects with a corresponding vertical geometric center line 11 on the lower column segment and is perpendicular to each other. By moving the position of the electronic level 5 and the corresponding laser line projector 2, the laser line projected by the laser line projector 2 to the surface of the upper column segment coincides with the corresponding vertical geometric center line on the upper column segment. According to the projection situation of the laser line projector 2 and the situation shown by the electronic level 5, the upper column segment clamp is lifted, lowered and swung sideways by an electric hydraulic rod to correct and adjust the horizontal, vertical and centering conditions of the upper column segment.

[0047] By adopting the above-mentioned automatic rapid correction device for steel columns, by controlling the lifting, falling and sideways swing of the electric hydraulic rod, observing that the laser lines projected outwards in two directions by the laser line projector coincide with the corresponding control lines on the ground, it is judged whether the horizontal, vertical and centering conditions of the upper section column meet the requirements. When the two electronic levels located on the upper section column show horizontality and the laser projected in the direction of the upper section column by the laser line projector coincides with the geometric center line of the upper section column, and the laser lines projected outwards in two directions by the laser line projector coincide with the corresponding control lines on the ground, the upper section column is horizontal, vertical and centered, and the correction of the upper section column is completed, so that the upper and lower section columns can be quickly aligned, and automatic adjustment can be realized, which effectively reduces the time for steel column correction and improves construction efficiency. It can replace the cable wind rope in the conventional correction method, reduce the impact of the cable wind rope setting on the inconvenience of human and material movement on the on-site construction operation surface during steel column construction, reduce the number of collaborative workers in the installation and correction process, and avoid safety hazards when setting the cable wind rope; it has a simple structure and is easy to install and use. The two L-shaped clamp components are connected through the corresponding comb-shaped slots, and can be applied to steel columns of various cross-sectional sizes and shapes with the wedge-shaped pin. The combination of the clamp, the wedge-shaped pin, the limit pin and the electric hydraulic rod forms a temporary fixed support structure when the upper and lower sections of the steel columns are connected, which eliminates the need for the production of temporary connection ear plates for the steel columns and the use of temporary fixing bolts in the connection construction, and reduces the use time of the lifting machinery during the installation and correction of the steel columns; in addition, it can be recycled to avoid waste of resources.

[0048] Preferably, in the above-mentioned automatic rapid correction device for steel columns, according to the projection of the laser line projector and the situation shown by the electronic level, the electric hydraulic rod is used to lift, lower and swing the clamp of the upper section column to correct and adjust the horizontality and verticality of the upper section column. When the two electronic levels located on the upper section column show horizontality and the laser line projected by the laser line projector in the direction of the upper section column coincides with the geometric center line of the upper section column, and the laser lines projected outward in two directions by the laser line projector coincide with the corresponding control lines on the ground, the upper section column is horizontal, vertical and centered.

[0049] Preferably, in the above-mentioned automatic rapid correction device for steel columns, similar to the upper section column, a slide groove is provided along its own axial direction on the strip-shaped component corresponding to the column surface with the vertical geometric center line in each L-shaped clamp component located in the lower section column, and each slide groove is provided with an electronic level and a laser line projector. The electronic level and the corresponding laser line projector are fixedly connected, and the electronic level and the corresponding laser line projector can move along the corresponding slide groove. The laser line projector projects light outward. When the electronic level is horizontal, the laser line projector can have a projection angle of 180° in the vertical plane perpendicular to the surface of the lower section column. By moving the position of the electronic level 5 and the corresponding laser line projector 2, the laser line projected by the laser line projector 2 to the surface of the lower section column coincides with the corresponding vertical geometric center line on the lower section column.

[0050] Preferably, in the above-mentioned automatic rapid correction device for steel columns, when the control line on the ground is not long enough, the light projected by the laser line projector located on the lower section column when the corresponding electronic level is horizontal is used as the extension line of the corresponding control line, and the electric hydraulic rod is used to lift and lower the clamp of the upper section column. When the two electronic levels located on the upper section column display horizontality and the laser line projected by the laser line projector toward the upper section column coincides with the geometric center line of the upper section column, the laser lines projected outward in two directions by the laser line projector coincide with the corresponding control line or the corresponding extension line on the ground, the upper section column is horizontal, vertical and centered.

