A pressure-releasing anchor rod and support method for a tunnel with extrusion surrounding rock
By designing a compression anchor with a resistance-increasing head and a gradient sleeve, the problem that traditional anchors cannot cope with the large deformation of the extrusive surrounding rock is solved, higher adaptability and stability are achieved, and the extrusion resistance is significantly improved. The support effect of the surrounding rock tunnel.
Patent Information
- Application Number
- CN202411001775.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-07-25
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2044-07-25
AI Technical Summary
Traditional compression anchors cannot effectively cope with the large deformation of the squeezing surrounding rock. They are prone to breakage of the rod body, pull-out of the anchor interface and failure of component matching. It is difficult to meet the support needs of tunnels with squeezing surrounding rock.
A pressure-resistance anchor including a pressure-resistance sleeve and an anchor rod body is designed. The top end of the anchor rod body is provided with a resistance-increasing head. The resistance-increasing head contacts the inner wall of the sleeve. The bottom end of the anchor rod body is used for anchoring. The resistance-increasing head moves along the length direction of the sleeve, and combines the gradient sleeve and snap ring structure to achieve first- and second-level pressure yielding effects and absorb the deformation energy of the surrounding rock.
This design improves the adaptability and stability of the anchor, can better cope with the large deformation of the compressive surrounding rock, is safe and reliable, greatly improves the support effect of the compressive surrounding rock, and has good application prospects.
Smart Images

Figure CN118532207B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of tunnel engineering construction auxiliary equipment, and in particular to a yield anchor rod and a supporting method for a squeeze rock tunnel. Background Art
[0002] With the continuous development of tunnel engineering, more and more challenges are faced, among which the most prominent one is the problem of extrusion surrounding rock. Due to the characteristics of large deformation and fast speed of this surrounding rock, traditional yield anchors cannot meet its support needs. Although traditional yield anchors can provide a certain support resistance, their ability to cope with large deformation of surrounding rock is obviously insufficient. Specifically, there are three main manifestations of its failure behavior: one is the breaking or shearing of the rod body due to insufficient deformation capacity; the second is the pulling off of the anchoring interface; the third is the failure of matching between the components of the anchoring system, such as the destruction of the tray (pad), nut and anchoring agent. In response to these problems, scholars have conducted in-depth research and designed a new type of anchor that can adapt to large deformation of surrounding rock and provide sustainable support resistance, namely, the yield anchor, also known as the large deformation anchor. Based on this yield anchor, supplemented by other support components, the current main yield support technology has been formed. A variety of anchoring methods suitable for large deformation of surrounding rock have been developed at home and abroad, but after analysis, it is found that the existing yield anchors still have many shortcomings and are difficult to be widely used in actual engineering. Summary of the invention
[0003] The purpose of the present invention is to provide a yield anchor and support method for a tunnel with squeezing surrounding rock, which has higher adaptability and stability, can better cope with the large deformation problem of the surrounding rock, provide strong guarantee for the safety and stability of the tunnel project, and meet the support needs of tunnels with large deformation of squeezing surrounding rock.
[0004] To achieve the above object, the present invention provides the following solutions:
[0005] The present invention provides a pressure-yielding anchor for a tunnel with squeezing surrounding rock, comprising a pressure-yielding sleeve and an anchor rod body, wherein the pressure-yielding sleeve is located on the outside of the anchor rod body, the pressure-yielding sleeve is provided with a fixing structure for fixing to the surrounding rock, the top end of the anchor rod body is provided with a resistance-increasing head, the resistance-increasing head contacts the inner wall of the pressure-yielding sleeve, the bottom end of the anchor rod body is used for anchoring, and the anchor rod body can drive the resistance-increasing head to move along the length direction of the pressure-yielding sleeve.
[0006] Preferably, the pressure-releasing sleeve includes a first gradual sleeve and a second gradual sleeve, the first gradual sleeve is sleeved on the outside of the second gradual sleeve, the resistance increasing head contacts the inner wall of the second gradual sleeve, the size of the first gradual sleeve gradually decreases from the top of the first gradual sleeve to the bottom of the first gradual sleeve, the size of the second gradual sleeve gradually decreases from the top of the second gradual sleeve to the bottom of the second gradual sleeve, and the inner wall of the first gradual sleeve contacts the outer wall of the second gradual sleeve.
