Design method and system of temporary vertical poles of Bailey plates
The temporary vertical pole structural scheme is selected through the finite element model and historical data scoring sorting, which solves the problem of inaccurate installation of temporary vertical poles on Beret sheets, improves construction efficiency and structural performance, and reduces material waste and risks.
Patent Information
- Application Number
- CN202410684111.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-30
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-05-30
AI Technical Summary
During bridge construction, the installation location and dimensions of the temporary vertical poles of Beret sheets are difficult to accurately determine, resulting in uncertain load-bearing capacity, low construction efficiency, reduced structural reliability and waste of materials.
By establishing a finite element model, simulating construction loads and support conditions, determining weak positions, and combining historical data and finite element analysis results, rating and sorting temporary vertical pole structural schemes, selecting the optimal scheme and revising the size to ensure the scientificity of the design and reliability.
It improves the accuracy and construction efficiency of temporary vertical poles, enhances structural performance and material utilization, and reduces on-site construction risks and material waste.
Smart Images

Figure CN118260847B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of bridge construction, and in particular to a design method and system for a temporary vertical pole of a Bailey sheet. Background Art
[0002] In the construction of bridges, temporary bridges and other structures, Bailey plates are widely used due to their modular and standardized characteristics. However, in the actual construction process, especially in the construction of complex structures such as inclined curved bridges, the fulcrum of the Bailey beam is often difficult to accurately correspond to the intersection nodes of the chord bar, vertical bar and diagonal bar in the Bailey plate, resulting in the Bailey plate being unable to fully exert its structural advantages, which in turn causes material waste and a decrease in bearing capacity. In the specific construction process, in order to improve the bearing capacity of the non-node position of the Bailey plate used as the fulcrum of the Bailey beam, the traditional method is to add temporary vertical bars at the non-node fulcrum position; when the Bailey beam fulcrum is not at the node position, the bearing capacity can be increased by 1 / 3 by adding temporary vertical bars.
[0003] However, the addition of temporary vertical poles during on-site construction cannot be done accurately. The fundamental reason is that the building structure in the application scenario is large, and the number of temporary vertical poles often increases. This addition work is currently often completed based on experience, which will lead to the following problems:
[0004] Uncertainty of bearing capacity: Due to the lack of scientific calculation basis for the installation position, structure and size of the temporary vertical pole, the bearing capacity of the fulcrum is difficult to predict, which poses a potential safety hazard;
[0005] Low construction efficiency: The location and size design of temporary vertical poles rely on workers' experience, which is prone to errors and requires repeated adjustments, increasing construction time and labor costs;
[0006] Reduced structural reliability: Inaccurate position of temporary vertical rods will affect the stability of the entire Bailey beam and increase the risk of structural failure;
[0007] Material waste: unreasonable temporary vertical pole arrangement not only fails to fully utilize the strength of the material, but may also lead to material waste and unnecessary cost increase.
[0008] Therefore, a more scientific and systematic method is needed to accurately determine the comprehensive plan such as the position, structure and size of the temporary vertical poles, so as to improve the bearing capacity of the support points of the Bailey beam at non-node positions and ensure the safety and efficiency of the construction process. Summary of the invention
[0009] The present invention provides a design method and system for a Bailey sheet temporary vertical rod, which can effectively solve the problems in the background technology.
[0010] In order to achieve the above object, the technical solution adopted by the present invention is:
[0011] The design method of temporary vertical poles of Bailey plates includes:
[0012] Establish a finite element model of several interconnected Bailey plates, input material properties and geometric dimensions, simulate the load and support conditions in actual construction, run finite element analysis, and obtain finite element analysis results;
[0013] According to the finite element analysis results, determining the weak positions of the non-node positions of each Bailey sheet, and using the weak positions as the positions to be installed of the temporary vertical rods;
[0014] Traversing historical data, obtaining several temporary vertical pole structure schemes available for selection, and comprehensively scoring each of the temporary vertical pole structure schemes in combination with the finite element analysis of the position to be installed, to obtain a scoring ranking;
[0015] Selecting a temporary vertical bar structure solution with the best score based on the score ranking, and adding the temporary vertical bar structure solution to the finite element model to obtain a revised model;
[0016] Performing finite element analysis on the revised model to obtain revised analysis results, and revising the final dimensions of the temporary vertical bar structure scheme at each of the locations to be installed according to the revised analysis results;
[0017] Among them, traverse the historical data to obtain several temporary vertical pole structure solutions available for selection, and conduct a comprehensive evaluation of each of the structure solutions in combination with the finite element analysis of the location to be installed, including:
[0018] Collect several temporary vertical pole structure plans;
[0019] Determine a number of evaluation indicators according to the finite element analysis of each of the positions to be installed, and establish an evaluation scheme for each position to be installed, wherein the first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators;
[0020] For each of the locations to be installed, calculating the total score of each of the temporary vertical pole structure solutions for each evaluation index;
[0021] For all locations to be installed, calculate the sum of the total scores of each temporary vertical pole structure solution, and calculate the standard deviation of the total scores of each temporary vertical pole structure solution at different locations to be installed;
[0022] The final comprehensive score of each temporary vertical pole structure scheme is determined by the sum of the total scores of the schemes and the standard deviation of the total scores of the schemes.