[0051] Preferably, in the above-mentioned automatic rapid correction device for steel columns, the clamp is made of a light and high-strength material. The clamp is composed of two L-shaped clamp parts, with a reserved comb-shaped slot at the end, and an integrated support plate 7 for supporting the electric hydraulic rod 8 extending perpendicularly to the slot surface from the corner of the L-shaped clamp part, that is, the strip-shaped component is provided with a support plate 7 for supporting the electric hydraulic rod 8.

[0052] Preferably, in the above-mentioned automated rapid correction device for steel columns, a pin hole 13 is provided at the connection between the two strip-shaped components of each L-shaped clamp component, and a limiting pin 9 is provided in the upper and lower corresponding pin holes 13 in the two clamps to achieve preliminary positioning and temporary fixation of the upper and lower section columns.

[0053] Preferably, in the above-mentioned automatic rapid correction device for steel columns, the support plate 7 located at the upper clamp is arranged below the corresponding slide groove 4, and the support plate 7 located at the lower clamp is arranged above the corresponding slide groove 4, thereby preventing motion interference between the electronic level 5 and the laser line projector 2 and the corresponding electric hydraulic rod 8.

[0054] Preferably, in the above-mentioned automatic rapid correction device for steel columns, the electronic level 5 is slidably connected to the corresponding slide groove 4 via a slider 14 , so that the electronic level 5 can be moved along the slide groove 4 .

[0055] Please continue reading Figures 1 to 13 The method for using the automatic rapid correction device for steel columns of this embodiment comprises the following steps:

[0056] Step 1, respectively set two clamps on the outer sides of the butt ends of the upper and lower section columns to be butted, each clamp includes two L-shaped clamp parts, each L-shaped clamp part includes two strip members, the two strip members are both horizontally arranged, one end of the two strip members is vertically connected and a pin hole perpendicular to the strip members is provided at the connection, the other ends of the two strip members are provided with comb-toothed slots along their own axes, the comb-toothed slot opening of one L-shaped clamp part is set upward, and the comb-toothed slot opening of the other L-shaped clamp part is set downward, the two L-shaped clamp parts are connected by corresponding comb-toothed slots to form a rectangular structure with adjustable size, the vertical geometric center line 11 is marked on the surface of a pair of adjacent columns on the lower section column, and the vertical geometric center line 11 is marked on the surface of a pair of adjacent columns on the upper section column. A vertical geometric center line 11, the vertical geometric center lines 11 of the upper and lower section columns are arranged correspondingly up and down, a slide groove 4 is arranged along its own axis on the strip-shaped component corresponding to the column surface with the vertical geometric center line 11 in each L-shaped clamp component, the electronic level 5 is fixedly connected with the corresponding laser line projector 2, and the electronic level 5 and the corresponding laser line projector 2 can move along the corresponding slide groove 4, four electric hydraulic rods 8 are arranged between the two clamps, and the four electric hydraulic rods 8 are respectively arranged around the rectangular structure, the laser line projector 2 projects light 10 outward, and when the electronic level 5 is horizontal, the laser line projector 2 can have a projection angle of 180° in the vertical elevation perpendicular to the surface of the corresponding section column, and a pin hole 13 is arranged at the connection between the two strip-shaped components of each L-shaped clamp component;

[0057] Step 2, mark two control lines 12 on the ground, each control line 12 intersects with the corresponding vertical geometric center line 11 on the lower section column and is perpendicular to each other;

[0058] Step 3, insert a wedge-shaped pin 1 between the strip-shaped member and the steel column, so that the clamp is tightly clamped on the surface of the upper section column;

[0059] Step 4: Use the lifting equipment to suspend the upper section column, preliminarily align the upper and lower section columns, and slowly lower the upper section column until it falls on the connection surface of the lower section column;

[0060] Step 5, manually fine-tune the upper column section by inserting the limit pins 9 into the upper and lower corresponding pin holes 13 in the two clamps, and setting four electric hydraulic rods 8 around the steel column and between the upper and lower clamps. The combination of the clamps, wedge-shaped pins, limit pins and electric hydraulic rods forms a temporary fixing and supporting structure, so that the upper and lower column sections are preliminarily aligned and temporarily fixed, and the upper column section is separated from the lifting equipment;

[0061] Step 6, turn on the laser line projector 2 and the electronic level 5 and move them horizontally, observe the laser line projector 2 directed to the surface of the upper column, and when the laser line coincides with the vertical geometric center line 11 of the upper column, the centering of the laser line projector 2 is completed;

