A construction technology of geological caisson in high water level and quicksand layer
By using support mechanisms and buoyant barrels of movable plates and positioning columns in the construction of geological caissons with high water level, the problem of inconvenience in installation, fixing and disassembly of well plates is solved, and the quality and safety of construction are improved.
Patent Information
- Application Number
- CN202411069473.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-06
- Publication Date
- 2024-11-05
- Estimated Expiration
- 2044-08-06
AI Technical Summary
In the construction of geological caissons with high water level quicksand layer, the limit fixation cannot be achieved during installation of well plates, and the well plates are inconvenient to disassemble, which affects construction quality and safety.
The supporting mechanism is adopted that combines the movable plate and the positioning column. By pushing the limit plate into the slot, the limit plate is quickly fixed and disassembled, and the tension mechanism is used to drive the limit plate to shrink for later disassembly. The buoyancy barrel and electric slide rail are combined to resist buoyancy and Improve installation accuracy.
The limit fixation between well plates and rapid disassembly in the later stage are achieved, which reduces construction difficulty and safety risks, and improves the quality and efficiency of caisson construction.
Smart Images

Figure CN118581917B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of caisson construction equipment, in particular to a caisson construction process for a high-water-level quicksand-containing geological layer. Background Art
[0002] In recent years, with the development of the economy and society, people have paid more and more attention to the urban drainage pipeline system. Caisson is a kind of overall sinking method used when open excavation is not suitable due to site or foundation stratum restrictions when building underground projects or deep buried foundations. Caisson is to dig soil in the well, rely on its own gravity to overcome the friction resistance of the well wall and sink to the designed elevation, and then seal the bottom with concrete and fill the well hole to make it the foundation of the structure. The quality of caisson construction directly determines the success or failure of drainage pipeline construction. Caisson over-sinking and bottom sand gushing have a great impact on the quality of caisson construction, and are related to the patency and durability of the drainage system.
[0003] Controlling the quality of caisson construction is the key and difficulty, especially in the sandy strata along rivers, where groundwater is very abundant, which accelerates the loss of water and soil. Based on the above problems, a quicksand layer caisson construction method disclosed in Chinese patent application CN111042173A includes a first plate body and a positioning block arranged on the side of the first plate body close to the right caisson plate, the side wall of the first plate body contacts the side walls of the two adjacent steel plates, the bottom wall of the first plate body is provided with a mounting block inserted into the mounting notch, and the side of the first plate body away from the mounting notch is provided with a positioning notch for the mounting block to be inserted, and the positioning notch opens toward the right caisson plate. When in use, this technical solution limits the first plate body by the limiting plate on the lower first plate body, and the mounting block on the first plate body is inserted into the positioning notch, and the first plate body is limited by the steel plate and the limiting plate, thereby replacing the manual installation method of the caisson plate by workers, which is conducive to reducing the safety accidents of workers falling into the well, and can also reduce the workload of workers.
[0004] Regarding the above technical solution, although the solution reduces the workload during use, it is unable to achieve the limiting fixation between the well plates during installation. In addition, the well plates are not convenient for later disassembly, which causes inconvenience during use. Summary of the invention
[0005] The invention provides a high-water-level quicksand-containing geological caisson construction process to solve the problem that the well plates cannot be limited and fixed during installation and the well plates are inconvenient to disassemble in the later stage.
[0006] According to one aspect of the present invention, a construction process for a geological caisson in a high-water-level quicksand layer is provided, comprising the following steps:
[0007] S1, level the site, measure and place the center point of the hole, drive piles around the caisson, and lead the water level point to the outside of the hole;
[0008] S2, rough layout, fill the blade foot soil mold, repair the slope and apply cement mortar on its surface, and then carry out precise layout after the bottom of the blade foot hardens;
[0009] S3, install the molding die, and check and adjust the fixation;
[0010] S4. The concrete should be poured evenly. Do not miss or over-vibrate the concrete. It should be flexibly controlled according to the slump of the concrete. The steel bars are dense at the blade foot. Control the depth when inserting the vibrating rod to prevent over-vibration from affecting the outer and inner molds.