[0023] Furthermore, the calculation formula of the comprehensive score is:
[0024] E=w 1 ×S j +w 2 ×σ j ;
[0025] Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the scheme.
[0026] Furthermore, the weak position is determined by analyzing at least one of a stress distribution diagram, a strain distribution diagram or a modal analysis result.
[0027] Furthermore, the evaluation indicators include at least three of bearing capacity, construction convenience, cost-effectiveness, material utilization rate and safety.
[0028] Furthermore, the weight coefficient is determined w 1 and w 2 , using at least one of the following methods: expert consultation, historical data analysis, weighting techniques, target trade-offs and simulations, and sensitivity analysis.
[0029] The design system of Bailey sheet temporary vertical poles includes:
[0030] Finite element analysis module, which builds a finite element model of several interconnected Bailey plates, inputs material properties and geometric dimensions, simulates the load and support conditions in actual construction, runs finite element analysis, and obtains finite element analysis results;
[0031] A result analysis module, which determines the weak position of each non-node position of the Bailey plate according to the finite element analysis result, and uses the weak position as the position to be installed of the temporary vertical rod;
[0032] A historical data acquisition module traverses historical data to obtain several temporary vertical pole structure solutions that can be selected;
[0033] A scheme ranking module is used to comprehensively score each of the temporary vertical pole structure schemes in combination with the finite element analysis of the position to be installed, and obtain a score ranking;
[0034] A model revision module, which selects a temporary vertical bar structure solution with the best score based on the score ranking, and adds the temporary vertical bar structure solution to the finite element model to obtain a revised model;
[0035] A size revision module, which revises the final size of the temporary vertical bar structure scheme at each of the locations to be installed based on the revised analysis results of the revised model by the finite element analysis module;
[0036] Wherein, the scheme sorting module includes:
[0037] An evaluation scheme establishing unit, which determines a number of evaluation indicators according to the finite element analysis of each of the positions to be installed, and establishes an evaluation scheme for each position to be installed, wherein the first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators;
[0038] A calculation unit, for each of the positions to be installed, calculates the total score of each of the temporary vertical pole structure schemes for each evaluation index, for all the positions to be installed, calculates the sum of the total scores of each of the temporary vertical pole structure schemes, and calculates the standard deviation of the total scores of each of the temporary vertical pole structure schemes at different positions to be installed;
[0039] The comprehensive score output unit determines the final comprehensive score of each temporary vertical pole structure scheme through the sum of the total scores of the schemes and the standard deviation of the total scores of the schemes.
[0040] Furthermore, in the comprehensive score output unit, the calculation formula of the comprehensive score is:
[0041] E=w 1 ×S j +w 2 ×σ j ;
[0042] Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the scheme.
[0043] The beneficial effects of the present invention are:
[0044] The present invention systematically solves the problems of inaccurate temporary vertical pole setting, insufficient bearing capacity and low construction efficiency in traditional methods through scientific modeling, precise analysis, optimized design and verification and revision. It accurately simulates and analyzes construction conditions based on finite element analysis to avoid errors in empirical judgment. It selects the optimal solution through scoring and sorting to improve structural performance and material utilization. It ensures the practical feasibility of the design solution through revision and verification to avoid on-site construction problems. BRIEF DESCRIPTION OF THE DRAWINGS
[0045] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are only some embodiments recorded in the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0046] Figure 1 It is a flow chart of the design method of the temporary vertical pole of the lightning sheet in the present invention;
[0047] Figure 2 A flowchart for comprehensive scoring in the present invention;
[0048] Figure 3 It is a schematic diagram of the structure of the temporary vertical pole of Bailey sheet in the present invention;
[0049] Figure 4 It is a structural schematic diagram of the connecting frame in the present invention;
[0050] Figure 5 It is a structural schematic diagram of the support frame in the present invention;
[0051] Figure 6 A schematic diagram of an implementation of a Bailey sheet temporary vertical rod in the present invention;
[0052] Figure 7 This is a schematic diagram of an implementation of the connecting frame in the present invention;
[0053] Figure 8 A schematic diagram of an implementation of a Bailey sheet temporary vertical rod in the present invention;
[0054] Fig. 9 This is a schematic diagram of an implementation of the connecting frame in the present invention;
[0055] 1. The first support beam; 11. The first support plate; 111. The first reinforcing plate; 12. The first slot; 13. The first channel steel; 131. The third reinforcing plate; 14. The first pin; 2. The second support beam; 21. The second support plate; 211. The second reinforcing plate; 22. The second slot; 23. The second channel steel; 231. The fourth reinforcing plate; 24. The second pin; 3. The connecting frame; 31. The supporting frame; 311. The first connecting rod; 312. The second connecting rod; 32. The first connecting seat; 33. The second connecting seat; 34. The first screw; 341. The first nut; 342. The second nut; 35. The second screw; 351. The third nut; 352. The fourth nut; 36. The first limiting seat; 361. The first plane; 362. The first limiting groove; 37. The second limiting seat; 371. The second plane; 372. The second limiting groove. DETAILED DESCRIPTION
[0056] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0057] It should be noted that when an element is referred to as being "fixed to" another element, it may be directly on the other element or there may be a central element. When an element is considered to be "connected to" another element, it may be directly connected to the other element or there may be a central element at the same time. The terms "vertical", "horizontal", "left", "right" and similar expressions used herein are for illustrative purposes only and do not represent the only implementation method.