[0062] Step 7, according to the projection of the laser projection instrument 2 and the situation shown by the electronic level 5, the clamp of the upper section column is lifted and lowered by the electric hydraulic rod 8 to calibrate and adjust the horizontality and verticality of the upper section column. When the two electronic levels 5 located on the upper section column show horizontality, and the projection light 10 of each laser projection instrument 2 located on the upper section column in two projection directions coincides with the corresponding control line 12 on the ground, the calibration of the upper section column is completed, that is, the horizontality and verticality of the upper section column meet the requirements;

[0063] Step 8: The upper and lower sections are connected by welding, and the clamps are removed after welding is completed.

[0064] Preferably, a support plate 7 for supporting the electric hydraulic rod 8 is provided on the strip-shaped component.

[0065] Preferably, the support plate 7 located at the upper clamp is arranged below the corresponding slide groove 4, and the support plate 7 located at the lower clamp is arranged above the corresponding slide groove 4, so as to prevent motion interference between the electronic level 5 and the laser line projector 2 and the corresponding electric hydraulic rod 8.

[0066] Preferably, the lower section column is pre-calibrated and installed, and a laser line is projected outwards by a laser line projector 2 located at the lower clamp to achieve marking of the ground control line.

[0067] The automatic rapid installation and correction device for steel columns provided by the present invention can not only be used repeatedly, but also has a wide range of applicable occasions, such as being used for the correction of steel columns with rectangular cross sections, such as Fig.11 As shown; it can also be used to correct steel columns with circular cross-sections, such as Fig.12 As shown; it can also be used to correct steel columns with special cross-sections, such as Fig.13 As shown; in addition, it can also be used for the correction of upper and lower steel columns with the same cross-sectional shape and different sizes.

[0068] In summary, the automatic rapid installation and correction device for steel columns provided by the present invention forms a temporary fixed support structure when the upper and lower steel column sections are connected through a combination of a clamp, a wedge-shaped pin, a limit pin and an electric hydraulic rod; a horizontal sliding groove 4 for measuring instruments is provided on the clamp, so that the instrument can be easily aligned with the steel column component section column; a laser line projector 2 with vertical 180° aiming and an electronic level 5 with automatic leveling measurement function are provided on the clamp, and after the clamp setting of the upper and lower section columns is completed, the laser emission port of the laser line projector 2 can be aligned with the upper section column by horizontally moving the electronic level 5 and the corresponding laser line projector 2, so that the vertical geometric center line of the upper section column can be projected to the outside; after the upper and lower section columns are connected in place, the limit pin 9 is inserted into the pin hole to achieve the limit of the upper and lower section columns. Positioning and preliminary centering; a vertical electric hydraulic adjustment rod is set between the support plates 7 of the upper and lower clamps, and the horizontality and verticality of the steel column are adjusted by the extension and retraction of the hydraulic adjustment rod; by observing whether the center lines of the upper and lower sections of the column projected outward by the laser projection instrument 2 in both directions coincide with the existing control line 12 on the ground when the electronic level 5 is horizontal, it is judged whether the horizontality and verticality of the upper section of the column meet the requirements, thereby replacing the temporary connecting ear plates and temporary fixing bolts used in the welding connection of the upper and lower sections of the steel column, reducing the use time of the lifting machinery in the installation and correction of the steel column, replacing the cable wind rope used in the correction of the steel column, solving the impact of the cable wind rope pulling on the on-site construction environment and the correction speed during the correction of the steel column, improving the efficiency and accuracy of the steel column correction, reducing the labor allocation during installation and correction, reducing the processing and construction costs, and reducing resource waste.

[0069] The above description is only a description of the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention. Any changes or modifications made by a person skilled in the art in the field of the present invention based on the above disclosure shall fall within the scope of protection of the claims.