[0011] Based on the above scheme, it is preferred that in S1, the center of the hole is used as the dot, the edge line of the soil mold blade is released, and a cement mortar layer is applied on its surface after the slope is repaired. The cement mortar is 1:3, the thickness of the cement mortar layer is 1.5-2.0 cm, and the mortar surface needs to be flat and smooth.
[0012] Preferably, based on the above scheme, the installation of the forming mold in S3 includes the following steps: step one, installing the steel blade foot; step two, installing the inner mold; step three, installing the steel bars; step four, installing the outer mold.
[0013] Preferably, when installing the forming mold in S3, the blade foot plate is installed first, and reinforced concrete is poured after the blade foot plate is installed. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected into the foundation pit at the same time until the blade foot plate moves down to the set elevation. The mold is hoisted and installed by hoisting equipment until multiple well plates are installed on the blade foot plate to form a desired shape, and then reinforced concrete is poured. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected at the same time until the well plate sinks to the set elevation.
[0014] Preferably, when the S3 mold is installed, the steel blade foot must be accurately laid out before installation, the temporary support for the inner mold installation must be firm, the inner mold position must be accurate, the steel bars must be evenly spaced before installation, and the horizontal ring reinforcement must be measured with a ruler before tying to determine the ring reinforcement spacing.
[0015] Preferably, based on the above scheme, the embedded parts on the top surface of the inner ring of the bottom section of S4 are determined by the construction team to ensure smooth and safe connection. After the concrete pouring is completed, the maintenance method is adjusted according to the temperature changes to ensure that the concrete is not frozen. When the concrete strength reaches 50% of the design strength, the formwork is removed.
[0016] Preferably, based on the above scheme, the molding mold includes a fixed seat and a supporting seat, the supporting seat is movably connected between the fixed seats, a supporting plate and a connecting plate are movably installed on the top of the supporting seat, and the height of the connecting plate is greater than the height of the support plate, a movable plate is movably installed on the top of the fixed seat, and the movable plate, the support plate and the connecting plate are all provided with grooves and positioning holes.
[0017] Preferably, based on the above scheme, the sides of the support plate and the connecting plate are provided with fixing grooves, a limiting plate is movably installed inside the fixing groove, a clamping groove is provided on the inner wall of the fixed seat and the movable plate, one end of the limiting plate is movably installed inside the clamping groove, and positioning columns are movably installed at the bottom of the support plate and the connecting plate.
[0018] Preferably, based on the above scheme, a slider is fixed to one end of the positioning column, a sliding groove is provided at the bottom of the support plate and the connecting plate, the slider is movably installed inside the sliding groove through a supporting mechanism, an opening is provided on the limiting plate, one end of the positioning column cooperates with the opening through the slot, the limiting plate is installed inside the fixed slot through a tension mechanism, and a protrusion is fixed on the slider.
[0019] Preferably, on the basis of the above scheme, a blade foot seat is fixed inside the fixed seat and the supporting seat, a lifting rod is fixedly installed on the blade foot seat, a movable column is installed on the lifting rod, a fixed rod is fixedly installed on one end of the movable column, a sealing plate is movably installed on the top of the fixed rod, a groove is opened on the bottom of the sealing plate, and the sealing plate is movably installed on the fixed rod through the groove.