[0058] Unless otherwise defined, all technical and scientific terms used herein have the same meaning as those commonly understood by those skilled in the art of the present invention. The terms used herein in the specification of the present invention are only for the purpose of describing specific embodiments and are not intended to limit the present invention. The term "and / or" used herein includes any and all combinations of one or more related listed items. Embodiment 1
[0059] Design methods for temporary vertical poles of Bailey plates, such as Figure 1 As shown, including:
[0060] S1: Establish a finite element model of several interconnected Bailey plates. The interconnected state simulates the connection relationship of the Bailey plates in the actual scene. Input material properties and geometric dimensions, simulate the load and support conditions in the actual construction, run finite element analysis, and obtain finite element analysis results. By establishing an accurate finite element model, it is possible to simulate the stress and deformation conditions in the actual construction, provide a scientific basis for subsequent analysis, and avoid the traditional practice of relying on experience. During the implementation process, it is necessary to ensure that the model can reflect the actual working conditions and improve the reliability of the analysis results.
[0061] S2: According to the results of finite element analysis, the weak positions in the non-node positions of each Bailey plate are determined, and the weak positions are used as the positions to be installed for the temporary vertical rods. In this step, multiple positions to be installed are often accurately obtained; this step can avoid the inaccuracy of manual judgment, and by accurately locating the positions to be installed for the temporary vertical rods, the weak points of the structure can be effectively strengthened; as a further preferred embodiment, in the finite element model, the determination of the weak position is achieved by analyzing at least one of the stress distribution diagram, the strain distribution diagram or the modal analysis results. Specifically, by observing the stress distribution diagram, the areas of stress concentration are usually shown as areas with darker colors or higher values. These areas may become potential weak points. Compare the stress values of each part in the model with the allowable stress or fatigue limit of the material. Areas that exceed these limits need special attention because they are more likely to be damaged in actual use. Similar to stress, the area of strain concentration also indicates that the material has undergone a large deformation at this location, which may be a weak point. By observing the overall and local deformation behavior of the structure under load, those parts with abnormal deformation can be found, which are usually the weak links of the structure. Modal analysis can reveal the vibration characteristics of a structure. If certain parts of the structure exhibit a large vibration response at a certain frequency, this may indicate that the part is relatively weak or inadequate to resist the expected dynamic loads.
[0062] S3: traverse historical data to obtain several temporary vertical pole structure solutions available for selection, and comprehensively score each temporary vertical pole structure solution in combination with the finite element analysis of the location to be installed to obtain a score ranking;
[0063] S4: Based on the scoring ranking, the temporary vertical bar structure scheme with the best score is selected, and the temporary vertical bar structure scheme is added to the finite element model to obtain a revised model; the design scheme is verified by the revised model, so as to avoid the design defects and insufficient bearing capacity of the determined temporary vertical bar structure during actual installation;
[0064] S5: Perform finite element analysis on the revised model to obtain revised analysis results. Revise the final size of the temporary vertical bar structure scheme based on the revised analysis results. Through the final revision, it can be ensured that the design scheme fully meets the actual construction requirements and avoid insufficient bearing capacity or material waste caused by inappropriate size.
[0065] The present invention accurately determines the installation position of the temporary vertical pole through scientific modeling and precise analysis, and then realizes the optimal selection of the structure based on the scoring and ranking of the historical temporary vertical pole structure schemes. Finally, the size revision of the selected structure at each installation position is realized through the establishment of a revised model, which systematically solves the problems of inaccurate temporary vertical pole setting, insufficient bearing capacity and low construction efficiency in traditional methods; based on finite element analysis, the construction conditions are accurately simulated and analyzed to avoid errors in empirical judgment; the optimal scheme is selected through scoring and ranking to improve structural performance and material utilization; the actual feasibility of the design scheme is ensured through revision and verification to avoid on-site construction problems.
[0066] In the above embodiment, steps S4 and S5 involve design verification and optimization using a finite element model. These two steps together constitute a systematic verification and improvement process, ensuring the reliability and efficiency of the design solution:
[0067] Specifically, in step S4, the optimal temporary vertical bar structure scheme is systematically selected through scoring and sorting, which can ensure that the selected scheme has the best performance expectation in theory. Of course, only the structural shape of the temporary vertical bar is selected in this step, and the specific size will be revised in the subsequent steps. The goal of the selection is to obtain the best comprehensive effect of the temporary vertical bar structure in all the locations to be installed, rather than just unilateral prominence. This method uses quantitative analysis to reduce the influence of subjective judgment and improves the objectivity and accuracy of the selection; integrating the selected scheme into the finite element model can theoretically verify the effectiveness of the structural design. By simulating the actual load conditions and structural responses, possible design defects or deficiencies can be identified and solved in advance to avoid problems in actual installation. Through model verification, it can be ensured that the selected scheme has sufficient structural bearing capacity, thereby reducing risks and potential structural failures in actual applications.