[0007] Preferably, a clamping ring is provided at the bottom end of the second gradient sleeve, and the resistance increasing head can be clamped with the clamping ring.
[0008] Preferably, a sleeve straight section is provided at the top end of the first gradient sleeve, the sleeve straight section is integrally formed with the first gradient sleeve, and the fixing structure is provided at the sleeve straight section.
[0009] Preferably, the fixing structure comprises a pad, the pad is sleeved on the straight section of the sleeve, and the size of the pad is larger than the size of the drilled hole.
[0010] Preferably, the fixing structure further comprises a tray, the tray is sleeved on the straight section of the sleeve, the tray is threadedly connected to the straight section of the sleeve, and the tray is arranged at the front end of the pad.
[0011] Preferably, the fixing structure further comprises a nut, the nut is sleeved on the straight section of the sleeve, the nut is threadedly connected to the straight section of the sleeve, and the nut is arranged at the front end of the tray.
[0012] Preferably, the pressure-releasing sleeve and the anchor rod body are coaxially arranged.
[0013] The present invention also provides a support method using the yield anchor for a squeeze rock tunnel, comprising: installing the resistance increasing head and the anchor rod body into a second gradient sleeve, then installing the second gradient sleeve into the first gradient sleeve, and fixing the sleeve with a pad, a tray, and a nut through the external thread of the straight section of the sleeve;
[0014] The pressure-releasing anchor used in the tunnel with squeezed surrounding rock is set inside the borehole, the bottom end of the anchor rod body extends into the bottom of the borehole to cooperate with grouting for initial anchoring, the pad is located outside the borehole and fixed on the tunnel surrounding rock, and the resistance-increasing head is located at the borehole opening;
[0015] As the deformation energy of the tunnel surrounding rock gradually accumulates, when the axial force applied to the anchor rod body exceeds the compression resistance designed for the compression anchor rod used in the extrusion rock tunnel, the resistance increasing head frictionally slides along the inner wall of the second gradual sleeve. When the resistance increasing head slides to the end of the second gradual sleeve, the retaining ring clamps the resistance increasing head. When the resistance increasing head continues to slide, the resistance increasing head pulls the second gradual sleeve out of the first gradual sleeve to achieve secondary compression relief.
[0016] Compared with the prior art, the present invention has achieved the following technical effects:
[0017] The main purpose of the present invention is to meet the support needs of tunnels with large deformation of extrusive surrounding rocks, and to be able to better deal with the problems of large deformation and fast speed of extrusive surrounding rocks. First, after the yield anchor used for the extrusive surrounding rock tunnel is assembled, the deformation energy of the tunnel surrounding rock is transmitted to the anchor rod body through the tray and the inner anchoring section. At this time, the resistance increasing head begins to frictionally slide along the inner wall of the second gradient sleeve. The deformation energy of the surrounding rock is absorbed by the material deformation of the anchor rod body and the structural deformation of the yield sleeve to resist the deformation and damage of the rock mass and relieve the deformation pressure of the surrounding rock. The present invention can cope with large deformation of the extrusive surrounding rock, is safe and reliable, and has low cost. It greatly improves the support effect of the extrusive surrounding rock and has good application prospects. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.