[0020] The invention discloses a construction process for a geological caisson with a high water level and containing quicksand. The process has a novel structure. When in use, a movable plate is installed on a limit plate through a positioning column. The limit plate is pushed into a slot by a supporting mechanism to quickly fix the fixing seat and the supporting seat. After the supporting plate and the connecting plate are removed, the tension mechanism drives the limit plate to shrink into the fixing slot, and the fixing seat and the supporting seat lose their fixing force, which is convenient for quick disassembly between the fixing seat and the supporting seat in the later stage. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] In order to more clearly illustrate the technical solutions of the embodiments of the present invention, the following briefly introduces the drawings required for describing the embodiments. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative work. In the drawings:
[0022] Figure 1 A schematic diagram of the work flow structure of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0023] Figure 2 It is a schematic diagram of the work flow structure of the installation mold of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0024] Figure 3 It is a structural schematic diagram of the stacked installation of support plates and connecting plates in a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0025] Figure 4 It is a structural schematic diagram of a fixing seat and a supporting seat of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0026] Figure 5 It is a structural schematic diagram of a connecting plate and a supporting plate of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0027] Figure 6 It is a structural schematic diagram of a limit plate of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0028] Figure 7 It is a schematic diagram of the side view structure of a fixing seat of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0029] Figure 8 It is a structural schematic diagram of a fixing rod form 1 of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0030] Fig. 9 It is a structural schematic diagram of a second fixing rod form of a high-water-level quicksand-containing geological caisson construction process of the present invention;
[0031] Fig.10 It is a schematic diagram of the first state structure of the inner mold, the outer mold and the buoyancy barrel of the present invention;
[0032] Fig.11 It is a schematic diagram of the structure of the inner mold, the outer mold and the buoyancy barrel in the second state of the present invention;
[0033] Fig.12 It is a schematic diagram of the structure of the inner mold, the outer mold and the buoyancy barrel in the third state of the present invention;
[0034] Description of Figure Numbers:
[0035] Fixed seat 1, movable plate 2, support seat 3, support plate 4, connecting plate 5, slot 6, positioning hole 7, positioning column 8, fixed slot 9, limit plate 10, opening 11, tension spring 12, slider 13, support spring 14, guide platform 15, blade foot seat 16, lifting rod 17, movable column 18, fixed rod 19, sealing plate 20, groove 21, inner mold 30, outer mold 50, buoyancy barrel 40, electric slide rail. DETAILED DESCRIPTION
[0036] The specific implementation of the present invention is further described in detail below in conjunction with the accompanying drawings and examples. The following examples are used to illustrate the present invention, but are not intended to limit the scope of the present invention.
[0037] It should be understood that when used in this specification and the appended claims, the term "comprising" indicates the presence of described features, integers, steps, operations, elements and / or components, but does not exclude the presence or addition of one or more other features, integers, steps, operations, elements, components and / or collections.
[0038] In order to simplify the drawings, only the parts related to the present invention are schematically shown in each figure, and they do not represent the actual structure of the product. In addition, in order to simplify the drawings and facilitate understanding, in some figures, only one of the parts with the same structure or function is schematically drawn or marked. In this article, "one" not only means "only one", but also means "more than one".
[0039] It should be further understood that the term “and / or” used in the specification and appended claims refers to any combination and all possible combinations of one or more of the associated listed items, and includes these combinations.
[0040] In the embodiments shown in the drawings, the indications of directions (such as up, down, left, right, front and back) used to explain the structure and movement of the various components of the present invention are not absolute but relative. These descriptions are appropriate when these components are in the positions shown in the drawings. If the descriptions of the positions of these components change, the indications of these directions also change accordingly.
[0041] In addition, in the description of the present application, the terms "first", "second", etc. are only used to distinguish the description and cannot be understood as indicating or implying relative importance.
[0042] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the specific implementation methods of the present invention will be described below with reference to the accompanying drawings. Obviously, the accompanying drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings and other implementation methods can be obtained based on these drawings without creative work.
[0043] See also Figure 1 , and combined with Figure 2 and Figure 3 As shown, a high-water-level quicksand-containing geological caisson construction process of the present invention includes a construction process, and the construction process includes the following steps:
[0044] S1: The site is leveled. The surveyor measures the center point of the hole for the leveling elevation of the site, drives piles around the caisson, and directs the water level point to the outside of the hole;
[0045] S2, rough layout, fill the blade foot soil mold, repair the slope and apply cement mortar on its surface, and then carry out precise layout after the bottom of the blade foot hardens;
[0046] S3, install the molding die, and check and adjust the fixation;
[0047] S4: Concrete pouring and maintenance. The concrete should be poured evenly. Do not miss or over-vibrate the concrete. It should be flexibly controlled according to the slump of the concrete. The steel bars are dense at the blade foot. Control the depth when inserting the vibrator to prevent over-vibration from affecting the outer mold 30 and the inner mold 30, and remove the mold.
[0048] In this embodiment, the mold installation in S4 includes the following steps: step 1, installing the steel blade foot; step 2, installing the inner mold 30; step 3, installing the steel bars; step 4, installing the outer mold 30.