[0068] In step S5, further finite element analysis of the revised model can obtain more detailed data to support the refinement and adjustment of the design plan, which allows engineers to optimize the structural size and layout according to the latest analysis results to ensure that the design is more in line with actual needs; by optimizing the structural size, the use of materials can be effectively controlled to avoid over-design and material waste, which not only saves costs but also improves the environmental friendliness of the project; the final revision ensures that the design plan fully complies with construction requirements and safety standards. This step is the key to ensuring that the final product of all design and analysis work can be reliably executed in actual construction.
[0069] As a preferred embodiment of the above, historical data is traversed to obtain several temporary vertical pole structure solutions that can be selected, and each structure solution is comprehensively scored in combination with the finite element analysis of the location to be installed, such as Figure 2As shown, including:
[0070] S31: Collect several temporary vertical pole structure schemes; obtain temporary vertical pole structure schemes of different types and designs through literature research, patent search and engineering cases;
[0071] S32: Determine a number of evaluation indicators according to the finite element analysis of each position to be installed, and establish an evaluation scheme for each position to be installed. The first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators. Of course, the indicators used to evaluate each position to be installed in this step are consistent.
[0072] During the implementation process, specific evaluation indicators may include load-bearing capacity, construction convenience, cost-effectiveness, material utilization rate, and safety. Of course, the above indicators are only some of the indicators that can be selected and are not intended to limit the scope of protection of the present invention.
[0073] Taking the evaluation scheme as an example, during the implementation process, three evaluation indicators, namely, bearing capacity, construction convenience, and cost-effectiveness, were determined, and three temporary vertical pole structure schemes, namely, Scheme A, Scheme B, and Scheme C, were collected. The specific scoring scheme is as follows in Table 1:
[0074] ;
[0075] Table 1
[0076] In addition to the above methods, the scoring scheme can also be a bar chart, in which case the scores in the above table will be reflected as the height of the bar;
[0077] S33: for each location to be installed, calculating the total score of each temporary vertical pole structure scheme for each evaluation index;
[0078] S34: for all locations to be installed, calculating the sum of the total scores of each temporary vertical pole structure solution, and calculating the standard deviation of the total scores of each temporary vertical pole structure solution at different locations to be installed;
[0079] S5: The final comprehensive score of each temporary vertical structure scheme is determined by the sum of the total scores of the schemes and the standard deviation of the total scores of the schemes.
[0080] In this embodiment, the description is continued in conjunction with the above Table 1. In addition to the installation positions corresponding to the above Table 1, two installation positions are also included. The scores of each position are as shown in Table 2:
[0081] ;
[0082] Table 2
[0083] According to Table 2 above, the sum and standard deviation of the total scores of each temporary vertical bar structure scheme are:
[0084] Plan A: The total score of the plans is 57; the standard deviation of the total score of the plans is 1.633;
[0085] Plan B: The total score of the plan is: 69; the standard deviation of the total score of the plan is: 1.414;
[0086] Plan C: The total score of the plans is 77; the standard deviation of the total score of the plans is 4.497;
[0087] During the implementation of the above-mentioned optimization scheme, an evaluation scheme was established to systematically conduct a comprehensive evaluation of the temporary vertical pole structure scheme, taking into account multiple evaluation indicators (such as bearing capacity, construction convenience, cost-effectiveness, etc.), making the evaluation process more scientific and comprehensive; based on the finite element analysis results, the bearing capacity of each temporary vertical pole structure scheme can be accurately evaluated to ensure that the selected scheme can effectively improve the bearing capacity of the Bailey plate at non-node positions, thereby improving the safety of the overall structure and reducing the risk of structural failure; by considering indicators such as construction convenience and cost-effectiveness, a temporary vertical pole structure scheme with more convenient installation and disassembly and lower construction cost can be selected to improve construction efficiency and reduce project costs; if indicators such as material utilization rate are introduced in the evaluation process, a scheme with high material conservation can be selected to avoid material waste, improve resource utilization efficiency, and respond to environmental protection requirements.
[0088] Through data analysis and scoring calculation, the uncertainty of traditional reliance on experience and judgment is avoided, making the selection of temporary vertical pole structure schemes more objective and reliable, and improving the accuracy of decision-making; by calculating the sum and standard deviation of the total score of the scheme, the performance of each temporary vertical pole structure scheme in different installation positions is comprehensively evaluated, and the scheme with the highest comprehensive score is selected to ensure the comprehensiveness and optimization of the scheme.
[0089] The method of using the sum of the total scores of the solutions and the standard deviation of the total scores of the solutions for comprehensive scoring has the following advantages:
[0090] Comprehensively evaluate the overall performance of the scheme: By calculating the total score of each temporary vertical pole structure scheme in all the locations to be installed, comprehensively evaluate the overall performance of each scheme to ensure that the selected scheme has good performance in different locations, rather than only excellent performance in certain locations. This method can reflect the comprehensive performance of the scheme in the entire project.