[0019] Figure 1 It is a schematic structural diagram of a pressure-yielding anchor rod for a squeeze rock tunnel according to the present invention;
[0020] Figure 2 It is a cross-sectional schematic diagram of a yield anchor used in a squeeze rock tunnel of the present invention;
[0021] Figure 3 It is a schematic structural diagram of the first gradient sleeve and the second gradient sleeve of the present invention;
[0022] Figure 4 It is a cross-sectional schematic diagram of the first gradient sleeve and the second gradient sleeve of the present invention;
[0023] Figure 5 It is a detailed view of the clamp ring of the present invention;
[0024] Figure 6 It is a schematic diagram of the structure of the resistance increasing head and the anchor rod body of the present invention;
[0025] Figure 7 It is a schematic diagram of anchoring and installing the yield anchor rod used in a squeeze rock tunnel of the present invention;
[0026] Figure 8 A schematic diagram of a first-level pressure relief of a pressure relief anchor used in a squeeze rock tunnel according to the present invention;
[0027] Fig. 9 It is a schematic diagram of the secondary pressure relief of the pressure relief anchor used in a squeeze rock tunnel of the present invention;
[0028] Among them: 1-nut, 2-tray, 3-pad, 4-sleeve straight section, 5-first gradient sleeve, 6-second gradient sleeve, 7-resistance increasing head, 8-clamping ring, 9-anchor rod body, 10-drilling hole, 11-grouting anchoring section, 12-surrounding rock. DETAILED DESCRIPTION
[0029] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0030] The purpose of the present invention is to provide a yield anchor and support method for a tunnel with squeezing surrounding rock, which has higher adaptability and stability, can better cope with the large deformation problem of the surrounding rock, provide strong guarantee for the safety and stability of the tunnel project, and meet the support needs of tunnels with large deformation of squeezing surrounding rock.
[0031] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the present invention is further described in detail below with reference to the accompanying drawings and specific embodiments.
[0032] Embodiment 1
[0033] like Figures 1 to 6 As shown: This embodiment provides a yield anchor for use in a squeezing surrounding rock tunnel, comprising a yield sleeve and an anchor rod body 9, the yield sleeve and the anchor rod body 9 are coaxially arranged, the yield sleeve is located on the outside of the anchor rod body 9, the yield sleeve is provided with a fixing structure for fixing to the surrounding rock 12, a resistance increasing head is provided at the top end of the anchor rod body 9, the resistance increasing head 7 is in contact with the inner wall of the yield sleeve, the bottom end of the anchor rod body 9 is used for anchoring, and the anchor rod body 9 can drive the resistance increasing head 7 to move along the length direction of the yield sleeve.
[0034] Specifically, in this embodiment, the resistance increasing head 7 and the anchor rod body 9 are integrally formed, the outer diameter of the top end of the resistance increasing head 7 is 37.4 mm, and the outer diameter of the bottom end of the resistance increasing head 7 is the same as the outer diameter of the anchor rod body 9, both of which are 24 mm. The resistance increasing head 7 and the anchor rod body 9 are both solid metal rods, which produce axial movement when subjected to the pressure of the external surrounding rock 12, and the resistance increasing head 7 continuously squeezes and rubs the second gradual sleeve 6.
[0035] In this embodiment, the pressure-releasing sleeve includes a first gradual sleeve 5 and a second gradual sleeve 6. The first gradual sleeve 5 is sleeved on the outside of the second gradual sleeve 6. The resistance increasing head 7 is located inside the second gradual sleeve 6. The resistance increasing head 7 contacts the inner wall of the second gradual sleeve 6. The size of the first gradual sleeve 5 gradually decreases from the top of the first gradual sleeve 5 to the bottom of the first gradual sleeve 5. The size of the second gradual sleeve 6 gradually decreases from the top of the second gradual sleeve 6 to the bottom of the second gradual sleeve 6. The inner wall of the first gradual sleeve 5 contacts the outer wall of the second gradual sleeve 6.
[0036] In this embodiment, a clamping ring 8 is provided at the bottom end of the second gradient sleeve 6, and the clamping ring 8 is integrally formed with the second gradient sleeve 6. The outer diameter of the top of the second gradient sleeve 6 is 37.4 mm, the outer diameter of the end of the second gradient sleeve 6 is 32 mm, the wall thickness of the second gradient sleeve 6 is 2 mm, the inner diameter of the clamping ring 8 is 28 mm, and the wall thickness of the clamping ring 8 is 2 mm. In this embodiment, the pressure-releasing effect is achieved by subjecting the second gradient sleeve 6 to axial friction and radial extrusion deformation by the resistance-increasing head 7; the function of the clamping ring 8 is that when the resistance-increasing head 7 moves to the end of the second gradient sleeve 6, the clamping ring 8 clamps the resistance-increasing head 7, and when the resistance-increasing head 7 continues to move, the resistance-increasing head 7 pulls out the second gradient sleeve 6, achieving a secondary pressure-releasing effect.