[0049] In this embodiment, the site is leveled in S1, and the surveying personnel measure and place the center point of the hole position, and drive guard piles outside the caisson, lead the water level point to the outside of the hole position, and place the edge line of the earth mold blade with the center of the hole as the dot. When repairing the slope in S4, the slope is corrected by the slope ruler, and the blade foot slope is 40°. After the slope is repaired, the 1:3 cement mortar is used in S5 for powdering. The mortar thickness is 1.5-2.0cm, and the mortar surface should be flat and smooth.
[0050] In this embodiment, when installing the mold in S8, the blade foot plate is installed first, and reinforced concrete is poured after the blade foot plate is installed. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected into the foundation pit at the same time until the blade foot plate moves down to the set elevation. The mold is hoisted and installed by hoisting equipment until multiple well plates are installed on the blade foot plate to form the required shape, and then reinforced concrete is poured. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected at the same time until the well plate sinks to the set elevation.
[0051] In this embodiment, when S8 installs the mold, the layout must be accurate before installing the steel blade foot, the temporary support used for installing the inner mold 30 must be firm, the position of the inner mold 30 must be accurate, the spacing between the steel bars must be evenly distributed before installing the steel bars, and the spacing between the horizontal ring bars must be measured with a ruler before tying.
[0052] In this embodiment, the embedded parts on the top surface of the inner ring of the bottom section concrete in S10 are determined by the construction team to ensure smooth and safe connection. After the concrete pouring is completed, the maintenance method is adjusted according to the temperature changes to ensure that the concrete is not frozen. In S11, when the concrete strength reaches 50% of the design strength, the mold can be removed. Safety must be ensured when removing the mold, and the stacking location must be convenient for subsequent work.
[0053] Please continue reading Figure 3 and Figure 4As shown, the molding mold of the present invention includes an inner mold 30 and an outer mold 30. The outer mold 30 is installed in the inner mold 30 to form a molding cavity, which is used to pour concrete to form a caisson. Specifically, the inner mold 30 and the outer mold 30 of the present invention have the same structure, and the difference is the size. Of course, the cross-section of the inner mold 30 and the outer mold 30 can be circular or rectangular. The outer mold 30 will be used as an example for detailed description below.
[0054] The outer mold 30 of the present invention includes a fixed seat 1 and a support seat 3. There are at least two fixed seats 1. The fixed seats 1 are arranged at intervals and connected through the support seats 3. In actual use, different numbers of support seats 3 can be set as needed to change the inner diameter size formed by the fixed seats 1 and the support seats 3 to meet different caisson needs.
[0055] Among them, a support plate 4 and a connecting plate 5 are movably installed on the top of the support seat 3, the support plate 4 is installed on the support seat 3, and the connecting plate 5 is installed on the support plate 4; a movable plate 2 is movably installed on the top of the fixed seat 1, and the two sides of the support plate 4 and the connecting plate 5 are connected to the movable plate 2, and slots 6 and positioning holes 7 are opened on the movable plate 2, the support plate 4 and the connecting plate 5. When the support plate 4, the movable plate 2 and the connecting plate 5 are superimposed and installed in the later stage, the height difference between the movable plate 2 and the connecting plate 5 is used to facilitate observation of the installation position.
[0056] Please continue reading Figure 5 As shown, the sides of the support plate 4 and the connecting plate 5 of the present invention are both provided with fixing grooves 9, and a limiting plate 10 is movably installed inside the fixing groove 9. The inner walls of the side ends of the fixing seat 1 and the movable plate 2 are both provided with card slots, and one end of the limiting plate 10 is movably installed inside the card slot.
[0057] like Figure 6 As shown, both ends of the bottom of the support plate 4 and the connecting plate 5 of the present invention are provided with slide grooves, a slider 13 is slidably engaged in the slide groove, a positioning column 8 is fixed at the bottom of the slider 13, and the free end of the positioning column 8 is inserted into the positioning hole 7 at the top of the adjacent support plate 4 or connecting plate 5. It should be noted that the positioning hole 7 is a waist-shaped long hole to accommodate the extension and contraction of the tension spring 12. At the same time, a guide platform 15 is provided on the side end face of the slider 13.