[0091] Consider the stability and consistency of the solution: By calculating the standard deviation of the total solution score of each solution in different installation locations, the stability and consistency of the solution can be evaluated. A solution with a smaller standard deviation means that its performance in various locations is more balanced, with less fluctuation, and has higher reliability and predictability, which helps to avoid choosing solutions that perform well in some locations but poorly in other locations.
[0092] Comprehensive consideration of multiple dimensions: By dividing the evaluation indicators into different dimensions, such as bearing capacity, construction convenience, cost-effectiveness, etc., multiple factors can be comprehensively considered, making the evaluation process more comprehensive and scientific, and avoiding the one-sidedness of single-dimensional evaluation.
[0093] Improve the accuracy and objectivity of decision-making: Comprehensive scoring and ranking are performed through specific numerical values, namely total scores and standard deviations, making the decision-making process more objective and reducing the influence of subjective judgment. Data-driven decision-making methods can improve the accuracy of selecting the best solution and ensure that the final selected solution has better performance in practical applications.
[0094] Among them, as a preferred embodiment of the above embodiment, the calculation formula of the comprehensive score is:
[0095] E=w 1 ×S j +w 2 ×σ j ;
[0096] Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the program.
[0097] In the specific implementation process, determine the weight coefficient w 1 and w 2 The method is mainly based on the project's priorities and strategic goals. These weights reflect the importance of different evaluation factors. The determination method includes expert consultation, historical data analysis, weight allocation technology, target trade-offs and simulations, and sensitivity analysis. For example, if the highest priority of the project is to ensure structural safety, then a higher w 1weights to ensure that the overall score, i.e. the overall performance and safety of the structure, has a greater impact; conversely, if the project is more concerned with the consistency and predictability of the solution, then w 2 Weights may be higher to emphasize stability under different conditions. Through these methods, weights can be customized to the specific needs and circumstances of the project so that the overall score accurately reflects the project goals. Embodiment 2
[0098] The design system of Bailey sheet temporary vertical poles includes:
[0099] Finite element analysis module, which builds a finite element model of several interconnected Bailey plates, inputs material properties and geometric dimensions, simulates the load and support conditions in actual construction, runs finite element analysis, and obtains finite element analysis results;
[0100] The result analysis module determines the weak position of each Bailey plate in the non-node position according to the finite element analysis results, and uses the weak position as the position to be installed for the temporary vertical rod;
[0101] A historical data acquisition module traverses historical data to obtain several temporary vertical pole structure solutions that can be selected;
[0102] The scheme ranking module comprehensively scores each temporary vertical bar structure scheme based on the finite element analysis of the location to be installed, and obtains the score ranking;
[0103] The model revision module selects the temporary vertical bar structure scheme with the best score based on the score ranking, and adds the temporary vertical bar structure scheme to the finite element model to obtain the revised model;
[0104] The size revision module revises the final size of the temporary vertical bar structure scheme at each location to be installed based on the revised analysis results of the revised model by the finite element analysis module;
[0105] Among them, the scheme sorting module includes:
[0106] An evaluation scheme establishing unit, which determines a number of evaluation indicators according to the finite element analysis of each position to be installed, and establishes an evaluation scheme for each position to be installed, wherein the first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators;
[0107] A calculation unit calculates, for each location to be installed, a total score of each temporary vertical pole structure scheme for each evaluation index, calculates the sum of the total scores of each temporary vertical pole structure scheme for all locations to be installed, and calculates the standard deviation of the total scores of each temporary vertical pole structure scheme at different locations to be installed;
[0108] The comprehensive scoring output unit determines the final comprehensive scores of each temporary vertical bar structure scheme through the sum of the total scores of the schemes and the standard deviation of the total scores of the schemes.
[0109] As a preferred embodiment of this embodiment, in the comprehensive score output unit, the calculation formula of the comprehensive score is:
[0110] E=w 1 ×S j +w 2 ×σ j ;
[0111] Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the program.
[0112] The technical effect achieved by this embodiment is the same as that of the above-mentioned embodiment 1, and will not be repeated here. Embodiment 3
[0113] This embodiment provides a temporary vertical rod structure solution that can be selected in Embodiment 1, specifically:
[0114] A Bailey sheet temporary vertical rod, used in the design method of the Bailey sheet temporary vertical rod as described in the first embodiment, as a temporary vertical rod structure scheme, such as Figures 3 to 5 As shown, the Bailey sheet temporary vertical rod includes a first support beam 1 and a second support beam 2 which are arranged opposite to each other. The first support beam 1 and the second support beam 2 have the same structure and are connected at one end of their length by a connecting frame 3; the connecting frame 3 includes a support frame 31 and a first connecting seat 32 and a second connecting seat 33 which are symmetrically arranged thereon, and the first connecting seat 32 and the second connecting seat 33 are connected to the first support beam 1 and the second support beam 2 respectively by a first screw 34 and a second screw 35; a first support plate 11 and a first slot 12 are respectively arranged at both ends of the length of the first support beam 1, and a second support plate 21 and a second slot 22 are respectively arranged at both ends of the length of the second support beam 2, the first screw 34 is respectively screwed to the first connecting seat 32 and the first support plate 11, the second screw 35 is respectively screwed to the second connecting seat 33 and the second support plate 21, and the external threads on the first screw 34 and the second screw are arranged in opposite directions.