[0037] In this embodiment, a sleeve straight section 4 is provided at the top of the first tapered sleeve 5, and the sleeve straight section 4 is integrally formed with the first tapered sleeve 5. The outer diameter of the sleeve straight section 4 is 44 mm, the outer diameter of the top of the first tapered sleeve 5 is 44 mm, and the outer diameter of the bottom of the first tapered sleeve 5 is 38 mm. The wall thickness of the first tapered sleeve 5 and the sleeve straight section 4 are both 3 mm, and the fixed structure is provided in the sleeve straight section 4. The first tapered sleeve 5 is located at the outermost part of the pressure anchor, which can protect the structure inside and prevent the second tapered sleeve 6 and the anchor rod body 9 from being sheared and damaged by the rock formation, and can also provide positive pressure in the friction deformation stage of the second tapered sleeve 6, which can well offset the eccentric force generated by the resistance increasing head 7 when squeezing and rubbing the second tapered sleeve 6.
[0038] In this embodiment, the fixing structure includes a nut 1, a tray 2 and a pad 3. The nut 1, the tray 2 and the pad 3 are sequentially sleeved on the straight section 4 of the sleeve from front to back. The nut 1, the tray 2 and the pad 3 are respectively threadedly connected to the straight section 4 of the sleeve, and the size of the pad 3 is larger than the size of the drill hole 10.
[0039] The main purpose of this embodiment is to meet the support needs of tunnels with large deformation of the extrusive surrounding rock 12, and to better deal with the problems of large deformation and fast speed of the extrusive surrounding rock 12. First, after the yield anchor used for the extrusive surrounding rock tunnel is assembled, the deformation energy of the tunnel surrounding rock 12 is transmitted to the anchor rod body 9 through the tray 2 and the inner anchoring section. At this time, the resistance increasing head 7 begins to frictionally slide along the inner wall of the second gradient sleeve 6. The deformation energy of the surrounding rock 12 is absorbed by the material deformation of the anchor rod body 9 and the structural deformation of the yield sleeve to resist the deformation and damage of the rock mass and relieve the deformation pressure of the surrounding rock 12. This embodiment can cope with large deformation of the extrusive surrounding rock 12, is safe and reliable, and has low cost. It greatly improves the support effect of the extrusive surrounding rock 12 and has good application prospects.
[0040] Embodiment 2
[0041] like Figures 7 to 9 As shown: This embodiment provides a support method for a yield anchor for a squeeze rock tunnel using the first embodiment, comprising the following steps: installing the resistance increasing head 7 and the anchor rod body 9 into the second tapered sleeve 6, and then installing the second tapered sleeve 6 into the first tapered sleeve 5, and fixing the sleeve straight section 4 with the backing plate 3, the tray 2, and the nut 1 through the external thread;
[0042] The pressure-releasing anchor for the squeeze rock tunnel is arranged inside the borehole 10, the bottom end of the anchor rod body 9 extends into the grouting anchoring section 11 at the bottom of the borehole 10 to cooperate with grouting for initial anchoring, the pad 3 is located outside the borehole 10 and fixed on the tunnel surrounding rock 12, and the resistance-increasing head 7 is located at the orifice of the borehole 10;
[0043] As the deformation energy of the tunnel surrounding rock 12 gradually accumulates, when the axial force applied to the anchor rod body 9 exceeds the yield resistance of the yield anchor designed for the extrusion surrounding rock tunnel, the resistance increasing head 7 slides along the inner wall of the second tapered sleeve 6. In this process, the resistance increasing head 7 and the second tapered sleeve 6 are subjected to the axial friction force provided by the second tapered sleeve 6 and the radial extrusion force provided by the first tapered sleeve 5 and the second tapered sleeve 6. As the sliding progresses and as the yield movement length of the resistance increasing head 7 increases, the inner diameters of the first tapered sleeve 5 and the second tapered sleeve 6 continue to decrease, and the axial friction force and radial extrusion force on the resistance increasing head 7 continue to increase, and its yield resistance also continues to increase accordingly. When the resistance increasing head 7 slides to the end of the second tapered sleeve 6, the retaining ring 8 clamps the resistance increasing head 7. When the resistance increasing head 7 continues to slide, the resistance increasing head 7 pulls the second tapered sleeve 6 out of the first tapered sleeve 5 to achieve secondary yield. This process relies on the structural deformation of the pressure sleeve to absorb the deformation energy of the surrounding rock 12 to resist the deformation and damage of the rock mass and relieve the deformation pressure of the surrounding rock 12.