[0058] A supporting spring 14 is arranged between the slider 13 and the slide groove of the present invention, and a fixing groove 9 is opened on the side end faces of the support plate 4 and the connecting plate 5, and a limiting plate 10 is movably installed inside the fixing groove 9, and a tension spring 12 is arranged at the end face of the limiting plate 10 that contacts the fixing groove 9, and an opening 11 is arranged on the top of the limiting plate 10, and the opening 11 is arranged opposite to the positioning hole 7, and the free end of the positioning column 8 passes through the positioning hole 7 and is inserted into the opening 11.
[0059] It should be noted that the fixed seat 1 and the supporting seat 3 of the present invention are hollow structures, and a blade foot seat 16 is fixed inside the fixed seat 1 and the supporting seat 3, a lifting rod 17 is fixedly installed on the blade foot seat 16, and a movable column 18 is installed on the lifting rod 17. A fixed rod 19 is fixedly installed on one end of the movable column 18, and a sealing plate 20 is movably installed on the top of the fixed rod 19. A groove 21 is opened at the bottom of the sealing plate 20, and the sealing plate 20 is movably installed on the fixed rod 19 through the groove 21. The lifting rod 17 preferably adopts an electric push rod. The lifting rod 17 controls the height of the fixed rod 19 in the later stage, and the sealing plates 20 of different widths are installed in the inside of the blade foot seat 16 to adjust the inclination angle of the blade foot. In addition, the sealing plate 20 cooperates with the blade foot in the later stage to push the fixed seat 1 and the supporting seat 3 downward, so that the fixed seat 1 and the supporting seat 3 can be quickly separated from the blade foot after casting. For the specific structure, please refer to Figure 7 , Figure 8 and Fig. 9 shown.
[0060] The supporting seat 3 is placed between the fixing seats 1, and sealing plates 20 of different widths are installed according to the inclination angle of the blade foot. The sealing plates 20 are installed inside the blade foot seat 16. The lifting rod 17 controls the height of the fixing rod 19, and the sealing plates 20 of different widths are installed inside the blade foot seat 16. The inclination angle of the blade foot is adjusted. The fixing rod 19 is rotated according to the shape of the fixing seat 1 and the supporting seat 3. After the blade foot is cast in the later stage, the sealing plate 20 cooperates with the blade foot to push the fixing seat 1 and the supporting seat 3 to move downward, so that the fixing seat 1 and the supporting seat 3 can be quickly separated from the blade foot after casting. When the mold needs to be superimposed and installed, the positioning column 8 is squeezed inward by hand. After the positioning column 8 is squeezed inward, one end of the positioning column 8 enters the inside of the slot 6 to position the positioning column 8. The column 8 descends again and enters the interior of the opening 11, and the positioning column 8 is released. The supporting mechanism generates a thrust for the slider 13, and the thrust pushes the positioning column 8 and the limit plate 10 to move. The limit plate 10 moves out from the interior of the fixing groove 9 and enters the interior of the card slot. The connection between the support seat 3 and the fixed seat 1 is realized through the limit plate 10, and the assembly is completed quickly without the need for bolts. In addition, the bottom of the movable plate 2, the support plate 4 and the connecting plate 5 are fixedly installed with fixing columns. The later fixing columns enter the interior of the positioning hole 7 to provide supporting force for the support plate 4 and the connecting plate 5. When in use, the height of the movable plate 2 and the support plate 4 is lower than the height of the connecting plate 5. When the support plate 4, the movable plate 2 and the connecting plate 5 are superimposed and installed in the later stage, the height difference between the movable plate 2 and the connecting plate 5 is convenient for observing the installation position.
[0061] When installing the molding mold, due to the abundant groundwater at the bottom of the quicksand layer, the molding mold will float up due to the buoyancy of the groundwater and the force of the quicksand layer on the molding mold being greater than the gravity of the molding mold. As a result, the molding mold will have low installation accuracy. On the other hand, anti-floating measures are needed to increase downward pressure.
[0062] In order to reduce the difficulty of installation, the present invention can set a buoyancy barrel 40 between the inner mold 30 and the outer mold 30. The inner mold 30 and the outer mold 30 are connected through the buoyancy barrel 40. When installing, water or sand can be injected into the buoyancy barrel 40 to increase its gravity, reduce the buoyancy of groundwater on it, and reduce the difficulty of construction. For the specific structure, please refer to Fig.10 and Fig.11 shown.