[0115] The temporary vertical rod is respectively connected with the upper and lower chord rods of the Bailey sheet through the first slots 12 and the second slots 22 at both ends of the first support beam 1 and the second support beam 2, and cooperates with the connecting frame 3 to adjust the distance between the adjacent ends of the first support beam 1 and the second support beam 2, so as to realize the tightening or loosening of the first slots 12 and the second slots 22 and the upper and lower chord rods of the Bailey sheet, so as to facilitate the disassembly and assembly of the temporary vertical rod and the Bailey sheet; wherein, the connecting frame 3 includes a support frame 31 and a first screw rod 34 and a second screw rod 35 screwed thereon, and the first support plate 11 and the second support plate 21 at the adjacent ends of the first support beam 1 and the second support beam 2 are respectively screwed through the first screw 34 and the second screw 35, and the first screw 34 and the second screw 35 are driven to move closer or farther from each other by rotating the support frame 31, so as to realize the adjustment of the distance between the adjacent ends of the first support beam 1 and the second support beam 2.
[0116] In an embodiment of the present invention, the first support beam 1 includes two symmetrically arranged first channel steels 13, and the second support beam 2 includes two symmetrically arranged second channel steels 23. The length ends of the first channel steel 13 and the second channel steel 23 are fixedly connected to the first support plate 11 and the second support plate 21 respectively.
[0117] The two first channel steels 13 and the two second channel steels 23 in the first support beam 1 and the second support beam 2 can be obtained by using two full-length channel steels and disconnecting the two at the same position; then, one end of the two first channel steels 13 or the two second channel steels 23 is welded to the steel plate to obtain the structural body of the first support beam 1 and the second support beam 2, making the temporary vertical pole structure of the present invention more practical.
[0118] Furthermore, the ends of the two first channel steels 13 away from the first support plate 11 are connected by a first pin 14, and the ends of the two second channel steels 23 away from the second support plate 21 are connected by a second pin 24; the groove bottoms of the two first channel steels 13 are arranged opposite to each other and cooperate with the first pin 14 to form a first groove 12 at the ends of the two first channel steels 13, and the groove bottoms of the two second channel steels 23 are arranged opposite to each other and cooperate with the second pin 24 to form a second groove 22 at the ends of the two second channel steels 23.
[0119] The first pin 14 and the second pin 24 are respectively arranged at the ends of the stable main structures of the first support beam 1 and the second support beam 2 that are far away from each other, so that the first pin 14 or the second pin 24 respectively cooperates with the two first channel steels 13 or the second channel steels 23 on both sides thereof to form the first clamping groove 12 and the second clamping groove 22 that can clamp the upper and lower chords of the Bailey plate. During the construction process, the first pin 14 and the second pin 24 are respectively abutted against the upper and lower chords of the Bailey plate.
[0120] In the embodiment of the present invention, Figure 5As shown, the support frame 31 includes a first connecting rod 311 and a second connecting rod 312 which are symmetrically arranged. The two ends of the length of the first connecting rod 311 and the second connecting rod 312 are fixedly connected to the first connecting seat 32 and the second connecting seat 33 respectively; the first connecting rod 311 and the second connecting rod 312 are both arranged in a bow shape, and the protrusions of the first connecting rod 311 and the second connecting rod 312 are both arranged toward the back sides of the two.
[0121] The first connecting seat 32 and the second connecting seat 33 are arranged opposite to each other and are fixed by welding the first connecting rod 311 and the second connecting rod 312 to form a support frame 31 structure. The first connecting rod 311 and the second connecting rod 312 are both arranged in a bow shape and symmetrically arranged on both sides of the first connecting seat 32 and the second connecting seat 33 to ensure the stability of the support frame 31 structure; and during the construction process, any steel pipe can be used to penetrate the support frame 31 and drive it to rotate, so as to facilitate the connection frame 3 to adjust the distance between the support beams on both sides.
[0122] In the embodiment of the present invention, Figure 6 and Figure 7 As shown, a first nut 341 and a second nut 342 are respectively provided at both ends of the length of the first screw rod 34, and a third nut 351 and a fourth nut 352 are respectively provided at both ends of the length of the second screw rod 35. The first nut 341 and the third nut 351 are both located inside the support frame 31. The nuts provided at both ends of the screw rods enhance the safety of the connection frame 3 during the adjustment process.
[0123] As a preferred embodiment of the above, Figure 8 and Fig. 9 As shown, the first nut 341 and the third nut 351 are fixedly connected to the first screw rod 34 and the second screw rod 35 respectively, and the first limit seat 36 and the second limit seat 37 are relatively arranged on the first nut 341 and the second nut 342, and the first limit seat 36 and the second limit seat 37 are respectively abutted by the first plane 361 and the second plane 371 opened thereon; the first plane 361 and the second plane 371 are respectively arranged along the length direction of the first screw rod 34 and the second screw rod 35, and the first limit groove 362 and the second limit groove 372 are opened thereon corresponding to the first screw rod 34 and the second screw rod 35 respectively.