Claims

1. An automatic rapid installation and correction device for steel columns, used to install an upper section column on top of an already installed lower section column to form a steel column, characterized in that: It includes two clamps, a limit pin, an electric hydraulic rod, an electronic level, a laser line projector and a plurality of wedge-shaped pins. The two clamps are respectively arranged on the outer sides of the butt ends of the upper and lower section columns to be butted. Each clamp includes two L-shaped clamp parts. Each L-shaped clamp part includes two strip-shaped members. The two strip-shaped members are both arranged horizontally. One end of the two strip-shaped members is vertically connected and a pin hole perpendicular to the strip-shaped members is arranged at the connection. The other ends of the two strip-shaped members are provided with a comb-shaped slot along their own axis. The comb-shaped slot opening of one L-shaped clamp part is arranged upward. The other L-shaped clamp part is provided with a comb-shaped slot opening upward. The comb-tooth-shaped slot opening of the component is set downward, and the two L-shaped clamp components are clamped together through the corresponding comb-tooth-shaped slots to form a rectangular structure with adjustable size. The vertical geometric center lines are marked on the surfaces of a pair of adjacent columns on the lower section column, and the vertical geometric center lines are marked on the surfaces of a pair of adjacent columns on the upper section column. A slide groove is provided along its own axial direction on the strip-shaped component corresponding to the column surface with the vertical geometric center line in each L-shaped clamp component located in the upper section column, and each slide groove is provided with an electronic level and a laser line projector. The electronic level is fixedly connected to the corresponding laser line projector. The electronic level and the corresponding laser line projector can move along the corresponding slide grooves, four electric hydraulic rods are arranged between the two clamps, and the four electric hydraulic rods are respectively arranged around the rectangular structure, and a number of wedge-shaped pins are arranged between the strip-shaped components and the corresponding section columns. By arranging limit pins in the upper and lower corresponding pin holes in the two clamps, the initial positioning and temporary fixation of the upper and lower section columns are realized. The clamps, wedge-shaped pins, limit pins and electric hydraulic rods are combined to form a temporary fixed support structure when the upper and lower section columns are connected. The laser line projector can project a laser line. When the electronic level is level Normally, the laser line projector can have a projection angle of 180° in the vertical elevation perpendicular to the surface of the upper section column; two orthogonal control lines are marked on the ground, each control line intersects with the corresponding vertical geometric center line on the lower section column and is perpendicular to each other; by moving the position of the electronic level and the corresponding laser line projector, the laser line projected by the laser line projector to the surface of the upper section column coincides with the corresponding vertical geometric center line on the upper section column, and according to the projection situation of the laser line projector and the situation shown by the electronic level, the electric hydraulic rod is used to correct and adjust the horizontal, vertical and centering conditions of the upper section column.

2. The automatic rapid installation and correction device for steel columns according to claim 1 is characterized in that: When the two electronic levels located on the upper section column show horizontality and the laser line projected by the laser line projector toward the upper section column coincides with the geometric center line of the upper section column, and the laser lines projected outward in two directions coincide with the corresponding control lines on the ground, the upper section column is horizontal, vertical and centered.

3. The automatic rapid installation and correction device for steel columns according to claim 1, characterized in that: A slide groove is provided along the axial direction of the strip-shaped component corresponding to the column surface with the vertical geometric center line in each L-shaped clamp component located in the lower section column. An electronic level and a laser line projector are provided in each slide groove. The electronic level and the corresponding laser line projector are fixedly connected. The electronic level and the corresponding laser line projector can move along the corresponding slide groove. When the electronic level is horizontal, the laser line projector can have a projection angle of 180° in the vertical plane perpendicular to the surface of the lower section column. By moving the position of the electronic level and the corresponding laser line projector, the laser line projected by the laser line projector to the surface of the lower section column coincides with the corresponding vertical geometric center line on the lower section column.

4. The automatic rapid installation and correction device for steel columns according to claim 1, characterized in that: When the control line on the ground is not long enough, the laser line projected by the laser line projector located on the lower node column when the corresponding electronic level is horizontal serves as the extension line of the corresponding control line. When the two electronic levels located on the upper node column display horizontality and the laser line projected by the laser line projector toward the upper node column coincides with the geometric center line of the upper node column, the laser lines projected outward in two directions coincide with the corresponding control line or the corresponding extension line on the ground, the upper node column is horizontal, vertical and centered.

5. The automatic rapid installation and correction device for steel columns according to claim 1, characterized in that: A supporting plate for supporting the electric hydraulic rod is arranged on the strip-shaped component.

6. The automatic rapid installation and correction device for steel columns according to claim 5, characterized in that: The supporting plate located at the upper clamp is arranged below the corresponding slide slot, and the supporting plate located at the lower clamp is arranged above the corresponding slide slot.