[0044] The present specification uses specific examples to illustrate the principles and implementation methods of the present invention. The above examples are only used to help understand the method and core idea of the present invention. At the same time, for those skilled in the art, according to the idea of the present invention, there will be changes in the specific implementation methods and application scope. In summary, the content of this specification should not be understood as limiting the present invention.
Claims
1. A pressure-relief anchor for a tunnel with extrusive surrounding rock, characterized in that: It comprises a pressure-releasing sleeve and an anchor rod body, wherein the pressure-releasing sleeve is located outside the anchor rod body, the pressure-releasing sleeve is provided with a fixing structure for fixing with the surrounding rock, the top end of the anchor rod body is provided with a resistance-increasing head, the resistance-increasing head contacts the inner wall of the pressure-releasing sleeve, the bottom end of the anchor rod body is used for anchoring, and the anchor rod body can drive the resistance-increasing head to move along the length direction of the pressure-releasing sleeve; The pressure-releasing sleeve includes a first gradual sleeve and a second gradual sleeve, the first gradual sleeve is sleeved on the outside of the second gradual sleeve, the resistance-increasing head contacts the inner wall of the second gradual sleeve, the size of the first gradual sleeve gradually decreases from the top end of the first gradual sleeve to the bottom end of the first gradual sleeve, the size of the second gradual sleeve gradually decreases from the top end of the second gradual sleeve to the bottom end of the second gradual sleeve, and the inner wall of the first gradual sleeve contacts the outer wall of the second gradual sleeve; A clamping ring is provided at the bottom end of the second gradient sleeve, and the resistance increasing head can be clamped with the clamping ring.
2. The yield anchor for a squeeze rock tunnel according to claim 1, characterized in that: The pressure-releasing sleeve and the anchor rod body are coaxially arranged.
3. The yield anchor for a squeeze rock tunnel according to claim 1, characterized in that: A sleeve straight section is arranged at the top end of the first gradient sleeve, the sleeve straight section is integrally formed with the first gradient sleeve, and the fixing structure is arranged on the sleeve straight section.
4. The yield anchor for a squeeze rock tunnel according to claim 3, characterized in that: The fixing structure comprises a pad, which is sleeved on the straight section of the sleeve, and the size of the pad is larger than the size of the drilled hole.
5. The yield anchor for a squeeze rock tunnel according to claim 4, characterized in that: The fixing structure also includes a tray, which is sleeved on the straight section of the sleeve, the tray is threadedly connected to the straight section of the sleeve, and the tray is arranged at the front end of the pad.
6. The yield anchor for a squeeze rock tunnel according to claim 5, characterized in that: The fixing structure also includes a nut, which is sleeved on the straight section of the sleeve, the nut is threadedly connected to the straight section of the sleeve, and the nut is arranged on the front end of the tray.
7. A method for supporting a compression anchor for a tunnel in a squeezed surrounding rock using the yield anchor described in claim 6, characterized in that: Install the resistance increasing head and the anchor rod body into the second gradient sleeve, then install the second gradient sleeve into the first gradient sleeve, and fix them with the backing plate, tray and nut through the external thread of the straight section of the sleeve; The pressure-releasing anchor used in the tunnel with squeezed surrounding rock is set inside the borehole, the bottom end of the anchor rod body extends into the bottom of the borehole to cooperate with grouting for initial anchoring, the pad is located outside the borehole and fixed on the tunnel surrounding rock, and the resistance-increasing head is located at the borehole opening; As the deformation energy of the tunnel surrounding rock gradually accumulates, when the axial force applied to the anchor rod body exceeds the compression resistance designed for the compression anchor rod used in the extrusion rock tunnel, the resistance increasing head frictionally slides along the inner wall of the second gradual sleeve. When the resistance increasing head slides to the end of the second gradual sleeve, the retaining ring clamps the resistance increasing head. When the resistance increasing head continues to slide, the resistance increasing head pulls the second gradual sleeve out of the first gradual sleeve to achieve secondary compression relief.