[0124] During the adjustment process of the connecting frame 3, the first screw rod 34 and the second screw rod 35 are driven to move closer to or farther from each other by rotating the supporting frame 31. The first screw rod 34 and the second screw rod 35 are prevented from rotating along with the rotation of the first connecting seat 32 and the second connecting seat 33 on the supporting frame 31 by the abutment of the first limiting seat 36 and the second limiting seat 37, so as to ensure that the first screw rod 34 and the second screw rod 35 move smoothly along the length direction thereof under the drive of the supporting frame 31. During the relative movement of the first screw rod 34 and the second screw rod 35, the first plane 361 and the second plane 371 on the first limiting seat 36 and the second limiting seat 37 maintain the abutment rotation state, and the relative sliding between the first plane 361 and the second plane 371 can cooperate with the relative movement of the first screw rod 34 and the second screw rod 35.
[0125] In the embodiment of the present invention, a first reinforcing plate 111 is provided at the connection between the first support plate 11 and the first screw rod 34, and a second reinforcing plate 211 is provided at the connection between the second support plate 21 and the second screw rod 35; a third reinforcing plate 131 is provided at the connection between the first pin 14 and the two first channel steels 13, and a fourth reinforcing plate 231 is provided at the connection between the second pin 24 and the two second channel steels 23. The structural strength of the connection position in the temporary vertical rod structure is enhanced by providing the reinforcing plates.
[0126] The present invention further discloses a processing method of a Bailey sheet temporary vertical rod, which is applied to the above-mentioned Bailey sheet temporary vertical rod, including processing of a first support beam 1, a second support beam 2 and a connecting frame 3, wherein the first support beam 1 and the second support beam 2 have the same structure:
[0127] The processing method of the first support beam 1 comprises the following steps:
[0128] One end of the two first channel steels 13 is welded to the first support plate 11, and the notches of the two first channel steels 13 are arranged opposite to each other. A first reinforcing plate 111 is added to the first support plate 11 and a threaded hole is opened; the ends of the two first channel steels 13 away from the first support plate 11 are connected through the first pin 14, and a third reinforcing plate 131 is added at the connection of the first channel steels 13; the processing method of the second support beam 2 is the same as that of the first support beam 1. In the specific implementation process, the two first channel steels 13 and the two second channel steels 23 in the first support beam 1 and the second support beam 2 can be obtained by truncation of two through-length channel steels at equal positions, making the temporary vertical bar structure of the present invention more practical and economical.
[0129] The processing method of the connecting frame 3 comprises the following steps:
[0130] The first connecting seat 32 and the second connecting seat 33 are arranged symmetrically and fixed by welding the first connecting rod 311 and the second connecting rod 312, and threaded holes are opened on the first connecting seat 32 and the second connecting seat 33 along the same direction; the first screw 34 and the second screw 35 are screwed into the threaded holes of the first connecting seat 32 and the second connecting seat 33 respectively; the first screw 34 and the second screw 35 are screwed into the threaded holes of the first support plate 11 and the second support plate 21 respectively, and the connecting frame 3 is connected to the first support beam 1 and the second support beam 2 on both sides thereof.
[0131] Furthermore, the present invention also discloses a method for using a Bailey sheet temporary vertical rod, comprising the following steps:
[0132] The first support plate 11 on the first support beam 1 and the second support plate 21 on the second support beam 2 are respectively connected by the first screw 34 and the second screw 35 on the connecting frame 3; the support frame 31 on the connecting frame 3 is rotated and the first screw 34 and the second screw 35 are driven to approach each other, so that the first support beam 1 and the second support beam 2 are approached to each other; the first slot 12 and the second slot 22 located at the ends of the first support beam 1 and the second support beam 2 away from each other are respectively aligned with the upper chord and the lower chord of the Bailey plate; the support frame 31 on the connecting frame 3 is rotated in the opposite direction and the first support beam 1 and the second support beam 2 are respectively driven to move away from each other by the first screw 34 and the second screw 35, so that the first slot 12 and the second slot 22 are respectively close to the upper chord and the lower chord and are tightened and fixed.
[0133] Those skilled in the art should understand that the present invention is not limited to the above embodiments, and the above embodiments and descriptions are only for explaining the principles of the present invention. Without departing from the spirit and scope of the present invention, the present invention may have various changes and improvements, and these changes and improvements fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.