[0063] Furthermore, buoyancy barrels 40 may be additionally provided on the outside of the outer mold 30 or the inside of the inner mold 30 , and the number of buoyancy barrels 40 may be increased or decreased according to actual needs.
[0064] It should be noted that, in order to further improve the anti-floating effect, the present invention can also set an electric slide rail on the inner side of the inner mold 30 or the outer side of the outer mold 30, and the buoyancy barrel 40 is installed on the inner mold 30 or the outer mold 30 through the electric slide rail. The slider 13 on the electric slide rail is used to control the up and down movement of the buoyancy barrel 40 to improve its anti-floating effect. For the specific structure, please refer to Fig.12 shown.
[0065] Finally, the method of the present application is only a preferred implementation scheme and is not intended to limit the protection scope of the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the protection scope of the present invention.
Claims
1. A high-water-level quicksand-containing geological caisson construction process, characterized in that: The following steps are included: S1, level the site, measure and place the center point of the hole, drive piles around the caisson, and lead the water level point to the outside of the hole; S2, rough layout, fill the blade foot soil mold, repair the slope and apply cement mortar on its surface, and then carry out precise layout after the bottom of the blade foot hardens; S3, install the molding die, and check and adjust the fixation; 4. The repairing kit for automotive dents, according to claim 1, wherein a bottom of the foot stand comprises a through-hole, and the two foot pieces comprise two bosses, wherein the bosses comprise a through-hole, a screw bolt, and a nut. The bosses comprise a through-hole, a screw bolt, and a nut. The bosses comprise a through-hole, a screw bolt, and a nut. S4. The concrete should be poured evenly. Do not miss or over-vibrate the concrete. It should be flexibly controlled according to the slump of the concrete. The steel bars are dense at the blade foot. Control the depth when inserting the vibrating rod to prevent over-vibration from affecting the outer and inner molds.
2. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 1, characterized in that: In the S1, the center of the hole is taken as the dot, and the edge line of the soil mold blade is released. When repairing the slope, a cement mortar layer is applied on the surface after the slope is repaired. The cement mortar is 1:3, the thickness of the cement mortar layer is 1.5-2.0 cm, and the mortar surface needs to be flat and smooth.
3. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 1, characterized in that: The installation of the forming mold in S3 includes the following steps: step 1, installing the steel blade foot; step 2, installing the inner mold; step 3, installing the steel bar; step 4, installing the outer mold.
4. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 3, characterized in that: When installing the forming mold in S3, the blade foot plate is installed first, and then reinforced concrete is poured. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected into the foundation pit until the blade foot plate moves down to the set elevation. The mold is hoisted and installed by hoisting equipment until multiple well plates are installed on the blade foot plate to form a desired shape, and then reinforced concrete is poured. After the reinforced concrete solidifies, the soil in the well is dug out, and water is injected into the foundation pit until the well plate sinks to the set elevation.
5. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 4, characterized in that: When installing the S3 mold, the steel blade foot must be accurately laid out before installation, the temporary support used for the inner mold installation must be firm, the inner mold position must be accurate, the steel bars must be evenly spaced before installation, and the horizontal ring reinforcement must be measured with a ruler before tying to determine the ring reinforcement spacing.
6. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 4, characterized in that: The embedded parts on the top surface of the inner ring of the S4 bottom section are determined by the construction team to ensure smooth and safe connection. After the concrete pouring is completed, the maintenance method is adjusted according to the temperature changes to ensure that the concrete is not frozen. When the concrete strength reaches 50% of the design strength, the formwork is removed.
7. A high-water-level quicksand-containing geological caisson construction process as claimed in claim 1, characterized in that: A blade foot seat is fixed inside the fixed seat and the support seat, a lifting rod is fixedly installed on the blade foot seat, a movable column is installed on the lifting rod, a fixed rod is fixedly installed on one end of the movable column, a sealing plate is movably installed on the top of the fixed rod, a groove is opened on the bottom of the sealing plate, and the sealing plate is movably installed on the fixed rod through the groove.