Claims
1. A design method for a temporary vertical pole of Bailey sheet, characterized in that: include: Establish a finite element model of several interconnected Bailey plates, input material properties and geometric dimensions, simulate the load and support conditions in actual construction, run finite element analysis, and obtain finite element analysis results; According to the finite element analysis results, several weak positions in the non-node positions of each Bailey plate are determined, and the weak positions are used as positions to be installed for the temporary vertical rods; Traversing historical data to obtain several temporary vertical pole structure solutions available for selection, including obtaining temporary vertical pole structure solutions of different types and designs through literature research, patent search and engineering case studies, and comprehensively scoring each of the temporary vertical pole structure solutions in combination with the finite element analysis of the location to be installed to obtain a scoring ranking; Based on the scoring order, a temporary vertical bar structure scheme with the best score is selected, and only the structural shape of the temporary vertical bar is selected. The goal of the selection is to obtain the best comprehensive effect of the temporary vertical bar structure in all the locations to be installed, and the temporary vertical bar structure scheme is added to the finite element model to obtain a revised model; Performing finite element analysis on the revised model to obtain revised analysis results, and revising the final dimensions of the temporary vertical bar structure scheme at each of the locations to be installed according to the revised analysis results; Among them, traverse the historical data to obtain several temporary vertical pole structure solutions available for selection, and conduct a comprehensive evaluation of each of the structure solutions in combination with the finite element analysis of the location to be installed, including: Collect several temporary vertical pole structure plans; Determine a number of evaluation indicators according to the finite element analysis of each of the positions to be installed, and establish an evaluation scheme for each position to be installed, wherein the first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators, wherein the evaluation indicators include at least three of the following: bearing capacity, construction convenience, cost-effectiveness, material utilization rate, and safety; For each of the locations to be installed, calculating the total score of each of the temporary vertical pole structure solutions for each evaluation index; For all locations to be installed, calculate the sum of the total scores of each temporary vertical pole structure solution, and calculate the standard deviation of the total scores of each temporary vertical pole structure solution at different locations to be installed; The final comprehensive score of each temporary vertical pole structure scheme is determined by the sum of the total score of the scheme and the standard deviation of the total score of the scheme; the calculation formula of the comprehensive score is: E=w 1 ×S j +w 2 ×σ j ; Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the scheme.
2. The design method of Bailey sheet temporary vertical pole according to claim 1 is characterized in that: The weak position is determined by analyzing at least one of a stress distribution diagram, a strain distribution diagram or a modal analysis result.
3. The design method of Bailey sheet temporary vertical pole according to claim 1 is characterized in that: Determine the weight coefficient w 1 and w 2 , using at least one of the following methods: expert consultation, historical data analysis, weighting techniques, target trade-offs and simulations, and sensitivity analysis.
4. The design system of Bailey sheet temporary vertical poles is characterized by: include: Finite element analysis module, which builds a finite element model of several interconnected Bailey plates, inputs material properties and geometric dimensions, simulates the load and support conditions in actual construction, runs finite element analysis, and obtains finite element analysis results; A result analysis module, which determines the weak position of each non-node position of the Bailey plate according to the finite element analysis result, and uses the weak position as the position to be installed of the temporary vertical rod; A historical data acquisition module, which traverses historical data to obtain a number of temporary vertical pole structure solutions available for selection, including obtaining temporary vertical pole structure solutions of different types and designs through literature research, patent search and engineering case approaches; A scheme ranking module is used to comprehensively score each of the temporary vertical pole structure schemes in combination with the finite element analysis of the position to be installed, and obtain a score ranking; A model revision module, which selects a temporary vertical bar structure scheme with the best score based on the score ranking, and selects only the structural shape of the temporary vertical bar, and the goal of the selection is to obtain the best comprehensive effect of the temporary vertical bar structure in all the locations to be installed, and adds the temporary vertical bar structure scheme to the finite element model to obtain a revised model; A size revision module, which revises the final size of the temporary vertical bar structure scheme at each of the locations to be installed based on the revised analysis results of the revised model by the finite element analysis module; Wherein, the scheme sorting module includes: An evaluation scheme establishing unit, which determines a number of evaluation indicators according to the finite element analysis of each of the positions to be installed, and establishes an evaluation scheme for each position to be installed, wherein the first dimension of the evaluation scheme is used to list the evaluation indicators, the second dimension is used to list the temporary vertical pole structure schemes, and the third dimension is used to reflect the score of the temporary vertical pole structure scheme based on the set evaluation indicators, and the evaluation indicators include at least three of the following: bearing capacity, construction convenience, cost-effectiveness, material utilization rate, and safety; A calculation unit, for each of the positions to be installed, calculates the total score of each of the temporary vertical pole structure schemes for each evaluation index, for all the positions to be installed, calculates the sum of the total scores of each of the temporary vertical pole structure schemes, and calculates the standard deviation of the total scores of each of the temporary vertical pole structure schemes at different positions to be installed; A comprehensive scoring output unit, which determines the final comprehensive scores of each of the temporary vertical pole structure schemes by the sum of the total scores of the schemes and the standard deviation of the total scores of the schemes; In the comprehensive score output unit, the calculation formula of the comprehensive score is: E=w 1 ×S j +w 2 ×σ j ; Among them, E is the comprehensive score, w 1 and w 2 is the weight coefficient corresponding to the sum and standard deviation, S j is the sum of the total scores of the schemes, σ j is the standard deviation of the total score of the scheme.
Citation Information
Patent Citations
Simulation assembling method used for continuous assembling construction of steel pipe arch rib segment bed jig method
CN105740560A
Bridge real-time monitoring and evaluating system and construction method thereof
CN115219127A
Upper-layer and lower-layer steel truss web member composite beam suitable for urban overhead and construction method of upper-layer and lower-layer steel truss web member composite beam
CN117488647A
System and method for converting steel trestle BIM (Building Information Modeling) model into finite element pretreatment model
CN118013610A
Bridge construction monitoring method, device and equipment and storage medium
CN118013617A